ER26-3380-000 · 2026-08-21 · Equinix Inc.

Comments of Equinix Inc. on the PJM Interconnection, LLC filing re Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)

PJM Interconnection, L.L.C.

)
Docket No. ER26-3380-000

)

COMMENTS OF EQUINIX INC. ON THE
PJM INTERCONNECTION, LLC FILING REGARDING ITS
RELIABILITY BACKSTOP PROCUREMENT TO ADDRESS
RESOURCE ADEQUACY CONCERNS STEMMING FROM LARGE LOADS

Equinix Inc. (“Equinix”) is pleased to have this opportunity to contribute its comments in response to the filing by PJM Interconnection, L.L.C. (“PJM”) entitled “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming From Large Loads” (the “RBP Filing”), which PJM submitted on July 31, 2026.1  We respectfully provide these comments for consideration by the Federal Energy Regulatory Commission (“Commission” or “FERC”) pursuant to Rules 211 and 214 of its Rules of Practice and Procedure, 18 C.F.R. §§ 385.211, 385.214, and the Commission’s notice issued in this docket.2

I. SUMMARY
Equinix supports the adoption of the RBP on the timeline proposed by PJM. It is an urgent and necessary mechanism which, if applied as intended as a one-time backstop, can help

1 PJM Interconnection, L.L.C., “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load Adjustments,” Docket No. ER26-3380-000, Transmittal Letter (July 31, 2026) (“Transmittal”). Capitalized terms not defined herein have the meanings given in the Transmittal, the PJM Open Access Transmission Tariff (“PJM Tariff”), or the PJM Reliability Assurance Agreement among Load Serving Entities (“RAA”).

2 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, Combined Notice of Filings, 91 Fed. Reg. 50,827 (Aug. 6, 2026) (establishing a comment date of August 21, 2026). Equinix filed a timely doc-less motion to intervene in this proceeding on Thursday, August 6, 2026.

PDF page 2

2
support much-needed near-term stability for both market and reliability conditions. However, Equinix believes FERC direction is required to achieve several key objectives: to enable  the bilateral procurement that all parties agree is the preferred path; to ensure the RPB is to truly function as a backstop, and not the default mechanism; to ensure the RBP is truly a one-time stabilization measure and not a recurring feature of the PJM market; and to avoid unnecessarily exacerbating the energy affordability concerns that have driven the extremely high degree of political and public attention on energy rates.

Equinix asks that FERC take the following actions:
1) Direct PJM, before the RBP bid submission window opens, to publish clear and complete requirements for demonstrating Qualifying RBP Offset UCAP MW, including the evidence PJM will accept and the process by which large loads may submit that evidence directly;

2) Direct PJM to provide affected loads sufficient transparency into the Large Load Adjustment data underlying RBP cost allocation, subject to appropriate confidentiality protections, together with a process to correct demonstrable errors or duplication;

3) Modify the proposed buyer-side RBP Collateral provisions so that collateral is calibrated to reasonably foreseeable forward exposure and the forms of credit support available under Attachment Q are permitted. PJM expressly consented to Commission modification or severance of its Section 205 proposal pursuant to NRG Power Marketing, LLC v. FERC.3 The Commission therefore can make this discrete modification without rejecting or delaying the RBP. As proposed, the $1.5 million/MW requirement and restriction to cash or letters of credit would unnecessarily and significantly worsen energy affordability issues;

4) Make clear that acceptance of the RBP is an extraordinary, one-time response and encourage PJM to continue work on durable reforms that allow needed resources to be studied, interconnected, permitted, and placed in service on timelines consistent with identified reliability needs; and

5) Require PJM to initiate the process of identifying and evaluating tariff-codified mechanisms that can be deployed to address significant and potentially long- lasting supply-demand gaps.

3 Transmittal at 3-4 (consenting to Commission modification or severance pursuant to NRG Power Marketing, LLC
v. FERC, 862 F.3d 108 (D.C. Cir. 2017)).

PDF page 3

3
II. BACKGROUND AND INTEREST OF EQUINIX
Equinix, based in Redwood City, California, is one of the oldest and largest data center developers in the world, with data centers across six continents, over 35 countries, and more than 70 metropolitan areas. Private enterprises, network operators, cloud providers, governmental entities and nonprofits house computing equipment and interconnect with one another within Equinix’s International Business Exchange (“IBX”) data centers. Many of Equinix’s customers utilize the computing equipment in our data centers and the interconnection services we provide to enable critical services, such as emergency response, grid operations, medical information, and national security. Each individual IBX facility may house as many as 400 co-located customers. Our IBX data centers range between a few megawatts up to approximately 100 MW, and average in the mid-30 MWs. Equinix also develops, owns and operates larger xScale data centers, which can exceed 750 MW. Our xScale data centers serve customers requiring a significant dedicated proportion, or even the entirety, of these larger facilities. The data centers Equinix develops, owns and operates are long-lived assets developed against investment horizons measured in decades rather than quarters.

