ER26-3380-000 · 2026-08-21 · Pennsylvania Office of Consumer Advocate

Protest of the Pennsylvania Office of Consumer Advocate to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)

Docket No. ER26-3380-000

PROTEST OF
THE PENNSYLVANIA OFFICE OF CONSUMER ADVOCATE

RE: RELIABILITY BACKSTOP PROCUREMENT TO ADDRESS RESOURCE ADEQUACY CONCERNS STEMMING FROM NEW LOAD ADJUSTMENTS

August 21, 2026

PDF page 2

i

Table of Contents

I. Introduction … 1
II. Executive Summary … 1
III. Summary of Cost Allocation Portion of PJM’s Tariff Filing … 4
IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value
Methodologies … 8
A. NSPL Determinations for Transmission Costs Allocations to LSEs … 10
B. PLC Determinations for Capacity Cost Allocations to LSEs … 11
V. Argument … 14
A. PJM’s proposal to have states determine the RBO methods for addressing cost
allocation of RBP costs is unjust and unreasonable because it presents a jurisdictional
problem that FERC must address … 14
B. There is time to get cost allocation right – by the time cost allocation comes due for
the first Delivery Year in which RBP Resources are expected to be in service (i.e.,
2028/2029) … 17
C. Potential Relief Options … 17
1. Option 1: Recognize and exercise exclusive jurisdiction over RBO value
methodologies; FERC can declare its exclusive jurisdiction over determining the RBO
methods and require jurisdictional transmission owners to make additional tariff filings
that propose RBO methods for their transmission zones within PJM … 17
2. Option 2: Relinquish exclusive jurisdiction over PLC methodologies; FERC can
declare that states have exclusive jurisdiction to determine PLC and NSPL methods,
and by extension the proposed RBO method, and require Electric Distributors that are
signatories to the RAA to report them to PJM … 19
3. Option 3: Establish a new jurisdictional category for PLC methodologies for
RBOs; FERC can legally distinguish PJM’s proposal for state utility commissions to
determine the RBO method from the PLC and NSPL methods and declare that state
utility commissions have exclusive jurisdiction to determine and approve the methods
for determining RBO values for purposes of PJM cost allocation of RBP obligations to
LSEs … 22
D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO
methods and requiring each transmission owner to file Attachment M-2 amendments
containing their proposed RBO method … 22
VI. Conclusion … 25

Appendix A

PDF page 3

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

)
)
)
)
)

Docket No. ER26-3380-000

I. Introduction
Before the Federal Energy Regulatory Commission (FERC or Commission), the
Pennsylvania Office of Consumer Advocate (PA OCA) files this Protest in response to the PJM Interconnection L.L.C.’s (PJM’s) July 31, 2026, Federal Power Act (FPA) Section 205 filing containing revisions to the PJM Open Access Transmission Tariff (Tariff) and the Reliability Assurance Agreement Among Load Serving Entities (RAA) to establish the Reliability Backstop Procurement (RBP)1—a one-time procurement of new capacity to address resource adequacy challenges in the PJM Region arising from insufficient commitments of capacity in the 2027/2028 and 2028/2029 Reliability Pricing Model (RPM) Auctions, primarily driven by the unprecedented addition of large loads, most notably data centers.

The PA OCA represents the interests of Pennsylvania utility consumers or ratepayers before FERC.2 “Ratepayers” refers to the millions of retail end users that are served by the PJM grid.

II. Executive Summary
Under FERC precedent, FERC possesses—and states lack—jurisdiction to determine or approve the methods that are used to develop peak load contribution (PLC) and network service

1 Reliability Backstop Procurement to Address Resource Adequacy and Large Loads, PJM Interconnection, L.L.C., Docket

No.
ER26-3380
(July
31,
2026)
(PJM
RBP
Filing),
https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260731-5214.
2 71 P.S. § 309-4.

PDF page 4

2

peak load (NSPL) values, which PJM uses for allocating capacity and transmission costs, respectively, to load serving entities (LSEs) within the PJM Region. Despite FERC’s longstanding exercise of authority over PLC and NSPL value determinations, PJM proposes in its RBP filing to address cost allocation of RBP obligations through “state and/or [state utility commission]- determined allocation of RBP UCAP MW to LSEs within each zone/area.” PJM defines the allocation of MW made through this method as a new term, an LSE’s “RBP Obligation” or “RBO.” PJM’s proposal is unjust and unreasonable because for states to determine the RBO values, they would have to determine and approve methods for RBO PLCs—and the states lack jurisdiction to do so. FERC must address this jurisdictional problem by rejecting PJM’s proposal for the allocation of RBO MWs and costs. And FERC must mandate an alternative that either maintains, or expressly—with a reasoned explanation—re-delineates the current jurisdictional boundary concerning PLC determination and approval. FERC can establish legally durable jurisdictional clarity, as follows:

Recognize and exercise exclusive jurisdiction over RBO value methodologies. FERC could (a) declare FERC’s exclusive jurisdiction to evaluate and approve RBO value methodologies, (b) determine PJM’s cost allocation proposal for RBP obligations is unjust and unreasonable because it unlawfully delegates the establishment of RBO methodologies to states,

(c) require jurisdictional transmission owners within PJM to submit additional filings based on this docket to further define the methods they will use to determine individual customers’ RBO values within each transmission owner zone, (d) mandate that all PJM transmission owners–including those that have not yet filed Attachment M-2s to the PJM OATT—make Section 205 tariff filings for the RBO value methodologies in Attachment M-2s, and (e) set a time frame to resolve protests and comments to the transmission owners’ tariff filings regarding the RBO methodologies;

PDF page 5

3

Relinquish exclusive jurisdiction over PLC methodologies. FERC could (a) reverse its prior decisions that appear to establish FERC’s exclusive jurisdiction over determining PLC methods and jurisdictionally analogous NSPL methods, (b) declare that states or state utility commissions have exclusive jurisdiction to determine and approve the PLC and analogous NSPL methods, and by extension the RBO method, and (c) mandate Electric Distributors that are signatories to the RAA to report the state or state utility commission-approved PLC/NSPL/RBO methodologies to PJM as necessary inputs into PJM’s cost allocation methods used for wholesale capacity costs and transmission costs; or

Establish a new jurisdictional category for PLC methodologies for RBOs. FERC could
(a) legally distinguish PJM’s proposal for state utility commissions to determine the RBO method from FERC’s jurisdiction over the PLC and analogous NSPL methods, and (b) declare that state utility commissions have exclusive jurisdiction to determine and approve the methods for determining RBO values for purposes of PJM cost allocation of RBP obligations to LSEs. For the reasons explained below, FERC should grant the first relief option by finding that PJM’s RBO cost allocation proposal is unjust and unreasonable, exercising jurisdiction over how RBO costs are allocated to LSEs, and directing all transmission owners to make mandatory Attachment M-2 filings that define their RBO allocation methodologies. Regarding jurisdiction, the RBO method is indistinguishable from the PLC and analogous NSPL methods that are currently under FERC jurisdiction. Importantly, if FERC decides that the RBO value methodology used by PJM for RBP cost allocation is somehow distinguishable from the PLC/NSPL value methodologies used for capacity/transmission cost allocation, FERC would have to expressly declare that states have jurisdiction over the RBO methods. Further, FERC would

PDF page 6

4

have to offer a reasoned explanation for departing from its prior interpretations of the FPA in analogous contexts.

