Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C. to Comments and Protests re the 07/31/2026 revised Open Access Transmission Tariff filing et al
PJM files a motion for leave to answer and answers the comments and protests on its July 31 Reliability Backstop Procurement, defending the 15-year term, $555/MW-day cap, cost allocation, LSE credit and exit rules and offering some clarifications.
Asks FERC to: Accept the answer and accept the RBP tariff revisions effective September 29, 2026, as requested.
Defends PJM's Reliability Backstop Procurement in ER26-3380, the capacity adequacy and cost allocation track that runs beside E-7's request for a report on ensuring adequate generation.
E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8) E-7 PJM: Cost-recovery agreement (P 77, p. 28)
Key points
- PJM says no protest undermines its one-time backstop procurement as just and reasonable.
PJM’s RBP proposal is a just and reasonable and not unduly discriminatory or preferential means to procure capacity through a one-time backstop procurement. PDF p. 2
- PJM says it frames the RBP around the region's 67 million people in 13 states and the District of Columbia.
to keep the lights on for 67 million people across 13 states and the District of Columbia PDF p. 3
- PJM is open to specific adjustments in a compliance filing if FERC orders them.
adjustments to incorporate intervenors’ suggestions into the RBP proposal in a compliance filing if so ordered by the Commission. PDF p. 9
- PJM says Electric Distributors only report and administer, and do not bear RBP Charges unless they are also the LSE.
Electric Distributors perform a reporting or administrative role in the RBP PDF p. 12
- PJM ties the 15-Delivery Year maximum term to the NEDC and governors' principles.
the fixed, maximum 15-Delivery Year term is informed by the NEDC/PJM Governors’ Principles PDF p. 31
- PJM defends the $555/MW-day UCAP cap as a MW-weighted average on a pay-as-bid procurement.
PJM has proposed that the levelized procurement cost of all selected RBP Sell Offers not exceed a maximum willingness to pay of $555/MW-day UCAP, on a MW-weighted average basis over all Delivery Years of the RBP. PDF p. 36
- PJM defends sizing the cost allocation on a snapshot of the 2028/2029 shortfall.
The Commission has long held that relying on snapshots is an acceptable and appropriate method for establishing baselines or targets, PDF p. 60
- PJM defends the LSE collateral requirement as protecting other ratepayers.
the basic need for a collateral requirement should not be controversial. PDF p. 74
- PJM says its Transmission Owner exit terms give enough notice.
None of these arguments render PJM’s proposed Tariff revisions unjust and unreasonable. PDF p. 95
Contents · 12 sections
- I. ANSWER
- A. The RBP Proposal Is a Measured and Timely Response that Received
- B. The Role of Electric Distributors in the RBP Is Appropriately Tailored.
- C. Nothing in Intervenors’ Protests, Comments Call into Question the
- D. RBP Offsets Should Neither Be Expanded to Include Additional Types of
- E. PJM Addresses Several Intervenor Requests for Clarification to the
- F. PJM’s Procurement Process Is Just and Reasonable.
- G. The Requirement for RBP Resources to Offer into the RPM As
- H. Arguments That RBP Should Be Extended to FRR Entities Are Baseless.
- I. PJM’s Proposed Cost Allocation Approach Appropriately Assigns Cost
- D. Jaramillo on Behalf of Northern Virginia Electric Cooperative, at 4 (Va. S.C.C. Dec. 16, 2024),
- II. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Credit and exit · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
PJM therefore asks that the Commission accept this Answer.Read this passage Filed comments: Reliability and curtailment
I. ANSWER
printed heading
I.Read this passage
A. The RBP Proposal Is a Measured and Timely Response that Received
printed heading · Topic match: Reliability and curtailment
The PJM region must address near-term deficiencies to begin focusing on the long-term solution, which is why Dominion Energy supports the RBP.”). 19 AEU Comments at 1 (“[Advanced Energy] United generally supports PJM’s July 31, 2026, filing as the best available solution to address the pressing…Read this passage Filed comments: Reliability and curtailment