Equinix has operated in the PJM Region for decades. Its facilities include the very first commercial data center in Data Center Alley in Northern Virginia, as well as numerous data centers in the Chicago area, New Jersey, and Northern Virginia. Equinix takes retail electric service from Electric Distributors and Load Serving Entities across the PJM Region and, in retail choice jurisdictions, procures its supply through competitive retail suppliers. Depending on how Equinix’s procurement of new capacity is credited, Equinix may therefore bear charges resulting from the RBP as states and Relevant Electric Retail Regulatory Authorities (“RERRAs”) further allocate them, and could be directly affected by any IRAS load-reduction obligation. Equinix has no financial interest in the outcome of the RBP as a seller; its interest is entirely on the load side.

PDF page 4

4
Equinix has always held itself to a high standard of care for the communities it operates in. Recognizing that more is needed to meet the current moment, Equinix recently memorialized its practices explicitly through its U.S. Community Principles.4  These principles include Equinix’s commitment to power responsibility, ensuring it “pays the full cost of its grid infrastructure needs so costs are not passed to consumers.”5 Equinix does not regard the reliability consequences of large load growth as someone else’s problem to solve, and it has committed capital to the long-term arrangements needed for new generating capacity and energy infrastructure.

Equinix’s interest in this proceeding is accordingly not in a lower capacity price next year. It is in the long-term stability, predictability, and durability of the rules that govern reliability and market conditions, including resource adequacy, across the PJM Region. As a load that intends to sign long-term supply commitments, Equinix needs to know what those commitments will provide, what risks will remain, and how to best address those remaining risks. That is the lens through which Equinix offers the comments that follow.

III. INTRODUCTION
Equinix supports PJM’s RBP approach as a one-time response to a severe resource adequacy shortfall posing a near-term threat to reliability. Equinix urges the Commission to accept the RBP on PJM’s proposed timeline while making limited, discrete modifications and clarifications that will make bilateral procurement more workable and avoid unnecessary financing costs. Those change can be made without delaying the procurement window or disturbing the core design of PJM’s proposal.

4 Available at https://equinixtogether.com/community-principles/.
5 Id.

PDF page 5

5
Equinix asks the Commission to exercise particularly keen oversight to ensure that the RBP achieves its objective as a backstop, and does not become not the default procurement mechanism for new capacity. As PJM describes its intent, the RBP “will only procure the capacity necessary to cover any remaining shortfall from the 2028/2029 BRA after PJM has accounted for new capacity being brought by new load.”6 The premise of the design of both the RBP and the closely-related Interim Resource Adequacy Service (“IRAS”) program7—as well as the focus of the National Energy Dominance Council / PJM Governors’ Principles8 that prompted these new programs—is that large loads that bring their own new capacity should neither be procured for, nor charged for capacity procured for loads that failed to procure for themselves. Equinix agrees with that premise without reservation, has signed on to the Ratepayer Protection Pledge,9 and has issued its own U.S. Community Principles10 that hold itself to an even higher standard of care for its communities, consistent with its nearly 30-year strong track record. In short, Equinix is among the companies developing new large loads that intends to cover that load with its own new capacity procurement. The premise only operates, however, if new large loads can reasonably act on it with confidence.

Equinix therefore does not ask the Commission to hold the RBP back. It asks the Commission to condition its acceptance on the following points, none of which would require any delay in the implementation of the RBP:

1) Equivalency. Whatever capacity qualifies as Qualifying RBP Offset UCAP MW

6  Transmittal at 26. 7  The IRAS is under consideration in Docket No. ER26-03515.
8  Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026) (“NEDC/PJM Governors’ Principles”) (urging PJM to “allocate the cost of any new capacity procured through the aforementioned Reliability Backstop Auction to load serving entities (LSEs) with new data centers that have not self-procured new capacity or agreed to be curtailable”), available at https://www.energy.gov/documents/statement-principles- regarding-pjm.
9 Available at https://www.whitehouse.gov/ratepayer-protection-pledge/.
10 Op. cit. fn. 3 and associated text.

