ER26-3380-000 · 2026-08-21 · American Electric Power Service Corporation

Limited Protest of American Electric Power Service Corporation to PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and…

Text extracted from the eLibrary original (SHA-256 584b5448d461bac0…). Download the original from the official source.

Contents · 9 sections
  1. I. EXECUTIVE SUMMARY p. 1
  2. II. CORRESPONDENCE AND COMMUNICATIONS p. 3
  3. III. BACKGROUND p. 4
  4. IV. PROTEST p. 10
  5. A. PJM’s Proposed Transmission Owner Exit Provisions are Unjust and p. 10
  6. B. PJM’s Proposed Cost Allocation Methodology Is Not Just and Reasonable p. 28
  7. C. PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving p. 32
  8. D. PJM’s Proposal Contains an Error Regarding Fixed Resource Requirement p. 34
  9. V. CONCLUSION p. 35

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Credit and exit · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, LLC ) Docket No.
Read this passage Filed comments: Reliability and curtailment

I. EXECUTIVE SUMMARY

printed heading · Topic match: Cost allocation

Cir. 2017) (NRG). 4 Capitalized terms not otherwise defined herein shall have the meaning ascribed to them in the PJM Tariff and the RBP Proposal, as applicable. 3 (“RTO”) exit obligations; (2) direct PJM to revise its proposed cost allocation methodology to clarify that: (a) Electric Distributors…
Read this passage Filed comments: Cost allocation

II. CORRESPONDENCE AND COMMUNICATIONS

printed heading

Derasmo Emily Beard TROUTMAN PEPPER LOCKE LLP 401 9th Street, NW Suite 1000 Washington, DC (202) 662-2181 chris.jones@troutman.com william.derasmo@troutman.com emily.beard@troutman.com 5 AEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to be…
Read this passage

III. BACKGROUND

printed heading · Topic match: Cost allocation

If no RBP Obligation is reported, PJM will assign RBP Charges to LSEs using PJM’s method for allocating capacity costs pursuant to RAA, Schedule 8.31 Finally, states and RERRAs may decide how to further allocate RBP Charges to the appropriate retail customers.32 RBP Buyers and Sellers must meet a…
Read this passage Filed comments: Cost allocation

IV. PROTEST

printed heading

IV.
Read this passage

A. PJM’s Proposed Transmission Owner Exit Provisions are Unjust and

printed heading · Topic match: Cost allocation

Any revised exit provisions should be consistent with these principles: (1) a departing Transmission Owner’s responsibility for RBP Charges is limited to the RBP Charges otherwise assigned to its zone/area under the Commission-accepted RBP cost allocation; (2) PJM may not require a departing…
Read this passage Filed comments: Cost allocation

B. PJM’s Proposed Cost Allocation Methodology Is Not Just and Reasonable

printed heading · Topic match: Cost allocation

PJM’s Static Load-Forecast Cost Allocation Is Unjust and Unreasonable Because It Disconnects Long-Term RBP Charges From Actual Load Responsibility PJM proposes to allocate RBP Charges by first imputing the current 6,831.3 MW shortfall to each Electric Distributor zone/area based in part on that…
Read this passage Filed comments: Cost allocation

C. PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving

printed heading · Topic match: Credit and exit

PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving Entities, Not Electric Distributors, Because Credit Responsibility Should Follow the Entity Responsible for RBP Charges PJM proposes to require that those LSEs allocated responsibility for RBP Charges for a given Delivery Year…
Read this passage Filed comments: Credit and exit

D. PJM’s Proposal Contains an Error Regarding Fixed Resource Requirement

printed heading

PJM’s Proposal Contains an Error Regarding Fixed Resource Requirement Entities That Must Be Addressed The RBP Proposal contains an error that, if the Commission accepts the RBP Proposal, the Commission should direct PJM to amend on compliance.
Read this passage

V. CONCLUSION

printed heading · Topic match: Cost allocation

Reject or direct PJM to modify the proposed RBP cost allocation methodology by: (a) expressly stating that Electric Distributors bear no financial liability for RBP Charges solely by virtue of their administrative role in reporting LSE RBP Obligations; (b) providing that collateral obligations…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that on this 21st day of August 2026, I have caused a copy of the foregoing document to be served electronically on each person listed on the Secretary’s official service list in the above-referenced proceeding. /s/ Emily Beard Emily Beard TROUTMAN PEPPER…