ER26-3380-000 · 2026-08-21 · American Electric Power Service Corporation

Limited Protest of American Electric Power Service Corporation to PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, LLC
)

Docket No. ER26-3380-000

LIMITED PROTEST OF
AMERICAN ELECTRIC POWER SERVICE CORPORATION

Pursuant to Rule 211 of the Federal Energy Regulatory Commission (“Commission”) Rules of Practice and Procedure,1 American Electric Power Service Corporation, on behalf of its affiliates Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc. (collectively, “AEP”), hereby submits this protest to PJM Interconnection, LLC’s (“PJM”) proposed revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a Reliability Backstop Procurement (“RBP”) to Address Resource Adequacy Concerns Stemming from Large Loads.2

I. EXECUTIVE SUMMARY

The resource adequacy crisis in PJM is undisputed.  PJM is confronting the most significant generation need in its history.  Demand from national security needs, advanced manufacturing, data centers, and electrification is accelerating faster than PJM’s current interconnection processes

1 18 C.F.R. §§ 385.211, 385.214 (2025).
2 Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load Adjustments, Docket No. ER26-3380 (filed July 31, 2026) (“RBP Proposal”).  AEP filed a doc-less motion to intervene in the captioned docket on August 5, 2026.

PDF page 2

2

and market mechanisms allow the region to plan and build the infrastructure needed to reliably support such unprecedented load growth.  Given the urgency of the problem, PJM rightfully proposes to move with extraordinary speed to commit significant capital to new generating capacity.  AEP has urged PJM to aggressively address both the current resource adequacy crisis and the existing structures that gave rise to the shortfall, and supports measures to address the PJM region’s capacity shortfall.  Notwithstanding AEP’s support for swift and decisive action, the amount of capital required for this effort and the associated potential impact on wholesale and retail rates render the details of implementation critically important.  With that in mind, several important elements of the RBP Proposal must be reformed to ensure that the RBP produces just and reasonable outcomes for customers.  Consequently, AEP urges the Commission to exercise caution, subject the RBP Proposal’s details to meaningful scrutiny, and make use of the broad discretion PJM has afforded the Commission through its willingness to make the components of the RBP design “severable” for purposes of NRG.3

Despite AEP’s overall support for the RBP concept as a near-term measure to address the region’s resource adequacy crisis, certain changes are needed.  Specifically, the Commission should:  (1) either reject PJM’s proposed Transmission Owner4 exit provisions or direct PJM to modify them to limit any continuing RBP financial obligation of a departing Transmission Owner to the RBP Charges already allocated to that Transmission Owner’s zone under the Commission- accepted RBP Charge cost allocation methodology, and confirm that any new provisions do not disturb the Commission’s established precedent governing Regional Transmission Operator

3 See RBP Proposal at 3.  NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (NRG).
4 Capitalized terms not otherwise defined herein shall have the meaning ascribed to them in the PJM Tariff and the RBP Proposal, as applicable.

PDF page 3

3

(“RTO”) exit obligations; (2) direct PJM to revise its proposed cost allocation methodology to clarify that:  (a) Electric Distributors bear no financial liability for RBP Charges solely by virtue of their administrative role to report Load Serving Entities’ (“LSEs’”) RBP Obligations; and (b) collateral obligations attach to LSEs allocated RBP Charges; and (3) direct PJM to acknowledge and correct on compliance the drafting error in RAA, Schedule 8.1.D, Section D.1.1 that would, as written, fail to achieve PJM’s stated intent with respect to Fixed Resource Requirement (“FRR”) Entities.

II. CORRESPONDENCE AND COMMUNICATIONS

Correspondence regarding this filing should be sent to the following individuals, who should be placed on the official service list in this proceeding:5

John C. Crespo
Senior Legal Counsel
American Electric Power Service Corporation
1 Riverside Plaza
Columbus, Ohio 43215
(614) 716-3727
jccrespo@aep.com

Christopher R. Jones
William R. Derasmo
Emily Beard
TROUTMAN PEPPER LOCKE LLP
401 9th Street, NW Suite 1000
Washington, DC
(202) 662-2181
chris.jones@troutman.com
william.derasmo@troutman.com
emily.beard@troutman.com

5 AEP respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to be designated for service on the official service list in this proceeding.

PDF page 4

4

III. BACKGROUND
To address the near-term reliability concerns exposed by PJM’s 2028/2029 Base Residual Auction (“BRA”), which cleared short of PJM’s target reserve margin by 6,831.3 MW at the Commission-approved price cap of $325/MW-day, PJM proposes to conduct a one-time RBP for procuring new capacity from September 30, 2026 to October 21, 2026.6  The proposed rules governing the RBP are set forth in PJM’s Tariff and PJM’s RAA and are designed to allow PJM to procure the capacity needed to meet the shortfall from the 2028/2029 BRA.7  The January 16, 2026 National Energy Dominance Council/PJM Governors’ Principles urged PJM to procure new capacity through a backstop auction commencing no later than September 2026, provide 15-year price certainty for new capacity resources, and allocate the costs of that capacity to LSEs with new data centers that have not self-procured new capacity or agreed to be curtailable.8  PJM explains that the initial RBP procurement target (“Initial Target”) for the RBP will be set at 6,831.3 MW, subject to reduction after PJM has accounted for certain self-supplied new capacity and opt-outs.9 Noting that PJM members have expressed a strong preference for bringing new capacity to the PJM system voluntarily rather than contracting through PJM, PJM has facilitated a bilateral matching process to connect new capacity with new load.  The process began with an RFP on June

6
 RBP Proposal at 25-27; see also PJM INSIDE LINES, PJM Capacity Auction Procures 138,318 MW of Generation Resources as Work Continues to Address Growing Electricity Demand (July 14, 2026), https://insidelines.pjm.com/pjm-capacity-auction-procures-138318-mw-of-generation-resources-as-work-continues- to-address-growing-electricity-demand/.

7 RBP Proposal at 26; id. at 3–6 (describing the forthcoming IRAS filing and broader holistic review); see also PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability (May 20, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520-powering-reliability-through- market-design.
8 DEP’T OF ENERGY, Statement of Principles Regarding PJM (Jan. 15, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.
9 RBP Proposal at 26.  FRR Entities are excluded from the RBP.  Id. at 31.

PDF page 5

5

9, 2026, and initial matches were expected in or around August 2026.10  Participation is voluntary and non-binding, and PJM is not a party to the resulting arrangements.  In addition to accounting for opt-outs, PJM will reduce the Initial Target by capacity obtained through this bilateral matching process or other voluntary agreements for new capacity (“Qualifying RBP Offset MW”),11 if reported to PJM within the RBP procurement window by October 21, 2026.12  This reduced capacity procurement target (“Final Target”) will then form the basis for the RBP procurement. PJM explains that offers in the RBP will be for a fixed 15-year Delivery Year term and are expected to commence commercial operation in the 2028/2029 Delivery Year.13  RBP capacity will be paid-as-bid and subject to a must-offer requirement for the term of its commitment.14  The total cost of the RBP could amount to up to $20 billion over the 15-year term, and $1.63 billion annually.15  Following the conclusion of the RBP, PJM states that it will post a report that provides a transparent overview of the aggregate MWs that were procured as well as a weighted average of the RBP Charges as soon as practicable.16  PJM concedes that there is a possibility that it may clear a set of resources that does not match the Final Target.17

PJM explains that, because the Final Target will be based on a region-wide shortfall, it is not proposing to match specific supply to specific demand or apply locational constraints in the

10
Id. at 30-31.
11 PJM explains that the Initial Target will only be decremented by a quantity of capacity that was not already counted as supply for the 2027/2028 Delivery Year and that serves load that was counted in the forecasted demand for the period from 2027 through the beginning of the 2028/2029 Delivery Year.  Id. at 37. 12 Id. at 31.
13 Id. at 48.
14 Id. at 42, 58-59.
15 This estimate is based on the following calculation: 6.8 GW (procurement target) × $555/MW-day (maximum willingness to pay) × 15 years (commitment term).
16 Id.
17 Id. at 80.