If FERC does not expressly identify a clear jurisdictional path forward, state utility commissions could find that they lack authority to determine the RBO methods. This would result in regulatory confusion or worse—yearslong litigation over the RBO method. Without expressly defined jurisdictional roles, the result will be to default to PJM’s backup plan, which is to allocate RBP costs to all LSEs PJM-wide on a pro rata basis using existing PLC methods. However, pro rata RBP cost allocation to LSEs using PLC values is unjust and unreasonable because it will likely result in non-large load customers being allocated RBP costs, despite these ratepayers not having caused the costs.

III. Summary of Cost Allocation Portion of PJM’s Tariff Filing
In its filing, PJM proposes that the states or state utility commissions (PJM refers to state utility commissions as the “Relevant Electric Retail Regulatory Authority” or “RERRA”)3 determine allocation of cleared RBP unforced capacity (UCAP) megawatts (MW) to LSEs, through the RBO methods, within each Electric Distributor’s zone/area, as reported by each Electric Distributor to PJM. If the Electric Distributors do not report the RERRA-approved RBO methods to PJM, PJM proposes to allocate RBP costs to LSEs using existing FERC-approved PLC values within the relevant transmission zone.

More specifically, PJM proposes the following as to cost allocation:
PJM is proposing that cost allocation to LSEs within an Electric
Distributor’s zone/area be based on “the state and/or RERRA-determined
allocation of cleared RBP UCAP MW to LSEs within each Electric Distributor’s
zone/area, as reported by each Electric Distributor to [PJM].” PJM has thus created

3 PJM RBP Tariff Filing at 174 (defining “Relevant Electric Retail Regulatory Authority” or “RERRA” according to its definition in PJM’s Operating Agreement); PJM, Intra-PJM Tariffs, OA § 1 (defining “Relevant Electric Retail Regulatory Authority” as “an entity that has jurisdiction over and establishes prices and policies for competition for providers of retail electric service to end-customers, such as the city council for a municipal utility, the governing board of a cooperative utility, the state public utility commission or any other such entity.”).

PDF page 7

5

a new defined term, the “RBP Obligation” or “RBO”, to refer to this state and/or RERRA-determined allocation of RBP UCAP MW to LSEs within each zone/area. The RBO is flexible. For example, it permits states and/or RERRAs to rely on their own, disparate definitions of data centers and large loads, and to determine which retail customers should be allocated RBP Charges, generally. PJM’s authority over wholesale markets does not extend to dictating the allocation of costs to retail load, data centers and other large loads and, for purposes of cost allocation to such data centers and other large loads, each state and/or RERRA may have its own methodology, developed in accordance with its unique needs and considerations. PJM’s proposal requires that Electric Distributors report, to PJM, the state and/or RERRA-determined allocations of RBP UCAP MW to LSEs in their zone(s)/area(s). To the extent that Electric Distributors report RBOs, the RBP Charge assessed daily to an LSE in the relevant zone/area will equal the LSE’s daily reported RBO MW in the zone/area divided by the total daily RBO MW in the zone/area, and multiplied by the total, daily RBP Charges allocated to the zone/area. In the unexpected event that RBOs are ultimately not reported to PJM, PJM will still need to proceed with settlement of the RBP Charges. In this case, PJM will rely on a back-up cost allocation methodology to determine allocation to LSEs. PJM’s back-up methodology applies PJM’s status quo method for allocating capacity costs pursuant to RAA, Schedule 8, which incorporates Load Adjustments for purposes of allocating capacity costs to LSEs. In other words, if no allocation is reported by the relevant Electric Distributors with allocated RBP UCAP MW, PJM will allocate RBP Charges based on the Peak Load Contribution submitted to PJM for the LSEs in the relevant zone/area.

Importantly, PJM is not proposing a backup methodology for how RBP Charges should be allocated to non-jurisdictional, retail customers served by each of the LSEs in any Electric Distributor’s zone/area. Even if Electric Distributors do not report any state and/or RERRA-determined RBOs in their zone(s)/area(s), and even if PJM subsequently applies the status quo allocation methodology to PJM’s LSE customers, PJM would not, under the proposed methodology, determine any further allocation to retail customers served by those LSEs.

PJM and the PJM states and/or RERRAs must cooperate to ultimately
allocate wholesale costs to end use, retail customers. In the Commission’s 2007 order on rehearing affirming its finding that PJM’s RPM market design was just and reasonable, the Commission noted that the “question of jurisdiction over resource adequacy is a complex matter that stands at ‘the confluence of state-federal jurisdiction.’” The proposed RBP methodology recognizes and respects this division of responsibility. While it is within PJM’s purview to allocate the costs of RBP Resources to LSEs, who are customers of PJM, the Commission has also recognized that it is beyond the scope of PJM’s authority to “address how LSEs [will subsequently] bill retail customers for such charges” as doing so would affect the “ability [of the PJM states and/or RERRAs] to allocate such charges.” Thus, PJM’s proposed methodology for allocating RBP Charges sets the table for states

PDF page 8

6

and/or RERRAs, by empowering them to make decisions about how to best further allocate RBP Charges to data centers and other retail customers.4 PJM explains why it believes its cost allocation proposal is just and reasonable.5 It continues by stating that its proposal recognizes that allocation to retail customers, including data centers, is within the state utility commission’s purview.6 Specifically, PJM states: The proposed cost allocation methodology assigns RBP costs in a manner that respects the balance of authority between states, the Commission, and PJM. Even in its infancy, the RPM required that the Commission “recognize the traditional role of state and local entities in regulating resource adequacy” while also remaining “aware of [its] responsibilities under the FPA to ensure that adequate service is provided, and that wholesale rates are just and reasonable.” Thus, the Commission found that the appropriate course of action was to “defer to state and local entities’ decisions when possible on resource adequacy matters, but in doing so . . . not shirk our congressionally-mandated responsibilities.” First, the proposed cost allocation methodology empowers states and/or RERRAs to submit RBP RBOs, which PJM would then apply to the allocation of RBP Charges to LSEs. However, under the proposed allocation framework, PJM would retain a back-up methodology for allocated RBP Charges to LSEs, which would apply if no RBOs are reported for a particular zone/area. PJM’s proposed Tariff language expressly provides states and/or RERRAs with the opportunity, within PJM’s proposed cost allocation framework, to submit state-determined RBOs. This back up cost allocation methodology is needed, because if no RBOs are reported for a particular zone/area, PJM would still need to allocate the RBP costs in a manner that is just and reasonable.

