Limited Protest of Vistra Corp. re PJM Interconnection, L.L.C.’s proposed Reliability Backstop Procurement mechanism
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3380-000
LIMITED PROTEST OF VISTRA CORP.
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) submits this limited protest of PJM Interconnection, L.L.C.’s (“PJM”) proposed Reliability Backstop Procurement (“RBP”) mechanism. This proceeding is the latest in PJM’s efforts to address the resource adequacy challenges it faces as supply struggles to keep up with forecasted demand. Vistra generally supports the proposal to use a backstop mechanism to address near-term the resource adequacy needs in the PJM system, even as Vistra believes it is critically important to ensure that the “ordinary” tools for ensuring resource adequacy, including the Reliability Pricing Model (“RPM”), remain the principal mechanisms by which PJM meets that critically important goal. Short-term fixes have a tendency to beget further short-term fixes. Vistra urges PJM—and the Commission— to ensure that RBP does not follow that well-trod path.
In that vein, Vistra appreciates PJM’s efforts to narrowly tailor the RBP to the immediate resource adequacy need in front of it. During the stakeholder process, PJM narrowed the procurement target from 15 GW to 6.8 GW,2 which brings the procurement amount in line with
1 18 C.F.R. § 385.211 (2026).2 Compare PJM Interconnection, L.L.C., Critical Issue Fast Path – Reliability Backstop Procurement PJM Proposal, at 4 n.4, (Apr. 16, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260416/20260416-item-05---pjm-reliability-backstop-procurement-proposal---paper.pdf (proposing an initial target of ~15 GW), with PJM Interconnection, L.L.C., Transmittal, Docket No. ER26-3380-000, at 31 (filed Jul. 31, 2026) (“Transmittal”) (setting the Initial RBP Target as 6,831.3 MW UCAP).
PDF page 2
-2-
the observed shortfall. By targeting the observed shortfall, PJM has mitigated the risk of capacity overprocurement, which could otherwise lead to harmful long term market impacts, including the premature retirements of needed resources, which would ultimately exacerbate the very reliability challenge RBP is intended to remedy. PJM’s targeted approach will help ensure the reliability of the PJM system without sacrificing affordability or unduly undermining the RPM and other tools that should form the basis of a durable approach to ensuring resource adequacy at just and reasonable rates.
I. LIMITED PROTEST
Notwithstanding Vistra’s general support of the proposal, Vistra submits this limited protest to address certain discrete issues and ensure that the RBP proposal is consistent with cost causation principles and is not unduly discriminatory. PJM explicitly “consent[ed] to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”3
First, PJM’s proposal to allocate RBP costs to all load-serving entities (“LSEs”)—for a locked-in fifteen-year period—regardless of whether they contributed to the current resource adequacy shortfall is unjust, unreasonable, and unduly discriminatory. PJM proposes to assign RBP costs to each Electric Distributor zone based on the zone’s share of the regional MW target, then to LSEs within the zone based on a state-determined allocation methodology. If a state does not set a methodology, PJM will default to allocating costs based on a LSE’s peak load
3 Transmittal at 3.
PDF page 3
-3-
contribution.4 But a LSE’s peak load contribution has no inherent relationship with its contribution to the need for the RBP. While a state may well propose a methodology that addresses Vistra’s concerns, there is no requirement that they do so, and PJM’s default methodology is fundamentally flawed.
