East Kentucky Power Cooperative, Inc. submits Request for Rehearing of the 09/29/2026 Order
Text extracted from the eLibrary original (SHA-256 e72b50ee12dbf292…). Download the original from the official source.
Contents · 14 sections
- I. Background
- A. RBP Proposal
- B. Protest
- C. The Commission’s Order Accepting the RBP Proposal Subject to
- II. Statement of Issues and Specification of Errors
- III. Request for Rehearing
- A. The Commission Erred by Failing to Address EKPC’s Argument That
- B. The Commission Erred by Failing to Address EKPC’s Argument That
- C. The Commission’s Order Is Arbitrary and Capricious Because It Fails
- D. The Commission’s Order Is Arbitrary and Capricious Because It Is
- E. The Commission’s Order Is Arbitrary and Capricious Because It
- F. The Commission Erred in Its Determination That There Is No Undue
- G. The Commission’s Acceptance of the RBP Is Not Based on Substantial
- IV. Conclusion
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Credit and exit
Pursuant to section 313 of the Federal Power Act (“FPA”)1 and Rule 713 of the Commission’s Rules of Practice and Procedure,2 East Kentucky Power Cooperative, Inc. (“EKPC”) respectfully requests rehearing of the Commission’s order accepting, subject to refund and additional proceedings, PJM…Read this passage Filed comments: Credit and exit
I. Background
printed heading
I.Read this passage
A. RBP Proposal
printed heading · Topic match: Cost allocation
If no RBOs are reported, PJM would allocate the zone/area’s RBP Charges to all load in the zone/area using each LSE’s ratio share of the Daily Unforced Capacity Obligation under RAA, Schedule 8.7 Separately, PJM proposed an LSE collateral requirement equal to an RBP Credit Rate of $1.5 million…Read this passage Filed comments: Cost allocation
B. Protest
printed heading · Topic match: Credit and exit
Coscia’s Affidavits also addressed the exposure basis and quantity underlying the credit and collateral requirements, the interaction with existing PJM credit rules, and the treatment of defaults.30 Proposed Tariff Attachment DD section 18.9(a) requires reallocation of defaulted RBP Charges among…Read this passage Filed comments: Credit and exit
C. The Commission’s Order Accepting the RBP Proposal Subject to
printed heading · Topic match: Credit and exit
EL26-108-000.35 The Commission identified three hearing topics: cost allocation, Transmission Owner exit rules, and LSE collateral requirements.36 It stated that “the other aspects of PJM’s RBP proposal are just and reasonable.”37 On cost allocation, the Commission questioned reliance on Load…Read this passage Filed comments: Credit and exit
II. Statement of Issues and Specification of Errors
printed heading · Topic match: Credit and exit
The Commission erred by failing to address EKPC’s argument that a self-supply LSE’s existing portfolio of resources must be considered.Read this passage Filed comments: Credit and exit
III. Request for Rehearing
printed heading · Topic match: Filing procedure
Request for Rehearing Under the Administrative Procedure Act and federal appellate court precedent, the Commission’s decisions will be set aside on appeal if they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,” or “unsupported by substantial…Read this passage Filed comments: Filing procedure
A. The Commission Erred by Failing to Address EKPC’s Argument That
printed heading · Topic match: Cost allocation
To the extent that the Order accepted this feature, the Commission must address EKPC’s objections on rehearing.Read this passage Filed comments: Cost allocation
B. The Commission Erred by Failing to Address EKPC’s Argument That
printed heading · Topic match: Cost allocation
If the Commission intended in its Order to accept this feature, the Commission must address EKPC’s objections on rehearing.Read this passage Filed comments: Cost allocation
C. The Commission’s Order Is Arbitrary and Capricious Because It Fails
printed heading · Topic match: Credit and exit
DD, § 18.3(b)). 73 See Order at PP 119, 123, 157. 74 Order at PP 23-27. 18 As EKPC explained in its Protest, the default allocation “socializes RBP costs across all load within the zone – including LSEs serving customer bases that contributed nothing to the capacity shortfall,” violating the…Read this passage Filed comments: Credit and exit
D. The Commission’s Order Is Arbitrary and Capricious Because It Is
printed heading · Topic match: Cost allocation
The Commission correctly determined that the relevant legal standard to use in this proceeding is its cost-causation principle that requires that all approved rates “reflect to some degree the costs actually caused by the customer who must pay them.”83 As the Commission explained in its Order, “a…Read this passage Filed comments: Cost allocation
E. The Commission’s Order Is Arbitrary and Capricious Because It
printed heading · Topic match: Credit and exit
To the extent the Order accepted that methodology or excluded EKPC’s objections from the hearing, its failure to address those predicate issues is arbitrary and capricious. 86 Order at PP 204-05. 87 Order at P 206. 88 See Coscia Reply Affidavit at PP 17-24, 71-73; EKPC September 18 Answer at 12-16.…Read this passage Filed comments: Credit and exit
F. The Commission Erred in Its Determination That There Is No Undue
printed heading · Topic match: Cost allocation
But that access alone does not establish that every self-supply LSE caused this incremental procurement need or receives benefits sufficient to justify its particular RBP Charges, collateral burdens, and default exposure.112 The Commission must 107 See Protest at 45-47; Bednarczyk Affidavit at PP…Read this passage Filed comments: Cost allocation
G. The Commission’s Acceptance of the RBP Is Not Based on Substantial
printed heading · Topic match: Cost allocation
The Commission must address whether such residual exposure exists, what collateral secures it, and how it is consistent with cost causation.Read this passage Filed comments: Cost allocation
IV. Conclusion
printed heading · Topic match: Credit and exit
Conclusion Wherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the Commission grant rehearing for the reasons discussed herein or, where the Order’s reservation of an issue is unclear, clarify that the paper hearing encompasses the independent LSE-level cost- allocation,…Read this passage Filed comments: Credit and exit
Certificate of Service
printed heading
Dated at Washington, DC this 29th day of October, 2026. /s/ Kelly A.Read this passage