ER26-3380-000 · 2026-08-21 · Ohio Energy Leadership Council
Comments of Ohio Energy Leadership Council on the Reliability Backstop Procurement proposed by PJM Interconnection, L.L.C
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3380-000
COMMENTS OF OHIO ENERGY LEADERSHIP COUNCIL
Pursuant to the Federal Energy Regulatory Commission (the “Commission”) Rules of Practice and Procedure, Ohio Energy Leadership Council (“OELC”) respectfully submits these comments on the Reliability Backstop Procurement (“RBP”) proposed in this proceeding by PJM Interconnection, L.L.C. (“PJM”).
I. SUMMARY AND REQUESTED COMMISSION ACTION
OELC supports the objective of maintaining resource adequacy and recognizes the need for timely, durable action where new load growth is genuinely causing incremental capacity needs. But the Commission should not permit the RBP or any associated definition of “Large Load” to turn existing, energy-intensive Ohio manufacturers into the financial backstop for load growth they did not cause. Accordingly, OELC respectfully requests that the Commission condition any acceptance of PJM’s RBP proposal on the following:
1. Establish a separate, protective threshold for non-data-center customers. A non-data- center customer—including traditional manufacturing, steelmaking, chemical, industrial, educational, institutional, information-technology, and retail customers—should be treated as a Large Load only if its Peak Load Contribution (“PLC”) is at least 150 MW. The lower 50 MW threshold should not apply to non-data-center customers.
2. Use a transparent, system-relevant measurement. For both threshold eligibility and any allocation that rests on load magnitude, PJM must measure PLC using the customer’s load during the established PJM system-peak hours used to develop capacity obligations—not the customer’s highest demand at any time during the measurement year.
PDF page 2
2
3. Specify the implementation details in tariff language. PJM should identify the applicable peak-hour set, the data source and metering boundary, treatment of behind-the- meter generation and demand response, the measurement period, notice and verification procedures, and a customer-level dispute process before any charge is imposed.
4. Ensure New Generation is Incentivized. The Commission should modify PJM’s
proposed resource-selection methodology to materially value new dispatchable
generation’s reliability attributes.
These protections are necessary for the proposal to satisfy the Federal Power Act’s just- and-reasonable standard. Section 205 requires that all Commission-jurisdictional rates, charges, practices, and classifications be just and reasonable. PJM bears the burden to demonstrate that each proposed RBP practice—including its resource-eligibility, accreditation, offer-quantity, selection, commitment, and cost-allocation rules—meets that standard.
II. OELC’S INTEREST AND EXPERIENCE
OELC is a not-for-profit trade association that represents its members’ interests in utility and ratemaking matters in Ohio. Managing the cost and availability of energy is a crucial component of success for many businesses, and OELC advocates for competitive, reasonable, and transparent laws, policies, and utility rates through effective lobbying and legal advocacy. OELC’s work is directed to ensuring that Ohio remains an attractive place for businesses and enterprises to remain, grow, invest, and create jobs.
For more than 30 years, OELC has helped its members understand and manage their electric and natural gas supply costs. OELC and its members have direct, long-standing experience with the practical effects of utility tariffs, rate design, energy legislation, and regulatory policy on Ohio businesses that must manage significant energy consumption and exposure to volatile energy costs. OELC’s members include energy-intensive manufacturing, industrial, educational, institutional, information-technology, and retail business customers in Ohio. Collectively, OELC’s members annually consume many billions of kilowatt-hours of electricity and are major
PDF page 3
3
contributors to Ohio’s economy and employment sector. For OELC’s members, electricity is not a discretionary purchase; it is a material production input, a prerequisite to continuous operations, and a major component of the delivered cost of goods and services.
OELC’s advocacy has included helping shape Ohio energy legislation concerning
renewable-energy, energy-efficiency, and peak-demand-reduction requirements, including legislation intended to prevent the unreasonable imposition of utility-initiated cost burdens on large energy consumers. OELC has also advocated for tariff mechanisms that recognize and provide value for customers that can manage peak consumption or curtail electric demand— actions that provide system-wide benefits to the electric grid.
