ER26-3380-001 · 2026-10-29 · East Kentucky Power Cooperative, Inc.

East Kentucky Power Cooperative, Inc. submits Request for Rehearing of the 09/29/2026 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000

)
EL26-108-00

)

REQUEST FOR REHEARING OF
EAST KENTUCKY POWER COOPERATIVE, INC.

Pursuant to section 313 of the Federal Power Act (“FPA”)1 and Rule 713 of the Commission’s Rules of Practice and Procedure,2 East Kentucky Power Cooperative, Inc. (“EKPC”) respectfully requests rehearing of the Commission’s order accepting, subject to refund and additional proceedings, PJM Interconnection, L.L.C.’s (“PJM”) revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) establishing the Reliability Backstop Procurement (“RBP”) .3

The Commission erred in accepting aspects of the RBP Proposal without adequately addressing EKPC’s cost-causation objections. The Commission did not explain why the existing self-supply portfolio of a load-serving entity (“LSE”) may be disregarded in determining the LSE’s RBP exposure, or why qualifying offsets need not reduce the obligations of the LSE or the load that supplied them. Nor did it explain whether it accepted PJM’s default allocation to all LSEs in a zone/area when no state- or Relevant Electric Retail Regulatory Authority (“RERRA”)- determined allocation is reported or reserved that distinct issue for further proceedings. The Commission rejected EKPC’s Fixed Resource Requirement (“FRR”) comparability argument without adequately addressing the relevance of comparable resource-planning actions by

1 16 U.S.C. § 825l (2018).
2 18 C.F.R. § 385.713 (2026). 3 PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026) (“Order”).

PDF page 2

2
Reliability Pricing Model (“RPM”) self-supply LSEs. And, despite setting certain collateral elements for paper hearing, the Commission did not adequately address EKPC’s foundational objections to the exposure, quantity, release, and default-allocation methodology underlying the LSE collateral requirement.

Although the Commission established paper hearing procedures on cost allocation, Transmission Owner exit rules, and LSE collateral requirements, it stated that aside from the issues reserved for hearing, “the other aspects of PJM’s RBP proposal are just and reasonable.”4 The Order does not clearly establish whether the independent cost-causation and collateral- methodology objections identified below remain open. To the extent that the Commission rejected those objections or accepted the challenged provisions, EKPC requests rehearing. Alternatively, EKPC requests clarification that the paper hearing encompasses those objections and that no adverse determination has been made on them. A subsequent section 205 proposal does not resolve whether the Order adequately addressed the framework before the Commission.

I. Background
A. RBP Proposal
PJM filed the RBP Proposal on July 31, 2026 as a one-time procurement of new capacity for terms of up to 15 years, beginning no earlier than the 2028/2029 Delivery Year and ending no later than the 2042/2043 Delivery Year.5 At the zone/area level, PJM proposed to allocate the Initial RBP Target to Electric Distributor zone/areas based on each zone/area’s pro rata share of the difference in forecasted Load Adjustments between the 2026/2027 and 2028/2029 Delivery Years, reduced by qualifying offset capacity and opted-out load, and to fix that allocation for the

4 Order at PP 23-24.
5 Order at PP 1, 15.

PDF page 3

3
15-year term.6 At the LSE level, within each zone/area, PJM proposed to allocate costs to LSEs based on a state- or RERRA-determined RBP Obligation (“RBO”) reported by the Electric Distributor. If no RBOs are reported, PJM would allocate the zone/area’s RBP Charges to all load in the zone/area using each LSE’s ratio share of the Daily Unforced Capacity Obligation under RAA, Schedule 8.7 Separately, PJM proposed an LSE collateral requirement equal to an RBP Credit Rate of $1.5 million multiplied by committed RBP MW, payable in cash or letter of credit 45 days before the first Delivery Year, with defaulted RBP Charges reallocated to remaining LSEs.8

B. Protest
EKPC timely intervened and filed a Protest, supported by the Affidavits of Adam
Bednarczyk and Carl F. Coscia, Ph.D. on August 21, 2026.9 EKPC also filed a Limited Answer on September 4, 2026,10 and a Second Limited Answer, supported by a Reply Affidavit of Dr. Coscia, on September 18, 2026.11 The Commission accepted EKPC’s Answers.12

In proposing the RBP, PJM claimed that the RBP is “a critical safety net designed to address current resource adequacy shortfalls.”13 EKPC shares PJM’s concern about resource

6 Order at P 99 (citing Proposed Tariff, attach. DD, § 18.3(a)). 7 Order at P 110 (citing Proposed Tariff, attach. DD, § 18.3(b)). 8 Order at PP 183-84 (citing Proposed Tariff, attach. DD, §§ 18.8, 18.9). 9 PJM Interconnection, L.L.C., “Protest of East Kentucky Power Cooperative, Inc.,” Docket No. ER26-3380-000 (filed Aug. 21, 2026) (“Protest”); Affidavit of Adam Bednarczyk, Attachment 1 to Protest (“Bednarczyk Affidavit”); Affidavit of Carl F. Coscia, Attachment 2 to Protest (“Coscia Protest Affidavit”). 10 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 4, 2026) (“EKPC September 4 Answer”). 11 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc.” (filed Sept. 18, 2026) (“EKPC September 18 Answer”); Reply Affidavit of Carl F. Coscia, Attachment 1 to EKPC September 18 Answer (“Coscia Reply Affidavit”).
12 Order at P 22.
13 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”).

PDF page 4

4
adequacy and the reliability challenges facing the PJM region. Fundamentally, however, as EKPC explained in its Protest,14 the RBP is inconsistent with the Commission’s cost-causation principles. EKPC has argued and demonstrated, with record evidence, that the RBP fails to “protect LSEs whose existing resource portfolios already support their expected load obligations from incurring additional costs.”15 That risk extends to entities like EKPC “whose supply portfolio contains sufficient resources to serve the load underlying PJM’s forecast.”16

As EKPC explained in its Protest, to be just and reasonable and not unduly discriminatory or preferential, rates must reflect the cost-causation principle that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.”17 In its Protest, EKPC explained that rate design decisions must be supported by “substantial evidence.”18 PJM failed to provide any evidence “that allocating costs based on total zonal load obligations bears any reasonable relationship to the load growth that caused the shortfall. LSEs with no or minimal large load growth may nonetheless be allocated disproportionate costs due to improper accounting of the offsets and opt-outs or the use of the default allocation methodology.”19 The potential for socializing costs across all LSEs, regardless of causation, fails the legal and economic tests of “just and reasonable” ratemaking.

14 Protest at 11-12, 18-19, 21, 28-31, 37-39.
15 Protest at 11.
16 Protest at 11.
17 Protest at 30 (quoting KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992)).
18 Protest at 21 (citing Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1233 (D.C. Cir. 2005) (“Upon applying the usual APA standard, we conclude that the Commission’s approval of the rate design is supported by substantial evidence in the record and is not otherwise arbitrary and capricious.”)).
19 Protest at 21.