PDF page 6

6

RBP.18  PJM states that, unlike the Reliability Pricing Model (“RPM”), whose annual three-year forward framework allowed PJM to model the necessary locational parameters, PJM does not have the information needed to determine such parameters for 15-year term capacity commitments.19 According to PJM, “including locational parameters based on today’s conditions would . . . lead to either over-procurement or under-procurement in given zones based on nothing more than speculation . . . .” and “ignore the role of PJM[] . . . to ensure delivery of capacity resources to load throughout PJM.”20  PJM does not propose direct market power screens or mitigation for the RBP, contending that the pay-as-bid structure with a maximum willingness to pay $555/MW-day limits the effectiveness of direct market screens or mitigation.21  RBP Sell Offers are considered binding, and RBP capacity that is subject to a Sell Offer is not permitted to exit the RBP to enter bilateral arrangements unless the project is not committed in the RBP following the conclusion of the procurement process.22

Each committed RBP Resource will individually settle as a contract-for-differences (“CfD”).23  This settlement structure turns on a committed RBP Resource’s individualized strike price.  A committed RBP Resource must offer all committed RBP Unforced Capacity (“UCAP”) MW as a price-taker in the RPM, unless a qualifying exception applies.  The market price for the RBP Resource is specifically defined as the resource’s unit-specific weighted average resource clearing price (“WARCP”) for all RPM Auctions in which the RBP Resource participated for the

18 Id. at 33.
19 Id. at 33-34.
20 Id. at 34.
21 Id. at 66-71.
22 Id. at 49.
23 Id. at 79-80.

PDF page 7

7

relevant Delivery Year.24  If the strike price is higher than the market price, the RBP Buyer must pay the difference between the strike price and the market price.25  If the strike price is lower than the market price, the RBP Resource must pay back the difference between the two.  PJM contends that this settlement structure protects RBP Buyers from paying RBP Resources a windfall, while protecting RBP Resources from settling below market prices.  The total MW eligible to settle as a CfD is the lesser of the RBP Resource’s daily committed RBP UCAP MWs, daily owned UCAP MWs, and daily cleared RPM UCAP MWs.26  In other words, RBP Buyers do not pay if the RBP Sellers’ capacity does not clear RPM also, an effort to further prevent over procurement. PJM proposes a three-tiered cost allocation system for RBP Charges, first allocating costs to Electric Distributor zones/areas, followed by LSEs, and then ultimately to retail customers.  For the last two steps, PJM’s cost allocation methodology relies on coordination between Electric Distributor zones/areas, state regulatory authorities, and state regulatory processes.  First, before allocating RBP Charges, PJM allocates cost responsibility to the relevant Electric Distributor zones/areas.  To do so, PJM proposes to determine each relevant Electric Distributor zone/area’s pro rata responsibility for the Initial Target based on forecasted load growth from the 2026/2027 Delivery Year to the 2028/2029 Delivery Year, incorporating certain load adjustments from the 2026 PJM Load Forecast.27  PJM then proposes to adjust each Electric Distributor zone/area’s allocation to reflect reductions based on its ability to procure Qualifying Offset MWs or successfully support an opt-out.28  After calculating the Final Target, PJM will reallocate RBP

24 Id. at 80.
25 Id. 26 Id. at 81.
27 See RBP Proposal, Attachment C, Affidavit of Danielle Croop ¶¶ 42-43 (“Croop Affidavit”).
28 Id. ¶ 44.

PDF page 8

8

Charges based on each Electric Distributor zone/area’s adjusted pro rata share of the Final Target.29 After receiving its allocation of RBP Charges, each Electric Distributor will coordinate with states and/or the Relevant Electric Retail Regulatory Authority (“RERRA”) to determine the allocation of RBP Charges attributable to an LSE in its zone/area (“RBP Obligation”) and report the RBP Obligation to PJM.30  PJM will then use the RBP Obligation to assess RBP Charges to each LSE. If no RBP Obligation is reported, PJM will assign RBP Charges to LSEs using PJM’s method for allocating capacity costs pursuant to RAA, Schedule 8.31  Finally, states and RERRAs may decide how to further allocate RBP Charges to the appropriate retail customers.32

RBP Buyers and Sellers must meet a variety of requirements to become eligible to participate in the RBP, including collateral requirements that apply in addition to and separate from existing collateral requirements.33  RBP Buyers are required to post collateral to mitigate the risk of potential defaults from non-payment of RBP Charges.  This requirement begins at an amount sufficient to mitigate the long-term risk of the RBP commitment.34  As with cost allocation, PJM first determines the overall credit requirement needed to address the risk associated with RBP commitments throughout the RBP 15-year term on a region-wide basis, assigning a $/MW rate applicable to all RBP capacity.35  In determining the credit requirement, PJM will multiply the total capacity committed in the RBP by the RBP Credit Rate, which is initially set at $1.5 million.36

29 Id.
30 Id. ¶¶ 51-52; RBP Proposal at 98. 31 Croop Affidavit ¶ 52; RBP Proposal at 98-99.
32 RBP Proposal at 100.
33 Id. at 109.
34 Id. at 111.
35 Id. at 115.
36 Id. at 116.

PDF page 9

9

Each LSE is then required to post, at least 45 days before the start of the Delivery Year, collateral equal to the product of $1.5 million and its allocated RBP Obligation.37  An RBP Buyer’s credit requirement is designed to go down over time, as the LSE’s RBP Obligation decreases.38 PJM also proposes rules setting forth the responsibilities of “various parties” in the event a Transmission Owner exits from PJM.39  PJM explains its goal to establish clear and enforceable rules to ensure that RBP Resources would be made whole for the entire term of the 15-year commitment.40  PJM thus proposes that a departing Transmission Owner with RBP commitments in its zone will have two options prior to exit:  depart with net load or net generation.

• Departing with load: If a Transmission Owner exits PJM with the net load in its region, before exiting, the Transmission Owner must either execute a binding agreement(s) that would maintain appropriate rates, terms, and conditions, and preserve the RBP commitments with the owners of the RBP Resources or pay (on an accelerated basis) all future RBP Charges it would have owed.41

• Departing with generation: If a Transmission Owner exits with net generation (i.e., RBP Resources) in its territory, the departing Transmission Owner must either ensure its RBP- contracted generation continues to serve PJM through a pseudo-tie (and agree to cover all related costs) or, if that is not possible:   (1) pay its remaining RBP obligations in full (on an accelerated basis) before exiting; or (2) execute a binding agreement(s) that would

37 Id. at 120.
38 Id. at 120-121.
39 Id. at 90.
40 Id. at 91.
41 Id. at 94-95.  The revenue collected will be credited to the remaining loads in PJM responsible for paying RBP Charges.  Id. at 95.  PJM states that, while the exiting Transmission Owner would initially be responsible to pay the costs necessary to ensure no RBP Resource becomes a stranded asset, nothing in the RBP Proposal would preclude a Transmission Owner from seeking to recover the costs from the relevant large loads.  Id.

PDF page 10

10

maintain appropriate rates, terms, and conditions of the RBP commitments, thus stepping into PJM’s role in the RBP context.42

In the event the Commission deems necessary, PJM consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff or RAA language to the extent necessary and permitted under section 205 of the Federal Power Act (“FPA”) and NRG,43 where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.44

IV. PROTEST
A. PJM’s Proposed Transmission Owner Exit Provisions are Unjust and
Unreasonable
The RBP Proposal, absent the modifications requested herein, could meaningfully and unfairly expand the negotiated terms of exit embedded in the Consolidated Transmission Owner’s Agreement (“TO Agreement”), Operating Agreement (“OA”) and RAA.  If and to the extent the Commission approves the RBP, AEP does not object to the notion that departing loads continue to pay for the RBP Charges assigned to them as a result of this one-time event, but objects to the imposition of an exit fee that obligates departing load to pay for charges that are unrelated to its fair allocation of RBP commitments.