PJM’s approach finds support in the Commission’s 2025 order accepting Midcontinent Independent System Operator, Inc.’s (“MISO”) Revised Expedited Resource Addition Study (“ERAS”) Proposal. In that matter, Commission found that RERRA participation in the ERAS process was permissible and not an improper delegation of federal authority to the states, as the participation of RERRA:

would be wholly pursuant to a Commission-jurisdictional process . . . proposed by MISO and approved by the Commission—not by

state authorities—and under which a [Generator Interconnection
Procedure] is on file with the Commission and any future revisions would be subject to Commission approval. Further, the ERAS

process would remain subject to the Commission’s authority

4 PJM RBP Transmittal Letter at 97-100 (citations omitted).
5 Id. at 100-04.
6 Id. at 104-08.

PDF page 9

7

pursuant to FPA sections 205 and 206. In contrast, in Talen, the
Maryland Commission established a state program that operated
outside a Commission-jurisdictional process and “interfered” with the Commission’s authority to establish interstate wholesale rates. Similarly, if accepted, PJM’s proposed cost allocation methodology would be set forth expressly in its Tariff, approved by and on file with the Commission. The Tariff would expressly permit states and/or RERRAs to participate in the cost allocation of RBP costs to LSEs by reporting RBOs, which would supplant PJM’s backup allocation methodology of RBP Charges to LSEs. Like MISO’s Revised ERAS Proposal, the proposed cost allocation methodology would nevertheless remain subject to the Commission’s authority pursuant to FPA sections 205 and 206.

Second, PJM’s proposed cost allocation methodology hews closely to the Commission’s most recent articulation of where the boundary between state/RERRA and federal jurisdiction exists with respect to large loads. Namely, while noting concerns “about the impact that large load additions can have on retail ratepayers, particularly the concern that other retail ratepayers may be forced to subsidize Network Upgrades needed to add large loads to the transmission system[,]” the Commission found that, in this realm, the scope of its regulatory authority is limited. “Specifically,” it is the PJM states that “have authority over how the wholesale costs of providing electricity, including transmission of such electricity, to those retail customers are recovered through retail rates.” PJM’s cost allocation framework recognizes the need to protect retail ratepayers from subsidizing new capacity procured to serve large loads while also recognizing PJM’s own jurisdictional limitations. As the Commission has found, it is the PJM states and/or RERRAs that have authority over how wholesale costs of these new capacity resources are recovered from retail customers through retail rates. In fact, PJM does not have a line of sight into the retail load and end-use customers served by each relevant LSE. PJM also recognizes that states may each define “large loads” and “data centers” differently. Thus, cost allocation methodology that provides PJM states and/or RERRAs with the ability to determine the specific RBOs that should be assigned to LSEs, as well as to cost allocate to end-use customers in their respective states in accordance with their laws and policies, supports the NEDC/PJM Governors’ Principles, which include the principle that the cost of new capacity should be allocated to data centers who have caused the need for additional capacity in the PJM Region.

Third, PJM’s proposed framework is pragmatic. In the short time remaining before the September 30, 2026 RBP, it would simply be infeasible for PJM to obtain detailed information about the large loads and the various LSEs serving such large loads from every state and RERRA in the PJM Region. States and RERRAs are simply in a better position to identify and cost allocate RBP Charges to large loads, including data centers, and the LSEs that serve them. States and RERRAs have granular information about large loads within their borders. Accordingly, PJM’s

PDF page 10

8

proposed cost allocation methodology deliberately leaves states and RERRAs with the flexibility to protect their own customers by allocating the costs of the procurement accordingly. Furthermore, PJM’s proposal recognizes that state laws on the allocation of capacity costs to large loads, including data centers, are evolving. The proposal recognizes and relies on the pledges of the 13 governors of the PJM states to “[u]se all available authorities to ensure that their state public utility commissions design rate class structures to ensure that their states’ LSEs allocate their share of the cost to procure new capacity through the . . . [a]uctions to new data center loads that have not otherwise procured capacity or agreed to be curtailable.” However, to the extent that states and/or RERRAs do not provide such information, PJM will rely on Commission-approved cost allocation methodologies in place today to properly allocate costs to Electric Distributor zones/areas and LSEs.

The proposed methodology addresses the consumer protection goals that
have been raised by the National Energy Dominance Council, PJM’s 13 state governors, and other state and federal entities, while heeding the Commission’s recent articulation of the boundary between state and federal jurisdiction.7

IV. FERC’s Exclusive Jurisdiction to Determine PLC and NSPL Value Methodologies In its filing, PJM does not recognize current FERC authority over PLC and NSPL value methodologies. As is established in more detail below in this section, FERC currently asserts jurisdiction over approving PLC and jurisdictionally analogous NSPL value methodologies, which are set by transmission owners through voluntary OATT Attachment M-2 filings, made pursuant to FPA Section 205. As a result, the PJM transmission owners, not Electric Distributors, establish methods for determining PLC and NSPL values within their transmission zones, not Electric Distributor zones. FERC currently permits the transmission owners to voluntarily file tariff attachments to PJM’s OATT, Attachment M-2s, which establish and specify these methods for determining PLC and NSPL values for individual retail customers for purposes of wholesale cost allocation to LSEs.

FERC, PJM, and public utilities have placed PLC (capacity) and NSPL (transmission) methodologies into the same category. For example, when a utility files an Attachment M-2 with

7 Id. (citations omitted).

PDF page 11

9

FERC to amend the PJM OATT, that Attachment M-2 includes both PLC and NSPL.8  Further, FERC describes PLC and NSPL methodologies together, as if they were conjoined twins, as follows:

FirstEnergy’s Attachment M-2 governs the determination of Peak Load
Contribution and Network Service Peak Load for each LSE in its respective transmission pricing zone for the PJM planning year. Under this attachment, certain FirstEnergy regulated affiliates provide PJM with the information necessary to determine the Peak Load Contribution and Network Service Peak Load each planning year for each wholesale LSE operating in the affiliates’ respective zones. To calculate the Peak Load Contributions, PJM first uses customer load data to calculate the five highest daily peaks for the summer period and then allocates an appropriate share to each EDC zone. Each EDC in PJM must then allocate a share of its PJM-assigned peak load to each customer on its system and aggregate these peak loads to the LSE level. PJM in turn uses the reported Peak Load Contributions to determine an LSE's capacity obligation. To calculate Network Service Peak Loads in the FirstEnergy zone, PJM first determines the FirstEnergy zone's highest transmission peak value. An LSE's Network Service Peak Load is equal to its total hourly load during the FirstEnergy zone’s highest peak value.9

PLC and NSPL methodologies thus involve an analogous and indistinguishable interpretation of cooperative federalism under the FPA. Appendix A offers a graphical interpretation of this cooperative federalism arrangement.10 Accordingly, FERC’s NSPL precedent and related public utility commission interpretations of FERC’s precedent directly bear on PLCs and, by natural extension, PJM’s proposed RBP methodology for capacity. Because NSPL, PLC, and RBP methodologies appear to be indistinguishable for jurisdictional purposes, this Protest analyzes all three.

