Protest of the Pennsylvania Office of Consumer Advocate to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal
The Pennsylvania Office of Consumer Advocate protests PJM's Reliability Backstop Procurement filing, arguing that states lack jurisdiction to set the method that allocates backstop obligations to load serving entities and that FERC must resolve the gap.
Asks FERC to: Reject PJM's state-determined allocation of backstop obligations, declare FERC jurisdiction over those methods, and require transmission owners to file Attachment M-2 amendments defining them.
Protest in PJM's separate backstop docket ER26-3380 on who pays for capacity added for large loads, a cost-shifting concern that mirrors the E-7 cost-recovery agreement directive and the adequacy report topic.
E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- Pennsylvania OCA says PJM's filing creates a one-time procurement of new capacity driven mainly by data center load.
a one-time procurement of new capacity to address resource adequacy challenges in the PJM Region arising from insufficient commitments of capacity in the 2027/2028 and 2028/2029 Reliability Pricing Model (RPM) Auctions PDF p. 3
- FERC, not the states, has jurisdiction over the methods that set peak load contribution values used to allocate capacity costs.
FERC possesses—and states lack—jurisdiction to determine or approve the methods that are used to develop peak load contribution (PLC) and network service PDF p. 3
- PJM's plan to let states set backstop obligation values is called unjust and unreasonable because states would need jurisdiction they lack.
PJM’s proposal is unjust and unreasonable because for states to determine the RBO values, they would have to determine and approve methods for RBO PLCs—and the states lack jurisdiction to do so. PDF p. 4
- If no state method is reported, PJM's fallback is pro rata allocation, which OCA says would charge non-large-load customers.
pro rata RBP cost allocation to LSEs using PLC values is unjust and unreasonable because it will likely result in non-large load customers being allocated RBP costs, despite these ratepayers not having caused the costs. PDF p. 6
- OCA lays out three relief options and recommends the first: FERC exercises jurisdiction and orders mandatory Attachment M-2 filings.
FERC should grant the first relief option by finding that PJM’s RBO cost allocation proposal is unjust and unreasonable, exercising jurisdiction over how RBO costs are allocated to LSEs, and directing all transmission owners to make mandatory Attachment M-2 filings PDF p. 5
Contents · 16 sections
- IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value
- A. PJM’s proposal to have states determine the RBO methods for addressing cost
- B. There is time to get cost allocation right – by the time cost allocation comes due for
- D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO
- I. Introduction
- II. Executive Summary
- III. Summary of Cost Allocation Portion of PJM’s Tariff Filing
- IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value Methodologies
- A. NSPL Determinations for Transmission Costs Allocations to LSEs
- B. PLC Determinations for Capacity Cost Allocations to LSEs
- V. Argument
- A. PJM’s proposal to have states determine the RBO methods for addressing cost
- B. There is time to get cost allocation right – by the time cost allocation comes
- C. Potential Relief Options
- D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO
- VI. Conclusion
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Registry access · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
ER26-3380-000 PROTEST OF THE PENNSYLVANIA OFFICE OF CONSUMER ADVOCATE RE: RELIABILITY BACKSTOP PROCUREMENT TO ADDRESS RESOURCE ADEQUACY CONCERNS STEMMING FROM NEW LOAD ADJUSTMENTS August 21, 2026 iRead this passage Filed comments: Registry access
Table of Contents
printed heading · Topic match: Cost allocation
Table of Contents I.Read this passage Filed comments: Cost allocation
IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value
printed heading · Topic match: Cost allocation
IV.Read this passage Filed comments: Cost allocation
A. PJM’s proposal to have states determine the RBO methods for addressing cost
printed heading
PJM’s proposal to have states determine the RBO methods for addressing cost allocation of RBP costs is unjust and unreasonable because it presents a jurisdictional problem that FERC must address. ............................................................................................ 14Read this passage
B. There is time to get cost allocation right – by the time cost allocation comes due for
