ER26-3380-000 · 2026-08-21 · Talen Energy Corporation
Motion to Intervene and Request for Clarification of Talen Energy Corporation re the Reliability Backstop Procurement filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
MOTION TO INTERVENE AND REQUEST FOR CLARIFICATION OF
TALEN ENERGY CORPORATION
Talen Energy Corporation (“Talen”) hereby submits this motion to intervene and
respectfully requests the Commission clarify one provision of the Reliability Backstop Procurement (“RBP”) filing submitted by PJM Interconnection, L.L.C. (“PJM”). PJM states in its transmittal letter that the RBP filing is “not intended to disrupt existing commercial agreements,”1 which is consistent with the directive from the Federal Energy Regulatory Commission (“FERC” or “Commission”). Yet, PJM’s proposal will unequivocally diminish the economic benefit secured by new load under previously negotiated contracts for the purchase and sale of capacity from existing generation resources. Accordingly, the Commission should clarify the proposed Tariff revisions at Attachment DD, section 18.3(a) to include a reduction to the Electric Distributor’s zone/area’s pro-rata allocation of the Initial RBP Target MW equal to the contracted amount of large load that has executed a power purchase agreement (“PPA”) or similar supply contract with an existing generation resource prior to the January 16, 2026 Statement of Principles.2
1
Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads at 3, Docket No. EC26-3380-000 (filed July 31, 2026) (“PJM RBP Filing”).
2 Statement of Principles Regarding PJM, NATL. ENERGY DOMINANCE COUNCIL (issued Jan. 16, 2026), available at https://www.energy.gov/documents/statement-principles-regarding-pjm. Talen submits its Request for Clarification pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure. 18 C.F.R. § 385.212 (2026).
PDF page 2
2
I. MOTION TO INTERVENE
Pursuant to Rule 214 of the Commission’s Rules of Practice and Procedure,3 Talen respectfully submits this motion to intervene in the above-captioned proceeding. The formal legal name of Talen is Talen Energy Corporation. Talen is a corporation organized and existing under the laws of Delaware. Talen maintains its principal place of business at 2929 Allen Parkway, 22nd Floor, Houston, Texas 77019. Talen is a leading independent power producer and energy infrastructure company which owns and operates approximately 15.7 gigawatts of power infrastructure in the United States. Talen produces and sells electricity, capacity, and ancillary services into wholesale U.S. power markets, including and primarily in PJM. A subsidiary of Talen has entered into a bilateral contract for the sale of electric power from an existing generation resource to new load that will come online during the Delivery Years set forth in the PJM RBP Filing. Accordingly, the actions taken by the Commission in this matter will directly affect the interests of Talen. Talen has a direct and material interest in the instant proceeding that no other party can adequately represent. Talen therefore requests that the Commission grant this motion to intervene and permit Talen to participate in this proceeding with full rights as a party thereto.
II. REQUEST FOR CLARIFICATION
A. The proposed Tariff revisions do not protect existing commercial agreements
from disruption.
The protection of existing private contracts is fundamental to the operations of state and federal government, including FERC.4 The Commission has previously acknowledged that “uncertainties regarding rate stability and contract sanctity can have a chilling effect on
3 18 C.F.R. § 385.214 (2026).4 See, e.g., U.S. Const, Art. I, § 10, clause 1 (setting forth that “[n]o State shall . . . pass any . . . [l]aw impairing the [o]bligation of contracts”).
PDF page 3
3
investments and a seller’s willingness to enter into long-term contracts and this, in turn, can harm customers in the long run.”5 The Commission has also recognized that electric industry innovation does not justify injecting uncertainty and upheaval into existing contracts.6
The past few years have presented historic opportunities and novel challenges. Although all market participants could have benefitted from regulatory certainty during this period, it was not an option to wait idly for PJM and the Commission to enact generalized market reform that would adequately address the evolving market dynamics and increasing load demand.7 Large load developers were faced with three options: bring their own power, rely on the market, or fix power costs through a bilateral PPA. Speed to power is paramount for new large load customers. Accordingly, certain developers chose to fix their costs—or so they thought—by means of a bilateral PPA. These contracts were executed at a time when the RBP was not known to be on the horizon. The PJM RBP Filing, without clarification, treats developers that chose Option No. 3 (bilateral PPAs) the same as developers that chose Option No. 2 (rely on the market). Such an outcome upsets the reasonable, investment-backed expectations that FERC has historically sought to protect.