PDF page 5

5
The evidence provided by EKPC in the Bednarczyk Affidavit shows that a generalized showing of regional reliability need does not support PJM’s particular rate design.20 As explained by Mr. Bednarczyk, the RBP does not “track mitigation measures” or keep costs aligned with the parties who create or mitigate the need.21 Existing resources cannot earn RBP revenue, and treating them differently becomes a problem when the Tariff also refuses to count them in deciding who caused the need.22 For self-supply LSEs like EKPC, the question is whether their own resource- adequacy actions reduce their RBP exposure.23 As Mr. Bednarczyk explained, self-supply LSEs face particular risk if their resource positions are not recognized,24 and crediting offsets only at the zonal level weakens incentives for forward procurement.25 And regarding PJM’s proposed default cost allocation, by defaulting to Daily Unforced Capacity Obligation, PJM is defaulting to a “broad capacity-allocation metric” that “does not identify the LSEs that created the residual procurement need.”26 Under the proposed default allocation methodology, an LSE whose load growth is ordinary and whose resources are sufficient bears costs caused by another LSE.27 As explained by Dr. Coscia, unlike Peak Load Contribution (“PLC”)-based charges, which follow measured load, the RBP Obligation assigns a fixed 15-year quantity based on a forecast that does not fall if the

20 Bednarczyk Affidavit at P 7.
21 Bednarczyk Affidavit at P 7.
22 Bednarczyk Affidavit at PP 25-26.
23 Bednarczyk Affidavit at P 35.
24 Bednarczyk Affidavit at P 36.
25 Bednarczyk Affidavit at P 38.
26 Bednarczyk Affidavit at P 17.
27 Bednarczyk Affidavit at P 18.

PDF page 6

6
load never appears.28 The Load Adjustment inputs were submitted for planning purposes and were never verified for cost allocation.29

Dr. Coscia’s Affidavits also addressed the exposure basis and quantity underlying the credit and collateral requirements, the interaction with existing PJM credit rules, and the treatment of defaults.30 Proposed Tariff Attachment DD section 18.9(a) requires reallocation of defaulted RBP Charges among remaining LSEs responsible for those charges, while application of the defaulting LSE’s collateral is permissive.31 Dr. Coscia’s Affidavits separately identify potential residual exposure under Operating Agreement section 15.2.2 for Members without an initial RBP allocation.32 That concern does not depend on EKPC receiving a zero allocation: it concerns the relationship between the exposure secured, the entities posting collateral, and the entities potentially bearing a residual loss.33

As explained by EKPC in its Protest and Answers, EKPC recognizes the urgency of PJM’s reliability concerns.34 But the RBP as accepted fails to achieve its objectives in a manner consistent with the requirements of the FPA. The RBP assigns long-term costs and collateral obligations through a framework that lacks the specificity necessary to be just and reasonable because the RBP does not sufficiently identify the LSE responsible for causing the capacity shortage, does not ensure that any offsets or opt-outs follow the entity that secured them, and does not protect LSEs whose existing resource portfolios already support their expected load obligations from incurring

28 Coscia Protest Affidavit at PP 159-61.
29 Coscia Protest Affidavit at PP 159-61.
30 See Coscia Reply Affidavit at PP 18-24, 71-73.
31 See Proposed Tariff, attach. DD, § 18.9(a); Coscia Reply Affidavit at PP 18-24.
32 See Coscia Protest Affidavit at PP 168-70; Coscia Reply Affidavit at PP 18-24.
33 See Coscia Reply Affidavit at PP 21-24.
34 Protest at 10-11. See also EKPC September 18 Answer at 3-4.

PDF page 7

7
additional costs. The RBP may attempt to address a legitimate reliability need. But simply attempting to address a legitimate need is not enough to make the RBP Proposal just and reasonable, especially where the resulting costs are not reasonably tied to cost causation.

C. The Commission’s Order Accepting the RBP Proposal Subject to
Additional Proceedings
In the Order, the Commission accepted the RBP for filing, suspended it for five months to become effective February 28, 2027, subject to refund, and established paper hearing procedures and an FPA section 206 proceeding in Docket No. EL26-108-000.35 The Commission identified three hearing topics: cost allocation, Transmission Owner exit rules, and LSE collateral requirements.36 It stated that “the other aspects of PJM’s RBP proposal are just and reasonable.”37 On cost allocation, the Commission questioned reliance on Load Adjustments, directed briefing on updated load forecast information, and “decline[d] to further address arguments raised in the protests related to PJM’s proposed cost allocation method at this time.”38 It separately upheld the FRR exclusion and rejected the comparability argument concerning RPM self-supply LSEs.39 On collateral, it upheld seller collateral, questioned LSE collateral, and expressly requested responses on “(1) what initial RBP Credit Rate is appropriate and (2) whether 45 days before the start of the delivery year is sufficient time for LSEs to post collateral.”40 Those questions do not clearly establish the treatment of the independent allocation and collateral-methodology objections raised here.

35 Order at PP 1, 23-27.
36 Order at P 24.
37 Order at P 23.
38 Order at PP 154-60. 39 Order at P 151.
40 Order at PP 203-06.

PDF page 8

8
The Commission set forth the correct standard by which it must evaluate PJM’s method for allocating RBP costs, explaining that “[u]nder the cost causation principle, all Commission- jurisdictional rates and charges must ‘reflect to some degree the costs actually caused by the customer who must pay for them,’”41 and that “costs must be allocated in a manner that is at least roughly commensurate with benefits.”42 The Commission explained that it “may approve a given cost allocation framework if it ‘has an articulable and plausible reason to believe that the benefits are at least roughly commensurate with’ the assigned costs.”43 Although the Commission articulated that standard and reserved aspects of cost allocation for further proceedings, it did not clearly explain the treatment of EKPC’s distinct LSE-level objections concerning portfolio recognition, offset attribution, and the default allocation. Instead, the Commission addressed the applicability of the RBP to FRR Entities, stated that aspects of PJM’s RBP Proposal may not be just and reasonable, and set a limited number of issues for additional proceedings.44 The Commission failed to address several of the central cost-causation concerns raised by EKPC.

II. Statement of Issues and Specification of Errors
Pursuant to Rules 713(c)(1) and (2), and 203(a)(7),45 EKPC provides the following statement of issues and specification of errors:

1. The Commission erred by failing to address EKPC’s argument that a self-supply LSE’s existing portfolio of resources must be considered. This failure is arbitrary, capricious, not the product of reasoned decision making, and contrary to law. 5 U.S.C. § 706(2). See, e.g., Env’t Def. Fund v. FERC, 2 F.4th 953, 967-68 (D.C. Cir. 2021) (“Thus, the overarching question in this case is whether ‘the Commission’s decisionmaking [wa]s reasoned, principled, and based upon the record.’”) (citation

41 Order at P 150 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); see also Ky. Pub. Serv. Comm’n v. Am. Elec. Power Serv. Corp., 193 FERC ¶ 61,110 (2025) (Ky. Comm’n)).