8 See, e.g., PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 3 (2012).
9 Id.
10 Infra App’x A.

PDF page 12

10

A. NSPL Determinations for Transmission Costs Allocations to LSEs
In AMTRAK v. PPL Elec. Utils. Corp.,11 FERC found that it has jurisdiction over determining NSPL methods and, ultimately, the NSPL values assigned to individual retail customers for purposes of PJM allocating transmission costs to LSEs, as follows: As an initial matter, we find that the Commission has jurisdiction over the matters raised in the complaint.  Amtrak challenges the NITS charges assessed by PJM and passed through to Amtrak by its retail supplier without mark-up, as well as the related PPL methodology for determining Network Service Peak Load

Contributions, both of which fall within the Commission’s jurisdiction.12

FERC explained that transmission owners’ tariff filings containing the PLC and NSPL methodologies are voluntary:

While many transmission owners have filed their methodologies for determining both capacity and [NSPL] contributions in Attachment M-2 to the PJM Tariff, the Commission has recognized that such a filing is voluntary and not required by PJM.13

The Pennsylvania Public Utility Commission (PA PUC) relied heavily on FERC’s decision in 2020 Amtrak to find that it lacked jurisdiction to determine or approve NSPL methods submitted by a transmission utility and EDC to PJM.14 Based on 2020 Amtrak, the PA PUC concluded that it does not have jurisdiction over the NSPL input into the Network Integration Transmission Service (NITS) charge or the method used to calculate the NSPL.15 In that litigation before the PA PUC, industrial consumers challenged the utility’s methodology in the creation of NITS tags and NSPL contribution, stating that it deviated from PJM’s allocation approach to determining coincident

11 171 FERC ¶ 61,237 (June 18, 2020) (2020 Amtrak), order on reh’g, 173 FERC ¶ 61,043 (Oct. 15, 2020).
12 2020 Amtrak Order at P 34 (emphasis added) (citing PJM, Intra-PJM Tariffs, OATT, 34.1 Monthly Demand Charge (1.0.0), § 34.1(a); N.Y. v. FERC, 535 U.S. 1, 20 (2002); Commonwealth Edison Company and Commonwealth Edison Company of Indiana, Inc., 133 FERC ¶ 61,118, at P 11 (2010 ComEd Order)).
13 Id. at P 45.
14 Petition of PPL Electric Utilities Corporation for Approval of Its Default Service Plan for the Period June 1, 2021 Through May 31, 2025, No. P-2020-3019356, 2020 PA. PUC LEXIS 646, *69-74 (Pa. Pub. Util. Comm’n 2020) (PPL DSP V Order), https://www.puc.pa.gov/pcdocs/1687575.docx.
15 Id. at *74.

PDF page 13

11

peak, it does not appear to be based on actual customer usage during peak events, and it is inconsistent with cost causation principles.16 The industrial customers further argued that the PA PUC has jurisdiction to regulate the methods through which Pennsylvania EDCs allocate transmission costs to individual customers, contending that because the NSPLs established by the EDC follow the customer, regardless of whether the customer takes default service supply from the EDC or competitive supply from a competitive supplier regulated by the PA PUC, the PA PUC should exercise jurisdiction over the NSPL calculation.17

In that proceeding, the PA PUC concluded:
We agree with the observation of [the EDC] that [the industrial customers] conflate the payment of NITS charges by an LSE, which are calculated using an NSPL[,] with the allocation of transmission charges to retail electric service customers, the latter occurring through either (a) [the EDC’s] [retail charge] for default service customers, or (b) the private electric supply service contract between [competitive supplier] and a shopping customer.18

Given FERC’s decision in 2020 Amtrak, and further given the PA PUC’s finding of its lack of state jurisdiction to regulate a PA PUC-licensed competitive supplier’s contract price with a retail customer, the PA PUC concluded that it only has jurisdiction over the retail allocation method used by the LSE/default supplier to charge retail capacity rates to default service customers.19 The PA PUC interpreted FERC’s “jurisdiction over NITS charges and the methodology used to calculate NSPLs” to be “exclusive.”20

B. PLC Determinations for Capacity Cost Allocations to LSEs
Not only has FERC exercised jurisdiction over transmission NSPL, but also over capacity PLC methods that include granular retail inputs. FERC has done so by approving Attachment M-

16 Id. at *69-70.
17 Id. at *71-73.
18 Id. at *74.
19 PPL DSP V Order, 2020 PA. PUC LEXIS 646, *74..
20 Id.

PDF page 14

12

2 filings from Pennsylvania transmission owners.21 Attachment M-2 filings amend the PJM Tariff, and FERC approves or rejects them accordingly.22

In so doing, FERC views PJM’s settlement of RPM costs with LSEs as a sale of capacity (a wholesale product) from wholesale entities (such as generators) to PJM LSEs (also wholesale entities) under wholesale rates subject exclusively to the jurisdiction of FERC. As a result, FERC also asserts jurisdiction over the methods by which EDCs assign capacity obligations, and thus costs, to PJM LSEs, even if that method entails a “bottom-up” determination of the allocation of capacity

obligations
to
LSEs/state-licensed
competitive
suppliers. These
bottom-up
determinations can entail assigning capacity obligations to individual retail accounts first (PLC values), then PJM determining the obligation of an LSE as the sum of the capacity obligations of the retails accounts which it serves.

FERC described FirstEnergy’s Attachment M-2 as follows:
FirstEnergy’s Attachment M-2 governs the determination of Peak Load
Contribution and Network Service Peak Load for each LSE in its respective
transmission pricing zone for the PJM planning year. Under this attachment, certain FirstEnergy regulated affiliates provide PJM with the information necessary to determine the Peak Load Contribution and Network Service Peak Load each

planning year for each wholesale LSE operating in the affiliates’ respective zones. To calculate the Peak Load Contributions, PJM first uses customer load data to calculate the five highest daily peaks for the summer period and then allocates an appropriate share to each EDC zone. Each EDC in PJM must then allocate a share of its PJM-assigned peak load to each customer on its system and aggregate these

21 See 2020 Amtrak, 171 FERC ¶ 61,237, at P 34 (2020) (noting that “many transmission owners have filed their methodologies for determining both capacity and [NSPL] contributions in Attachment M-2 to the PJM Tariff,” and that “the Commission has recognized that such a filing is voluntary and not required by PJM”).
22 See, e.g., PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 1 (2012) (setting Attachment M-2 dispute for FPA hearing and settlement judge procedures). See also FirstEnergy Letter Order, PJM Interconnection, L.L.C., Docket Nos. ER24-284 & ER24-285 (Dec. 13, 2023), https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20231218-3074; PECO Letter Order, PJM Interconnection, L.L.C., Docket No. ER14-2340 (Aug. 7, 2014), https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20140807-3018; PPL Letter Order, PJM Interconnection, L.L.C., Docket Nos. ER22-991-000 & ER22-991-001 (May 11, 2022), https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20220511-3061.

PDF page 15

13

peak loads to the LSE level. PJM in turn uses the reported Peak Load Contributions to determine an LSE's capacity obligation.23

When parties disputed FirstEnergy’s proposed revisions to its Attachment M-2, FERC responded by establishing evidentiary hearing and settlement procedures.24 In the relevant settlement procedures, FERC identified that “[t]he primary issue underlying the Partial Settlement [was] whether Attachments M-1 and M-2 are just and reasonable, and not unduly

discriminatory.”25 FERC’s Settlement Judge reviewed them under the FPA’s legal standard, because they are a filed rate within PJM’s governing documents.26

Accordingly, FERC currently regulates the process by which “certain FirstEnergy
regulated affiliates provide PJM with the information necessary to determine the Peak Load Contribution” that involves “[e]ach EDC in PJM . . .  then allocat[ing] an appropriate share of its PJM-assigned peak load to each customer on its system and aggregat[ing] these peak loads to the LSE level.”27

Based on the above, FERC currently asserts jurisdiction over approving PLC and NSPL value methodologies.

