ER26-3380-000 · 2026-08-21 · Institute for Policy Integrity, New York University School o

Comments of Institute for Policy Integrity at New York University School of Law on PJM Interconnection, L.L.C.’s Section 205 filing to implement Reliability…

Text extracted from the eLibrary original (SHA-256 3612692fabec68ad…). Download the original from the official source.

Contents · 11 sections
  1. I. BACKGROUND p. 2
  2. II. FERC should reject the proposed tariff revisions because PJM has failed to p. 6
  3. A. PJM must prove that its proposed tariff revisions are just and reasonable p. 6
  4. B. FERC should reject the proposed tariff because PJM has not adequately p. 8
  5. C. The Backstop Auction will not isolate the Legacy Capacity Market from the p. 10
  6. D. FERC should reject the tariff revisions because PJM can address its resource p. 14
  7. III. If FERC permits PJM to implement the Backstop Auction, FERC should require p. 23
  8. A. FERC should require PJM to adjust the Backstop Auction design to mitigate p. 23
  9. B. FERC should require PJM to adjust Backstop Auction design to mitigate the p. 26
  10. C. FERC should require PJM to adjust the Backstop Auction design to avoid p. 28
  11. IV. Conclusion p. 28

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Part II explains that FERC should reject PJM’s proposed tariff because PJM has 1 This document does not purport to present the views, if any, of New York University School of Law. 2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from…
Read this passage Filed comments: Reliability and curtailment

I. BACKGROUND

printed heading · Topic match: Cost allocation

PJM may implement future BRAs with more reliable load forecasts, since the PJM Board recently directed PJM Staff to implement a host of reforms to the load forecasting process, including state review of large load additions, addressing duplicative requests, and the use of additional third-party…
Read this passage Filed comments: Cost allocation

II. FERC should reject the proposed tariff revisions because PJM has failed to

printed heading

FERC should reject the proposed tariff revisions because PJM has failed to demonstrate that the Backstop Auction is just and reasonable.
Read this passage

A. PJM must prove that its proposed tariff revisions are just and reasonable

printed heading · Topic match: Cost allocation

PJM must prove that its proposed tariff revisions are just and reasonable and supported by substantial evidence.
Read this passage Filed comments: Cost allocation

B. FERC should reject the proposed tariff because PJM has not adequately

printed heading · Topic match: Reliability and curtailment

FERC, 744 F.3d at 93 (establishing the “substantial evidence” standard). 30 Tariff, supra n. 28, Attachment DD, section 16. 31 FERC Order Delays Capacity Auction to Allow for Consideration of Resource Adequacy Reform, PJM INSIDE LINES (June 12, 2023), https://perma.cc/9QVK-YF3G. 32 See id. 9…
Read this passage Filed comments: Reliability and curtailment

C. The Backstop Auction will not isolate the Legacy Capacity Market from the

printed heading · Topic match: Cost allocation

And these effects would persist for the next 15 years because capacity committed through the Backstop Auction must also bid into the BRA for each year of its contract.
Read this passage Filed comments: Cost allocation

D. FERC should reject the tariff revisions because PJM can address its resource

printed heading · Topic match: Cost allocation

Transmission costs are a significant element of the cost of providing power.76 Suppliers must pay for the cost of network upgrades to serve their new supply, but it can be difficult to predict what these costs will be.77 The resulting uncertainty makes it difficult to include these costs upfront in…
Read this passage Filed comments: Cost allocation

III. If FERC permits PJM to implement the Backstop Auction, FERC should require

printed heading

But if FERC permits PJM to implement the Backstop Auction, it should require PJM to implement adjustments to the proposed market design which reduce the risk that the Backstop Auction will result in unjust and unreasonable rates.82 FERC should require PJM to adjust its proposed market design to…
Read this passage

A. FERC should require PJM to adjust the Backstop Auction design to mitigate

printed heading · Topic match: Cost allocation

PJM proposes to set the procurement target for the Backstop Auction as the 2028/2029 BRA capacity shortfall.84 PJM chose this number based on forecasts for one delivery year and did not forecast capacity needs over the next 15 years.
Read this passage Filed comments: Cost allocation

B. FERC should require PJM to adjust Backstop Auction design to mitigate the

printed heading · Topic match: Cost allocation

PJM proposes to assign the costs of the Backstop Auction to zones based on their pro rata share of the procurement target, and then to allocate costs to LSEs based cost allocation mechanisms submitted by the relevant state or RERRA.
Read this passage Filed comments: Cost allocation

C. FERC should require PJM to adjust the Backstop Auction design to avoid

printed heading

To do this, FERC should require PJM to eliminate the requirement that demand response resources must have a 15-year agreement in place to participate in the Backstop Auction.94 Demand response resources are some of the least expensive capacity resources available and imposing onerous restrictions…
Read this passage

IV. Conclusion

printed heading · Topic match: Cost allocation

In the alternative, if FERC is inclined to permit PJM to implement some version of the Backstop Auction, FERC should require PJM to refile its proposed tariff with 93 See Old Dominion, 898 F.3d at 1255 (establishing the cost causation principle). 94 Tariff Filing, supra n. 2, 54. 95 See generally…
Read this passage Filed comments: Cost allocation