ER26-3380-000 · 2026-08-21 · American Municipal Power, Inc.

Comments of American Municipal Power, Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
COMMENTS OF
AMERICAN MUNICIPAL POWER, INC.
American Municipal Power, Inc. (“AMP”) hereby provides its comments on the July 31, 2026 filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1 in which PJM proposed revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a Reliability Backstop Procurement (“RBP”) for the PJM region.

The RBP is “a one-time time procurement of new capacity to address resource adequacy challenges in the PJM Region.”2 The mechanism is designed to procure a targeted quantity of capacity under fixed agreements with terms up to fifteen years beginning with the 2028/2029 Delivery Year and ending with the 2042/2043 Delivery Year.3 PJM has set this Initial RBP Target at 6,831.3 MW,4 which may be decremented to account for certain new offsetting capacity (Qualifying RBP Offset UCAP MW), as well as for any qualifying Electric Distributor zone/areas that opt out of procuring capacity through the RBP. While the RBP will procure capacity on an RTO-wide basis, the capacity target (and associated costs) will be allocated to specific Electric Distributor zone/areas

1 PJM, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (July 31, 2026) (“PJM Filing”).
2  PJM Filing, Transmittal Letter at 1.
3 Id. at 8.
4  This quantity (in megawatts (“MW”) of Unforced Capacity (“UCAP”)) is the amount that PJM’s Base Residual Auction for the 2028/2029 Delivery Year cleared short of PJM’s RTO-wide reliability requirement at the price cap of $325/MW-day. Id. at 7.

PDF page 2

2
in PJM, with a further allocation of costs to Load Serving Entities (“LSEs”) located in the zone/areas that receive an allocation.

PJM has effectively confirmed that neither AMP, nor any AMP member, will be allocated any of the costs of procuring the Initial RBP Target (i.e., RBP Charges) under PJM’s proposal, as all AMP members appear to be within zone/areas that do not receive any allocation of the Initial RBP Target. AMP strongly supports PJM’s proposal in this respect, as any allocation of RBP Charges to AMP or its members would be inconsistent with cost causation principles and the Ratepayer Protection Pledge. Because the PJM Filing is potentially ambiguous regarding allocation of the Initial RBP Target among the zone/areas, however, AMP submits these comments to clarify and complete the record. Additionally, PJM’s Filing demonstrates an administrative error with regard to the zone/area definition that PJM should address.

I. COMMENTS
A. PJM appropriately allocates the Initial RBP Target to zone/areas with large load growth documented in forecast load adjustments.

The critical first step in assigning cost responsibility for RBP Charges is PJM’s allocation of the Initial RBP Target, which PJM appropriately proposes to assign “to each Electric Distributor’s zone/area using that zone/area’s pro-rata share of the difference between the forecasted Load Adjustments for the 2026/2027 Delivery Year and the 2028/2029 Delivery Year.”5 In other words, the Initial RBP Target of 6,831.3 MW will be

5  PJM Filing, Attach. A, proposed Tariff, Attachment DD, section 18.3(a).

PDF page 3

3
allocated to those Electric Distributor zone/areas that have provided to PJM projections of large load growth between 2026 and 2028.6

Although there are several more steps in determining ultimate liability for RBP Charges, zone/areas that do not receive any allocation at this first step are effectively excluded from responsibility for RBP Charges. As PJM explains, this allocation framework is consistent with cost causation principles and the Ratepayer Protection Pledge.7

B. PJM should clarify the definition of “zone/area” is the one accepted by
the Commission in Docket No. ER26-2447.
While AMP supports PJM’s proposal to allocate the Initial RBP Target to
zone/areas with large load growth, there appears to be a ministerial issue with the definition of “zone/area” in the PJM Filing. Specifically, the filing includes a definition of zone/area that does not reflect revisions accepted by the Commission in Docket No. ER24-2447.8 In that proceeding, PJM proposed to amend the RAA to add the new defined term “Large Load Adjustment,” which, in turn, included a definition of zone/area.9 In 6

See, e.g., id., Attach. C, Croop Aff. at ¶¶ 41-43; Transmittal Letter at 96-97 (“PJM is proposing to allocate daily RBP Charges to relevant Electric Distributor zones/areas, pro rata, based on the zone/area’s assigned share of the total, region-wide Final RBP Target MW, floored at zero, and in accordance with RAA Schedule 8, as revised in 2024 to incorporate Load Adjustments in equations that ‘specify that load forecasts will be adjusted by zone/area and specifically include a variable for Load Adjustments[.]’”); see id. at 101.

