Motion to Intervene and Request for Clarification of Talen Energy Corporation re the Reliability Backstop Procurement filing
Text extracted from the eLibrary original (SHA-256 1c887c5e39a2fde4…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
ER26-3380-000 MOTION TO INTERVENE AND REQUEST FOR CLARIFICATION OF TALEN ENERGY CORPORATION Talen Energy Corporation (“Talen”) hereby submits this motion to intervene and respectfully requests the Commission clarify one provision of the Reliability Backstop Procurement (“RBP”) filing submitted by…Read this passage Filed comments: Reliability and curtailment
I. MOTION TO INTERVENE
printed heading
Talen therefore requests that the Commission grant this motion to intervene and permit Talen to participate in this proceeding with full rights as a party thereto.Read this passage
II. REQUEST FOR CLARIFICATION
printed heading
II.Read this passage
A. The proposed Tariff revisions do not protect existing commercial agreements
printed heading · Topic match: Cost allocation
Such new load will be subject to RBP Charges, assuming states follow the Commission’s directive to implement RBP cost allocation mechanisms.11 Therefore, this “new load” must pay incremental capacity charges resulting from the RBP, thereby minimizing the economic benefit the load freely negotiated…Read this passage Filed comments: Cost allocation
B. The Commission should clarify Attachment DD, section 18.3(a) to further
printed heading · Topic match: Cost allocation
Specifically, Talen requests that the Commission require the following underlined language to Attachment DD, section 18.3(a) in its approval of the PJM RBP Filing: (a) Cost Allocation to Electric Distribution zone/area The Office of the Interconnection shall allocate the Initial RBP Target MW to…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading
CONCLUSION For the reasons discussed herein, Talen respectfully requests that the Commission clarify proposed Attachment DD, section 18.3(a), as discussed above, to bring the language in alignment with PJM’s characterization of the PJM RBP Filing and directive from Chairman Swett.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 21st day of August, 2026. /s/ Andrew DeVore Andrew DeVore Kirkland & Ellis LLP 1301 Pennsylvania Avenue, N.W.Read this passage