42 Order at P 150.
43 Order at P 150 (quoting Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)).
44 Order at PP 2, 150-51.
45 18 C.F.R. §§ 385.713(c)(1), 385.713(c)(2), 385.203(a)(7) (2026).

PDF page 9

9
omitted); NBCUniversal Media, LLC v. NLRB, 815 F.3d 821, 823 (D.C. Cir. 2016) (“NBCUniversal”) (“When an agency’s decision lacks adequate justification because it is neither logical nor rational, or because it fails to offer a coherent explanation of agency precedent, the judgment under review is wanting for lack of reasoned decisionmaking.”).

2. The Commission erred by failing to address EKPC’s distinct argument that PJM’s treatment of Qualifying RBP Offset UCAP MW reduces the aggregate procurement target without requiring the offset to reduce the RBO MW, RBP Charges, or collateral obligation of the LSE or load that supplied or sponsored it. To the extent the Commission accepted that treatment, its failure to explain the resulting allocation is arbitrary and capricious and contrary to cost-causation principles. Alternatively, the Commission failed to clarify that LSE-specific offset attribution remains within the paper hearing. 5 U.S.C. § 706(2). See, e.g., Env’t Def. Fund v. FERC, 2 F.4th 953, 967-68 (D.C. Cir. 2021); New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“It is well established that the Commission must respond meaningfully to the arguments raised before it.”) (quoting TransCanada Power Mktg., Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015)).

3. The Commission erred by accepting the challenged cost-allocation features without adequately applying its cost-causation principles or, alternatively, by failing to clarify that those issues remain open for paper hearing. In particular, to the extent the Order accepted the default allocation among LSEs, it did so without explaining its consistency with cost causation. The Commission’s failure to provide a reasoned explanation is arbitrary, capricious, not the product of reasoned decision making, and contrary to law. 5 U.S.C. § 706(2). See, e.g., N.Y. & Atl. Ry. Co. v. Surface Transp. Bd., 635 F.3d 66, 71 (2d Cir. 2011) (“Surface Transp.”) (“An agency also acts in an arbitrary and capricious manner if the ‘agency departs from its own precedent without a reasoned explanation.’”) (citation omitted); Greater Boston Television Corp. v. FCC, 444 F.2d 841, 851-53 (D.C. Cir. 1970) (“Greater Boston”) (“An agency’s view of what is in the public interest may change. . . . But an agency changing its course must supply a reasoned analysis indicating that prior policies and standards are being deliberately changed, not casually ignored.”) (citations omitted); FPL Energy Marcus Hook, L.P. v. FERC, 430 F.3d 441, 448 (D.C. Cir. 2005) (“FPL Energy”) (“[W]e can only uphold the Commission’s interpretation if we can ‘discern a reasoned path’ to the decision.”); NBCUniversal, 815 F.3d at 823 (D.C. Cir. 2016) (“When an agency’s decision lacks adequate justification because it is neither logical nor rational, or because it fails to offer a coherent explanation of agency precedent, the judgment under review is wanting for lack of reasoned decisionmaking.”); Motor Vehicle Mfrs. Ass’n of the United States v. State Farm Mut. Ins. Co., 463 U.S. 29, 43 (1983) (“Motor Vehicles”) (“[A]n agency rule would be arbitrary and capricious if the agency . . . offered an explanation for its decision that runs counter to the evidence before the agency[.]”).

4. The Commission failed to engage in reasoned decision making to the extent it accepted, or excluded from further examination, the challenged LSE collateral

PDF page 10

10
methodology without addressing EKPC’s objections concerning the exposure secured, applicable MW quantity, interaction with Attachment Q and Peak Market Activity, reduction and release standards, application of collateral before default reallocation, and potential residual exposure under Operating Agreement section 15.2.2. Alternatively, the Commission failed to clarify that those issues remain open for paper hearing. 5 U.S.C. § 706(2). See, e.g., Surface Transp., 635 F.3d at 71 (“An agency also acts in an arbitrary and capricious manner if the ‘agency departs from its own precedent without a reasoned explanation.’”) (citation omitted); Greater Boston, 444 F.2d 841 at 851-53 (“An agency’s view of what is in the public interest may change. . . . But an agency changing its course must supply a reasoned analysis indicating that prior policies and standards are being deliberately changed, not casually ignored.”) (citations omitted); FPL Energy, 430 F.3d at 448 (“[W]e can only uphold the Commission’s interpretation if we can ‘discern a reasoned path’ to the decision.”); NBCUniversal, 815 F.3d at 823 (“When an agency’s decision lacks adequate justification because it is neither logical nor rational, or because it fails to offer a coherent explanation of agency precedent, the judgment under review is wanting for lack of reasoned decisionmaking.”); Motor Vehicles, 463 U.S. at 43 (“[A]n agency rule would be arbitrary and capricious if the agency . . . offered an explanation for its decision that runs counter to the evidence before the agency[.]”).

5. The Commission erred in its determination that there is no undue discrimination between FRR Entities and RPM LSEs. This determination is arbitrary, capricious, and not the product of reasoned decision making. 5 U.S.C. § 706(2). See, e.g., Env’t Def. Fund v. FERC, 2 F.4th 953, 967-68 (D.C. Cir. 2021) (“Thus, the overarching question in this case is whether ‘the Commission’s decisionmaking [wa]s reasoned, principled, and based upon the record.’”) (citation omitted); Pacific Gas & Elec. Co. v. FERC, 306 F.3d 1112, 1115, 1121 (D.C. Cir. 2002) (noting that Commission “must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record” and remanding case because reviewed orders “provided no explanation as to how or why” the Commission’s conclusion produced necessary outcome); NBCUniversal, 815 F.3d at 823 (“When an agency’s decision lacks adequate justification because it is neither logical nor rational, or because it fails to offer a coherent explanation of agency precedent, the judgment under review is wanting for lack of reasoned decisionmaking.”).