PDF page 6

6
under proposed section 18.2 must also qualify to relieve the associated load of reduction obligations under IRAS. Equinix recognizes that the Commission is limited in this docket to addressing issues raised within the IRAS docket, although PJM has throughout its Transmittal Letter acknowledged the interaction of the two programs. To the extent that PJM believes its proposed requirements for Qualifying RBP Offset UCAP MW would fail to meet the requirements of IRAS, however, that should be made clear in this docket, and the Commission should consider whether the Qualifying RBP Offset UCAP MW definition should be adjusted to address those concerns so as to avoid conflicting or incompatible criteria.

2) Clarity, in time to be useful. The RBP bid submission window is scheduled to close three weeks after it opens.11 PJM should be directed to publish, before that window opens, the specific evidentiary showing it will accept to verify Qualifying RBP Offset UCAP MW, including permissible treatment of commercially sensitive information and the process for direct submissions by large loads.

3) Allocation transparency. Direct PJM to provide affected loads access, subject to appropriate confidentiality protections, to the zonal Large Load Adjustment data on which their RBP cost allocation will rest and a defined process to correct demonstrable errors or duplication.12

4) Buyer-side collateral. Modify the proposed RBP Collateral provisions so that the RBP Credit Rate is calibrated to reasonably foreseeable forward exposure and the forms of credit support accepted under Tariff, Attachment Q are available. PJM has expressly consented to Commission modification or severance of discrete aspects of its Section 205 proposal, so this change can be made without rejecting or delaying the RBP.13

Separately, Equinix encourages the Commission to make clear that acceptance of the RBP is a response to extraordinary near-term conditions, not an endorsement of recurring backstop procurements as a substitute for durable market, interconnection, transmission and other required reforms. PJM and its stakeholders should continue that longer-term work on a considered schedule rather than waiting for the next emergency.

11  Transmittal at 32 (Qualifying RBP Offset UCAP MW “may be reported to PJM during the bid submission window, which will close three weeks after the window opening”); id. at 27 (targeting commencement of the procurement window on September 30, 2026).
12 Transmittal at 32 (Qualifying RBP Offset UCAP MW “may be reported to PJM during the bid submission window, which will close three weeks after the window opening”); id. at 27 (targeting commencement of the procurement window on September 30, 2026).
13 Op cit. fn. 3.

PDF page 7

7
These limited requests would preserve PJM's proposed procurement timeline while ensuring it is reasonably feasible for load to undertake the bilateral procurement PJM intends and expects to minimize the scope and total cost of the RBP. These requests would also serve to reduce or eliminate avoidable costs that otherwise would be passed through to customers, exacerbating energy affordability concerns.

IV. COMMENTS
A. The RBP Is an Appropriate One-Time Response, but the Commission Should
Not Assume Current Conditions are a One-Time Aberration.
As PJM’s RBP transmittal letter observes, the Commission has long recognized that where market-design measures alone prove insufficient, it “is willing to consider specific proposals to provide an appropriate last resort process such as an RTO/ISO administered auction to create a long-term commitment which can support cost-effective financing where the problem is projected to be a long-term one.”14 Equinix agrees that the present circumstances fit that description. Two consecutive auctions have cleared short at the cap; PJM represents that all evidence points to the December 2026 auction clearing short as well. Equinix accordingly supports the RBP as a one-time mechanism, and supports PJM’s decision to design a tailored instrument rather than invoke the Reliability Backstop Auction provisions that have sat unused in Attachment DD, section 16 for twenty years.15 The existing provisions were built for a different problem.

Equinix asks the Commission, however, not to lull itself—or the region—into the belief that acceptance of the RBP would restore a “Pax PJM” in which supply and demand track one

14  PJM Interconnection, L.L.C., 107 FERC ¶ 61,112, at P 21 (2004), order on reh’g, 110 FERC ¶ 61,053 (2005), quoted in Transmittal at 27.
15  Transmittal at 29 (noting that the existing Reliability Backstop Auction in Tariff, Attachment DD, section 16 “was proposed over 20 years ago but has never once been used”).