Through its dedicated lobbying and regulatory advisors, OELC actively participates in legislative matters affecting Ohio energy and utility policy and participates in matters before the Public Utilities Commission of Ohio (“PUCO”). That work includes electric distribution-rate proceedings for Ohio electric utilities and other PUCO proceedings affecting member utility rates and issues. OELC is therefore well positioned to explain how wholesale capacity-market and large- load-cost-allocation decisions affect Ohio end-use customers and the competitiveness of Ohio’s industrial economy.
A capacity-cost allocation that fails to distinguish new, unusually large, data-center-driven load from the established industrial base would have immediate practical consequences. It would raise the cost of making steel, chemicals, and other essential materials in Ohio; put further pressure on facilities competing against foreign producers; impair the ability of domestic firms to invest and retain jobs; and contribute to price pressure throughout downstream supply chains. The Commission should not adopt a rate design that creates those consequences without a clear and demonstrated causal connection to the RBP need.
PDF page 4
4
III. A 50 MW THRESHOLD FOR NON-DATA-CENTER CUSTOMERS WOULD BE
ARBITRARY, OVERINCLUSIVE, UNJUST AND UNREASONABLE.
A 50 MW threshold may be an administratively convenient number, but it is not a demonstrated measure of responsibility for the extraordinary new-load conditions at issue. It would draw into the Large Load category an extensive range of established industrial facilities whose operational demand reflects manufacturing processes, long-standing production footprints, and employment-intensive operations—not a new, concentrated demand shock. A threshold must do more than identify customers that use a meaningful amount of electricity. It must identify customers whose incremental system-peak demand creates the need for the specific capacity procurement and associated charges.
A 50 MW non-data-center threshold fails that test for a number of reasons. Energy- intensive manufacturers use substantial electricity because they produce essential goods. Their demand is often steady, process-driven, and embedded in the long-established load profile on which PJM’s system planning, capacity obligations, and tariffs have been built. The fact that a steel mill, chemical facility, or other manufacturer exceeds 50 MW at times says nothing about whether it is a new load addition, whether it contributed to the relevant load adjustment, or whether it caused an incremental reliability need.
By contrast, the RBP’s stated purpose is to address a shortfall associated with rapid additions of load. The Commission should not permit a proxy that converts the mere size of an established customer into proof of causation. That would make the charge overinclusive, sever the link between cost and responsibility, and expose existing manufacturers to a substantial new cost obligation based on a trait—electricity intensity—that is central to their productive activity and unrelated to the new-load phenomenon the RBP is meant to address.
PDF page 5
5
Traditional industrial facilities—particularly steel and chemical producers—are foundational to domestic supply chains. They supply inputs used in infrastructure, transportation, construction, energy systems, agriculture, health care, and national-defense-related production. A durable national-security and national economic strategy requires that these industries have access to reliable and reasonably priced power. Reliability and affordability are complementary objectives, not competing ones. The Commission need not choose between supporting data-center growth and supporting domestic industry. It can do both by applying a definition that targets the new load that creates the incremental requirement while maintaining reliable service to the traditional industrial base.
Penalizing existing manufacturers for energy intensity simply weakens the very industrial capacity on which the nation depends, while doing little to improve the signal sent to the new load that drives the need for additional capacity. Energy prices are already a decisive component of manufacturing competitiveness. Capacity charges and other demand-related costs are not absorbed in a vacuum. They increase the delivered energy cost of production, reduce operating margins, constrain capital spending, and affect decisions about production volumes, facility expansions, and employment. OELC’s members compete not only with other domestic facilities but with international producers that may operate under materially different energy, regulatory, labor, and capital-cost conditions.