AEP has publicly announced that it is evaluating whether continued membership in PJM will be in the best interest of its customers in the long run.  It is common knowledge that PJM’s

42 Id. at 92-94.  PJM states that the exact amount that an exiting Transmission Owner would owe would be determined through a separate filing with the Commission.  Id. at 94.  Thereafter, PJM states that it would pay the collected revenues from the Transmission Owner to the impacted RBP Resources as payments become due.  Id.
43 NRG, 862 F.3d 108.
44 RBP Proposal at 3.  PJM cautions that if severance or modification gives rise to complications, it may delay the opening of the RBP procurement window, causing downstream impacts such as the need to delay the BRA for the 2029/2030 Delivery Year.  Id.

PDF page 11

11

governing documents do not contain an exit fee, and Commission precedent confirms that a departing member’s obligation with regard to generating capacity charges extend only through the last RPM auction in which that departing member’s load was included.  With that in mind, the RBP Proposal’s exit provisions stand to broaden what the Commission has deemed necessary for departing load to honor cost commitments.  Principles of cost causation require PJM to demonstrate a reasonable nexus between the capacity procured in the RBP and the reliability need for which customers are being charged.  As drafted, the RBP Proposal would impose a financial obligation on a departing Transmission Owner based not on the RBP Charges allocated to an Electric Distributor zone/area pursuant to PJM’s proposed RBP cost allocation methodology, but on where PJM happens to procure or locate new RBP resources.  In this respect, the RBP Proposal flouts cost causation principles by imposing an exit fee that could far exceed the RBP Charges allocated to a departing Transmission Owner’s zone.45

For these reasons and as explained further below, the Commission should reject the proposed Transmission Owner exit provisions or, at minimum, require PJM to revise them before acceptance.  Any revised exit provisions should be consistent with these principles:  (1) a departing Transmission Owner’s responsibility for RBP Charges is limited to the RBP Charges otherwise assigned to its zone/area under the Commission-accepted RBP cost allocation; (2) PJM may not require a departing Transmission Owner to assume or guarantee, payment of obligations associated with RBP Resources beyond that limited responsibility, nor require acceleration of any payment obligation; (3) any proposed RTO replacement arrangement or continuity agreement must be calculated by reference to the withdrawing Transmission Owner’s allocated RBP Charges, not by

45 See K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992) (finding that cost causation requires that all approved rates reflect to some degree the costs actually caused by the customer who pays them).

PDF page 12

12

artificial reference to RBP Resources physically located in the relevant zone; (4) a Transmission Owner’s responsibility for RBP Charges should remain eligible for the RBP Settlement Credits and RPM Auction Credits that would apply as cost offsets if the same load remained in PJM; and

(5) the exit fee attributable to a departing Transmission Owner’s responsibility for RBP Charges should be reasonably capable of being calculated with the information known based on the results of the RBP.

1. The Proposed Exit Terms Lack Sufficient Clarity and Detail
The RBP Proposal’s proposed allocation of RBP Charges to departing Transmission Owners, first of all, lacks needed detail in light of the enormity of the financial burden it stands to impose.  Moreover, even the language that is sufficiently clear creates an unjust and unreasonable obligation on a withdrawing member.

Specifically, section 18.7 of the proposed Tariff language lacks administrable standards and is underdeveloped for the following reasons:

• Section 18.7 (a) first mentions voluntary agreements that a departing Transmission Owner “may” enter into with RBP Resources in the applicable zone under the standard that they “preserve[] the RBP commitments . . . with the owners of RBP Resources . . . .”46  It is not clear what this standard requires, including whether that agreement is intended to preserve that unit’s obligations to PJM, or whether the RBP Resource could agree to serve as a capacity resource to the departing Transmission Owner.

• PJM also has not explained or justified its request to have unfettered discretion to merely elect not to “retain” an RBP Resource that can be pseudo-tied back to PJM, as provided in

46 RBP Proposal, Attachment B, Clean Tariff Records, Attachment DD, § 18.7(a) (“Proposed Tariff”).

PDF page 13

13

section 18.7(a).47  Pursuant to the second paragraph of section 18.7(a), PJM wants the right to “elect” not to retain such a resource that could be pseudo-tied and foist a financial obligation on the departing member to take on 100 percent of the RBP Resource’s remaining revenue requirement for the 15-year term.48

• Section 18.7(b) in turn is also fatally vague.  It provides that a departing Transmission Owner exiting with net load that has been allocated RBP Charges for RBP Resources not located in its zone should enter into bilateral contracts with RBP resource not located in its Zone—i.e., with resources remaining in PJM—under the vague notion that such an agreement would “preserve[] the RBP commitments.”49  Since a departing Transmission Owner will have no relationship with any such unit, it is not clear what sort of contract may satisfy this requirement.

2. The Proposed Exit Terms are Unjust and Unreasonable Because the
RBP Charges of Departing Zones Are Not Reduced By
Corresponding RPM Revenues or Other Offsets
PJM’s proposed exit provisions are also unjust and unreasonable because they:  (1) appear to require a departing Electric Distributor zone/area to assume liability for the gross cost of RBP Resources without preserving the offsets and settlement protections that would apply if the same load remained in PJM; and (2) do not protect departing Transmission Owners from assuming RBP Charges in the event that RBP Resource capacity becomes surplus in PJM.  Under PJM’s proposed CfD structure, RBP Buyers pay RBP Charges based not simply on the full quantity of RBP MW acquired, but rather on an adjusted value that reflects a corresponding settlement value from PJM.

47 Id.
48 Id.
49 Id. § 18.7(b).

PDF page 14

14

Under PJM’s proposed exit structure, however, departing load appears to be required to fund the full RBP strike price without the adjustment afforded to remaining members.

The RBP Charge is intended to be netted against the resource’s RPM market value through the offsetting the RBP Settlement Credit, which is based on the lesser of three MW values:  (1) daily committed RBP UCAP MWs, (2) daily owned UCAP MWs, and (3) daily cleared RPM UCAP MWs.50  That offset is central to PJM’s own explanation of the RBP as a supplement to, not a replacement for, RPM.51  However, PJM’s proposed Transmission Owner withdrawal provisions only provide that a Transmission Owner departing with net load that has been allocated RBP Charges for RBP Resources—if it does not enter into agreements that maintain appropriate rates, terms and conditions that preserve the RBP commitments with the owners of such RBP Resources—must pay all forward obligations on an accelerated basis through the remaining term of the RBP commitment.52  This proposed term does not make clear that a Transmission Owner departing with net load and responsible for funding RBP commitments throughout their 15-year commitment term would be afforded the offset price for an RBP Resource that it would receive if it stayed in PJM.

In the example provided by PJM, the RBP Resource may clear substantially more MWs in the RBP than in the RPM, but is still eligible to receive RBP Settlement Credits that reduce the RBP Charge assessed.53  If a Transmission Owner’s post-exit obligation is calculated based only on the gross RBP Charge, while disregarding the quantity of RBP MW that clears both the RBP and RPM, the exit fee allocated to an exiting Transmission Owner would be calculated without

50
RBP Proposal at 81.
51 See id. at 7.
52 Proposed Tariff, Attachment DD § 18.7(b).
53 RBP Proposal at 85.

PDF page 15

15

accounting for the offsets that would otherwise accrue had it stayed in PJM.  Consequently, departing Transmission Owners and their load remain exposed to a substantial portion of the RBP Charges with no corresponding opportunity to receive an offset to the RBP Charge, thus forcing the departing Transmission Owner and its customers to pay more than similarly situated load that stays in PJM.  This result is unjust, unreasonable, and unduly discriminatory, and is not tied to cost causation.