23 PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 3 (2012) (emphasis added).
24 Id. at P 1.
25 PJM Interconnection, L.L.C., 144 FERC ¶ 63,011, at P 24 (2013).
26 See 16 U.S.C. § 824d(d) (“[N]o change shall be made by any public utility in any such rate, charge, classification, or service, or in any rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public.”); see also Okla. Gas and Elec. Co. v. FERC, 11 F.4th 821, 829 (D.C. Cir. 2021) (identifying filed rate doctrine extends to matters directly affecting rates); PJM Power Providers Group v. FERC, 96 F.4th 390, 394 (3d. Cir. 2024) (summarizing filed rate doctrine and applying it to PJM’s Tariff); Duquesne Light Co., 189 FERC ¶ 61,181, at n.109 (2024) (citing 16 U.S.C. § 824d(d))).
27 PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 3 (2012).

PDF page 16

14

V. Argument
A. PJM’s proposal to have states determine the RBO methods for addressing cost
allocation of RBP costs is unjust and unreasonable because it presents a jurisdictional
problem that FERC must address.
FERC cannot delegate its FPA authority to the states.28 Likewise, the states cannot take the power that belongs to FERC under the FPA.29 PJM’s act of allocating wholesale costs to wholesale customers (LSEs)—including capacity and transmission costs—is FERC-jurisdictional under the

FPA.30 As established above, FERC has even asserted its jurisdiction over the PLC and NSPL
inputs that are a part of PJM’s allocation of capacity costs and transmission costs to LSEs.31 Specifically, FERC has asserted its jurisdiction to approve the methods for determining PLC and NSPL values that are assigned to individual retail customers for purposes of PJM allocating

capacity and transmission costs to LSEs serving those retail customers.32
To be clear, the PLC and NSPL values—which are determined by the PLC/NSPL
methodologies adopted by the PJM transmission owners and typically filed in Attachment M-2s to the PJM OATT—are assigned to individual retail customers to create capacity and transmission obligations, respectively, which PJM then sums to determine an aggregate amount for purposes of

28 Cf. Mistretta v. United States, 488 U.S. 361, 372-73 (1989) (quoting American Power & Light Co. v. SEC, 329 U.S. 90, 105 (1946)) (noting that the “Court has deemed [congressional delegations of statutory authority to be] ‘constitutionally sufficient if Congress clearly delineates the general policy, the public agency which is to apply it, and the boundaries of this delegated authority.’” (emphasis added)). Here, the boundary of Congress’s delegation includes the FPA’s bright line between federal and state jurisdiction. Miss. Power & Light Co. v. Mississippi ex rel. Moore, 487 U.S. 354, 374 (1988) (“Congress has drawn a bright line between state and federal authority in the setting of wholesale rates and in the regulation of agreements that affect wholesale rates.”).
29 See Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 153 (2016).
30 See 16 U.S.C. § 824(b)(1) (explaining FPA’s jurisdictional bright line); Hughes, 578 U.S. at 153 (“The [FPA] . . . vests in [FERC] exclusive jurisdiction over wholesale sales of electricity in the interstate market” which is “a domain Congress reserved to FERC alone.”); South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d 41, 84-87 (D.C. Cir. 2014) (in the electric transmission context, FERC “has ‘clear’ authority to reallocate capacity and production costs.”). 31 See supra Part IV; PPL DSP V Order, 2020 PA. PUC LEXIS 646, *74 (Pa. Pub. Util. Comm’n 2020) (finding FERC’s “jurisdiction over NITS charges and the methodology used to calculate NSPLs” to be “exclusive” based on Amtrak 2020). But cf. 2020 Amtrak, 171 FERC ¶ 61,237 (June 18, 2020), order on reh’g, 173 FERC ¶ 61,043, at P 24 (Oct. 15, 2020) (2020 Amtrak Rehearing Order) (finding that Amtrak’s “clarification on whether or not the calculation and application of Network Service Peak Load falls within the Commission’s exclusive jurisdiction” was “unnecessary to the result reached in this case and [was] therefore denied”).
32 2020 Amtrak Rehearing Order, 173 FERC ¶ 61,043, at P 24 (2020).

PDF page 17

15

capacity and transmission cost allocation to LSEs serving those retail accounts. The PLC/NSPL values follow the retail customers as they shop between LSEs that are either state-licensed competitive suppliers or default suppliers within a restructured state. PJM sums or aggregates the capacity obligations of all the retail accounts that the LSE serves and then allocates the corresponding wholesale capacity costs or transmission costs to that LSE. This cost allocation method by PJM assigns costs to LSEs roughly commensurate with cost causers (i.e., the retail accounts that the LSEs serve). However, once the wholesale capacity costs are allocated to LSEs, FERC jurisdiction ends and state jurisdiction begins regarding how the LSE performs cost allocation to its retail customers. In vertically integrated states, the LSE is the transmission owner/Electric Distributor, and state utility commissions oversee the retail cost allocation. In restructured states, like Pennsylvania, the LSE is one of two entities: a state-licensed competitive supplier or the Electric Distributor; the PA PUC solely exercises jurisdiction over the retail allocation done by the Electric Distributor to default service customers.

As established above, PJM proposes in its RBP filing that state utility commissions determine the methods for assigning RBO values to individual retail customers/data centers/large loads for purposes of PJM allocating RBO capacity costs to LSEs serving those retail customers. PJM’s RBO proposal presents a jurisdictional question that FERC must address: While FERC’s jurisdiction clearly covers the act of PJM allocating wholesale capacity costs and transmission costs to LSEs (i.e., by PJM summing the capacity/transmission obligations of all the retail accounts that the LSE serves based on PLC/NSPL values and assigning the aggregate costs to the LSEs),33 does FERC jurisdiction rightfully reach down to the methods for determining PLC/NSPL inputs, and by extension the RBO value inputs?

33 Cf. Tri-State Generation and Transmission Association, Inc., 196 FERC ¶ 61,127 (2026) (approving proposal to “allocate the cost of interconnection facilities and any additional network upgrades that a transmission provider

PDF page 18

16

To support its proposal, PJM distinguishes between (1) the RBO methods for assigning RBO values to data centers and other large load retail customers for purposes of PJM’s allocation of RBP costs to LSEs, and (2) retail cost allocation methods used by LSEs in an Electric Distributor’s zone to price capacity to individual retail customers.34 While this distinction brings helpful clarity between the PLC/NSPL values used by PJM for allocating wholesale capacity costs to LSEs and retail cost allocation methods used by LSEs to charge capacity rates/prices to individual retail customers, it does not resolve the jurisdictional problem presented in PJM’s filing through PJM’s proposal for states to exercise jurisdiction to determine the RBO methods. Moreover, in its filing, PJM asserts that establishing RBO methods to allocate RBP costs to end use, retail customers requires cooperative federalism.35 It cites to a 2007 FERC Order where FERC distinguished between wholesale cost allocation methods and retail cost allocation methods.36 Again, the cite to this FERC order does not resolve the jurisdictional problem presented by PJM’s proposal. Rather, the quotes that PJM relies on from this 2007 FERC Order provide support for the PA OCA’s assertion that PJM’s proposal presents a jurisdictional problem, as FERC clearly recognized its complete authority over wholesale cost allocation methods. Furthermore, for cooperative federalism to function, there must be clear divisions between federal and state jurisdiction.

directly assigns to Tri-State Merchant to the Utility Member, who may elect to pass those costs directly to its HIL Customer.”).