The just and reasonable standard in the Federal Power Act (“FPA”) requires that costs be allocated in a manner that is “roughly commensurate” with benefits.5 As applied here, that principle means that the costs of incremental investments needed to ensure reliable service should be borne by the parties that cause the need for those investments.6 And the Commission may not approve a scheme requiring a party to pay for facilities from which it derives “benefits that are trivial in relation to the costs.”7
The resource adequacy shortfall that caused PJM to pursue the RBP is the result of certain LSEs agreeing to serve load in excess of their available supply. It is the cumulative effect of those shortfalls that led to PJM’s resource adequacy deficit. By the same token, LSEs with sufficient supply to cover their load obligation did not cause the need for RBP. Although PJM contends that the resource adequacy shortfall is simply the subsequent product of growth among new large
4 Transmittal at 98-99 (citing id., Attach. B (Revisions to the PJM Open Access Transmission Tariff and PJM Reliability Assurance Agreement) at attach. DD, § 18.3(b)(iii) (“Proposed Tariff”)).5 See Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260-62 (D.C. Cir. 2018); Long Island Power Auth. v. FERC, 27 F.4th 705, 714-15 (D.C. Cir. 2022) (quoting Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009) (“Illinois Commerce I”)); Neb. Pub. Power Dist. v. FERC, 957 F.3d 932, 939-41 (8th Cir. 2020); Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022); see also BNP Paribas Energy Trading GP
v. FERC, 743 F.3d 264, 267-68 (D.C. Cir. 2014) (“The Natural Gas Act requires that rates be just and reasonable and not unduly discriminatory. The Commission has ‘added flesh to these statutory bones’ through adoption of the ‘cost causation’ principle . . . . The flip side of this principle is that the Commission generally may not single out a party for the full cost of a project, or even most of it, when the benefits of the project are diffuse.”); K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).
6 See BNP Paribas Energy Trading, 743 F.3d at 267; Battle Creek Gas Co. v. Fed. Power Comm’n, 281 F.2d 42, 46-48 (D.C. Cir. 1960); El Paso Elec. Co. v. FERC, 76 F.4th 352, 357-58, 361 (5th Cir. 2023) (“El Paso II”).7 See Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 18-19 (D.C. Cir. 2021); Illinois Commerce I, 576 F.3d at 477; Ill. Com. Comm’n v. FERC, 756 F.3d 556, 561-62, 564 (7th Cir. 2014) (“Illinois Commerce II”).
PDF page 4
-4-
loads,8 neither the RPM nor the physics of the bulk power system distinguishes among retail customers.9 The shortfall is simply the result of certain LSEs committing to serve more demand than they have supply. Allocating the cost of covering the cumulative shortfall to LSEs that had no shortfall and, thus, did not contribute to it would be patently inconsistent with cost causation.10 Nor do such entities meaningfully benefit from RBP because they already procured the capacity they need. To the extent those entities enjoy any benefits from RBP, they are trivial in relation to the costs that RBP promises to impose.
Second, PJM’s proposal is unduly discriminatory because it excludes Fixed Resource Requirement (“FRR”) entities from RBP cost allocation based on the very cost causation principle described above, while not applying the principle to other entities to which it equally applies.11 PJM proposes to exclude FRR entities principally because they have already paid for sufficient capacity to meet their needs, such that “[a]llocating RBP Charges to FRR load would, in essence, require that they pay twice for capacity it has already procured.”12 Vistra takes no issue with that treatment of FRR entities in isolation. But, as explained above, the same principle—excluding entities that procured sufficient capacity from RBP cost allocation—applies equally to competitive retail suppliers that similarly have procured sufficient generation to meet their load needs. As a result, it would be textbook undue discrimination to exclude FRR entities from RBP because they have already paid for the capacity they need while not excluding competitive retail suppliers that have done the same. Entities are “similarly situated” where there are “no differences
8 See Transmittal at 6-8, 19.9 Cf. BNP Paribas Energy Trading, 743 F.3d at 268-69 (establishing that “the cost causation principle itself manifests a kind of equity” such that all load is economically marginal).10 See El Paso II, 76 F.4th at 362; S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, (D.C. Cir. 2014).11 Transmittal at 31-32.12 Id. n.92.
PDF page 5
-5-
material to the inquiry at hand.”13 Here, the inquiry at hand is whether an entity bears responsibility for the resource adequacy shortfall the RBP is designed to cure. On that question, there is no difference between FRR entities and competitive retail suppliers with balanced books. Both have secured capacity to cover their load. Neither entity contributed to the shortfall, so neither should be swept into the auction mechanism designed to remedy it.
