ER26-3380-000 · 2026-08-21 · FirstEnergy Service Company

Comments and Protest of FirstEnergy Service Company re PJM Interconnection, L.L.C.'s 07/31/2026 filing proposing to establish a Reliability Backstop…

Text extracted from the eLibrary original (SHA-256 7b550dfa48ee3eca…). Download the original from the official source.

Read topic-matched comments in ER26-3380

Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Credit and exit

PJM proposes to impose a new and onerous collateral obligation on each LSE allocated RBP Charges.21 Under the Proposed Tariff, the cumulative LSE credit requirement would initially equal $1.5 million multiplied by the total MW of committed RBP Unforced Capacity (“UCAP”) allocated to the LSE.22 PJM…
Read this passage Filed comments: Credit and exit

CONCLUSION

printed heading

CONCLUSION FirstEnergy respectfully requests that the Commission consider the foregoing comments and protest in its consideration of PJM’s RBP Proposal, reject PJM’s filing, institute an FPA Section 206 proceeding, and establish settlement proceedings.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 21st day of August, 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, D.C. 20005