Comments of Calibrant Energy requesting clarification re the PJM Interconnection, LLC’s proposed revisions to the Open Access Transmission Tariff and the…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, LLC
)
Docket No. ER26-3380-000
)
REQUEST FOR CLARIFICATION OF CALIBRANT ENERGY
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure,1 Calibrant Energy (Calibrant) respectfully submits this request for clarification of PJM Interconnection, LLC’s (PJM) proposed revisions to its Open Access Transmission Tariff (Tariff) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”). Calibrant seeks only a narrow clarification of proposed Tariff Attachment DD Section 18.2 (c) in order to eliminate confusion or ambiguity and the potential, if read wrongly, to result in unjust and unreasonable or unduly discriminatory barriers to the participation of resources that could otherwise contribute as part of the solution to the region’s resource adequacy challenges. Specifically, Calibrant seeks to clarify that bilateral contracts between loads and behind-the- meter generation resources to support load response are sufficient evidence to support Qualifying RBP Offset UCAP eligibility under proposed Tariff Attachment DD Section 18.2 (c). Calibrant develops energy generation and storage assets throughout the United States, including in the PJM footprint. Calibrant participated in PJM’s stakeholder process to ensure that the behind-the-meter generation projects that it develops in the region, which are new “steel-in- the-ground” projects capable of reliably serving the long-term capacity needs of the region with a faster development timeline than front-of-the-meter new capacity resources, are fully eligible to
1 18 C.F.R. § 385.211.
PDF page 2
2
participate either as Qualifying RBP Offset UCAP that reduces the RBP target for procurement or as RBP Resources. Specifically, Calibrant sought to ensure that its behind-the-meter generation projects would be eligible to provide capacity as demand response via RBP. Calibrant is appreciative of PJM’s engagement during the stakeholder process and PJM’s recognition of the potential for behind-the-meter generation projects to contribute to addressing the region’s resource adequacy challenges through its inclusion of pathways for demand resources to qualify as both Qualifying RBP Offset UCAP and RBP Resources. Calibrant here seeks a limited clarification of PJM’s proposed tariff provisions only regarding the evidence that must be submitted to be eligible as Qualifying RBP Offset UCAP under proposed Tariff Attachment DD Section 18.2 (c), which is consistent with PJM’s position during the stakeholder process.
I. REQUEST FOR CLARIFICATION
PJM’s Proposed Tariff Attachment DD Section 18.2 (c) sets forth the evidence that must be submitted during the RBP bid submission window in order for new capacity that will serve the region to be eligible as Qualifying RBP Offset UCAP MW. Three types of supporting evidence may qualify under this provision, each of which is subject to differing additional criteria. Under proposed Section 18.2 (c)(i), a signed bilateral contract may qualify; under (ii) a RERRA-approved or accepted integrated resource plan may qualify; and under (iii) a signed commitment with a Curtailment Service Provider or DER Aggregator may qualify. As a developer of behind-the-meter generation projects, Calibrant expects that it would provide as qualifying evidence pursuant to Section 18.2 (c)(i) a signed bilateral contract with an end-use customer to enable load response. Under this pathway, a contract would qualify if its term is for provision of Qualifying RBP Offset UCAP MW for at least five Delivery Years with a
PDF page 3
3
commercial operation date for the project prior to the 2032/2033 Delivery Year, and matched with load indicating that it will come online in the 2027/2028 or 2028/2029 Delivery Year. Calibrant notes that nothing in the requirements under Section 18.2 (c)(i) or definition of Qualifying RBP Offset UCAP MW limit applicability of the bilateral contract evidentiary path to capacity that is front-of-meter rather than behind-the-meter generation that can support load response.