PDF page 8

8
another closely and the annual auction will do the rest. The conditions that produced the current shortfalls are structural. Supply did grow between the two auctions—by a net 1,294.4 MW ICAP between the 2027/2028 and 2028/2029 BRAs—but, as PJM puts it, “the addition of new supply has not kept pace with rapid large load demand growth.”16 Replacement supply arrives on interconnection, permitting, and construction timelines that no procurement mechanism can compress below physical limits, while PJM’s own twenty-year forecast continues to project significant long-term load growth.17 The gap between those two rates is what produced the 2027/2028 and 2028/2029 results, and nothing in the RBP changes either rate. Morever, significant increases in demand and significant shortfalls in supply availability may well occur as a result of multiple factors. While the current supply-demand gap is, inarguably, predominantly driven by data center growth, other causes of supply-demand imbalance could yield similarly untenable BRA results, as discussed further herein. A more thoughtful, advanced preparation that is thoroughly vetted through unrushed stakeholder and FERC review processes is needed to address the likelihood of significant supply-demand gaps in the future.

B. Bilateral Procurement Is the Most Economic and Most Just and Reasonable
Path: the Commission Should Ensure the RBP Does Not Displaces It.
1. RBP Cost Allocation Should Align with Load Procurement of its Own
New Capacity.
The Commission’s long-held cost causation principle requires that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.”18 PJM

16  Transmittal at 7 & n.16 (citing 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 8 (July 14, 2026)).
17  Transmittal at 6-7 & n.15 (describing PJM’s updated 20-year load forecast and continued significant long-term load growth).
18  Ill. Com. Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009)(citing KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 708 (D.C. Cir. 2000); Pacific Gas & Elec. Co. v. FERC, No. 03-1025, 373 F.3d 1315, 1320-21 (D.C. Cir. 2004)).

PDF page 9

9
invokes that principle in support of its allocation methodology, and correctly observes that decrementing a zone’s allocation by Qualifying RBP Offset UCAP MW “guards against assigning costs to those who will not benefit from the addition of the new capacity procured through the RBP.”19 Equinix agrees. The difficulty is that the decrement will operate at the level of the Electric Distributor zone/area, and the further allocation within the zone is left to states and RERRAs under mechanisms that, in most jurisdictions, do not yet exist. New Jersey presents one example of how that allocation can be properly structured with its recent Data Center Fair Share Act,20 and as PJM notes in its transmittal letter Virginia’s State Corporations Commission and the Data Center Coalition are collaborating on model tariff language that will hopefully also help address these questions.21

Further allocation within each zone is left to states and RERRAs, as necessitated by the split in jurisdiction between wholesale and retail markets. As a result, the wholesale decrement alone cannot guarantee that the individual load responsible for qualifying bilateral procurement receives the corresponding retail benefit.

Equinix does not ask the Commission to dictate retail allocation. It does ask PJM to provide states and RERRAs the information needed to implement retail mechanisms consistent with the RBP's design and cost-causation rationale. In particular, PJM should identify the Qualifying RBP Offset UCAP MW reflected in each zone's decrement and work with state authorities so those data can be used in retail proceedings. That coordination is important if the RBP is to encourage bilateral procurement while protecting customers that did not cause the need

19  Transmittal at 102 (“By reducing allocated load further based on Qualifying RBP Offset UCAP MW, the proposed methodology guards against assigning costs to those who will not benefit from the addition of the new capacity procured through the RBP.”).
20 Data Center Fair Share Act, P.L. 2026, c, 32; S. 731, 222nd Leg., Reg. Sess. (N.J. 2026)(the “NJ Data Center Fair Share Act”).
21 Transmittal at 10.

PDF page 10

10
for backstop procurement.
It is one thing to say that cost causation need not be perfect; it is another to socialize, within a rate class, the costs of either 1) speculation by others onto the members of that class who behaved responsibly, or 2) large load adjustment calculations that are insufficiently tethered to reasonable assumptions and calculations. It is certainly true, as PJM asserts, that retail cost allocation measures are outside of PJM’s wholesale market jurisdiction.22  It is equally true, as PJM observes,

“[S]erving emerging large loads while meeting the mandates of the PJM state utility commissions will ‘require proactive collaboration among states, industry, and PJM to develop standardized regulatory tools and model retail tariff structures that individual state commissions may consider as they address the integration of new large electric loads.’”23

PJM is launching two tidal waves through its proposed market design changes, waves that would inevitably flow across the jurisdictional divide and impact the retail markets. The clearly foreseeable impacts of wholesale market changes on retail market conditions require further action. At the very least, consistent with the Transmittal’s acknowledgment of the need for “proactive collaboration,” PJM could convene state actors with relevant jurisdiction to coordinate efforts.  This “proactive collaboration” could help ensure wholesale and retail market elements flange up with minimal unintended adverse consequences, and better realize the shared intent of the NCED/PJM Governors’ Principles and of PJM’s RBP filing to 1) incent large loads to bilateral procurement and 2) minimize energy affordability impacts.