This outcome is asymmetrical and inconsistent with PJM’s stated premise that RPM remains the foundational capacity market and that the RBP merely addresses incremental resource adequacy concerns.  If a Transmission Owner departing with load is required to fund the entire RBP payment obligation for an RBP Resource, principles of cost causation require that departing load should receive a corresponding RPM Auction Credit or RBP Settlement Credit tied to the full amount of capacity for which it is paying.  Otherwise, the RBP would function less as a supplemental reliability mechanism and more as an additional capacity procurement obligation requiring load to pay a higher RBP Charge for the RBP Resources in its zone than it would have otherwise been assessed had the load stayed in PJM.  The Commission should direct PJM to explain why this outcome fairly represents a Transmission Owner’s responsibility for its RBP Charges.

PJM should also be required to demonstrate why it proposes to limit the RBP Settlement Credit to overlapping RPM-cleared MW only for load remaining in PJM, and how that limitation produces a just and reasonable allocation of RBP Charges and benefits for departing Transmission Owners or Electric Distributor zones/areas.  This design increases the risk that a departing Transmission Owner will be allocated an unreasonable share of RBP Charges following its withdrawal from PJM.  The examples put forth in the RBP Proposal illustrate that the economic

PDF page 16

16

value of the CfD is limited to the quantity of MW that clears in both RPM and the RBP.54  This limitation becomes particularly significant in the event that future load reductions, market changes, or an Electric Distributor or Transmission Owner exit result in RBP Resources becoming surplus to PJM’s capacity needs.  For example—and as a result of PJM’s decision not to implement locational parameters in the RBP—if a Transmission Owner leaves PJM with the net load that formed the basis for its allocation of RBP Charges, the RBP Resources procured on its behalf that are located outside of the zone/area may no longer be needed in PJM.  Under such circumstances, RPM clearing levels may decline, thereby reducing or eliminating the quantity of MW eligible for CfD settlement and associated RBP Settlement Credits or RPM Auction Credits, while customers in the exiting zones/areas remain responsible for the underlying RBP Charges.  The RBP Proposal therefore creates the possibility that departing load will continue paying for RBP Resources long after the market no longer recognizes equivalent capacity value through RPM. This is especially concerning with respect to PJM’s proposed long-term cost responsibility framework.  If an Electric Distributor or Transmission Owner remains responsible for RBP Charges after an exit, PJM has not demonstrated that corresponding RPM revenues or CfD settlement benefits, including RPM Auction Credits and RBP Settlement Credits, will remain available throughout the 15-year commitment.  The RBP Proposal therefore risks creating an unfairly fixed financial obligation under which customers remain responsible for unabated RBP Charges, even as the quantity of RBP MW eligible to receive RPM Auction Credits declines over time.  At a minimum, PJM should clarify how withdrawing Transmission Owners will be protected from paying for RBP Resources whose capacity has become surplus to PJM’s needs and no longer

54 Id. at 84-86.

PDF page 17

17

receives corresponding RPM value either because of the Transmission Owner’s withdrawal or other changes in conditions impacting resource adequacy in PJM.

3. Any Imposed Exit Terms Should Be Consistent with Cost Causation
And Should be Capable of Determination in Advance of Withdrawal
In addition to the issues addressed above, the RBP Proposal reflects a disconnect between a departing load’s responsibility for RBP Charges upon withdrawal and PJM’s proposed exit charges without explanation regarding how the proposed exit fee is tied to the departing load’s initial allocation of RBP Charges.  The starting point for this analysis is PJM’s decision to propose an RBP process with no locational deliverability requirement.55  The RBP Proposal expressly assumes that new generation anywhere in PJM is deliverable to any load in PJM.  Under its proposal, PJM could acquire all 6,831.3 MW of new supply in New Jersey, or North Carolina, or even suburban Chicago.  More to the point for AEP, PJM could decide to acquire all—or at least a disproportionate share of — the new capacity in Ohio.  This is a stark departure from the RPM’s design, which does include locational elements, and relies on Capacity Emergency Transfer Objectives (“CETO”) and Capacity Emergency Transfer Limits (“CETL”) modeling to ensure that cleared capacity can address the reliability needs of constrained areas.56  As a result, customers may be required to fund RBP Resources that are not deliverable to their zone, while resources that are necessary to address local reliability needs may not be procured at all.  The RBP Proposal

55 Id. at 33.
56 PJM’s claim that it cannot predict future CETO or CETL values with precision does not eliminate the need to establish a reasonable relationship between the resources procured and the reliability benefits for which customers are charged.  At minimum, PJM should be required to explain how it will evaluate whether RBP Resources remain reasonably connected to the reliability needs of a zone that continues to bear RBP Charges, including after an Electric Distributor or Transmission Owner exits PJM.  Absent such a showing, the proposed cost responsibility framework risks obligating customers to pay for capacity that is incapable of addressing their underlying reliability needs.

PDF page 18

18

therefore raises a fundamental question regarding whether the RBP can reasonably achieve its stated reliability objective without accounting for known transmission limitations. Setting aside whether this approach will ensure reliability for the entire PJM region (which shares the costs of the RBP), the lack of a locational element undermines PJM’s proposed exit provisions.  If a transmission owning member of PJM exercises its contractual right to leave, its obligations for RBP Charges cannot be more than if that member decided to stay.  As proposed, a Transmission Owner remaining in PJM would pay RBP Charges according to PJM’s proposed cost allocation methodology (if accepted), while a departing Transmission Owner could be required to assume responsibility for RBP commitments tied to the RBP Resources in its zone/area, regardless of whether those commitments correspond to the RBP Charges allocated to that zone/area.  Indeed, under PJM’s proposal, a departing Transmission Owner would essentially have to indemnify each RBP Resource in its zone for the remainder of its RBP capacity commitment, even though—due to the lack of a locational element in the RBP—said RBP Resources may not be at all tied to that Transmission Owner.

Based on the exclusion of locational parameters from the RBP’s design, the location of selected RBP Resources may bear little relationship to the RBP Charges allocated to any particular zone/area.  Thus, if PJM procures a substantial amount of RBP capacity in one zone/area, the Transmission Owner for that zone/area could face exit-related obligations materially greater than those imposed by the RBP Charges otherwise allocated to that zone/area.  PJM’s potentially punitive proposal threatens to place an undue burden on departing Transmission Owners solely by virtue of where RBP Resources are located.  This outcome would create an undue barrier to a Transmission Owner’s ability to exercise its long-held contractual right to leave.

PDF page 19

19

Such an outcome would not comport with the principles of cost causation, nor would it provide meaningful notice to Transmission Owners of the financial consequences of RTO withdrawal.  Furthermore, it would potentially impose a disproportionate financial burden and expand the contractual requirements on Transmission Owners seeking to withdraw from PJM. Stated differently, PJM’s proposed exit framework could transform each LSE’s allocated RBP Charge into an unduly burdensome exit fee for a departing Transmission Owner.  The Commission should reject the proposed exit provisions and require PJM to limit a departing Transmission Owner’s liability to the RBP Charges allocated to its zone under PJM’s proposed cost allocation methodology, as accepted by the Commission.  Modifying PJM’s proposal in this manner would still insulate existing PJM members from RBP-related cost shifts upon a member’s departure while avoiding the creation of obligations that are not tied to an Electric Distributor zone/area’s allocated RBP Charges.