6. The Commission erred by failing to meaningfully consider the evidence provided in the Bednarczyk and Coscia affidavits. 5 U.S.C. § 706(2). See, e.g., Sithe/Independence Power Partners, L.P. v. FERC, 165 F.3d 944, 948 (D.C. Cir. 1999) (“The Commission must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record, and the path of its reasoning must be clear.” (quoting Town of Norwood v. FERC, 962 F.2d 20, 22 (D.C. Cir. 1992) (internal citations and quotations omitted))); Williston Basin Interstate Pipeline Co. v. FERC, 358 F.3d 45, 48 (D.C. Cir. 2004) (The Commission must make a “reasoned decision based upon substantial evidence in the record.”); Motor Vehicles, 463 U.S. at 43 (agency decision is arbitrary and capricious if “offer[s] an explanation for its decision that runs counter to the evidence before [it]”); S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 54 (D.C. Cir. 2014) (The Commission’s findings

PDF page 11

11
must be supported by substantial evidence, which means “such relevant evidence
as a reasonable mind might accept as adequate to support a conclusion.”); BNP
Paribas Energy Trading GP v. FERC, 743 F.3d 264, 270 (D.C. Cir. 2014) (“[W]e
cannot affirm on the basis of a Commission rationale that fails to respond to critical arguments raised before the agency.”); New England Power Generators Ass’n, Inc.

v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“It is well established that the
Commission must respond meaningfully to the arguments raised before it.”)
(quoting TransCanada Power Mktg., Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir.
2015)).
III. Request for Rehearing
Under the Administrative Procedure Act and federal appellate court precedent, the Commission’s decisions will be set aside on appeal if they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,” or “unsupported by substantial evidence.”46 For the Commission to have engaged in reasoned decision-making, it must have examined the relevant data and provided a rational connection between the facts found and the choices made.47 If the Commission “does not provide a rational explanation for its action based on relevant data, then that action is arbitrary and capricious.”48 Here, EKPC, a party aggrieved by the Commission’s Order,49 seeks rehearing of the Order because it is arbitrary and capricious, an abuse of discretion, not based upon substantial evidence in the record, and otherwise contrary to law. The FPA’s just-and-reasonable standard incorporates the cost-causation principle, under which all approved rates must “reflect to some degree the costs actually caused by the customer who must pay them,” and costs must be allocated in a manner at least roughly commensurate with

46 5 U.S.C. §§ 706(2)(A), 706(2)(E). See also Vistra Corp. v. FERC, 80 F.4th 302, 312 (D.C. Cir. 2023); S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 55 (D.C. Cir. 2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 528 (D.C. Cir. 2010).
47 Motor Vehicle Mfrs. Ass’n v. Motor Vehicles Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983).
48 La. PSC. v. FERC, 20 F.4th 1, 6-7 (D.C. Cir. 2021) (citing 5 U.S.C. § 706(2)(A) and Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43)).
49 See 16 U.S.C. § 825l(a) (party aggrieved by order of Commission may seek rehearing). See also Order at PP 20-22 (noting Joint Protestors’ respective interventions and consequent party status in this proceeding).

PDF page 12

12
benefits.50 The Commission must have an “articulable and plausible reason to believe that the benefits are at least roughly commensurate with” the assigned costs.51 Undue discrimination occurs where similarly situated customers are treated differently without adequate justification.52 Finally, a filed rate must possess the minimum specificity that the Commission can reasonably require, such that customers can determine who is responsible for a charge and in what amount.53

A. The Commission Erred by Failing to Address EKPC’s Argument That
It Is Unjust and Unreasonable for the RBP to Ignore a Self-Supply
LSE’s Existing Portfolio.
In its Protest and Answers, EKPC argued that the RBP should consider a self-supply LSE’s existing portfolio in determining the LSE’s RBP obligations. The Commission failed to address this argument. That failure was arbitrary and capricious, not the product of reasoned decision making, and contrary to law.

As EKPC explained in its Protest, the RBP fails to account for existing resources in an LSE’s supply portfolio. The relevant question in evaluating the RBP under the Commission’s cost- causation principle is whether the entity assigned costs as a result of the RBP caused the resource adequacy shortfall that the RBP is intended to address and/or whether it benefits from the procurement and associated allocated costs.54 An LSE whose self-supply portfolio fully covers its load, including any incremental large load, has not contributed to the resource adequacy gap on that showing.55 Any broader regional benefit does not, without further explanation, justify the

50 KN Energy, 968 F.2d at 1300; Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476-77 (7th Cir. 2009); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1260 (D.C. Cir. 2018). See also Order at P 150.
51 Ill. Com. Comm’n, 576 F.3d at 477.
52 TranSource, 168 FERC ¶ 61,119 at P 240.
53 Pub. Utils. Comm’n of Cal. v. FERC, 254 F.3d 250, 255 (D.C. Cir. 2001); Protest at 18-19.
54 See Protest at 11-12.
55 Protest at 11-14; 45-47; Bednarczyk Affidavit at PP 25, 31, 61-63.

PDF page 13

13
particular RBP costs assigned to that LSE. The Commission did not explain why cost causation does not require PJM to credit a self-supply LSE’s resource position against that LSE’s own RBO, RBP Charges, and collateral requirements.

This issue is not clearly resolved by the paper hearing questions concerning updated zone/area load forecasts.56 Correcting the measurement of load growth does not itself determine how an existing self-supply position affects an LSE’s responsibility in the first instance. To the extent that the Order accepted this feature, the Commission must address EKPC’s objections on rehearing. If it intended to reserve it, then the Commission should expressly confirm that the hearing encompasses existing portfolio recognition.

The Commission’s failure to respond to EKPC’s significant, record-supported objections, and its reliance on distinctions that do not address the cost-causation question presented, is arbitrary and capricious and not the product of reasoned decision-making.57 Accepting a rate design that may require a self-supply LSE to pay for RBP capacity that provides it little or no additional reliability benefit is inconsistent with the requirement that costs be at least roughly commensurate with benefits.58 This outcome also weakens the incentives that the RBP is intended to promote and is in tension with the Ratepayer Protection Pledge’s objective of ensuring that new large loads, not prudently planning LSEs and their existing customers, bear the costs of new capacity.59

56 See Order at PP 157, 159-60.
57 Motor Vehicles, 463 U.S. at 43; PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C. Cir. 2005).
58 Ill. Com. Comm’n, 576 F.3d at 477; Bednarczyk Affidavit at P 34.
59 See EKPC September 18 Answer at 9-10; Bednarczyk Affidavit at PP 34, 38; Order at P 161.

PDF page 14

14
Section 205 of the FPA requires that “all rules and regulations affecting or pertaining to” rates and charges subject to the jurisdiction of the Commission “shall be just and reasonable.”60 Courts have consistently required the Commission to use reasoned, principled decision-making in determining whether rates are just and reasonable. Courts have explained that the Commission must “adequately explain how the evidence it relied on ‘support[ed] the conclusion it reached.’”61 Acknowledging but failing to address EKPC’s argument regarding recognizing an LSE’s existing supply portfolio is insufficient to meet this standard. To the extent that the Order accepted the challenged treatment of self-supply portfolios, the Commission should grant rehearing; alternatively, it should clarify that this issue remains open for paper hearing.

B. The Commission Erred by Failing to Address EKPC’s Argument That
It Is Unjust and Unreasonable That the Qualifying RBP Offset UCAP
MW Reduces the Aggregate Procurement Target Without Requiring
the Offset to Reduce the RBO MW, RBP Charges, or Collateral
Obligation of the LSE or Load That Supplied or Sponsored It.
PJM’s treatment of portfolio benefits exposes the central cost-causation defect: qualifying capacity reduces the regional procurement target, but the proposed Tariff does not ensure that the corresponding benefit follows the LSE that supplied it.62 The assertion that RPM-cleared resources support the pooled regional requirement or that additional capacity may confer regional reliability benefits does not explain why PJM recognizes an LSE’s contribution when reducing the regional target yet disregards that contribution when determining the LSE’s own RBP Charges and collateral obligation.