7 See id., Transmittal Letter at 100-108. 8 See PJM Interconnection, L.L.C., 188 FERC ¶ 61,200 (2024), compliance filing accepted, Letter Order, Docket Nos. ER24-2447-002, -003 (May 1, 2025).
9  PJM originally proposed the following definition for Large Load Adjustment: "Large Load Adjustment" shall mean any MW quantity of adjustments to summer peak load at the "zone/area" level and summed by Zone as further detailed in PJM Manuals. For purposes of this definition, a "zone/area" is an area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load MW value. A zone/area is a service area of an Electric Distributor that is a separately identifiable, geographic area bounded by wholesale metering (e.g., the service territory of an operating company of a Transmission Owner). PJM Interconnection, L.L.C., 188 FERC ¶ 61,200 at P 6 (quoting PJM, Intra-PJM Tariffs, RAA Article 1 -- Definitions (48.0.0)).

PDF page 4

4
response to concerns raised by AMP that PJM’s proposed definition of zone/area was potentially ambiguous, the Commission required PJM to revise the definition.10 The Commission also directed PJM to remove the word “Large” from the proposed term “Large Load Adjustment.”11 PJM made the required compliance filing,12 which the Commission accepted in an unreported letter order on May 1, 2025.13

The RAA definitions included in the PJM Filing do not reflect the revised zone/area definition accepted by the Commission; rather, the Filing reflects the definitions for “Large Load Adjustment” and “zone/area” included in PJM’s original filing in Docket No. ER24- 2447.14 Although the PJM Filing appears to utilize the currently effective eTariff version of the RAA definitions,15 the Commission has made clear that the FERC-accepted version of a tariff is the filed rate, even if not reflected in eTariff.16

10 Id. at P 41.
11 Id. at P 42.
12 PJM’s compliance filing proposed the following revised definition of “Load Adjustment:” “Load Adjustment” shall mean any MW quantity of adjustments to summer peak load at the “zone/area” level and summed by Zone as further detailed in PJM Manuals. For purposes of this definition, a “zone/area” is the service area within a Zone for which the relevant Electric Distributor specifies a separate Obligation Peak Load (OPL) MW value that is a separately identifiable, geographic area bounded by wholesale metering (e.g., the service territory of an operating company of a Transmission Owner). PJM, Amendment to Compliance Filing to Clarify Terms Related to Capacity Obligations for Load Adjustments, Docket No. ER24-2447-003, at Attach. A (Dec. 23, 2024). 13 PJM Interconnection, L.L.C., Letter Order, Docket Nos. ER24-2447-002, -003 (May 1, 2025). 14 See PJM Filing, Attach. A, RAA Article 1 – Definitions.
15 See RAA Article 1 – Definitions (55.0.0), https://etariff.ferc.gov/TariffSectionDetails.aspx?tid=1731&sid=373284. The version accepted by the Commission in Docket No. ER24-2447-003 (48.2.0) was accepted on May 1, 2025 to be effective August 21, 2024, but it was superseded effective March 24, 2025 by RAA revisions submitted in Docket No. ER25-1022-000. PJM Interconnection, L.L.C., Letter Order, Docket Nos. ER25-1022-00 (March 4, 2025).
16 Lackawanna Energy Ctr. v. PJM Interconnection, L.L.C., 187 FERC ¶ 61,089, at P 54, order on reh’g,189 FERC ¶ 61,029, at P 28 (2024).

PDF page 5

5
The revisions to the definition of zone/area accepted in Docket No. ER24-2447- 003 were for clarification purposes, and do not appear to materially impact the substantive meaning of the term.17 Given the importance of zone/areas in the RBP Charge allocation framework, however, PJM should specifically address the discrepancy between the definition of zone/area in the PJM Filing and the version accepted by the Commission in Docket No. ER24-2447-003.

C. The PJM Filing is potentially ambiguous regarding the Initial RBP
Target allocation.
Because the allocation of the Initial RBP Target determines the Electric Distributor zone/areas that will be responsible for RBP Charges, clarity is essential regarding which zone/areas are receiving such an allocation, and those that are not.18 Unfortunately, the PJM Filing and related communications leave some ambiguity on this important issue. The affidavit of Danielle Croop accompanying the PJM Filing states that:

the total region-wide Initial RBP Target is allocated to each
Electric Distributor zone/area in accordance with Schedule 8
of the RAA, which was revised in 2024 to incorporate Load
Adjustments
by
Electric
Distributor
zone/area.
More
specifically, the allocation of RBP UCAP MW to specific
Electric Distributor zones/areas will be based on the
forecasted load growth from the 2026/2027 Delivery Year to
the 2028/2029 Delivery Year and incorporate the Load
Adjustments set forth in PJM Table B9b from the 2026 PJM
17  The Commission was principally concerned that, as originally proposed by PJM, “the two-sentence definition of ‘zone/area’ within the definition of Large Load Adjustment is ambiguous because the two sentences could be read together or separately, and it is therefore unclear whether a zone/area must meet both conditions.” PJM Interconnection, L.L.C., 188 FERC ¶ 61,200 at P 41. PJM addressed this concern by making the definition a single sentence. See supra note 12.
18 Cf., Sw. Power Pool, Inc., 182 FERC ¶ 61,100, at P 34 (2023) (explaining that “Section 205 of the FPA and the Commission's regulations require that rates be ‘clearly and specifically’ stated. These requirements ensure that the public has adequate notice of the proposed rate, and that the Commission has an opportunity to evaluate the proposal to ensure that it is just and reasonable and not unduly discriminatory or preferential.” (citation modified)).

PDF page 6

6
Load Forecast to ultimately determine the initial allocated pro-
rata share to each relevant Electric Distributor zone/area.19
The affidavit also includes the following table showing the allocation of the Initial RBP Target:20

Further, PJM provided an additional table as part of an August 10, 2026 stakeholder presentation regarding the RBP process, which appears to confirm the positive allocations to specific zone-areas and added information regarding certain zone/areas that will receive a zero obligation:21

19  PJM Filing, Attach. C, Croop Aff. at ¶ 43 (citing 2026 PJM Load Forecast Report Data Tables, PJM Interconnection, L.L.C., Tab Table B9b (Feb. 2026), https://www.pjm.com/- /media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx [https://perma.cc/SST2- EGUZ]; 2026 PJM Load Forecast Report, PJM Interconnection, L.L.C., 5-6 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf [https://perma.cc/J24E-7CV7] (describing Table B9b results)).
20 Id. ¶ 46.
21  PJM and Charles River Assoc., Reliability Backstop Procurement Execution, at 11 (Aug. 10, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260810/20260810-pjm- and-cra-reliability-backstop-procurement-presentation.pdf.

PDF page 7

7
These tables account for the entire Initial RBP Target of 6,831.3 MW to be allocated across fourteen zone/areas, and the latter table notes fifteen other zone/areas specifically identified as receiving an allocation of zero. PJM has, however, pointed to its PJM Long-Term Load Forecast EDC/LSE Submission Template as containing the definitive list of zone/areas within PJM, and there are 160 listed.22 PJM’s specific identification of the Initial RBP Target allocation of zero for some, but not all, zone/areas in the table above (aside from those receiving an Initial Share of RBP Charges) creates

22 See PJM Large Load adjustment request template, Zone-Areas tab, https://www.pjm.com/- /media/DotCom/committees-groups/subcommittees/las/postings/large-load-adjustment-request- template-2027-load-forecast.xlsx (attached hereto as Exhibit A).

PDF page 8

8
potential confusion as to the treatment of zone/areas that should have an allocation of zero but are not listed.

Each of AMP’s members in PJM23 operates an electric distribution system for which the relevant Electric Distributor specifies (or could specify) a separate Obligation Peak Load, and is located within a separately identifiable, geographic area bounded by wholesale metering (i.e., each should qualify as a potential zone/area). PJM has confirmed that only the zone/areas identified as receiving an Initial Share of RBP Charges in the tables above will face RBP Charges, and that RBP Charges will not be shifted from one zone/area to another. None of AMP’s members appear to be situated within zone/areas to which PJM is allocating any portion of the Initial RBP Target, and therefore none should bear any RBP Charges. Given the potential ambiguity on this issue, however, these comments are intended to ensure the record is clear regarding the treatment of AMP and its members for purposes of the Initial RBP Target allocation. 23  Including AMP member Delaware Municipal Electric Corporation’s individual members.

PDF page 9

9
II. CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. submits its comments in this proceeding and asks that the Commission consider them in acting on the PJM Filing.