At a minimum, any RBP exit fee must be defined through an objective formula that can be calculated using the information known once the RBP results are final.  The cost of exiting an RTO must be clear and transparent so that a Transmission Owner can act in the best interests of its customers.  As stated above, the formula should begin with the departing Transmission Owner’s zone or area-level’s allocation of RBP Charges established under a Commission-accepted cost allocation for RBP Charges, as adjusted for any Qualifying RBP Offset MW, opt-outs, or other accepted reductions.  That amount should then be converted into a fixed, annual payment obligation for each remaining Delivery Year of the RBP commitment term, based on the RBP Charges that would otherwise have been assessed to the load remaining in PJM.  The RBP exit fee should be reduced by any RBP Settlement Credits, RPM Auction Credits, refunds, offsets, or other credits that would have applied had the load remained in PJM, and it should not include any

PDF page 20

20

additional obligation tied to the identity or physical location of RBP Resources selected by PJM. With respect to any amounts not reasonably capable of being estimated as of the date of calculation, the Tariff should include an obligation for those credits or other amounts to be paid over time as they are realized.  This approach would preserve PJM’s stated objective of preventing cost shifts to remaining load while giving departing Transmission Owners, customers, and state regulators a transparent and reasonably calculable measure of the financial consequences of withdrawal.

4. If An RBP Exit Fee is Accepted, the Commission Should Respect and
Confirm Existing Exit Standards For RTO Withdrawal
To the extent the Commission accepts any exit obligation for RBP Charges, it must make clear that its ruling is limited to those charges and does not undermine existing precedent governing existing PJM withdrawal obligations.  The Commission has already addressed the contractual obligations that apply when a PJM member exits, and nothing in this proceeding should expand those obligations beyond the specific Tariff language adopted for RBP Charges.  AEP’s concerns with the RBP withdrawal obligations addressed above underscore a broader need for the Commission to clarify how the proposed RBP framework will impact departing Transmission Owner’s responsibilities upon withdrawal now, before PJM creates new long-term obligations that could affect future RTO transition decisions.  Such clarification will allow Transmission Owners, customers, and state regulators the ability to evaluate the consequences of any potential RTO transition before long-term obligations are created.  The relationship between any new RBP exit requirements and PJM’s existing exit framework must be clearly defined such that PJM’s members and their customers and state regulators have adequate notice of how a member’s contractual obligations for departure will change should the Commission approve the RBP.  This topic is thus

PDF page 21

21

ripe for consideration in this proceeding because the terms of the RBP Proposal, if accepted, stand to expand Transmission Owners’ contractual obligations upon departure from PJM.

a. The Current Terms for Departing PJM
PJM is fundamentally a membership organization and membership, by law, is strictly
voluntary.57  The Commission can neither compel entry into an RTO nor enjoin a utility’s exit if the standard for departure has been satisfied.58  Each transmission owning member of PJM has a contractual right to leave.  The first part of the Commission’s section 205 role in a utility’s departure from an RTO (excluding of course its review of RTO replacement arrangements) is solely to ensure that the departing utility satisfies the “contractual obligations” applicable to it under its RTO’s governing documents upon withdrawal.59  The Commission has squarely rejected the notion that, absent specific contractual commitments, RTO exit is subject to a broader and more amorphous “hold harmless” standard and, in the case of PJM, there is no “exit fee.”60 In PJM today, the “contractual obligations” that must be satisfied for departure are clear. Section 3.4 of the TO Agreement provides that any party that withdraws from the TO Agreement

57 See, e.g., Reg’l Transmission Organizations, Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 30,994 (1999) (cross-referenced at 89 FERC ¶ 61,285) (adopting “an open collaborative process that relies on voluntary regional participation to design RTOs”), order on reh’g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000) (cross- referenced at 90 FERC ¶ 61,201), petitions for review dismissed sub nom. Public Utility Dist. No. 1 of Snohomish County, Wash. v. FERC, 272 F.3d 607 (D.C. Cir. 2001); Louisville Gas & Elec. Co., 114 FERC ¶ 61,282 at P 29 (2006) (“LG&E”) (“[P]articipation in an RTO is voluntary.”); see also Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002) (“Atlantic City”) (finding that the Commission has no authority to regulate RTO membership as a change- in-control transaction under section 203 of the Federal Power Act).
58 Duquesne Light Co., 122 FERC ¶ 61,039 at P 48 (2008) (“Duquesne I”) (“[M]ovement from one Commission-approved RTO to another is not barred by Order No. 2000.  As we recognized in LG&E, companies that voluntarily join RTOs should have the ability to withdraw from an RTO as long as the replacement rates that are established are just and reasonable.”).
59 LG&E, 114 FERC ¶ 61,282 at P 27; Duquesne I, 122 FERC ¶ 61,039 at PP 28-29.
60 Mw. Indep. Transmission Sys. Operator, Inc., 124 FERC ¶ 61,219 at P 222 (2008) (“Duquesne II”). (“Under the TO Agreement, in this regard, there is no exit fee requirement nor is there a hold harmless provision.  Considered in this context, we find that any weight that Reliant may have assigned to an asserted hold harmless guarantee has no reasonable basis in the TO Agreement itself and therefore, for all the reasons explained by the Commission in the January 17 Order, cannot be a basis for obligating Duquesne.”).

PDF page 22

22

“shall remain liable for any and all obligations under [the TO] Agreement that such Party incurred, that were incurred on behalf of such Party, or that arose hereunder prior to the date upon which such Party’s withdrawal, transfer, or assignment became effective.”61  One of the most significant applications of this rule is the liability of a departing member for Transmission Expansion Costs incurred by PJM under Schedule 12 of the PJM Tariff.  The Commission explored this issue in detail in the Duquesne proceedings.  In Duquesne I, the Commission made a number of determinations about Duquesne’s proposed exit demonstration, but found that Duquesne had not sufficiently addressed the “. . . full extent of its remaining transmission function obligations, as required by section 3.4 of the TO Agreement.”62  Specifically, the Commission found that “. . . Duquesne had not adequately addressed its financial liability to PJM with respect to its allocated share of [Regional Transmission Expansion Plan (“RTEP”)] project costs.”63  Accordingly, the Commission required Duquesne to address these obligations in a compliance filing, and accepted additional record development on this question.

After considerable briefing on the matter, the Commission concluded that section 3.4 of the TO Agreement obligates a departing Transmission Owner to pay the costs of Regional Facilities and Necessary Lower Voltage Facilities allocated to it under PJM Tariff Schedule 12 and its appendix through the end of the calendar year of its exit but does not subject the departing Transmission Owner to future-period costs related to those facilities.64  The Commission determined that the departing member would owe the entirety of the Lower Voltage Facility costs

61 TO Agreement § 3.4.
62 See Duquesne II, 124 FERC ¶ 61,219 at P 16.
63 Id.
64 Id.

PDF page 23

23

directly assigned to it.65  The Commission justified these findings on the basis that PJM’s assignment of Lower Voltage Facility costs “is fixed” at the time of the cost assignment, while cost assignments for Regional Facilities and Necessary Lower Voltage Facilities “are not fixed during the RTEP process” and are instead reallocated annually pursuant to Schedule 12.66 The Commission explained that the Schedule 12 appendix (today, Schedule 12 – Appendix A) assigns RTEP costs “on an evolving, superseding basis”67 and that, pursuant to Schedule 12: a new transmission owner joining PJM would become subject to these

charges . . .   regardless of when the projects were approved and regardless of who these projects may have previously benefitted.  And a departing

transmission owner leaving PJM would, pursuant to this language, no
longer be subject to these charges; it would not have a zonal annual peak
load as it would no longer be a zone in PJM.68

The Commission also pointed to the lack of any mechanism under Schedule 12 for PJM “to allocate future-period project costs to a former transmission owner based on the fictional assumption that this former transmission owner’s zone can or should remain a part of PJM for future-year schedule 12 purposes.”69  To that end, “[j]ust as PJM would not be permitted to exclude, from its schedule 12 appendix, load data applicable to the entry of a new transmission owner’s zone, it would not be allowed to continue to include a former transmission owner’s zone.”70