printed heading · Topic match: Cost allocation
B.Read this passage Filed comments: Cost allocation
D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO
printed heading
D.Read this passage
I. Introduction
printed heading · Topic match: Cost allocation
The PA OCA represents the interests of Pennsylvania utility consumers or ratepayers before FERC.2 “Ratepayers” refers to the millions of retail end users that are served by the PJM grid.Read this passage Filed comments: Cost allocation
II. Executive Summary
printed heading · Topic match: Cost allocation
Despite FERC’s longstanding exercise of authority over PLC and NSPL value determinations, PJM proposes in its RBP filing to address cost allocation of RBP obligations through “state and/or [state utility commission]- determined allocation of RBP UCAP MW to LSEs within each zone/area.” PJM defines…Read this passage Filed comments: Cost allocation
III. Summary of Cost Allocation Portion of PJM’s Tariff Filing
printed heading · Topic match: Cost allocation
Summary of Cost Allocation Portion of PJM’s Tariff Filing In its filing, PJM proposes that the states or state utility commissions (PJM refers to state utility commissions as the “Relevant Electric Retail Regulatory Authority” or “RERRA”)3 determine allocation of cleared RBP unforced capacity…Read this passage Filed comments: Cost allocation
IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value Methodologies
printed heading
Each EDC in PJM must then allocate a share of its PJM-assigned peak load to each customer on its system and aggregate these peak loads to the LSE level.Read this passage
A. NSPL Determinations for Transmission Costs Allocations to LSEs
printed heading · Topic match: Cost allocation
Corp.,11 FERC found that it has jurisdiction over determining NSPL methods and, ultimately, the NSPL values assigned to individual retail customers for purposes of PJM allocating transmission costs to LSEs, as follows: As an initial matter, we find that the Commission has jurisdiction over the…Read this passage Filed comments: Cost allocation
B. PLC Determinations for Capacity Cost Allocations to LSEs
printed heading · Topic match: Cost allocation
Each EDC in PJM must then allocate a share of its PJM-assigned peak load to each customer on its system and aggregate these 21 See 2020 Amtrak, 171 FERC ¶ 61,237, at P 34 (2020) (noting that “many transmission owners have filed their methodologies for determining both capacity and [NSPL]…Read this passage Filed comments: Cost allocation
V. Argument
printed heading
V.Read this passage
A. PJM’s proposal to have states determine the RBO methods for addressing cost
printed heading · Topic match: Cost allocation
PJM’s proposal to have states determine the RBO methods for addressing cost allocation of RBP costs is unjust and unreasonable because it presents a jurisdictional problem that FERC must address.Read this passage Filed comments: Cost allocation
B. There is time to get cost allocation right – by the time cost allocation comes
printed heading · Topic match: Cost allocation
There is time to get cost allocation right – by the time cost allocation comes due for the first Delivery Year in which RBP Resources are expected to be in service (i.e., 2028/2029).Read this passage Filed comments: Cost allocation
C. Potential Relief Options
printed heading · Topic match: Cost allocation
Importantly, if FERC decides that the RBO value methodology used by PJM for RBP cost allocation is distinguishable from the PLC/NSPL value methodologies used for capacity/transmission cost allocation, FERC must expressly declare that states have jurisdiction over the RBO methods.Read this passage Filed comments: Cost allocation
D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO
printed heading · Topic match: Retail and wholesale authority
Comm’n 2020), https://www.puc.pa.gov/pcdocs/1687575.docx. 45 PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 1 (2012); PJM Interconnection, L.L.C., 144 FERC ¶ 63,011, at P 24 (2013) (“[t]he primary issue underlying the Partial Settlement [was] whether Attachments M-1 and M-2 are just and…Read this passage Filed comments: Retail and wholesale authority
VI. Conclusion
printed heading · Topic match: Cost allocation
As compared to Figure 1 and Figure 2 – where assignment of MWs is subject to federal jurisdiction per Amtrak v PPL – PJM now proposes to have states establish this method.Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading · Topic match: Registry access
Harrisburg, Pennsylvania; August 21, 2026. /s/ Josiah Harmar Josiah Harmar Assistant Consumer Advocate PA Attorney ID # 338426 JHarmar@paoca.orgRead this passage Filed comments: Registry access