22 See, e.g., Transmittal at 14-16. 23 Transmittal at 11 (quoting Letter of Chair of Virginia State Corporation Commission, Kelsey Bagot and President and CEO of Data Center Coalition, Josh Levi to Ms. Paula Conboy, Chair of PJM Board of Managers, and Mr. David Mills, President and CEO of PJM Interconnection, L.L.C., at 1 (June 30, 2026), available at https://perma.cc/S7C6-C86H)

PDF page 11

11
2. Bilateral Procurement Requires Clear, Usable Implementation Rules. Equinix asks the Commission to recognize that the RBP’s central design premise—that load will bring its own capacity—places a responsibility on load, and that load can only be reasonably expected to discharge that responsibility if four conditions are met:

• First, PJM must clearly identify when and how Qualifying RBP Offset UCAP MW will reduce the RBP procurement attributable to a zone and provide states and RERRAs information sufficient to trace that decrement to the procurement that created it. Load must be assured that new bilateral capacity procurement will protect it from RBP cost allocation. That assurance must be reliable at the level of the individual load, not merely at the level of the zone.

• Second, load must be assured that the same new capacity procurement credited against RPB cost allocation will protect it from IRAS curtailment. As noted above, while the Commission is limited in what it can do with respect to IRAS in this docket, it can ensure that the definitions applicable to RBP do not conflict with those applicable to IRAS. As a practical matter, a load facing an unquantified probability of curtailment cannot justify the cost of procuring new capacity: if it may be curtailed whether or not it self-supplies, it has insufficient reason to bilateral procurement. The two instruments must be read together because, from a load perspective, there is very little purpose to considering them separately; protection from RBP cost allocation pales in comparison to the risk of significant, lengthy and/or repeated curtailment that could challenge continued reliability of the information systems our emergency response, financial, medical, security and other sectors- and even grid operations- have come to rely upon.

• Third, PJM should coordinate with the states and RERRAs responsible for retail allocation so they have the information necessary to implement the RBP's cost- causation design, and consider a convening to ensure wholesale and retail rate designs work as seamlessly together as possible. Again, Equinix does not ask the Commission to prescribe a retail rate or allocation methodology; it asks that the wholesale construct provide a usable factual foundation for the authorities that must make those retail decisions.

• Fourth, crediting terms must be defined clearly enough to permit effective, manageable procurement by load, including the evidence that must be shown to ensure that credit is awarded. The proposed Tariff sets out the elements at a high level—a signed bilateral contract of at least five Delivery Years, documentation of an expected online date no later than June 1, 2032, and evidence matching the capacity to load.24 What it does not supply is the form and detailed content requirements of that showing, including what documents PJM will accept, what redactions are permitted,

24  Tariff, Attachment DD, section 18.2(c) (as proposed); Transmittal at 39 (bilateral contracts of at least five Delivery Years, documented expected online date no later than June 1, 2032, matched to load with an executed electric service agreement or transmission service agreement for the 2027/2028 or 2028/2029 Delivery Years).

PDF page 12

12
what happens when a contract is contingent, and how a load whose Electric
Distributor declines to report on its behalf can make the showing directly. PJM has
committed to accept reports from “large loads” among others,25 which Equinix
appreciates. PJM should be directed to publish the accompanying evidentiary
specification before the procurement window opens. Moreover, a load that has
satisfied PJM’s evidentiary standard once should not be required to satisfy a different standard, on different evidence, for the other half of the same interconnected policy: as noted above, the criteria, and the evidence required to establish those criteria, must be the same for both the RBP and the IRAS to support significant bilateral

contracting.26  Equinix anticipates raising this issue as appropriate in the IRAS
proceeding.
4. The Peak Shaving, Five year Minimum Term, and Fixed RBP Credit
Level Features Properly Support Bilateral Procurement.
Peak shaving. Equinix applauds PJM’s recognition, in the second proposed opt-out, that to the extent load participates in a state-codified peak shaving adjustment program, it has already addressed that extent of its capacity needs and should not be procured for again.27 That recognition is sound and should be preserved in the RBP. The Transmittal separately notes that a zone/area receiving that opt-out may still be subject to load reduction under IRAS.28  While that issue is not formally before the Commission in this docket, other than the reference in the Transmittal letter itself, Equinix flags it because 1) the reference threatens to undermine the use of the Peak Shaving programs to achieve the objectives of the RPB, and 2) the interaction between a federal curtailment construct and state-codified peak-shaving programs raises distinct