34 PJM RBP Transmittal Letter at 99.
35 Id.
36 Id. at 99-100.

PDF page 19

17

B. There is time to get cost allocation right – by the time cost allocation comes
due for the first Delivery Year in which RBP Resources are expected to be in service
(i.e., 2028/2029).
PJM states that its proposed RBO framework is pragmatic because in the short time
remaining before the September 30, 2026 RBP, it would simply be infeasible for PJM to obtain detailed information about the large loads and the various LSEs serving such large loads from every state and RERRA in the PJM Region.37

However, the important date for purposes of determining final RBO methods for PJM’s
costa allocation of RBP costs to LSEs is when RBP obligations begin accruing for the first Delivery Year in which RBP Resources are expected to be in service.38 Hence, September 2026 is not the deadline. There is time for FERC to address this cost allocation jurisdictional problem and ensure that RBO methods are appropriately determined.

C. Potential Relief Options
1. Option 1: Recognize and exercise exclusive jurisdiction over RBO value
methodologies; FERC can declare its exclusive jurisdiction over determining
the RBO methods and require jurisdictional transmission owners to make
additional tariff filings that propose RBO methods for their transmission zones
within PJM.
If the methods for determining NSPL and PLC contributions are rightfully transmission-
owner-determined under the FPA, for transmission zones within PJM, those methods are FERC jurisdictional and PJM and states do not have discretion or authority to interfere with them given that Attachment M-2s fall within transmission owner filing rights under FPA Section 205.39 The

37 Id. at 107.
38 Id. at 108. 39 See supra Part IV; 16 U.S.C. § 824(b)(1) (explaining FPA’s jurisdictional bright line); cf. Tri-State Generation and Transmission Association, Inc., 196 FERC ¶ 61,127 (2026) (approving proposal to “allocate the cost of interconnection facilities and any additional network upgrades that a transmission provider directly assigns to Tri-State Merchant to the Utility Member, who may elect to pass those costs directly to its HIL Customer.”); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 153 (2016) (“The [FPA] . . . vests in [FERC] exclusive jurisdiction over wholesale sales of electricity in the interstate market” which is “a domain Congress reserved to FERC alone.”); South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d 41, 84-87 (D.C. Cir. 2014) (in the electric transmission context, FERC “has ‘clear’ authority to reallocate capacity and production costs.”).

PDF page 20

18

methods for determining RBO values are analogous to the methods for determining NSPL and PLC contributions because they each require granularly determining retail customers’ contributions to a category of wholesale costs. Because the methods for determining RBO values are—for jurisdictional purposes—analogous to and indistinguishable from equivalent methods for determining NSPL and PLC contributions,40 this same legal analysis and conclusion naturally extend to the methods for determining RBO values that will be assigned to individual retail customers/data centers for purposes of PJM allocating RBP costs to LSEs serving those retail customers. A FERC decision providing that the states can oversee the RBO value methodologies, while FERC retains exclusive jurisdiction to oversee the PLC/NSPL value methodologies, would result in conflicting FPA interpretations and would therefore produce an unjust or absurd result.41 Given the above, FERC can declare that it has exclusive jurisdiction to oversee RBO methods and find PJM’s cost allocation proposal regarding RBO methods unjust and unreasonable given that PJM proposes that state utility commissions determine and approve the RBO methods. As further relief, FERC should require jurisdictional transmission owners within PJM to submit additional 205 tariff filings based on this docket to propose the RBO method for determining individual retail customers’ RBO values within their respective transmission zones. As further relief, FERC should mandate that the transmission owners make the 205 filings as attachments to the PJM tariff and not permit such filings to be voluntary. The PA OCA further requests that FERC mandate that all jurisdictional transmission owners within PJM make Attachment M-2 filings for

40 Cf. Scott Brewer, Exemplary Reasoning: Semantics, Pragmatics, and the Rational Force of Legal Argument by Analogy, 109 HARV. L. REV. 925, 936 (1996) (“[E]xemplary, analogical reasoning is . . . thoroughly familiar - in Anglo-American legal systems, anyway - in statutory and constitutional cases.” (citing California v. Carney, 471 U.S. 386 (1984)).
41 Ramaprakash v. FAA, 346 F.3d 1121, 1125 (2003) (“An agency’s failure to come to grips with conflicting precedent constitutes ‘an inexcusable departure from the essential requirement of reasoned decision making.’” (quoting Columbia Broad. Sys. v. FCC, 454 F.2d 1018, 1027 (D.C. Cir. 1971))).

PDF page 21

19

PLC and NSPL methods, as this would improve transparency over cost allocation of capacity, transmission, and RBP costs within PJM.

2. Option 2: Relinquish exclusive jurisdiction over PLC methodologies;
FERC can declare that states have exclusive jurisdiction to determine PLC
and NSPL methods, and by extension the proposed RBO method, and require
Electric Distributors that are signatories to the RAA to report them to PJM.
It is undisputed that FERC’s jurisdiction covers the act of PJM allocating wholesale costs to LSEs (i.e., by PJM summing the capacity/transmission obligations of all the retail accounts that the LSE serves based on PLC/NSPL values and assigning the aggregate costs to the LSEs). However, PJM’s filing raises the question of whether FERC’s jurisdiction rightfully reaches down to the methods for determining PLC/NSPL inputs, and by extension the methods for determining the RBO inputs. This question raises confusion about federal and state roles withing the FPA’s cooperative federalism, and about where the dividing lines of jurisdiction properly rest. PJM’s filing suggests that the answer is not that everything is FERC jurisdictional up to the point where PJM allocates to the LSEs.

Indeed, this question recognizes that the PLC/NSPL/RBO methods are inputs to PJM’s cost allocation methods for capacity, transmission, and RBP costs, respectively. They are not PJM cost allocation methods in and of themselves. As inputs to PJM’s cost allocation methods for wholesale capacity and transmission costs, they are developed using individual retail customer data. As inputs, they assign values to individual retail customers that follows the individual retail customers as the customers shop among state-licensed competitive suppliers and default suppliers within a state. As inputs, they directly and substantially impact retail cost allocations of capacity and transmission costs to retail customers,

Moreover, in establishing the PLC/NSPL methods, it is curious how transmission owners, which do not legally have direct relationships with retail customers from a rates perspective, would

PDF page 22

20

be the ones with the information to establish the methods for determining PLC/NSPL values for retail customers. It would seem, as PJM suggests, that individual Electric Distributors and state utility commissions are simply in a better position to establish methods to determine PLC/NSPL/RBO values that get assigned to retail customers, given that the Electric Distributors, not transmission owners, serve retail customers pursuant to state utility commission-approved tariffs, which establish the rate classifications that retail customers belong in. Additionally, Electric Distributors, not transmission owners, have granular information about retail customers within their borders. Accordingly, PJM’s proposal raises the question of whether the methods for determining and assigning PLC/NSPL/RBO values to individual retail customers is exclusively a state not federal power because state utility commissions have the authority to protect their retail customers by assigning these values recognizing state utility commission-approved tariffs and rate classifications.

