Comments of Equinix Inc. on the PJM Interconnection, LLC filing re Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from…
Text extracted from the eLibrary original (SHA-256 907abeb182beec32…). Download the original from the official source.
Contents · 9 sections
- I. SUMMARY
- II. BACKGROUND AND INTEREST OF EQUINIX
- III. INTRODUCTION
- IV. COMMENTS
- A. The RBP Is an Appropriate One-Time Response, but the Commission Should
- B. Bilateral Procurement Is the Most Economic and Most Just and Reasonable
- C. The Commission Should Modify the Proposed Buyer-Side RBP Collateral
- D. The RBP Should Remain a One-Time Backstop While PJM Addresses the
- V. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C. ) Docket No.Read this passage Filed comments: Reliability and curtailment
I. SUMMARY
printed heading · Topic match: Credit and exit
Equinix asks that FERC take the following actions: 1) Direct PJM, before the RBP bid submission window opens, to publish clear and complete requirements for demonstrating Qualifying RBP Offset UCAP MW, including the evidence PJM will accept and the process by which large loads may submit that…Read this passage Filed comments: Credit and exit
II. BACKGROUND AND INTEREST OF EQUINIX
printed heading · Topic match: Reliability and curtailment
It is in the long-term stability, predictability, and durability of the rules that govern reliability and market conditions, including resource adequacy, across the PJM Region.Read this passage Filed comments: Reliability and curtailment
III. INTRODUCTION
printed heading · Topic match: Cost allocation
ER26-03515. 8 Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026) (“NEDC/PJM Governors’ Principles”) (urging PJM to “allocate the cost of any new capacity procured through the aforementioned Reliability Backstop Auction to load serving entities (LSEs) with…Read this passage Filed comments: Cost allocation
IV. COMMENTS
printed heading
IV.Read this passage
A. The RBP Is an Appropriate One-Time Response, but the Commission Should
printed heading
Equinix asks the Commission, however, not to lull itself—or the region—into the belief that acceptance of the RBP would restore a “Pax PJM” in which supply and demand track one 14 PJM Interconnection, L.L.C., 107 FERC ¶ 61,112, at P 21 (2004), order on reh’g, 110 FERC ¶ 61,053 (2005), quoted in…Read this passage
B. Bilateral Procurement Is the Most Economic and Most Just and Reasonable
printed heading · Topic match: Cost allocation
The Commission’s long-held cost causation principle requires that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.”18 PJM 16 Transmittal at 7 & n.16 (citing 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 8 (July 14,…Read this passage Filed comments: Cost allocation
C. The Commission Should Modify the Proposed Buyer-Side RBP Collateral
printed heading · Topic match: Credit and exit
PJM proposes to require each LSE allocated RBP cost responsibility to post RBP Collateral equal to an RBP Credit Rate—set initially at $1.5 million—multiplied by the RBP UCAP MW committed.31 As proposed, RBP Collateral could take only two forms: a cash deposit or a letter of credit.32 PJM explains…Read this passage Filed comments: Credit and exit
D. The RBP Should Remain a One-Time Backstop While PJM Addresses the
printed heading
RBP Resources would be paid on a pay-as-bid basis under a contract for differences, subject to a maximum willingness to pay of $555/MW-day UCAP39 and without direct market power screens or mitigation;40 and each committed RBP Resource must offer its committed MW into every RPM Auction through…Read this passage
V. CONCLUSION
printed heading · Topic match: Credit and exit
Equinix respectfully requests, however, that in accepting the RBP, the Commission take the following discrete actions: 1) Direct PJM, before the RBP bid submission window opens, to publish clear guidance as to the evidence it will accept in support of Qualifying RBP Offset UCAP MW, including the…Read this passage Filed comments: Credit and exit
CERTIFICATE OF SERVICE
printed heading
Dated this the 21st day of August 2026, at Washington, D.C. /s/ Arthur Haubenstock Arthur Haubenstock Sr.Read this passage