The Commission should not introduce a new cost burden on domestic manufacturing at a time when the RBP record itself demonstrates capacity-market scarcity: PJM reports that the 2028/2029 Base Residual Auction cleared 6,831.3 MW UCAP short of the regional reliability requirement at the $325/MW-day market price cap.1 The very conditions that cause a backstop
1 Application (July 31, 2026), p. 7.
PDF page 6
6
procurement to be expensive make it all the more important to allocate its costs narrowly and accurately.
The likely effect of an overbroad 50 MW threshold is not confined to the affected bill. Energy-intensive manufacturers transmit higher production costs through supply chains, or they absorb them by reducing investment, output, or employment. Neither outcome advances reliability, affordability, or economic resilience. In the current inflation-sensitive environment, the Commission should avoid a tariff design that can add avoidable cost pressure to domestically produced materials and the goods made from them.
PJM’s own filing provides the critical factual premise for a targeted, rather than indiscriminate, response. PJM states that its forecast predicts 32 GW of peak-load growth from 2024 through 2030 and that 30 GW of that growth is projected to come from data centers.2 The filing also explains that the RBP is intended to address resource-adequacy challenges “primarily driven by the unprecedented addition of large loads, most notably data centers, in the PJM Region.”3
The RBP record further shows that the projects PJM identified as prospective new large loads bear are distinct from historic energy-intensive manufacturers. PJM’s April 2026 request for information drew responses concerning 47 potential projects averaging 850 MW, with a median size of 300 MW.4 According to PJM the “RFI revealed substantial large load interest from 21 entities representing 47 potential projects in the PJM Region averaging 850 MW each, with a median size of 300 MW.”5 That evidence supports a threshold that distinguishes exceptional new demand from the established businesses that are already integral to Ohio’s industrial economy.
2 Id., p. 6.3 Id., p. 1.4 Id., p. 18.5 Id.
PDF page 7
7
The record points to data-center-driven load growth; it does not establish that existing non- data-center customers with 50–149 MW of system-peak PLC are causing the resource-adequacy shortfall. Indeed, PJM acknowledges that its forthcoming filing, rather than the RBP filing itself, will propose a regional Large Load definition. The proper policy response is to align costs with new data-center load and its procurement choices—not to shift the burden to legacy industrial customers that did not make those commitments because they did not cause the underlying capacity shortfall. The Commission should require PJM to develop that definition on evidence, with an explicit distinction between new data centers and non-data-center customers. A 150 MW system-peak PLC threshold for non-data-center customers is a conservative and rational boundary: it is only one-half of the median project size PJM identifies in the record, yet it avoids recasting substantial numbers of traditional facilities as the type of extraordinary load the RBP was designed to address.
IV. The Commission Should Require PJM To Use PLC Values Not a Customer’s Highest Demand at Any Time in the Measurement Year.
The definition of Large Load will be no more rational than its measurement method. OELC strongly recommends that PJM measure load using a customer’s PLC values established during PJM system peaks, not the customer’s highest demand during any hour in the measurement year. Capacity procurement exists to ensure that sufficient resources are available when the PJM system faces its highest coincident peak demand. The relevant question, therefore, is not whether a particular customer ever reached a high demand level in an isolated hour. It is whether the customer materially contributes to the regional peak conditions that establish the system’s capacity need. A customer-specific annual maximum can occur in a season, hour, or operating condition that does not coincide with the PJM system peak. It may reflect a one-time production event, an outage recovery, a weather-related operational adjustment, commissioning activity, or another
PDF page 8
8
idiosyncratic event with no meaningful relationship to the reliability condition the RBP addresses. Using that noncoincident maximum would overstate the customer’s capacity responsibility and produce classifications untethered from the need for incremental capacity.