Furthermore, if this act of determining PLC/NSPL/RBO values and assigning them to individual retail customers is exclusively a state power, cooperative federalism would necessitate that state utility commission oversee the Electric Distributors’ determinations of the methods and that Electric Distributors, as a condition of being a signatory to the RAA, be required to report them to PJM so that PJM can perform its function to allocate wholesale capacity and transmission costs.

Based on the above, if the methods of determining NSPL and PLC contributions are not rightfully transmission owner-determined under the FPA, those methods are not FERC jurisdictional and hence states can exercise jurisdiction over them. However, because the methods for determining RBO values are—for jurisdictional purposes—analogous to and indistinguishable

PDF page 23

21

from equivalent methods for determining NSPL and PLC contributions,42 this same legal analysis and conclusion would naturally extend to the methods for determining RBO values that PJM proposes will be assigned to individual retail customers/data centers for purposes of PJM allocating RBP costs to LSEs serving those retail customers. By introducing a new interpretation of FERC’s statutory authority under the FPA, PJM’s proposal would require complicated changes to PLC and NSPL methods that utilities have filed in Attachment M-2 of PJM’s Tariff.

To depart from prior determinations, FERC must use reasoned decision making.43 PJM’s
filing and the PA OCA’s Protest offers FERC a rationale for departing from its prior decisions over PLC/NSPL methods and declaring state jurisdiction to oversee and determine the methods for determining PLC/NSPL methods and by extension the RBO method proposed in PJM’s filing.

If FERC believes that states have exclusive authority to oversee Electric Distributors’ determination of PLC/NSPL/RBO values, it should declare that unequivocally and provide

reasoned decision making in doing so. As further relief, FERC should direct and oversee an orderly timely transition to replace the Attachment M-2 methodologies for setting PLC/NSPL values with Electric Distributor-reported methods. FERC and PJM should require Electric Distributors, as signatories to the RAA, and as a condition of the RAA, to report their state or state utility commission-approved PLC/NSPL/RBP value methodologies to PJM. PJM should only accept

from Electric Distributors the state or state utility commission-approved tariffs or orders establishing the PLC/NSPL value methodologies for the Electric Distributors’ borders.

42 Cf. Scott Brewer, Exemplary Reasoning: Semantics, Pragmatics, and the Rational Force of Legal Argument by Analogy, 109 HARV. L. REV. 925, 936 (1996) (“[E]xemplary, analogical reasoning is . . . thoroughly familiar - in Anglo-American legal systems, anyway - in statutory and constitutional cases.” (citing California v. Carney, 471 U.S. 386 (1984)).
43 See Leggett & Platt, Inc. v. NLRB, 988 F.3d 487, 494 (D.C. Cir. 2021) (“Courts have long recognized that ‘any agency’s unexplained departure from prior agency determinations is inherently arbitrary and capricious in violation of APA § 706(2)(A).’” (citation omitted)); see also Loper Bright Enters. v. Raimondo, 603 U.S. 369, 388 (2024) (quoting Skidmore v. Swift & Co., 323 U.S. 134, 140 (1944)) (giving weight to agency statutory interpretation’s “consistency with earlier and later pronouncements”).

PDF page 24

22

3. Option 3: Establish a new jurisdictional category for PLC
methodologies for RBOs; FERC can legally distinguish PJM’s proposal for
state utility commissions to determine the RBO method from the PLC and
NSPL methods and declare that state utility commissions have exclusive
jurisdiction to determine and approve the methods for determining RBO
values for purposes of PJM cost allocation of RBP obligations to LSEs.
The PA OCA has not identified a way to legally distinguish the RBO method from the PLC and NSPL methods that are currently under FERC jurisdiction; hence, this Protest addresses the first two options. Importantly, if FERC decides that the RBO value methodology used by PJM for RBP cost allocation is distinguishable from the PLC/NSPL value methodologies used for capacity/transmission cost allocation, FERC must expressly declare that states have jurisdiction over the RBO methods. Otherwise, without a clear jurisdictional path forward, when this issue comes before state utility commissions, such commissions could find that they lack authority to determine the RBO methods, resulting in this important issue not advancing with greater clarity as to the details defining the RBO method. The result will be to default to PJM’s backup plan, which is allocating RBP costs to all LSEs PJM-wide on a pro rata basis using existing PLC methods. However, cost allocation to LSEs on a pro rata basis using PLC values is unjust and unreasonable because it will likely result in non-large load customers being allocated RBP costs despite these ratepayers not having caused these costs.

D. FERC should adopt Option 1 by affirming its exclusive jurisdiction over RBO methods and requiring each transmission owner to file Attachment M-2 amendments containing their proposed RBO method.

FERC already exercises exclusive jurisdiction over PLC and NSPL methods that are indistinguishable from RBO methods for jurisdictional purposes, and FERC should expressly include RBO methods within this existing jurisdiction. FERC’s existing jurisdiction manifests at the state level in unavoidable ways. For example, the PA PUC interpreted FERC’s “jurisdiction

PDF page 25

23

over NITS charges and the methodology used to calculate NSPLs” to be “exclusive.”44 And
FERC’s existing jurisdiction shows up at the federal level in unavoidable ways. For example, FERC addressed a dispute regarding FirstEnergy’s Attachment M-2—which contains both the PLC

and NSPL methodologies—by establishing hearing and settlement procedures under the FPA’s
Section 205 legal standard.45 Attachment M-2 falls under Section 205 because it is a filed rate within PJM’s governing documents.46

The methods for determining RBO values are analogous to the FERC-jurisdictional
methods for determining NSPL and PLC contributions because they each require granularly
determining retail customers’ contributions to a category of wholesale costs. Because the methods for determining RBO values are—for jurisdictional purposes—analogous to and indistinguishable from equivalent methods for determining NSPL and PLC contributions,47 existing FERC

jurisdiction naturally extends to the methods for determining RBO values that will be assigned to individual retail customers/data centers for purposes of PJM allocating RBP costs to LSEs serving those retail customers.

If FERC were to insist upon state jurisdiction in this context, that could create cascading
confusion and litigation risk. By introducing a new interpretation of FERC’s statutory authority

44 PPL DSP V Order, No. P-2020-3019356, 2020 PA. PUC LEXIS 646, *69-74 (Pa. Pub. Util. Comm’n 2020), https://www.puc.pa.gov/pcdocs/1687575.docx.
45 PJM Interconnection, L.L.C., 141 FERC ¶ 61,009, at P 1 (2012); PJM Interconnection, L.L.C., 144 FERC ¶ 63,011, at P 24 (2013) (“[t]he primary issue underlying the Partial Settlement [was] whether Attachments M-1 and M-2 are just and reasonable, and not unduly discriminatory.”).
46 See 16 U.S.C. § 824d(d) (“[N]o change shall be made by any public utility in any such rate, charge, classification, or service, or in any rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public.”); see also Okla. Gas and Elec. Co. v. FERC, 11 F.4th 821, 829 (D.C. Cir. 2021) (identifying filed rate doctrine extends to matters directly affecting rates); PJM Power Providers Group v. FERC, 96 F.4th 390, 394 (3d. Cir. 2024) (summarizing filed rate doctrine and applying it to PJM’s Tariff); Duquesne Light Co., 189 FERC ¶ 61,181, at n.109 (2024) (citing 16 U.S.C. § 824d(d))).
47 Cf. Scott Brewer, Exemplary Reasoning: Semantics, Pragmatics, and the Rational Force of Legal Argument by Analogy, 109 HARV. L. REV. 925, 936 (1996) (“[E]xemplary, analogical reasoning is . . . thoroughly familiar - in Anglo-American legal systems, anyway - in statutory and constitutional cases.” (citing California v. Carney, 471 U.S. 386 (1984)).