60 16 U.S.C. § 824d(a). 61 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (quoting Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. Cir. 1985)).
62 See Protest at 28-31; Bednarczyk Affidavit at PP 34-38.

PDF page 15

15
Where capacity satisfies PJM’s criteria for Qualifying RBP Offset UCAP MW, the proposed Tariff does not require the corresponding reduction to follow the LSE or load that supplied or sponsored it.63 That is an attribution issue, not a request to expand offset eligibility to all existing capacity. The Order summarized EKPC’s argument that the proposal “unfairly socializes the benefit of prudent resource planning by LSEs,” but did not resolve whether an offset must reduce the sponsoring LSE’s RBO MW, RBP Charges, and associated collateral obligation.64 PJM’s response that pooled benefits are a feature of an RTO does not explain why a targeted procurement may recognize an entity’s contribution when reducing the regional target without ensuring corresponding recognition in that entity’s own allocation.65

Moreover, the assertion that the existence of pooled benefits merit spreading costs to those who are not causing the need for a special resource procurement to an RTO is contrary to the Commission’s own standards for recognizing RTOs, and contrary to the cost causation principle that is built into the FPA.  The Commission has not required socialization of costs as a result of pooling of benefits as a feature of an RTO.  For example, an RTO’s market “must provide all transmission customers with efficient price signals that show the consequence of their transmission usage decisions.”66 Far from requiring socialization of costs due to the pooling of benefits, the regulation mandates that a transmission customer must be able to experience the benefits and the harms resulting from its own choices.  That principle is necessary for cost causation as well.  An arrangement in which a transmission operator such as an RTO is entitled, simply because it is the dominant operator in the region, to require region-wide allocation of costs based solely on the

63 See Bednarczyk Affidavit at PP 27-31, 34, 38; Protest at 28-31.
64 Order at PP 130, 157; Protest at 30-31; Bednarczyk Affidavit at PP 14, 27, 29-30.
65 See Order at P 133; EKPC September 18 Answer at 16-17.
66 18 C.F.R. § 35.34(k)(2)(i).

PDF page 16

16
alleged region-wide sharing of the benefits from a given LSE’s own investments is contrary to section 205. Accordingly, the Commission must reject the RTO’s demand for socialization of costs based on the presumptive pooling of benefits.

Similar to the Commission’s failure to address EKPC’s arguments with respect to consideration of an existing self-supply portfolio, the issue of whether Qualifying RBP Offset UCAP should follow the LSE or load that sponsored or supplied it is not clearly resolved by the Commission’s paper hearing questions.67 Correcting the measurement of load growth does not itself determine whether qualifying offsets follow their sponsor. If the Commission intended in its Order to accept this feature, the Commission must address EKPC’s objections on rehearing. Alternatively, the Commission should expressly confirm that the hearing encompasses qualifying offsets if it intended to reserve this issue.

The Commission’s failure to respond to EKPC’s objections is arbitrary and capricious and not the product of reasoned decision-making.68 Accepting a rate design that fails to require an offset to reduce costs incurred by the LSE or load that sponsored or supplied it is inconsistent with the requirement that costs be at least roughly commensurate with benefits.69 By failing to ensure that the offset follows the LSE or load, the LSE or load could incur costs of new capacity that it does not need to meet its own obligations, without a Commission explanation of whether any broader regional benefits are roughly commensurate with those costs. As noted above, such an outcome weakens the incentives that the RBP is intended to promote and is in tension with the Ratepayer Protection Pledge’s objective.70

67 See Order at PP 157, 159-60.
68 Motor Vehicles, 463 U.S. at 43; PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C. Cir. 2005).
69 Ill. Com. Comm’n, 576 F.3d at 477.
70 See EKPC September 18 Answer at 9-10; Bednarczyk Affidavit at PP 34, 38; Order at P 161.

PDF page 17

17
The Commission must use reasoned, principled decision-making in determining whether rates are just and reasonable and must “adequately explain how the evidence it relied on ‘support[ed] the conclusion it reached.’”71 Failing to address EKPC’s argument regarding attribution of Qualifying RBP Offset UCAP MW is insufficient to meet this standard. To the extent that the Order accepted PJM’s proposed treatment of Qualifying RBP Offset UCAP MW, the Commission should grant rehearing; alternatively, it should clarify that this issue remains open for paper hearing.

C. The Commission’s Order Is Arbitrary and Capricious Because It Fails
to Address PJM’s Proposed Default Cost Allocation.
The Order does not clearly resolve the status of PJM’s default allocation of RBP Charges and associated collateral obligations to LSEs in an Electric Distributor zone/area based on Daily Unforced Capacity Obligation when no RBO is reported.72 The Commission summarized EKPC’s objections to that default allocation and PJM’s purported defense, but made no express determination on that fallback method.73 At the same time, it accepted the tariff records for filing, suspended them subject to refund and further proceedings, and stated that aspects outside the issues specifically reserved for the paper hearing were just and reasonable.74 If the Commission accepted the default allocation, it did so without explaining why that allocation satisfies cost causation. If it reserved the issue, it should clarify that the paper hearing includes the fallback allocation among LSEs, not merely the allocation among zone/areas.

71 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (quoting Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. Cir. 1985)).

72 Order at P 110 (citing Proposed Tariff, attach. DD, § 18.3(b)).
73 See Order at PP 119, 123, 157.
74 Order at PP 23-27.

PDF page 18

18
As EKPC explained in its Protest, the default allocation “socializes RBP costs across all load within the zone – including LSEs serving customer bases that contributed nothing to the capacity shortfall,” violating the principle that costs must be allocated to the entities that cause them.75 PJM offered no evidence that allocating costs based on total zonal load obligations bears any relationship to the load growth that caused the shortfall. EKPC explained that, under the default allocation, all LSEs in a zone/area will be held accountable “regardless of whether they serve any large load or contributed to the need for backstop procurement,” and that LSEs cannot know whether they will face the RBO allocation or the default allocation, contrary to the requirement of clear and transparent procedures.76 EKPC’s Protest showed that reliance on a preexisting allocation methodology approved in a different context does not justify using that same allocation as the default for a fixed, forecast-based 15-year obligation.77 EKPC reiterated that PJM’s fallback RBP cost allocation “still spreads RBP costs to load without demonstrating that the charged LSEs caused the procurement need or receive commensurate benefits.”78 In its Order, the Commission found that PJM’s proposed cost allocation to initially assign RBP costs to zone/areas, “with the ultimate cost allocation to the LSEs as determined by the state and/or RERRA,” may be just and reasonable because it respects state authority.79 That rationale applies, however, only where a state or RERRA actually determines an allocation. This justification provides no support for the default allocation, which by definition applies when no state or RERRA allocation is reported. Nor does the Commission’s finding that Load Adjustments

75 Protest at 20-21 (citing Old Dominion Elec. Coop., 898 F.3d at 1260); Bednarczyk Affidavit at PP 17-18.
76 Protest at 17-18. See also Order at P 119.
77 Protest at 20-21; Coscia Protest Affidavit at PP 158-61.
78 EKPC September 18 Answer at 3, 7-8.
79 Order at PP 154, 161.