Respectfully submitted,
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com
Dated: August 21, 2026
/s/ Gerit F. Hull
Lisa G. McAlister
Senior Vice President & General Counsel
Gerit F. Hull
Deputy General Counsel for Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
lmcalister@amppartners.org
ghull@amppartners.org

PDF page 10

Exhibit A
PJM Long-Term Load Forecast EDC/LSE Submission Template Zone-Areas Tab

PDF page 11

Zone/Areas defined in Capacity Exchange. This list was culled the posted Daily Zonal Scaling Factor file ZONENAME AREANAME

AECO
AECO
AECO
VINELAND
AEP
AEP_INDIANA
AEP
AEP_MICHIGAN
AEP
AEPOHIO
AEP
AMPO
AEP
ANDERFRANK
AEP
APCO
AEP
AUBURN
AEP
AVILLA
AEP
BEDFORD
AEP
BLUFFTON
AEP
BUCKEYE
AEP
CBEC
AEP
COLUMBUS
AEP
CVEC
AEP
DANVILLE
AEP
DOWAGIAC
AEP
ELK
AEP
GARRETT
AEP
GLOUSTER
AEP
HOOSIER
AEP
IM
AEP
IMP_FIRM_SALE
AEP
KPCO
AEP
MARTINSVILLE
AEP
MIDWEST
AEP
MISHAWAKA
AEP
NEWCARLISLE
AEP
NILES
AEP
NORTHEAST
AEP
ODEC
AEP
OLIVE
AEP
OMEG
AEP
PAWPAW
AEP
RADFORD
AEP
RICHLANDS
AEP
ROCKPORT
AEP
SALEM
AEP
SHELBY
AEP
SOUTHHAVEN
AEP
STCLAIRSVILLE
AEP
STURGIS
AEP
VANCE
AEP
VATECH
AEP
WABASH
AEP
WABASH_AEP
AEP
WABASHSDI

PDF page 12

AEP
WAPAKONETA
AEP
WAPAKONETA2
AEP
WAPAKONETA3
AEP
WARREN
AEP
WESTERVILLE
AEP
WHEELING
AEP
WVP
APS
AP_AECI
APS
AP_ODEC
APS
CHAMBERSBURG
APS
FRONTROYAL
APS
HAGERSTOWN
APS
HREA
APS
LETTERKENNY
APS
MON_POWER
APS
MONTALTO
APS
NEWMARTINSVILLE
APS
PE
APS
PHILIPPI
APS
TARENTUM
APS
THURMONT
APS
WILLIAMSPORT
APS
WPP
ATSI
AMPO
ATSI
BUCKEYE
ATSI
BUCKFE
ATSI
CPP
ATSI
OHIO
ATSI
PP
BGE
BGE
COMED
BATAVIA
COMED
COMED
COMED
GENEVA
COMED
NAPERVILLE
COMED
ROCHELLE
COMED
ROCKFALLS
COMED
STCHARLES
COMED
WINNETKA
DAY
AMPO
DAY
BUCKEYE
DAY
DAY
DEOK
BETHEL
DEOK
BLANCHESTER
DEOK
BUCKCIN
DEOK
DEK
DEOK
DEOK
DEOK
EKPC
DEOK
GEORGETOWN
DEOK
HAMERSVILLE
DEOK
HAMILTON

PDF page 13

DEOK
LEBANON
DEOK
RIPLEY
DEOK
WILLIAMSTOWN
DOM
CVEC
DOM
DOM
DOM
NCEMC
DOM
NVEC
DOM
ODEC
DOM
REC
DOM
SEPA
DPL
DOVER
DPL
DPL
DPL
DPL_BERLIN
DPL
DPL_DEMEC
DPL
DPL_EASTON
DPL
DPL_LEWES
DPL
DPL_ODEC
DUQ
DUQ
DUQ
PITCAIRN
EKPC
EKPC
EKPC
LONGBRANCH
JCPL
BUTLER
JCPL
JCPL
JCPL
JCPL_AECI
JCPL
LAVALETTE
JCPL
MADISON
JCPL
PEMBERTON
JCPL
SEASIDEHTS
METED
GOLDSBORO
METED
KUTZTOWN
METED
LEWISBERRY
METED
METED
METED
METED_AECI
METED
MIDDLETOWN
METED
ROYALTON
OVEC
OVEC
PECO
PECO
PENELEC
EASTCONEMAUGH
PENELEC
GIRARD
PENELEC
HOOVERSVILLE
PENELEC
PENELEC
PENELEC
PENELEC_AECI
PENELEC
PENELEC_BERLIN
PENELEC
SMETHPORT
PENELEC
SUMMERHILL
PENELEC
WELLSBORO
PEPCO
PEPCO
PEPCO
SMECO
PPL
CITIZENS_ELECTRIC
PPL
EPHRATA

PDF page 14

PPL
OLYPHANT
PPL
PERKASIE
PPL
PPL
PPL
PPL_AECI
PPL
PPL_MUNIS
PPL
PPL_UTILITIES
PPL
UGI
PSEG
MILLTOWN
PSEG
PARKRIDGE
PSEG
PSEG
PSEG
SOUTHRIVER
RECO
RECO

PDF page 15

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 21st day of August, 2026.

/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com