25  Transmittal at 43 (PJM “will also accept reports and evidence of Qualifying RBP Offset UCAP MW provided during the RBP bid submission window by other jurisdictional, as well as non-jurisdictional entities, including, but not limited to, Transmission Owners, LSEs, interconnecting customers, large loads, and state regulatory agencies.”).
26 To be clear, Equinix does not ask that the RBP’s seller-side eligibility rules be conformed to the offset rules. PJM has given reasoned explanations for holding RBP Resources to more stringent standards than Qualifying RBP Offset UCAP MW—those resources take a fifteen-year commitment and a must-offer obligation, and PJM is entitled to insist on a higher showing of viability. The potential asymmetry Equinix objects to is the one between the two load- side constructs, where no such justification has been offered, and where conflicting requirements could undermine the objectives of both programs.
27 Transmittal at 45 (citing NJ Data Center Fair Share Act ); Tariff, Attachment DD, section 18.1(d) (as proposed).
28 Transmittal at 45.

PDF page 13

13
jurisdictional and policy questions, which Equinix anticipates addressing in the IRAS proceeding.

Five-year minimum term. Equinix supports PJM’s selection of a five-Delivery-Year minimum term for the bilateral contracts and bilateral procurement arrangements that may generate Qualifying RBP Offset UCAP MW.29 The balance PJM strikes is the right one: a five- year floor is long enough to demonstrate that the capacity has been well-established, is not transitory, and is likely to be available to support resource adequacy needs even after the initial contracting term is over. It is also short enough to avoid foreclosing commercially reasonable structures, as well as avoiding excess costs and financing burdens, all of which would serve to deter bilateral contracting. A longer minimum would have excluded a meaningful share of the very bilateral procurement the RBP is designed to encourage.

Fixing the RBP credited value at the time of procurement. Equinix likewise supports PJM’s proposal to determine the UCAP value of Qualifying RBP Offset UCAP MW using the applicable ELCC Class Ratings for the 2028/2029 Delivery Year BRA, or unit-specific UCAP values where no class rating exists, rather than re-rating that capacity annually over the life of the arrangement.30 Load contracting today cannot price accreditation risk fifteen years forward, and a floating credit would transfer to load a modeling risk it has no ability to manage. Fixing the capacity value at the time of procurement solely for purposes of crediting against the RBP and its cost allocation (and not for operational reliability reasons) is therefore just, reasonable, and an important feature of making long-term bilateral commitments feasible. Equinix therefore urges the Commission to preserve this element in the RBP. Equinix anticipates addressing the

29  Transmittal at 39-40; Tariff, Attachment DD, sections 18.2(c)(i)-(ii) (as proposed).
30  Transmittal at 32; Tariff, Attachment DD, section 18.2(d) (as proposed).

PDF page 14

14
treatment of accreditation under IRAS in the separate IRAS proceeding.
C. The Commission Should Modify the Proposed Buyer-Side RBP Collateral
Requirement to Avoid Excessive and Unduly Restrictive Requirements.
PJM proposes to require each LSE allocated RBP cost responsibility to post RBP
Collateral equal to an RBP Credit Rate—set initially at $1.5 million—multiplied by the RBP UCAP MW committed.31 As proposed, RBP Collateral could take only two forms: a cash deposit or a letter of credit.32 PJM explains that the $1.5 million figure was chosen to hold collateral covering “approximately 50% of the notional value of all RBP commitments” from day one.33 Equinix respectfully submits that this requirement as currently framed is not just and reasonable, for three reasons.

The Commission can remedy these defects without rejecting or delaying the RBP. PJM expressly consented to Commission modification or severance of its proposal. That consent is especially important here: the buyer-side collateral provisions are discrete from the procurement's core design, and modifying them would leave the RBP otherwise intact while avoiding an unnecessary financing burden.34

First, the calibration is disproportionate and internally inconsistent. Sellers—who bear genuine development, supply chain, and permitting risk and have the most control over those risks, and whose non-performance is the failure mode PJM says most threatens the region— would be required to post 20% of three Delivery Years of offer value.35 Buyers, whose obligation