PDF page 19

19
may not reasonably capture load growth address the separate question of how costs are allocated among LSEs within a zone/area.80

If the Order accepted PJM’s default allocation, the Commission failed to respond
meaningfully to significant objections or articulate a rational connection between the allocation metric and responsibility for this procurement. The Commission’s concerns about the upstream

zone/area allocation do not resolve the separate downstream question of which LSEs should pay when no RBO is reported.81 The Commission should grant rehearing of any acceptance of the

fallback method. Alternatively, it should clarify that the method remains open for examination in the paper hearing, including whether allocating a fixed, long-term procurement obligation by Daily Unforced Capacity Obligation assigns costs roughly commensurate with the burdens imposed or

benefits received by the charged LSEs.
D. The Commission’s Order Is Arbitrary and Capricious Because It Is
Inconsistent with the Commission’s Cost Causation Principles.
The Commission must provide a reasoned explanation for departing from its precedent.82
Here, the Commission’s Order does not clearly apply the Commission’s longstanding and well-
established cost-causation principle to the challenged LSE-level allocation features. To the extent

80 Order at PP 154-56.
81 See Order at PP 153-160; Protest at 17-21; EKPC September 18 Answer at 3, 7-8.
82 See, e.g., Motor Vehicles, 463 U.S. at 57 (“An agency’s view of what is in the public interest may change, either with or without a change in circumstances. But an agency changing its course must supply a reasoned analysis . . . .”); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must provide a reasoned explanation for departing from precedent or treating similar situations differently.”) (quoting ANR Pipeline Co. v. FERC, 71 F.3d 897, 901 (D.C. Cir. 1995)) (alteration incorporated); MISO Transmission Owners
v. FERC, 45 F.4th 248, 264 (D.C. Cir. 2022) (“FERC is, of course, entitled to change its mind. But to do so, it must provide a ‘reasoned explanation’ for its decision to disregard ‘facts and circumstances’ that justified its prior choice.”) (quoting FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009)); Surface Transp. Bd., 635 F.3d at 71 (“An agency also acts in an arbitrary and capricious manner if the ‘agency departs from its own precedent without a reasoned explanation.’”) (internal citation omitted); Greater Boston, 444 F.2d at 851-53 (“An agency’s view of what is in the public interest may change. . . . But an agency changing its course must supply a reasoned analysis indicating that prior policies and standards are being deliberately changed, not casually ignored.”) (citations omitted).

PDF page 20

20
the Order accepted those features in departure from that principle, the Commission fails to explain why it departed from that principle.

The Commission correctly determined that the relevant legal standard to use in this proceeding is its cost-causation principle that requires that all approved rates “reflect to some degree the costs actually caused by the customer who must pay them.”83 As the Commission explained in its Order, “a cost allocation method can satisfy the cost causation principle if the Commission ‘has an articulable and plausible reason to believe that the benefits are at least roughly commensurate with’ the allocation of the costs.”84 To the extent the Order accepted the challenged LSE-level allocation features rather than reserving them, it must explain their consistency with that standard.

The independent defects discussed in Sections III.A, III.B, and III.C above present a common question: whether the wholesale allocation identifies the burdens imposed on, or benefits received by, the LSE required to pay. The Order directs further consideration of updated forecast information, which may improve the allocation among zone/areas. But the use of an updated forecast does not by itself justify disregarding an LSE’s resource position, failing to attribute a qualifying offset to its sponsor, or allocating costs to all LSEs when no RBO is reported. EKPC does not demand exact precision or deny that regional procurement may confer broader benefits. It asks the Commission to identify a record-supported basis for finding that those asserted benefits are roughly commensurate with the particular costs imposed.85 To the extent that the Order accepted these features without that explanation, it departs from the standard the Commission itself

83 Order at P 150 (quoting KN Energy Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992), and citing Ky. Pub. Serv. Comm’n v. Am. Elec. Power Serv. Corp., 193 FERC ¶ 61,110 (2025) (Ky. Comm’n)).
84 Order at P 150 (quoting Ill. Com. Comm’n, 576 F.3d at 477).
85 See Order at P 150; Protest at 20-21.

PDF page 21

21
articulated. To the extent that it deferred them, the Commission should confirm that the hearing encompasses these LSE-level cost-causation questions rather than only the accuracy of zone/area forecasts.

E. The Commission’s Order Is Arbitrary and Capricious Because It
Failed to Address All the Issues Properly Raised Regarding Collateral
Requirements.
The Commission correctly found that PJM had not adequately supported its proposed LSE collateral requirement and that the requirement may be unjust and unreasonable.86 Its express briefing questions on collateral requirements, however, identify for paper hearing only the initial RBP Credit Rate and whether posting 45 days before the Delivery Year affords sufficient time.87 Those questions do not clearly encompass the independent methodological objections EKPC raised regarding the proposed collateral requirement. Specifically, the Commission erred in failing to determine what exposure is secured, whether gross RBP payment value or net contract-for- differences exposure is the appropriate basis, what MW quantity applies, and how the requirement interacts with Attachment Q and Peak Market Activity. The Commission also failed to address objective reduction and release standards and the treatment of collateral when an LSE defaults.88 As Dr. Coscia explained, these “matters go to the methodology of the credit requirement rather than to the selection of a replacement figure.”89 The Credit Rate and posting deadline depend on the underlying exposure and methodology. To the extent the Order accepted that methodology or excluded EKPC’s objections from the hearing, its failure to address those predicate issues is arbitrary and capricious.

86 Order at PP 204-05.
87 Order at P 206.
88 See Coscia Reply Affidavit at PP 17-24, 71-73; EKPC September 18 Answer at 12-16.
89 Coscia Reply Affidavit at P 17.

PDF page 22

22
EKPC highlights here some of the arguments and evidence that it presented about the need to resolve the merits of the collateral requirement methodology (which must be done before the mechanics of the collateral requirement are addressed in the paper hearing). First, regarding the determination of the exposure to be secured through the collateral requirement, PJM’s own filing reinforces the distinction between gross payment value and the exposure billed through the RBP. Its July 31 transmittal states that “Load Settlement is an inverse of the RBP Credits.”90 In Table 2, the RBP Charge is $2,500 per day on a total resource payment of $12,500 per day, with the remaining $10,000 settled through RPM.91 The incremental RBP Charge is therefore the contract- for-differences differential, not the combined gross payment. The collateral methodology must explain why it secures the gross amount rather than the differential payable by load through the RBP Charge.92

That distinction also identifies EKPC’s cost-allocation injury. EKPC does not challenge the reliability benefit of capacity that closes the shortfall; instead, EKPC challenges the requirement that load that did not cause the shortfall bear the incremental payment above the RPM price, without a supported cost-causation justification. Moreover, the RBP differential varies with the RPM clearing price in each Delivery Year. A supported collateral methodology must account for that variation over the commitment term rather than treat gross payments as the exposure without explaining the treatment of the RPM settlement component.93

The methodology also depends on which allocation applies to an LSE and when that allocation becomes ascertainable. The Commission should address how the RBO-based and

90 PJM RBP Filing at 83.
91 PJM RBP Filing at 82-84 & tbl. 2.
92 See PJM RBP Filing at 79-84; Coscia Reply Affidavit at PP 16-17.
93 See PJM RBP Filing at 79-84; Proposed Tariff, attach. DD, § 18.5(g); Protest at 21.