By contrast, system-peak PLC is a familiar and objective planning construct used by PJM for many years. It measures demand when capacity is most needed by the region. PJM itself relies on load adjustments and capacity-obligation concepts that are intended to assign changes in forecasted load to the zone or area where they occur. The Large Load definition should employ the same fundamental principle: identify load by its contribution to the relevant system condition, rather than by an isolated and potentially unrepresentative maximum peak demand. If a customer can be classified as a Large Load based on its highest demand at any time in a year, a single non-coincident operating hour could trigger a long-lived tariff consequence. That approach would be unpredictable, hard to audit, and unfair to customers with variable manufacturing processes. It could also perversely encourage customers to alter operations during individual high-demand hours without reducing their contribution to system peaks, thereby producing no genuine reliability benefit.
The Commission should thus reject a methodology that confuses a facility’s maximum operating demand with its system-relevant contribution to capacity requirements. A capacity- related classification must be based on capacity-related data. Accordingly, the Commission should direct PJM to file tariff language or an implementation manual, subject to Commission review, that resolves at minimum the following issues:
1. Use of PLC Values. Identify the precise PJM peak-hour set and the period used to calculate the customer’s peak load for purposes of defining a “Large Load Customer,” including the process for publishing those hours and correcting data errors. OELC recommends that PJM be directed to use the existing PLC methodology; an annual maximum, an unannounced ad hoc interval, or a noncoincident peak should not be used.
PDF page 9
9
2. Net-load treatment. Specify the treatment of behind-the-meter generation, demand response, energy storage, and other load-management arrangements, including the data necessary to verify net system contribution.
3. Customer notice and verification. Provide customers with advance notice of proposed classification, their underlying interval data and calculated PLC, a reasonable time to correct errors, and a transparent mechanism for challenging a classification before charges take effect.
4. Temporal nexus to new load. For purposes of the RBP, require PJM and the relevant electric distributor to demonstrate that the customer’s qualifying PLC reflects new or incremental load relative to the forecast or baseline used to establish the relevant RBP target. Existing load should not be reclassified solely because it is large. These elements are indispensable. Without them, customers cannot forecast their exposure, evaluate the accuracy of their bills, or meaningfully participate in any state retail-cost-allocation proceeding. Ambiguity in the definition and measurement of load invites inconsistent results, disputes, and cost shifting—the opposite of the transparent and reasonable tariff administration OELC seeks.
V. PJM’S RBP RESOURCE-SELECTION METHODOLOGY IS NOT JUST AND
REASONABLE BECAUSE IT DOES NOT ADEQUATELY INCENTIVIZE NEW
DISPATCHABLE GENERATION.
In addition, the Commission should reject or condition the RBP’s resource-selection provisions. The question is not simply whether PJM can procure a numerical quantity of UCAP at the lowest levelized price. The question under Federal Power Act section 205 is whether the proposed procurement practice is just and reasonable in light of the specific resource-adequacy problem PJM says it is trying to solve. On this record, the answer is no.
PJM seeks a long-term reliability backstop because the 2028/2029 Base Residual Auction (BRA) cleared materially short of the regional reliability requirement. A just-and-reasonable remedy must be designed to obtain the resources most capable of serving load during the reliability-risk conditions for which the backstop is being created. PJM’s proposal does not do so. It treats capacity as substantially homogeneous for selection purposes, although resources differ in
PDF page 10
10
their ability to start, dispatch, sustain output, perform in stress conditions, operate through extended events, and respond to changing reliability needs during a commitment that can extend through the 2042/2043 Delivery Year.
Not all resources accredited in UCAP terms are equally useful for meeting a reliability shortfall. A resource capable of dispatchable, sustained generation during system stress provides a different reliability service from a resource whose capacity depends on load curtailment, customer participation, a limited operating duration, or changing conditions outside PJM’s direct operational control. That distinction is particularly important for a one-time, 15-year procurement intended to provide a durable reliability backstop. The Commission should direct PJM to separately evaluate and reflect in the methodology the dispatchability, firm availability, duration, fuel assurance, operational control, and demonstrated performance during the conditions that drive the RBP need.