31  Tariff, Attachment DD, section 18.8(b)(i)(A) (as proposed); Transmittal at 116.
32  Tariff, Definitions – RBP Collateral (as proposed) (“either (1) a cash deposit, including any interest thereon, or
(2) a letter of credit issued for the benefit of PJM or PJM Settlement”); Transmittal at 108 n.260, 110.
33  Transmittal at 117 (explaining that $1.5 million per MW “ensures that PJM holds sufficient collateral to cover approximately 50% of the notional value of all RBP commitments,” calculated as 15 years × 365 days × $555/MW- day = $3,038,625).
34  Op cit. fn. 3.
35  Tariff, Attachment DD, section 18.8(a)(iv) (as proposed); Transmittal at 112 (seller credit requirement equal to the sum of 20% of the RBP Sell Offer Price × RBP UCAP MW for each of the first three Delivery Years offered).

PDF page 15

15
is to pay a known, tariffed, declining schedule of charges, would be required to post roughly half of a fifteen-year notional value. A requirement calibrated to a rolling forward exposure window—one to three years of RBP Charges, measured on the same principle PJM applies to sellers—would mitigate the same non-payment risk at a small fraction of the cost. Second, the analogy to Financial Transmission Rights does not hold. PJM justifies restricting RBP Collateral to cash or letters of credit by reference to “the credit requirements imposed on inherently riskier Financial Transmission Rights.”36 FTR exposure is volatile, marked to changing congestion outcomes, and can move sharply within a Delivery Year. RBP Charges are the opposite: fixed by a Commission-approved contract for differences, known in advance, reduced by the establishment of new capacity that is reasonably likely to continue in existence so long as the market is available to pay, and payable on a schedule that only shrinks. That risk profile is well within the range PJM manages every day under Attachment Q, which accommodates unsecured credit based on creditworthiness and corporate guaranties.37 Equinix asks the Commission to direct PJM to accept, for RBP purposes, the forms of credit support it accepts under Attachment Q, including unsecured credit for LSEs that satisfy PJM’s existing creditworthiness standards.

Third, the requirement works against the ratepayer protection rationale offered to support it. PJM invokes the Ratepayer Protection Pledge in support of buyer-side collateral.38 But collateral- especially cash and letters of credit- is not free. An LSE that must post cash or purchase a letter of credit covering half the notional value of a fifteen-year commitment will

36  Transmittal at 109-10 (analogizing to “the credit requirements imposed on inherently riskier Financial Transmission Rights”).
37  Tariff, Attachment Q (PJM Credit Risk Management Policy). PJM expressly declined to house the RBP credit rules in Attachment Q. See Transmittal at 108-09.
38  Transmittal at 109-10 (invoking the Ratepayer Protection Pledge as support for the buyer-side collateral requirement).

PDF page 16

16
almost certainly have to finance that posting, and the cost of that financing will appear in retail rates. On the region-wide Final RBP Target, the aggregate posting contemplated by a $1.5 million per MW rate runs to billions of dollars of tied-up capital. Requiring load to pre-fund half of a fifteen-year obligation on day one, in the two most expensive forms of assurance available, would by itself materially increase the rates that the Pledge was adopted to protect. Equinix urges the Commission to direct PJM to recalibrate the RBP Credit Rate to a rolling forward-exposure measure and to broaden the permissible forms of RBP Collateral.

D. The RBP Should Remain a One-Time Backstop While PJM Addresses the
Structural Constraints That Produced the Shortfall.
The RBP will, if accepted, create a second capacity construct that operates alongside the Reliability Pricing Model (“RPM”) for fifteen Delivery Years. RBP Resources would be paid on a pay-as-bid basis under a contract for differences, subject to a maximum willingness to pay of $555/MW-day UCAP39 and without direct market power screens or mitigation;40 and each committed RBP Resource must offer its committed MW into every RPM Auction through 2042/2043 as a $0/MW-day price taker.41 Equinix understands why PJM made each of these choices, and does not ask the Commission to reject them in this proceeding.

The Commission should be clear-eyed about what a bifurcated market means if it
persists. A block of supply equal to as much as the entire observed shortfall will sit outside price formation for fifteen years while remaining inside the reliability requirement. Whatever the

39  Transmittal at 61-62; Tariff, Attachment DD, section 18.5(f) (as proposed).
40  Id. at 65-66 (describing the pay-as-bid structure and the absence of a “marginal unit” in any meaningful sense); id. at 66 (“No direct market power screens or mitigation are being proposed for the RBP.”).
41  Tariff, Attachment DD, section 18.6(a) (as proposed); Transmittal at 56 (a committed RBP Resource “must offer its available capacity, up to the total quantity of committed RBP UCAP MW, into the RPM Auctions as a price taker, i.e., $0/MW-day UCAP . . . continuing each subsequent Delivery Year through the end of the fixed, 15-year term”).

