ER26-3380-000 · 2026-08-21 · American Municipal Power, Inc.

Comments of American Municipal Power, Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing

Text extracted from the eLibrary original (SHA-256 9f464a52a820ddad…). Download the original from the official source.

Contents · 5 sections
  1. I. COMMENTS p. 2
  2. A. PJM appropriately allocates the Initial RBP Target to zone/areas with p. 2
  3. B. PJM should clarify the definition of “zone/area” is the one accepted by p. 3
  4. C. The PJM Filing is potentially ambiguous regarding the Initial RBP p. 5
  5. II. CONCLUSION p. 9

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

AMP strongly supports PJM’s proposal in this respect, as any allocation of RBP Charges to AMP or its members would be inconsistent with cost causation principles and the Ratepayer Protection Pledge.
Read this passage Filed comments: Cost allocation

I. COMMENTS

printed heading

I.
Read this passage

A. PJM appropriately allocates the Initial RBP Target to zone/areas with

printed heading · Topic match: Cost allocation

The critical first step in assigning cost responsibility for RBP Charges is PJM’s allocation of the Initial RBP Target, which PJM appropriately proposes to assign “to each Electric Distributor’s zone/area using that zone/area’s pro-rata share of the difference between the forecasted Load…
Read this passage Filed comments: Cost allocation

B. PJM should clarify the definition of “zone/area” is the one accepted by

printed heading · Topic match: Cost allocation

ER24-2447-002, -003 (May 1, 2025). 9 PJM originally proposed the following definition for Large Load Adjustment: "Large Load Adjustment" shall mean any MW quantity of adjustments to summer peak load at the "zone/area" level and summed by Zone as further detailed in PJM Manuals.
Read this passage Filed comments: Cost allocation

C. The PJM Filing is potentially ambiguous regarding the Initial RBP

printed heading · Topic match: Cost allocation

PJM has confirmed that only the zone/areas identified as receiving an Initial Share of RBP Charges in the tables above will face RBP Charges, and that RBP Charges will not be shifted from one zone/area to another.
Read this passage Filed comments: Cost allocation

II. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. submits its comments in this proceeding and asks that the Commission consider them in acting on the PJM Filing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 21st day of August, 2026. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.com