In contrast, proposed Section 18.2 (c)(iii) appears to apply to the commercial relationship between curtailment service providers and flexible loads that may not be supported by physical assets, and incorporates additional limitations that would not appropriately apply to Qualifying RBP Offset UCAP MW provided by behind-the-meter generation projects. Specifically, Section 18.2 (c)(iii) requires that the new load will either (a) participate directly as demand response starting immediately in the 2028/2029 Delivery Year Second Incremental Auction or (b) “purchase replacement Qualifying RBP Offset UCAP MW that are eligible generation or storage resources.” Such provisions make little sense in the context of a behind-the-meter generation project that contracts with the end-use customer to achieve a load reduction. Because behind-the- meter generation projects require steel in the ground, they may, like front-of-the-meter projects and unlike load response unsupported by physical generation assets, have a commercial operation date that does not allow for participation in the 2028/2029 Delivery Year. But, as is the case for front-of-the-meter generation projects, that is not a basis to disqualify them entirely from providing capacity that could meet the region’s resource adequacy needs over the long-run. Likewise, the alternate option under Section 18.2 (c)(iii) to purchase replacement eligible generation or storage resources makes little sense in a context in which otherwise eligible capacity from a behind-the-meter generation project has already been procured by the new load,
PDF page 4
4
but has simply not yet come online. These restrictions make more sense applied to load flexibility unsupported by physical assets than they do the load response enabled by behind-the- meter generation in the types of configurations that Calibrant develops.
In addition, Section 18.2 (c)(iii) requires evidence that the “new load(s)” subject to the signed commitment with a Curtailment Service Provider or DER Aggregator will participate “in a MW quantity equal to MW quantity of the new load(s)” as Annual Demand Resources or DER Capacity Aggregation Resources. As an initial matter, it is unclear whether this requirement attaches to the quantity of new load matched to Qualifying RBP Offset UCAP MW or the entirety of a customer’s load at a given site. But if a new load supported by behind-the-meter generation were required to participate as demand resource or to purchase replacement Qualifying RBP Offset UCAP MW at no less than 100% of their full load in order to constitute Qualifying RBP Offset UCAP MW, such a constraint would be unjust and unreasonable or unduly discriminatory. There is no reasonable basis to bar a behind-the-meter generation project from serving a new load’s capacity needs in part, particularly where front-of-the-meter generation projects face no equivalent obligation to match 100% of the new load in order to be eligible as Qualifying RBP Offset UCAP MW. Prohibiting smaller generation projects from partially enabling a larger load’s provision of load response would preclude them from helping to address a resource adequacy crisis in the region; Calibrant does not believe PJM intended Section 18.2 (c)(iii) to impose such a constraint on participation by behind-the-meter generation in RBP.
Fortunately, the Tariff is broad enough to allow bilateral contracts between a behind-the- meter generation project and a new load to support the resulting capacity’s qualification as Qualifying RBP Offset UCAP MW. This pathway is best suited to the particularities of behind-
PDF page 5
5
the-meter generation development and would avoid the mismatches noted above that could limit the ability of behind-the-meter steel in the ground to help meet the region’s critical resource adequacy needs. It also reflects the fact that contracting for behind-the-meter generation to support load response looks more like contracting with front-of-the-meter assets than like the load flexibility unsupported by physical assets that 18.2 (c)(iii) appears tailored to.
II. CONCLUSION
For the foregoing reasons, Calibrant respectfully requests that PJM or the Commission clarify that behind-the-meter generation projects can provide evidence that they are eligible as Qualifying RBP Offset UCAP MW under Proposed Tariff Attachment DD Section 18.2 (c)(i), and that such projects are not restricted to demonstration via Section 18.2 (c)(iii).
Respectfully submitted,
/s/ Kim Smaczniak
Kim Smaczniak
Miles Farmer
Avi Zevin
Nathan Lobel
Roselle LLP
300 New Jersey Ave. NW, Suite 300
Washington, DC 20001
kim.smaczniak@rosellellp.com
miles.farmer@rosellellp.com
avi.zevin@rosellellp.com
nathan.lobel@rosellellp.com
PDF page 6
6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated: August 21, 2026
/s/ Nathan Lobel
Nathan Lobel
Roselle LLP
300 New Jersey Ave. NW, Suite 300
Washington, DC 20001
nathan.lobel@rosellellp.com