PDF page 17

17
merits of that approach as an emergency response, its longer-run effects on entry signals, customer costs, and resource incentives warrant deliberate evaluation outside the compressed schedule of this filing.

The broader lesson is that the RBP addresses an immediate procurement gap neither eliminates the underlying constraints on bringing new supply to load, nor paves the way for the mechanisms needed to address future significant supply-demand gaps before they disrupt the market and in more considered fashion. PJM developed this proposal under acute time pressure and expressly asked the Commission to modify or sever aspects of the filing as needed to permit timely acceptance. That flexibility is appropriate for the present filing, but it should not become the region's default method of addressing future supply-demand imbalances.

Future imbalances could arise from many sources, including additional load growth, generation retirements, the unexpected loss of major resources, electrification, or delays in interconnection, transmission, permitting, supply chains, and construction. It would be prudent to assume there may very well be a next time, if not many future reoccurrences of similar supply- demand imbalances to those that resulted in this and the IRAS proceedings. PJM has already begun a broader inquiry into durable market design, and should be commended for doing so, especially with respect to its thoughtful and insightful white paper.42 Equinix supports that work and believes it should include the practical reforms necessary for new resources - including resources procured bilaterally by large loads - to be studied, interconnected, permitted, and placed in service on timelines that can actually address identified reliability needs.

42 PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability (May 9, 2026), available at https://perma.cc/3W8Z-M4TQ.

PDF page 18

18
Accordingly, Equinix asks the Commission to make clear that acceptance of this RBP is not precedent for recurring emergency procurements and direct PJM to initiate the process of identifying and evaluating tariff-codified mechanisms that can be deployed to address significant and potentially long-lasting supply-demand gaps, so that the next response is a rule rather than a rush. This step would not present any cause for delay of the RBP.

V. CONCLUSION
Equinix supports the Reliability Backstop Procurement as a one-time mechanism and urges the Commission to accept it so that the procurement window may open as scheduled. Equinix respectfully requests, however, that in accepting the RBP, the Commission take the following discrete actions:

1) Direct PJM, before the RBP bid submission window opens, to publish clear guidance as to the evidence it will accept in support of Qualifying RBP Offset UCAP MW, including the process for direct submissions by large loads;

2) Direct PJM to provide affected loads, subject to appropriate confidentiality protections, access to the RBP target adjustment data relevant to RBP cost allocation and a process to correct demonstrable errors or duplication;

3) Modify the buyer-side RBP Collateral provisions so that collateral is calibrated to reasonably foreseeable forward exposure and the forms of credit support accepted under Tariff, Attachment Q are available. PJM expressly consented to Commission modification or severance of its Section 205 proposal, so the Commission can make this discrete change without rejecting or delaying the RBP;

4) Make clear that acceptance of the RBP is an extraordinary, one-time response and encourage PJM to continue work on durable reforms that allow needed resources to be studied, interconnected, permitted, and placed in service on timelines consistent with identified reliability needs; and

5) Require PJM to initiate the process of identifying and evaluating tariff-codified mechanisms that can be deployed to address significant and potentially long-lasting supply-demand gaps.

Equinix does not ask the Commission in this docket to resolve how bilateral procurement should be treated under IRAS. Equinix does, however, flag that PJM's objective of encouraging large

PDF page 19

19
loads to bring new capacity will depend on coherent and consistent treatment of those investments across its related reforms, and Equinix expects to address that issue directly in the IRAS proceeding.

Equinix again appreciates the opportunity to submit these comments. We look forward to further participation in this and related dockets.

Respectfully submitted,
/s/ Arthur Haubenstock
Arthur Haubenstock
Sr. Counsel, Global Regulatory
Equinix Inc.
700 “K” Street, N.W., Suite 600
Washington DC, 20001
(202) 322-9073
ahaubenstock@equinix.com

PDF page 20

CERTIFICATE OF SERVICE

I hereby certify that I have on this date caused a copy of the foregoing document to be served on each person included on the official service list maintained for this proceeding by the Commission’s Secretary, by electronic mail or such other means as a party may have requested, in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.

Dated this the 21st day of August 2026, at Washington, D.C.

/s/ Arthur Haubenstock

Arthur Haubenstock
Sr. Counsel, Global Regulatory
Equinix Inc.