PDF page 26

24

under the FPA, state jurisdiction would render the RBO legally vulnerable and would likely require complicated changes to PLC and NSPL methods that utilities have filed in Attachment M-2 of PJM’s Tariff.48

A clear expression of FERC jurisdiction over transmission owners’ RBO methodologies—
filed within mandatory Attachment M-2s—is the most legally durable way to resolve the legal and regulatory confusion identified in this Protest. Accordingly, FERC should affirm its exclusive jurisdiction over RBO methods and require each transmission owner to file Attachment M-2

amendments containing their proposed RBO method. To the extent a transmission owner does not currently have an Attachment M-2 on file, FERC should require them to make the filing so that the RBO and PLC methodologies are transparent and publicly available.

This is the just and reasonable result.

48 Ramaprakash v. FAA, 346 F.3d 1121, 1125 (2003) (“An agency’s failure to come to grips with conflicting precedent constitutes ‘an inexcusable departure from the essential requirement of reasoned decision making.’” (quoting Columbia Broad. Sys. v. FCC, 454 F.2d 1018, 1027 (D.C. Cir. 1971)); see also Leggett & Platt, Inc. v. NLRB, 988 F.3d 487, 494 (D.C. Cir. 2021) (“Courts have long recognized that ‘any agency’s unexplained departure from prior agency determinations is inherently arbitrary and capricious in violation of APA § 706(2)(A).’” (citation omitted)); Loper Bright Enters. v. Raimondo, 603 U.S. 369, 388 (2024) (quoting Skidmore v. Swift & Co., 323 U.S. 134, 140 (1944)) (giving weight to agency statutory interpretation’s “consistency with earlier and later pronouncements”).

PDF page 27

25

VI. Conclusion
In conclusion, FERC should find that PJM’s cost allocation proposal, within its RBP Tariff filing, is unjust and unreasonable because it presents a jurisdictional problem and insufficiently defines the Reliability Backstop Obligation method. FERC should remedy the unjust and unreasonable tariff by (1) declaring FERC’s exclusive jurisdiction to determine RBO value methodologies; (2) determining that PJM’s cost allocation proposal for RBP obligations is unjust and unreasonable because it insufficiently defines the RBO method; (3) requiring jurisdictional transmission owners within PJM to submit additional filings based on this docket to further define the RBO method for determining individual customer’s RBO values within each transmission owner zone; (4) mandating that the transmission owners make conforming Attachment M-2 tariff filings under FPA Section 205, containing the RBO value methodologies (and PLC/NSPL value methodologies); and (5) setting a time frame to resolve protests and comments to the transmission owners’ tariff filings regarding the RBO methodologies.

Pennsylvania Office of Consumer
Advocate
555 Walnut Street
5th Floor, Forum Place
Harrisburg, PA 17101-1923
717-783-5048

Dated: August 21, 2026
Respectfully submitted,

Counsel for:
Darryl Lawrence
Pennsylvania Consumer Advocate

/s/ Melanie Joy El Atieh
Melanie Joy El Atieh
Deputy Consumer Advocate
PA Attorney ID # 209323
MElAtieh@paoca.org

Josiah Harmar
Assistant Consumer Advocate
PA Attorney ID # 338426
JHarmar@paoca.org

PDF page 28

App’x A -1

Appendix A
Protest of Pennsylvania Office of Consumer Advocate
ER26-3380
Differentiating Peak Load Contribution Assignments from Cost Allocation
This appendix attempts to graphically describe the existing processes for assigning capacity and transmission peak load contribution megawatts (MWs) and allocating costs (Figure 1 and Figure 2), and highlights the jurisdictional challenge raised in PJM’s backstop auction filing (Figure 3). Figure 1

Figure 1 - MW Obligation Jurisdiction
As shown in Figure 1, the assignment of MW obligations from the RTO to the Zone/Area, and then to LSE and to retail customers currently happens through PJM’s application of the Peak Load Contribution (PLC) and Network Service Peak Load (NSPL) methods for capacity and transmission service, respectively.  While PJM utilizes PLC and NSPL in settlements with LSEs, the underlying PLC/ NSPL methods are established, and voluntarily filed as attachment M-2 to the PJM OATT, by the transmission owners.  All of these actions are under federal jurisdiction, including: 1) the assignment of MW obligations from Region to Zone/Area, 2) the assignment of MWs from Zone/Area to LSE, and importantly, 3) the assignment of MWs from the LSEs to the

PDF page 29

App’x A -2

retail customers, per Amtrak v PPL.  In step #3, PJM’s OATT dictates the mechanism according to which MW obligations are assigned to the retail customer through the application of the transmission owner’s PLC/ NSPL method. Then the EDC sums these MWs across each LSE’s retail customers and reports the summation to PJM for purposes of MW obligation allocation to that LSE.

Figure 2

Figure 2 - State Cost Allocation
While federal jurisdiction oversees the process and methods for the assignment of MW obligations and LSE-level summation and reporting to PJM to effectuate cost assignment, the rates charged to retail customers for recovery of those revenues is state jurisdictional through either (1) retail utility tariffs, which may include state approval of direct pass through of federal rates, or (2) retail contracts between state-licensed competitive suppliers and retail consumers. This is shown in Figure 2 in the orange box in the bottom right corner – governed by state rates and rate design. This extends to the need for explicit approval from the PA PUC for Electric Distribution Company default service tariffs to pass through federal rates – such as Network Integration Transmission Service (NITS) and Transmission Expansion Charges (TEC) – to retail customers.

PDF page 30

App’x A -3

Figure 3

Figure 3 - Concern Over State Apportionment of MW Obligation
OCA’s concern centers over the lack of state jurisdiction to establish an as-yet-to-be-developed method of assigning reliability backstop obligation (RBO) MWs to retail customers.  This is shown in the lower lefthand corner of Figure 3.  As compared to Figure 1 and Figure 2 – where assignment of MWs is subject to federal jurisdiction per Amtrak v PPL – PJM now proposes to have states establish this method. If states lack the jurisdiction to establish this method, then PJM will implement its backstop cost allocation method that will allocate reliability backstop costs to all consumers based on the PLC method. This result – which is outside of the state’s control due to jurisdictional boundaries – would be unjust and unreasonable.

PDF page 31

1

CERTIFICATE OF SERVICE
I certify that today I served this document on this proceeding’s official service list.

Harrisburg, Pennsylvania; August 21, 2026.

/s/ Josiah Harmar

Josiah Harmar
Assistant Consumer Advocate
PA Attorney ID # 338426
JHarmar@paoca.org