The importance of reliance interests and the risk of chilling investment due to regulatory instability are not lost on this Commission. That is why Chairman Laura Swett recently explained
5 Market–Based Rates for Wholesale Sales of Electric Energy, Capacity and Ancillary Services by Public Utilities, Order No. 697, 72 Fed. Reg. 39,904, 119 FERC ¶ 61,295, at P 6 (2007).6 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888 at p. 84, 61 Fed. Reg. 21,540 (May 10, 1996) (“Order No. 888”) (holding that that “changes in the industry have been and continue to be dramatic,” but FERC “does not believe they compel generic abrogation of requirements and transmission contracts”).7 Delay could also be seen as a national security risk. See generally PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (Chairman Phillips dissent at P 3) (explaining that “maintaining U.S. leadership in Artificial Intelligence (AI) is necessary to maintaining our national security”).
PDF page 4
4
that the Commission’s actions with respect to large load reforms and procedures “are not intended to disrupt existing commercial agreements.”8 PJM appeared to take note because PJM stated in its filing that its proposal “avoids disrupting existing commercial arrangements.”9 However, the PJM RBP Filing does not adequately implement this principle and requires further clarification. Under proposed Attachment DD, section 18.3(a), each Electric Distributor zone/area’s
allocation of the Initial RBP Target may be reduced by the quantity of “Qualifying RBP Offset UCAP MW” or by an opt-out provision.10 This does not account for new load that has entered into a bilateral PPA with an existing generation resource. As a result, each Electric Distributor zone/area will continue to be allocated an inflated share of the Initial RBP Target. Such new load will be subject to RBP Charges, assuming states follow the Commission’s directive to implement RBP cost allocation mechanisms.11 Therefore, this “new load” must pay incremental capacity charges resulting from the RBP, thereby minimizing the economic benefit the load freely negotiated under its fixed-cost, bilateral PPA (essentially, paying twice for capacity).
8 Statement of FERC Chairman Laura Swett, FERC Open Meeting (June 18, 2026) at 10:42, https://ferc.gov/news- events/events/june-18-2026-open-meeting-10082025.9 Proposed Tariff, Attachment DD, section 18.3(a). Qualifying RBP Offset UCAP MW means unforced capacity that has not received a reliability pricing model commitment or been committed in a Fixed Resource Requirement Plan as of the commencement date of the RBP, is supplied by new build or incremental generation that will perform based on PJM dispatch instructions by no later than June 1, 2032, and is evidenced by signed bilateral contracts, signed commitment letters, or self-supply that is in a relevant electric retail regulatory authority- approved or accepted integrated resource plan. See PJM RBP Filing at 35 (citing Proposed Tariff, Attachment DD, section 18.2(c)).10 Id. at 35 (citing Proposed Tariff, Attachment DD, section 18.2(c)).11 Id. at 96-97 (“PJM is proposing to allocate daily RBP Charges to relevant Electric Distributor zones/areas, pro rata, based on the zone/area’s assigned share of the total, region-wide Final RBP Target MW . . . .”).
PDF page 5
5
B. The Commission should clarify Attachment DD, section 18.3(a) to further reduce each Electric Distributor zone/area’s allocation of the Initial RBP Target.
PJM has expressly consented “to the Commission’s exercise of authority to modify and/or sever the proposed Tariff and RAA language, as needed and permitted under the FPA and NRG Power Marketing, where such modification is consistent with PJM’s overarching objectives in this filing.”12 If the Commission exercises its authority to modify the PJM RBP Filing, then PJM requested that “the Commission expressly prescribe the revised rate or rule in its order.”13 The Commission should do so here. Specifically, Talen requests that the Commission require the following underlined language to Attachment DD, section 18.3(a) in its approval of the PJM RBP Filing:
(a) Cost Allocation to Electric Distribution zone/area
The Office of the Interconnection shall allocate the Initial RBP
Target MW to each Electric Distributor’s zone/area pro-rata share of
the difference between the forecasted Load Adjustments for the
2026/2027 Delivery Year and the 2028/2029 Delivery Year.