PDF page 23

23
default allocations determine collateral obligations, the opportunity to review those inputs before posting, and the associated liquidity consequences.94 PJM’s September 10 Answer distinguished forward RBP exposure from backward-looking Peak Market Activity and offered to remove language permitting RBP settlements to enter that calculation.95 That response leaves the question whether the Tariff implements the exclusion and coordinates the RBP requirement with other applicable Attachment Q credit requirements; EKPC does not presume that the same exposure remains secured twice if the Tariff fully implements the exclusion. PJM also clarified that section 18.9(a) reallocates defaulted RBP Charges among LSEs already responsible for RBP Charges.96 The remaining question is whether and how Operating Agreement section 15.2.2 could expose other Members to residual losses. The Commission should resolve that interaction, including whether collateral must be applied before reallocation, rather than assume that all Members face direct allocation under section 18.9(a).97

These issues remain material regardless of whether an LSE receives an initial RBP allocation. An LSE or PJM Member without incremental large-load growth or an initial allocation may still face residual exposure if the governing default provisions permit it, while an allocated LSE must be able to identify the exposure and quantity it is required to secure.98 EKPC does not contend that every LSE must post an identical amount. Rather, EKPC contends that differences in collateral burdens must follow a supported measure of exposure and that the resulting default and liquidity risks must be addressed. The Commission’s credit standard requires a reasonable balance

94 See Protest at 26-27.
95 See PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.,” at 86 & n. 259 (filed Sept. 10, 2026) (“PJM September 10 Answer”).
96 PJM September 10 Answer at 67 n.205. See also Coscia Reply Affidavit at PP 19-24.
97 See Coscia Reply Affidavit at PP 18-24, 71.
98 See Coscia Protest Affidavit at PP 168-70; Coscia Reply Affidavit at PP 24, 73.

PDF page 24

24
between default protection and participants’ flexibility to manage collateral, with requirements correlated to risk.99 Adjusting a percentage or posting deadline alone cannot establish that balance. The Commission should clarify that the LSE collateral hearing encompasses these

methodological issues, including the exposure basis, applicable MW quantity, interaction with existing credit requirements, reduction and release standards, application of collateral, and residual default exposure.100 To the extent that the Order accepted any of those features or excluded them from further examination, the Commission should grant rehearing and address EKPC’s supporting evidence.

PJM’s expected section 205 filing does not absolve the Commission of its obligation to address the arguments and evidence presented to it. EKPC understands that PJM plans to make a section 205 filing on October 29, the date of this rehearing request.101 PJM prepared a presentation for the October 22 Special Members Committee meeting that previews that section 205 filing. The presentation describes a Credit Rate of 40% of discounted total RBP payment obligations, exclusion of RBP positions and associated RPM MW from Peak Market Activity, and collateral based on generation coming online for the applicable Delivery Year.102 These descriptions are not operative tariff revisions, nor do they fully address the arguments and evidence presented by EKPC. If the filed Tariff fully implements the stated Peak Market Activity exclusion, the objection to collateralizing the same exposure twice must be evaluated in light of that change. The remaining

99 Order at P 205 n.334 (citing PJM Interconnection, L.L.C., 186 FERC ¶ 61,055, at P 29 (2024)).
100 See Coscia Reply Affidavit at PP 17, 71-73; EKPC September 18 Answer at 12-16.
101 See PJM Interconnection, L.L.C., “Motion for Abeyance of PJM Interconnection, L.L.C.,” Docket Nos. ER26- 3380-000, EL26-108-000 (filed Oct. 12, 2026).
102 PJM Interconnection, L.L.C., Tariff, Section 9.2(b) Stakeholder Consultation of Upcoming 205 Filing on Reliability Backstop Procurement, at 2, 8–10 (presentation prepared for Special Members Committee meeting, Oct. 22, 2026), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20261022- special/item-01---1-tariff-section-92b-stakeholder-consultation-of-upcoming-205-filing-on-reliability-backstop- procurement---presentation.pdf (“October 22 Presentation”).

PDF page 25

25
implementation questions are whether the Tariff implements the exclusion, coordinates the RBP requirement with other applicable Attachment Q requirements, and expressly confines the collateral quantity to the applicable in-service MW. A change to the Credit Rate alone does not resolve those questions or the gross-versus-differential exposure and residual-default issues raised by EKPC in its Protest, Answers, and supporting Affidavits; EKPC seeks a supported methodology, not merely a different initial Credit Rate.103

F. The Commission Erred in Its Determination That There Is No Undue
Discrimination Between FRR Entities and RPM LSEs.
The Commission erred in finding that RPM self-supply LSEs are not similarly situated to FRR Entities, and that the RBP is therefore not unduly discriminatory, where both have taken materially similar planning actions and the Commission identified no cost-causation distinction justifying the differential treatment.104 The Commission found that PJM’s exclusion of FRR Entities from the RBP was just and reasonable and rejected arguments that the RBP unduly discriminates against self-supply LSEs that participate in the RPM. It reasoned that FRR load and capacity are removed from RPM while self-supplied capacity is not, and that only FRR Entities fully bear the risk of over- or under-supply.105 The Commission therefore determined that the FRR exclusion was just and reasonable.106

EKPC does not ask the Commission to subject FRR Entities to the RBP. Instead, EKPC challenges the Commission’s failure to explain why comparable resource-planning actions by an RPM self-supply LSE receive no corresponding recognition when determining that LSE’s RBP

103 See October 22 Presentation at 8-10; EKPC September 18 Answer at 12-13; Coscia Reply Affidavit §§ V-VI. To be clear, EKPC’s rehearing request addresses the Order and does not prejudge the final section 205 filing.
104 See 16 U.S.C. § 824d(b); Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 367 (D.C. Cir. 2002).
105 Order at P 151.
106 Order at P 151.