OELC understands that the 2028/2029 BRA Effective Load Carrying Capability (ELCC) values used in the proposal assign Demand Response an ELCC value of 91%, while assigning Gas Combined Cycle an ELCC value of 78%.6 If PJM uses those values as a dispositive measure of the relative capacity contribution of these resources for RBP selection, it sends the wrong investment signal. It can advantage demand response over new dispatchable combined-cycle generation even though the latter adds new, controllable supply capable of sustained operation. PJM has not shown why an accreditation comparison developed for the 2028/2029 BRA should govern a procurement expressly designed to address a longer-term reliability problem. The problem is not that demand response has no role in reliability. Properly contracted, measurable, and dispatchable demand response can provide tremendous value, and for many years
6 See Application (July 31, 2026), p. 32.
PDF page 11
11
OELC has advocated for PUCO-approved interruptible programs operated by Ohio’s electric distribution utilities. The problem is that PJM has not demonstrated that the 2028/2029 BRA’s methodology properly captures the distinct reliability value of new dispatchable generation in the RBP context. The Commission should require PJM to make that showing before it permits an accreditation construct to drive 15-year resource commitments and the resulting charges to load.
VI. CONCLUSION AND RECOMMENDATIONS.
OELC does not oppose the development of new resources to meet incremental demand. To the contrary, a reliable electric system is essential to OELC’s members. OELC’s concern is that the cost of that reliability must be assigned in a manner consistent with the actual source of the need. PJM itself represents that its proposal respects the distinction between wholesale and retail authority and that states will determine how costs assigned to a load serving entity are collected from retail customers. PJM further states that each state may use its own definitions of data centers and large loads when allocating RBP charges at retail.
The Commission should ensure that PJM’s federal tariff framework facilitates, rather than frustrates, a properly targeted Ohio retail allocation. A clear 150 MW system-peak PLC guardrail for non-data-center customers will provide a principled and administrable floor of protection for existing manufacturers. It does not prevent Ohio or another state from adopting additional safeguards for its retail customers. Nor does it impair PJM’s ability to procure needed capacity from resources. It simply prevents the definition from capturing a broad group of established industrial customers based on a low, non-causal threshold.
PJM’s record also makes clear that it expects states to protect existing customers when assigning RBP costs: the filing states that the appropriate retail customers are new large loads, including data centers, “and not residential customers or small industrial customers.” OELC agrees with the principle but urges the Commission not to treat it as limited to only “small” industrial
PDF page 12
12
customers. Traditional manufacturers do not become a cause of load growth merely because they are energy intensive. The requested 150 MW threshold ensures that the protection is meaningful for the existing industrial base.
The Commission can advance resource adequacy without sacrificing affordability, domestic competitiveness, or the industrial base that remains indispensable to Ohio and the United States. Accordingly, OELC respectfully requests that the Commission condition its action to require: (1) a 150 MW system-peak PLC threshold for non-data-center customers; (2) PLC measurement based on established PJM system peaks, rather than any customer-specific peak during the measurement year, and a clear and transparent process for categorizing and notifying customers of those values; (3) a resource-selection methodology that materially values new dispatchable generation’s reliability attributes and, thus, encourages their development. Date: August 21, 2026
Respectfully submitted,
/s/ David F. Proaño
David F. Proaño (Counsel of Record)
Benjamin A. Kurtz
BAKER & HOSTETLER LLP
127 Public Square, Suite 2000
Cleveland, OH 44114
216-621-0200 / Fax 216-696-0740
Email: dproano@bakerlaw.com
Email: bkurtz@bakerlaw.com
*Willing to Accept Service by Email*
COUNSEL FOR OHIO ENERGY
LEADERSHIP COUNCIL
PDF page 13
CERTIFICATE OF SERVICE
I hereby certify that on this 21st day of August 2026, I served the foregoing document by electronic means on each person listed on the Federal Energy Regulatory Commission’s official service list in Docket No. ER26-3380-000.
/s/ David F. Proaño
David F. Proaño
Counsel of Record