In reaching that decision, the Commission expressly rejected several arguments that would have imposed significant regional transmission costs on departing Transmission Owners.  First,

65 Id. P 168. 66 Id.
67 Id. P 165.
68 See id. P 164.
69 Id. P 167.
70 Id.

PDF page 24

24

the Commission dismissed the notion that “an RTEP report, once filed with the Commission, becomes binding on all zones then existing in PJM, presumably until all such project costs have been submitted for filing and recovered by PJM.”71  As the Commission noted, “PJM has chosen an allocation method for the higher voltage projects included in its RTEP that treats these costs as system-wide costs that are imposed on any new transmission owners that may join PJM and, similarly, may not be imposed on departing members.”72

Second, the Commission rejected the argument that its holding in a prior proceeding concerning the Midcontinent Independent System Operator (“MISO”) Transmission Owners Agreement had any relevance to the question of a departing PJM Transmission Owner’s RTEP cost liability.73  The Commission noted that although it had previously held in the context of the MISO Transmission Owners Agreement that “[i]n principle, a transmission owner should not be able to avoid previously allocated costs by withdrawing from the [RTO],” the Commission’s finding in that proceeding “was based on existing tariff provisions pertaining to financial obligations of withdrawing transmission owners, as reflected in the [MISO] Transmission Owners Agreement.”74  While the Commission “agree[d] that it might be just and reasonable for PJM to adopt a similar requirement, in the future,” the Commission noted it was “required here to interpret PJM’s tariff as currently drafted.”75  PJM never “adopt[ed] a similar requirement.” TO Agreement section 3.4 has not changed since the Commission decided Duquesne II in 2008.

71 Id. P 171.
72 Id.
73 Id. P 173.
74 See id. (citing Mw. Indep. Transmission Sys. Operator, Inc., 118 FERC ¶ 61,209 at P 193 (2007)).
75 Id.

PDF page 25

25

Third, the Commission was not swayed by an argument that it was required to hold a departing Transmission Owner “liable for regional RTEP costs shown to have reliability benefits” for that Transmission Owner’s zone.76  The Commission noted that Schedule 12 did not require that any “determinations of benefits to individual zones . . . be made,” and high-voltage facilities costs were “allocated during the year incurred to all transmission zones then-existing in PJM.”77 Finally, the Commission dismissed the notion that a departing Transmission Owner “should be required to pay, as a condition of its withdrawal, an exit fee that reflects its share of existing PJM financial expenditures and commitments.”78  The Commission reiterated its prior finding that “[t]he TO Agreement . . .  does not require [a transmission owner] to pay an exit fee as a condition to its withdrawal.”79

As it relates to generating capacity obligations, Section 5.1.1 of the RAA allows an LSE to withdraw from the RAA effective, inter alia, “upon completion of its obligations hereunder” and after giving prior written notice to the PJM Office of the Interconnection.80  As a general matter, the withdrawing LSE’s obligations under the RAA “shall be completed as of the end of the last month for which such Party’s obligations have been set at the time said notice is received.”81  The RAA directs that a withdrawing LSE pay a Locational Reliability Charge for each PJM zone in which it serves load during a Delivery Year.82  As the Commission explained in Duquesne I, this means the departing LSE must pay for all capacity PJM acquired on the LSE’s behalf, up to and

76 Id. P 172.
77 Id.
78 Id. P 176.
79 Id.
80 RAA § 5.1.1.
81 Id. § 5.1.2.
82 Id. §§ 5.1.3(a), 7.2, 7.2A, 11.1-11.3.

PDF page 26

26

including all RPM auctions (PJM’s capacity auctions) in which the LSE’s load forecasts are
included.83
Consequently, under Duquesne I and II, when an LSE exits PJM, it is only required to pay
for capacity PJM has acquired for it up through the last capacity auction in which the LSE’s load forecasts were included.  In Duquesne I, the Commission concluded that these provisions required Duquesne to pay (in the form of Locational Reliability Charges) for all capacity PJM acquired on its behalf up through and including RPM auctions in which its load forecasts were included.84  The Commission also directed PJM “to support reasonable arrangements to permit Duquesne to utilize that capacity in satisfying its reliability obligations to the Midwest ISO or to any other reliability organization.”85

Pursuant to the RAA, a withdrawing load-serving entity must also settle all “202(c)
charges” allocated to it.86  These charges pertain to the costs incurred by certain generation owners in compliance with orders of the Secretary of Energy under FPA section 202(c) to keep otherwise retiring generators operating under declared emergency conditions.  Section 7.2A of the RAA

directs each RAA Party to “pay, as to the loads it serves during a Delivery Year, a 202(c) charge”

83 Duquesne I, 122 FERC ¶ 61,039 at PP 83, 93.
84 Id. P 92.
85 Id. P 93.
86 RAA §§ 5.1.3(a), 7.2A.  Specifically, section 7.2A of the RAA provides: “Each Party shall pay, as to the loads it serves during a Delivery Year, a 202(c) charge for each resource that is (1) directed to maintain operations for resource adequacy purposes for the PJM Region and is not expressly limited to resolve resource adequacy issues in specific Locational Deliverability Area(s) or Zone(s) by order of the Secretary of Energy pursuant to Federal Power Act section 202(c) on or after May 30, 2025, and (2) subject to an agreement between the parties identified in such 202(c) order setting forth a rate for compensation using the formula rate methodology and processes based on the Deactivation Avoidable Cost Credit set forth in Tariff, Part V, sections 114, 115, 116, 118, 118A with refinements to ensure recovery of incurred costs, which may include, but are not limited to, maintenance and necessary repairs, and where any refinements to such formula rate are acknowledged and reviewed by the Independent Market Monitor.  The foregoing 202(c) charge to each Load Serving Entity shall be equal to the monthly aforementioned rate multiplied by each Load Serving Entity’s pro rata share of the sum of the total Daily Unforced Capacity Obligations across all Zones in the PJM Region for all days within the calendar month covered by the relevant Federal Power Act section 202(c) order.”

PDF page 27

27

for certain resources.87  This provision was recently added to the RAA and allocates the costs incurred by generating units directed to remain operational pursuant to emergency orders issued by the U.S. Secretary of Energy under FPA section 202(c).88

b. The Commission Should Be Clear That Any Treatment of RBP
Charges Does Not Undermine The Commission’s Precedents
On Other PJM Contractual Exit Commitments
As explained above, PJM is a voluntary membership organization, and the ability of a member to withdraw upon satisfying its contractual obligations is central to the continued viability of the RTO model and to public utilities’ ability to make long-term decisions in the best interests of their customers.  Those rights depend on clear, enforceable contractual commitments, not after- the-fact efforts to expand withdrawal obligations through generalized claims of cost shifting or administrative convenience.  The RBP Proposal is PJM’s first attempt to add a new long-term financial obligation that would have to be addressed in connection with a Transmission Owner’s withdrawal.  If the Commission concludes that some limited RBP-related exit obligation is necessary to prevent RBP Charges from being shifted to remaining load, it should make equally clear that any such ruling is confined to the specific Tariff language governing RBP Charges and does not disturb the Commission’s existing precedent regarding other PJM contractual exit commitments.  The Commission should not allow this proceeding to become a vehicle for revisiting or diluting the settled principles recognized in Duquesne I and II and related orders, including the absence of any general PJM exit fee and the requirement that withdrawal obligations be grounded in the governing agreements as actually written.

87 Id. § 7.2A (emphasis added).
88 PJM Interconnection, L.L.C., 193 FERC ¶ 61,192 at P 1 (2025) (citing 16 U.S.C. § 824a(c)), order on reh’g, 195 FERC ¶ 61,002 (2026)).