PJM offers no reasoned basis for treating these entities differently. Nor can it. The fact that FRR entities opt out of the RPM does not justify the differential treatment. RBP is designed to cure PJM’s resource adequacy shortfall. The material questions at hand, then, is who caused that shortfall and who benefits from additional procurement? On those questions, FRR entities and competitive suppliers with balanced supply and demand books are similarly situated. The mechanism by which each entity accomplished the goal of covering its own capacity needs is irrelevant to the question of who should pay for the procurement necessary to cover the shortfall. Neither FRR entities nor competitive suppliers with sufficient supply to serve their demand contributed to the shortfall, so neither should be required to pay to remedy it. To ensure RBP is just and reasonable and not unduly discriminatory, the Commission should not permit PJM to impose RBP costs on competitive retail suppliers that already have balanced books. This result is also in line with the PJM Governors’ principles that PJM repeatedly invokes. Those principles direct that RBP costs be allocated “to LSEs with new data centers that have not self-procured new capacity or agreed to be curtailable,” with “any remaining costs . . .
13 See ISO New England Inc., 162 FERC ¶ 61,205, at P 44 (2018) (quoting N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10, n.30 (2018) (“To say that entities are similarly situated does not mean that there are no differences between them; rather, it means that there are no differences that are material to the inquiry at hand.”)).
PDF page 6
-6-
allocated to LSEs based on their remaining net short positions.”14 A competitive supplier with a balanced book, by definition, has no net short position.
Finally, Vistra is also concerned with PJM’s fixed approach for allocating RBP costs. The proposed Tariff language provides that each “zone/area’s assigned share of the Final RBP Target MW shall remain constant throughout the fixed 15-year term.”15 If there is anything that the last five years have shown conclusively in PJM, it’s that load growth can be hard to anticipate in advance. Over the 15 years following the RBP, load will grow more than expected in some places and less than expected in others, but the RBP cost allocation will be frozen in time. That static approach all but guarantees that costs will not be allocated in a manner that is roughly commensurate with benefits. Although PJM claims that the 15-year contract term will provide financing certainty, it is not clear why the zonal allocation needs to be frozen to accomplish that goal. The principal concern for financiers should be that project costs can be recovered, not the ultimate retail customers from which that is derived.
Neither of these issues requires the Commission to reject RBP altogether. Rather, the Commission can and should require PJM to modify its proposal by allocating RBP costs to LSEs based on their net short positions. PJM explicitly consented to the Commission’s modification of the proposed Tariff as permitted under section 205 of the FPA and NRG. These are discrete issues that require necessary modification, consistent with NRG, and preserve the overarching goal of PJM’ filing. 16
14 Statement of Principles Regarding PJM, National Energy Dominance Council, at 1 (Jan. 15, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.15 Proposed Tariff, attach. DD, §18.3(b)(ii). 16 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) (explaining that the Commission can make minor modifications with the utility’s consent.).
PDF page 7
-7-
II. CONCLUSION
As this Commission considers PJM’s proposal, it is important not to miss the forest for the trees. RBP is intended to be a one-time, narrowly tailored solution to incentivize new resource additions to meet short-term load growth.17 This is not PJM’s first stop-gap measure. The cascade of “one-time” interventions in PJM’s capacity market risks creating a negative feedback loop that divorces the market from economic fundamentals, jeopardizing its ability to attract much-needed infrastructure investment. While there are important near-term challenges to address, in the long term, price signals based on market fundamentals are critical to ensuring resource adequacy and affordability. Without market signals based on accurate supply and demand dynamics, PJM will continue to struggle to incentivize and retain sufficient generation to meet demand. Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 400
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
Nicholas M. Gladd
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
Counsel for Vistra Corp.
Dated: August 21, 2026
17 Transmittal at 1,7, 25.
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: August 21, 2026
San Francisco, CA
/s/ Jenae Sharp
Jenae Sharp
Wilson Sonsini Goodrich & Rosati
One Market Plaza,
Spear Tower #3300
San Francisco, CA 94105
(650) 722-6123
jmsharp@wsgr.com