B. The Role of Electric Distributors in the RBP Is Appropriately Tailored.
printed heading · Topic match: Cost allocation
The allocation of these inputs impacts cost allocation and credit requirements.”38 These “allocation inputs” are, indeed, inputs to PJM forecasts that Electric Distributors already provide.Read this passage Filed comments: Cost allocation
C. Nothing in Intervenors’ Protests, Comments Call into Question the
printed heading · Topic match: Reliability and curtailment
Furthermore, PJM proposes to procure for the known and measurable shortfall reflected in the 2028/2029 BRA in recognition that the value is not in dispute and that the RBP is not intended to be the one and only solution to the resource adequacy challenges facing the PJM Region today. 3.Read this passage Filed comments: Reliability and curtailment
D. RBP Offsets Should Neither Be Expanded to Include Additional Types of
printed heading · Topic match: Connecting load and generation
It is true that there may be more than one just and reasonable means of accommodating short lead-time resources in PJM's auctions, and in determining whether to accept PJM's filing, the Commission must only determine that PJM’s proposed solution is just and reasonable, not that it is superior to…Read this passage Filed comments: Connecting load and generation
E. PJM Addresses Several Intervenor Requests for Clarification to the
printed heading · Topic match: Reliability and curtailment
PJM Addresses Several Intervenor Requests for Clarification to the Proposed Opt-Outs. 1.Read this passage Filed comments: Reliability and curtailment
F. PJM’s Procurement Process Is Just and Reasonable.
printed heading · Topic match: Cost allocation
The JCA asserts, “it is also unduly discriminatory to require some ratepayers to pay for fifteen-year procurements when other ratepayers are insulated from RBP charges due to exemptions or bilateral/self-supply arrangements of only five years.”103 But ratepayers can choose.Read this passage Filed comments: Cost allocation
G. The Requirement for RBP Resources to Offer into the RPM As
printed heading · Topic match: Cost allocation
The Commission has consistently rejected the position that requiring resources that are procured outside of a capacity market to offer into the capacity market as price takers would unjustly and unreasonably distort or suppress capacity market clearing prices.136 Indeed, as recently as last year,…Read this passage Filed comments: Cost allocation
H. Arguments That RBP Should Be Extended to FRR Entities Are Baseless.
printed heading · Topic match: Reliability and curtailment
This does not implicate FRR Entities.160 By definition, FRR Entities must bring new capacity for all new loads within their territory.161 If an FRR Entity does not include sufficient capacity in its FRR Capacity Plan, the FRR Entity is subject to “an FRR Commitment Insufficiency Charge, in an…Read this passage Filed comments: Reliability and curtailment
I. PJM’s Proposed Cost Allocation Approach Appropriately Assigns Cost
printed heading · Topic match: Cost allocation
Accordingly, “PJM evaluated methodologies for determining the amount of collateral required from LSEs.”248 PJM determined that “a methodology that first determines the aggregate collateral necessary to address the payment exposure associated with the portfolio of committed RBP Resources and then…Read this passage Filed comments: Cost allocation
D. Jaramillo on Behalf of Northern Virginia Electric Cooperative, at 4 (Va. S.C.C. Dec. 16, 2024),
printed heading · Topic match: Credit and exit
With respect to collateral requirements, the Virginia State Corporation Commission approved Dominion’s proposed terms, “including: (1) $1.5 million/MW; (2) a reduction up to 70% based on the customer’s established credit; (3) provisions for third-party guarantees and letters of credit; and (4)…Read this passage Filed comments: Credit and exit
II. CONCLUSION
printed heading
CONCLUSION PJM asks that the Commission consider this Answer and accept the proposed Tariff revisions in this docket, effective September 29, 2026, as requested.Read this passage
CERTIFICATE OF SERVICE
printed heading · Topic match: Registry access
Appendix A Protests, Comments, Requests for Clarification, and Answers Filed to Date Docket No.Read this passage Filed comments: Registry access