PDF page 26

26
exposure.107 The relevant inquiry is not whether FRR Entities and RPM self-supply LSEs are identical in every respect, but whether the differences identified justify the challenged treatment under RBP.108 Both FRR Entities and RPM self-supply LSEs engage in planning to cover their load obligations. In that regard, they are similarly situated. But only RPM self-supply LSEs are subject to RBP costs, even though those LSEs have sufficient resources for their load-serving obligations (just like FRR Entities). The Commission identified RPM participation and the ability to purchase additional capacity or sell excess capacity as distinctions.109 Those distinctions require analysis of whether, and to what extent, an RPM self-supply LSE with sufficient owned or contracted resources contributes to the shortfall or receives benefits commensurate with its assigned RBP costs. Excluding FRR Entities because their load and resources are removed from RPM does not, without that analysis, explain why an RPM self-supply LSE’s comparable planning actions warrant no recognition in its own RBP exposure. As a result, the Commission’s Order runs afoul of the FPA section 205(b) prohibition on unreasonable differences in rates among similarly situated customers.110

The Commission’s reliance on FRR Entities’ assumption of over- and under-supply risk likewise requires a connection to the costs at issue.111 EKPC does not deny that RPM participation provides access to pooled capacity. But that access alone does not establish that every self-supply LSE caused this incremental procurement need or receives benefits sufficient to justify its particular RBP Charges, collateral burdens, and default exposure.112 The Commission must

107 See Protest at 45-47; Bednarczyk Affidavit at PP 59-60, 64.
108 See N.Y. Indep. Sys. Operator, Inc., 162 FERC ¶ 61,124, at P 10 (2018).
109 Order at P 151.
110 16 U.S.C. § 824d(b).
111 See Order at P 151.
112 See Bednarczyk Affidavit at PP 60-62, 64; Protest at 45-47.

PDF page 27

27
explain why the identified differences are material to those obligations rather than treat the distinction between FRR and RPM participation as dispositive.

The temporary suspension of the FRR Commitment Insufficiency Charge further qualifies the Commission’s reliance on FRR Entities’ assumption of supply risk. For the 2025/2026 through 2028/2029 Delivery Years, no FRR Commitment Insufficiency Charge will be assessed.113 That suspension does not eliminate FRR supply risk throughout an RBP commitment that may run through 2042/2043; RAA, Schedule 8.1, section D.7 resumes the insufficiency charge beginning in 2029/2030.114 EKPC’s comparability argument therefore does not depend on identical risk throughout the term. It rests on the Commission’s failure to explain why comparable planning actions that avoid contributing to the shortfall warrant different treatment in assigning RBP exposure.

G. The Commission’s Acceptance of the RBP Is Not Based on Substantial
Evidence and Therefore Is Arbitrary and Capricious.
To the extent that the Order accepted the challenged allocation and collateral features, the Commission did not adequately address the evidence supporting EKPC’s objections. A generalized regional reliability benefit does not itself answer the LSE-specific allocation and exposure questions presented here. The Commission erred by failing to meaningfully address evidence in the record on cost causation, which was provided by EKPC in its Protest and in the Bednarczyk and Coscia Affidavits. In the Bednarczyk Affidavit, EKPC provided evidence showing how the RBP “creates cost, credit, collateral, and risk allocation obligations that do not consistently satisfy the principles of transparency, traceability, and cost causation.”115 The

113 RAA, Schedule 8.1, section D.7; EKPC September 18 Answer at 11, n.43. Section D.7 provides that the FRR Commitment Insufficiency Charge resumes beginning with the 2029/2030 Delivery Year. 114 Id.
115 Bednarczyk Affidavit at P 7.

PDF page 28

28
evidence also shows that the RBP converts what should be a targeted, incremental large-load cost- causation problem into a generalized load-ratio obligation that penalizes self-supply LSEs that acted prudently and rewards policies that incentivize inadequate resource planning.116 And Mr. Bednarczyk shows that the RBP cost allocation process proposed by PJM “does not provide a transparent means for an LSE to assess its wholesale RBP exposure, evaluate the benefits of qualifying offsets or opt-outs, understand its related credit obligations, or determine whether its actions will make it reliability neutral.”117 Moreover, with respect to the proposed default cost allocation method, Mr. Bednarczyk provides evidence that the “Daily Unforced Capacity Obligation is a broad capacity allocation metric,” and “it does not identify the LSEs that created the residual procurement need.”118 The Commission should address this evidence to the extent it accepted the challenged features or clarify that the evidence remains for consideration in the paper hearing.

Similarly, the Coscia Affidavits address whether the LSE collateral requirement is tied to measured exposure, whether the same exposure may be secured twice, and how an obligation based on a default allocation can be determined and reviewed.119 They also identify the interaction between proposed Tariff Attachment DD section 18.9(a) and Operating Agreement section 15.2.2.120 PJM’s clarification that section 18.9(a) reallocates defaults among LSEs already paying RBP Charges does not resolve the separate question of residual exposure under the Operating Agreement.121 That question matters to any PJM Member without an initial RBP allocation and

116 Bednarczyk Affidavit at PP 7, 9, 12, 18.
117 Bednarczyk Affidavit at P 14.
118 Bednarczyk Affidavit at P 17.
119 See Coscia Reply Affidavit at PP 17, 24, 71-73; EKPC September 18 Answer at 12-16. 120 See Coscia Reply Affidavit at PP 18-24; EKPC September 18 Answer at 12.
121 See PJM September 10 Answer at 67 n.205, 84 & n.252; Coscia Reply Affidavit at PP 18–24.

PDF page 29

29
does not depend on an assumption that the LSE will receive no allocation under revised inputs. The Commission must address whether such residual exposure exists, what collateral secures it, and how it is consistent with cost causation. EKPC’s evidentiary objection concerns the absence of that analysis, not a prediction of its allocation under a future filing.

The Commission is required to address the arguments and evidence presented to it.122 To the extent that the Order accepted the challenged features without addressing that evidence, the Commission should grant rehearing and provide a reasoned determination; alternatively, it should clarify that these evidentiary issues remain open for paper hearing.

122 See, e.g., BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 270 (D.C. Cir. 2014); New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018).

PDF page 30

30
IV. Conclusion
Wherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the Commission grant rehearing for the reasons discussed herein or, where the Order’s reservation of an issue is unclear, clarify that the paper hearing encompasses the independent LSE-level cost- allocation, offset-attribution, and collateral-methodology issues identified above without an adverse determination on their merits.

Respectfully submitted,

Denise R. Foster Cronin
Chief Compliance Officer and Senior Vice
President
East Kentucky Power Cooperative, Inc.
4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Tel.: 859-745-9615
Email: denise.cronin@ekpc.coop

On Behalf of
East Kentucky Power Cooperative, Inc.

/s/ Daniel E. Frank

Daniel E. Frank
Allison E. S. Salvia
Kelly A. Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Tel.: 202-383-0100
Email: danielfrank@eversheds-sutherland.com
allisonsalvia@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com

Counsel for
East Kentucky Power Cooperative, Inc.

Dated: October 29, 2026

PDF page 31

Certificate of Service

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC this 29th day of October, 2026.

/s/ Kelly A. Cuthbertson

Kelly A. Cuthbertson