The difference between the forecasted Load Adjustments for the
2026/2027 and the 2028/2029 Delivery Years shall be reduced for
the purpose of this calculation to the extent:
(i) an Electric Distributor, LSE, Transmission Owner,
or other entity provides the Office of Interconnection
with evidence of Qualifying RBP Offset UCAP MW,
in accordance with Tariff, Attachment DD, section
18.2 and as may be further set forth in the PJM
Manuals; or
(ii) an Electric Distributor zonee[sic]/area meets one of
the opt-out provisions set forth in accordance with
Tariff, Attachment DD, section 18.1(d); and
12 Id. at 131 (internal citations omitted).13 Id.
PDF page 6
6
(iii) an Electric Distributor, LSE, Transmission Owner,
or other entity provides the Office of Interconnection
with evidence of a bilateral contract executed prior
to January 16, 2026, for the sale of capacity from an
existing Generation Capacity Resource to and
purchased by load under a power purchase
agreement or similar power supply contract
indicating that the load will be coming online in the
2027/2028 or 2028/2029 Delivery Year, for a term of
at least five Delivery Years with a commercial
operation date prior to the start of the 2032/2033
Delivery Year; provided that, such reduction shall be
equal to the total quantity of capacity to be sold and
purchased under such bilateral contract during the
2027/2028 and 2028/2029 Delivery Years.
The resulting reduced MW, floored at zero, is used to calculate the zone/area’s assigned pro-rata share of the Final RBP Target MW.
The zone/area’s assigned share of the Final RBP Target MW shall
remain constant throughout the fixed 15-year term.
The Office of the Interconnection shall allocate the total RBP
Charges, assessed daily, to an Electric Distributor’s zone/area on a pro-rata basis using the zone/area’s assigned share of the total Final RBP Target MW across all zones/areas.
The proposed language would effectively treat capacity procured through previously executed bilateral contracts with existing generation resources the same as Qualifying RBP Offset UCAP MW for purposes of reducing an Electric Distributor zone/area’s allocation of the Initial RBP Target and, as a result, allocation of RBP Charges.
This clarifying language does not reduce the Initial RBP Target such that capacity contracts with existing generation resources would be treated as Qualifying RBP Offset UCAP MW.14 This means that PJM will continue to procure the amount of capacity it has deemed necessary under the Initial RBP Target; however, the allocation of RBP Charges would be fairly distributed such that new load that has previously contracted for capacity with existing generators under qualifying
14 See Proposed Tariff, Attachment DD, section 18.2(b).
PDF page 7
7
bilateral contracts would not have their previous negotiated economic bargains upset by the PJM RBP Filing. This outcome is consistent with the directive from Chairman Swett to not “disrupt existing commercial arrangements.”15 It is also consistent with PJM’s characterization of the PJM RBP Filing as revisions that “avoid[] disrupting existing commercial arrangements.”16
III. CONCLUSION
For the reasons discussed herein, Talen respectfully requests that the Commission clarify proposed Attachment DD, section 18.3(a), as discussed above, to bring the language in alignment with PJM’s characterization of the PJM RBP Filing and directive from Chairman Swett.
Respectfully Submitted,
/s/ Jennifer Mansh
Jennifer Mansh
Senior Vice President, Regulatory
Counsel
Talen Energy Corp.
600 Hamilton Street, Suite 600
Allentown, PA 18101
Jennifer.Mansh@talenenergy.com
/s/ John Decker
John Decker
Andrew DeVore
Kirkland & Ellis LLP
1301 Pennsylvania Avenue, N.W.
Washington, D.C. 20004
(202) 389-3470
(202) 389-3117
John.decker@kirkland.com
andrew.devore@kirkland.com
Counsel for Talen Energy Corporation
Dated: August 21, 2026
15 Supra at n.12.16 Supra at n.13.
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused to be served the foregoing document upon each person designated on the official service list compiled by the Secretary in this docket. Dated at Washington, D.C. this 21st day of August, 2026.
/s/ Andrew DeVore
Andrew DeVore
Kirkland & Ellis LLP
1301 Pennsylvania Avenue, N.W.
Washington, D.C. 20004
Counsel for Talen Energy Corporation