PDF page 28

28

The Commission should furthermore expressly reaffirm that any expansion of a Transmission Owner’s responsibility for charges upon withdrawal accepted in this proceeding is limited to RBP Charges and does not otherwise expand a departing Transmission Owner’s obligations under the TO Agreement, RAA, or PJM Tariff beyond their existing terms, and does not authorize PJM to impose new withdrawal conditions unrelated to the specific RBP Charges allocated pursuant to the cost allocation methodology approved by the Commission in this proceeding.  The Commission should provide that clarity now, before the RBP Proposal imposes new 15-year obligations that could materially affect future RTO transition decisions by Transmission Owners and customers, by requiring that PJM modify its proposal to create a defined, transparent RBP exit fee and by reconfirming the contractual obligations applicable to Transmission Owners withdrawing from PJM, consistent with its past precedents.

B. PJM’s Proposed Cost Allocation Methodology Is Not Just and Reasonable
And Requires Further Development

Given the amount of customer funding the RBP Proposal could require, ensuring a just and reasonable and not unduly discriminatory cost allocation of RBP Charges is of paramount importance.  As proposed, the cost allocation terms included in the RBP Proposal leave key questions unanswered.  First, PJM’s proposed location-based cost allocation methodology is at odds with its decision not to include locational parameters in the RBP.  Second, PJM’s use of a single load forecast as the basis for 15-years of cost allocation is unreasonable absent some allowance for adjustment to allocation over time.  Third, the proposed provisions require further development to ensure that Electric Distributors are not left responsible for an unreasonable allocation of RBP Charges.

PDF page 29

29

1. PJM’s Static Load-Forecast Cost Allocation Is Unjust and
Unreasonable Because It Disconnects Long-Term RBP Charges From
Actual Load Responsibility

PJM proposes to allocate RBP Charges by first imputing the current 6,831.3 MW shortfall to each Electric Distributor zone/area based in part on that zone/area’s forecasted load growth from the 2026/2027 Delivery Year to the 2028/2029 Delivery Year.89  PJM’s proposal to use the forecasted load growth between those Delivery Years to allocate a financial obligation that will run through the 2042/2043 Delivery Year creates a number of problems.  First, PJM’s proposal to allocate costs based on zonal responsibility for its current reliability shortfall is at odds with its concession that there will be no locational element to the RBP.  PJM’s theory that its load forecast is a reliable proxy for where in the PJM region the resource adequacy shortfall exists, paired with its decision not to include a locational element to capacity procurement, creates a fundamental disconnect between the product procured and the allocation of RBP Charges for the product.  For example, load in western PJM may end up paying for significant new generation investments in eastern PJM that ultimately do not benefit that western load, or vice versa.

Second, the temporal mismatch created by the RBP Proposal is independently
unreasonable.  PJM proposes to allocate a 15-year stream of RBP Charges through the 2042/2043 Delivery Year using a single snapshot of relative load growth between the 2026/2027 and 2028/2029 Delivery Years, even though load growth patterns are highly likely to shift materially over that period as large-load projects, interconnection timelines, retirements, and customer commitments change.  PJM acknowledges that it cannot project CETO and CETL 15 years out because it lacks the information needed to determine those locational parameters.  PJM cannot

89 In her affidavit, Ms. Croop explains that the allocation of RBP MWs to each Electric Distributor zone/area will be based on the forecasted load growth from the 2026/2027 Delivery Year to the 2028/2029 Delivery Year and incorporate the Load Adjustments from the 2026 PJM Load Forecast.  See Croop Affidavit ¶ 43.

PDF page 30

30

invoke that uncertainty to avoid locational procurement while simultaneously locking in cost allocation for the full commitment term based on a near-term forecast that it cannot reasonably expect to remain representative.

For these reasons, the cost allocation methodology contemplated by the RBP Proposal is unjust, unreasonable and unduly discriminatory.  The Commission should reject the proposed methodology or, at minimum, direct that PJM implement the necessary corrections and clarifications described in this Protest to ensure that the RBP functions as designed.  This includes, at minimum, a requirement that PJM revise the RBP Proposal to include a mechanism to revisit cost allocation for RBP Charges as the actual load and reliability landscape evolves.

2. PJM’s Cost Allocation Provisions Must be Further Clarified to Avoid
Placing Unreasonable Burdens on Electric Distributors

The proposed provisions governing cost allocation to LSEs—i.e., the parties taking transmission service on behalf of the large load customer in question—require further development to ensure that Electric Distributors are not left responsible for an undue allocation of RBP Charges. Unlike PJM’s allocation of RBP Charges to Electric Distributor areas/zones, which will be set to a fixed amount and assigned by PJM, the proposed allocation of RBP Charges to LSEs is much less definitive, thereby exposing Electric Distributors to risk for assuming unwarranted RBP costs.

According to the RBP Proposal, after PJM allocates RBP Charges to each Electric
Distributor zone/area, those RBP Charges will be further allocated to each LSE based on the LSE’s pro-rata share of the zone’s RBP Obligation.  This allocation depends entirely on actions by parties that neither PJM nor the Electric Distributor can compel.  Although PJM’s proposal nominally places payment obligations on LSEs rather than Electric Distributors, the practical reality is more complex.  The Electric Distributor is the entity responsible for a host of administrative functions that will impact on how costs are allocated among LSEs according to their pro-rata share of their

PDF page 31

31

RBP Obligations.  Should this fail, PJM proposes that it will allocate costs among LSEs in the zone using each LSE’s load ratio share of the Daily Unforced Capacity Obligation for the zone as determined in Schedule 8 of the RAA.  Importantly, PJM’s proposal also does not mention which party bears responsibility if LSEs decide not to pay their allocated share of RBP Charges or if their load commitments shift over time, or if an LSE disputes their previously-allocated share of RBP Charges.  Given that the Electric Distributors zones/areas are assigned a fixed amount of RBP Charges that will be expressly defined by the Tariff, the ambiguities regarding LSEs’ responsibilities for RBP Charges leave Electric Distributors at a significant disadvantage for bearing costs that, by design, should be allocated fairly among responsible LSEs before ultimately being allocated to load.  This outcome would be consistent with both the design of the RBP and the Trump Administration’s Ratepayer Protection Pledge.90

To remedy these deficiencies, the Commission should direct PJM to clarify that the full 15-year RBP financial obligation follows the LSE serving the large-load or data center customer whose load growth gives rise to the RBP responsibility, not the Electric Distributor for the zone/area in which that customer happens to be located.  If the purpose of the RBP is to ensure that new large loads and data centers bear the incremental capacity costs associated with their service, then the legally enforceable obligation should be assigned at the outset to the LSE serving that load and should remain with that service obligation for the full RBP commitment term.  The Tariff should also provide that, if the large-load or data center customer later switches suppliers, the corresponding RBP obligation transfers to the successor LSE serving that same load.  That structure would prevent residual liability from falling on an Electric Distributor merely because

90 THE WHITE HOUSE, Ratepayer Protection Pledge Proclamation (Mar. 4, 2026) https://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ (“Ratepayer Protection Pledge”).

PDF page 32

32

the load is located in its zone/area, while ensuring that the entities serving and receiving revenues from the load remain responsible for the capacity costs caused by that load.

This approach is consistent with PJM’s asserted cost-causation rationale and with the Ratepayer Protection Pledge’s premise that large loads and data centers—not other customers and not the Electric Distributor as a default guarantor—should be responsible for the incremental capacity costs required to serve them.  At a minimum, the Commission should direct PJM to:  (1) expressly state in the Tariff that an Electric Distributor shall have no financial obligation for RBP Charges solely by virtue of defining the zone/area or by reason of a failure to report RBP Obligation MW, and that the obligation to report is ministerial in character—not a condition whose non-fulfillment exposes the Electric Distributor to financial liability for the zone/area’s allocated charges; and (2) provide that Electric Distributors are not held financially liable in a circumstance where an LSE fails to pay its share of, or otherwise disputes its allocation of RBP Charges.

C. PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving
Entities, Not Electric Distributors, Because Credit Responsibility Should
Follow the Entity Responsible for RBP Charges
PJM proposes to require that those LSEs allocated responsibility for RBP Charges for a given Delivery Year must post credit associated with that obligation.  PJM must clarify that collateral obligations attach only to LSEs allocated responsibility for RBP Charges, not to Electric Distributors acting solely in an administrative or delivery-service role.  PJM expressly states that RBP Buyer collateral is intended to protect against the risk that an entity responsible for RBP Charges fails to pay those charges.  This collateral obligation should therefore follow the entity ultimately responsible for the RBP Charge.  Given that LSEs are the parties taking transmission service on behalf of the large loads that have caused the need for the RBP, the burden to acquire collateral should reside with the LSE.

PDF page 33

33

The Commission should direct PJM to clarify that the obligation to post RBP Collateral applies exclusively to LSEs allocated responsibility for RBP Charges and does not attach to an Electric Distributor solely because the applicable load is located within its distribution service territory.  PJM explains that RBP Buyer collateral is intended to mitigate the risk of non-payment of RBP Charges and that only LSEs allocated responsibility for RBP Charges generally will have a credit requirement.  The RBP Proposal therefore appears to recognize that collateral should follow financial responsibility for RBP Charges.  Given the substantial magnitude and long duration of the proposed collateral requirements, however, the Tariff should expressly state that Electric Distributors have no obligation to post RBP Collateral unless they are serving the underlying load in their capacity as an LSE.  Failure to provide such clarification creates unnecessary uncertainty regarding which market participants ultimately bear the financial obligations associated with the RBP framework.

This clarification is also necessary to ensure consistency with the cost-causation principles that PJM invokes throughout the filing.  PJM’s proposed cost allocation methodology is premised on assigning RBP Charges to the LSEs serving the load that gives rise to the resource adequacy need underlying the RBP.  It would therefore be inconsistent and unreasonable to require an Electric Distributor, whose role in the RBP framework is limited to delivery service and administrative reporting of allocations, to provide collateral backing obligations incurred by competitive suppliers serving that load.  This concern is particularly acute in the AEP Ohio Electric Distributor zone/area, where essentially all large-load and data center customers driving forecasted load growth are shopping customers served by competitive retail suppliers acting as LSEs. Requiring AEP Ohio to post collateral for obligations attributable to those suppliers would improperly shift credit risk from the entities serving and benefiting from the load to an Electric

PDF page 34

34

Distributor that neither controls generation supply decisions nor receives the revenues associated with serving that load.  Such a result would be inconsistent with cost-causation principles and should be expressly foreclosed in the Tariff.

The Commission should therefore direct PJM to modify the RBP Tariff language to expressly state that, “RBP Collateral shall be required only of those Load Serving Entities allocated responsibility for RBP Charges pursuant to Attachment DD.  An Electric Distributor shall have no obligation to post RBP Collateral solely by virtue of serving as the Electric Distributor for a zone or area, except to the extent the Electric Distributor is also acting as the Load Serving Entity for the applicable load.”

D. PJM’s Proposal Contains an Error Regarding Fixed Resource Requirement
Entities That Must Be Addressed

The RBP Proposal contains an error that, if the Commission accepts the RBP Proposal, the Commission should direct PJM to amend on compliance.  In RAA, Schedule 8, Article 1, Section D 1.1, PJM proposes language stating that “An FRR Entity may not use an Existing Generation Capacity Resource not owned by such FRR Entity as of June 1, 2027 or any resource committed through the Reliability Backstop Procurement to satisfy its Capacity FRR Plan.”91  This mistake, lacking the ability to use both owned or contracted resources, if accepted, would represent a critical error in the filed rate as applied to FRR Entities.  In conversations with PJM since the RBP Proposal was submitted, PJM has conceded to AEP that this mistake was a simple drafting error. Consequently, PJM must acknowledge this error on the record of this proceeding and commit to fixing it in a compliance filing.

91 RBP Proposal, Attachment B, Clean Tariff Records, RAA, Art. 1 § D 1.1 (emphasis added).

PDF page 35

35

V. CONCLUSION
AEP recognizes that PJM faces a genuine and pressing resource adequacy challenge and does not oppose a carefully tailored one-time backstop procurement designed to address the 2028/2029 BRA shortfall.  That said, the extraordinary speed, cost, and duration of the RBP Proposal require the Commission to scrutinize the proposed terms carefully before customers are exposed to billions of dollars in long-term financial commitments.  As explained in this Protest, the RBP Proposal contains provisions that are unjust, unreasonable, and unduly discriminatory. AEP therefore respectfully requests that the Commission reject those provisions of the RBP Proposal or, at minimum, condition any acceptance of the RBP Proposal on the modifications and clarifications described above.

Specifically, the Commission should:
1. Reject or direct PJM to substantially revise the RBP Proposal’s Transmission Owner exit provisions to:  (a) ensure that a departing Transmission Owner’s financial obligation for RBP Charges is limited to the charges allocated to its zone under PJM’s Commission- accepted RBP cost allocation methodology, subject to reduction by any RBP Settlement Credits, RPM Auction Credits, refunds, offsets, or other credits that would have applied had the load remained in PJM; and (b) make the cost of exiting PJM transparent and readily ascertainable through an objective, pre-determinable formula;

2. Reaffirm the Commission’s established precedent governing RTO exit obligations, and expressly confirm that any RBP exit obligation accepted in this proceeding is confined to RBP Charges and does not disturb, expand, or supersede the contractual exit framework established in Duquesne I and II and related orders, including the absence of any general PJM exit fee;

PDF page 36

36

3. Reject or direct PJM to modify the proposed RBP cost allocation methodology by:  (a) expressly stating that Electric Distributors bear no financial liability for RBP Charges solely by virtue of their administrative role in reporting LSE RBP Obligations; (b) providing that collateral obligations attach exclusively to LSEs allocated responsibility for RBP Charges and not to Electric Distributors acting in a delivery-service or reporting capacity; and (c) adopting a mechanism to revisit cost allocation over the 15-year RBP commitment term as actual load and reliability conditions evolve; and

4. Direct PJM to correct the identified drafting error in RAA, Schedule 8.1.D, Section D.1.1 affecting FRR Entities on compliance, and to acknowledge that error on the record of this proceeding.

These conditions are necessary to ensure that any one-time backstop procurement approved by the Commission addresses PJM’s asserted reliability need without imposing unjust, unreasonable, unduly discriminatory, or insufficiently reviewed long-term costs on AEP, its affiliates, and their customers.

        Respectfully submitted,

/s/ John C. Crespo
John C. Crespo
Senior Legal Counsel
American Electric Power Service Corporation
1 Riverside Plaza
Columbus, Ohio 43215
(614) 716-3727
jccrespo@aep.com

PDF page 37

37

/s/ Christopher R. Jones
Christopher R. Jones
William R. Derasmo
Emily Beard
TROUTMAN PEPPER LOCKE LLP
401 9th Street, NW Suite 1000
Washington, DC
(202) 662-2181
chris.jones@troutman.com
william.derasmo@troutman.com
emily.beard@troutman.com

Counsel for American Electric Power Service Corporation

Dated: August 21, 2026

PDF page 38

CERTIFICATE OF SERVICE

I hereby certify that on this 21st day of August 2026, I have caused a copy of the foregoing document to be served electronically on each person listed on the Secretary’s official service list in the above-referenced proceeding.

/s/ Emily Beard
Emily Beard
TROUTMAN PEPPER LOCKE
401 9th Street, NW Suite 1000
Washington, DC
(202) 274-1949
emily.beard@troutman.com