ER26-3380-000 · 2026-08-21 · Constellation Energy Generation, LLC

Limited Protest of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s 07/31/2026 filing

Text extracted from the eLibrary original (SHA-256 b435d43e3cac6d68…). Download the original from the official source.

Contents · 15 sections
  1. I. LIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP p. 3
  2. A. Introduction and Summary p. 3
  3. B. PJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable p. 5
  4. C. The Risk Is Most Acute When Available RBP UCAP Precedes or Exceeds p. 8
  5. D. Annual RBP Isolation and a Matched Demand Adjustment Will Preserve the p. 10
  6. II. THE PHRASE “MAXIMUM FACILITY OUTPUT” IN TARIFF SECTION p. 13
  7. III. QUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A p. 15
  8. IV. LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS p. 16
  9. V. THE MODIFICATIONS PROPOSED HEREIN COMPLY WITH NRG POWER p. 17
  10. VI. CONCLUSION p. 18
  11. I. Qualifications and Purpose of Affidavit p. 22
  12. II. Background p. 23
  13. III. PJM Must Isolate the Impact of the RBP Central Procurement p. 24
  14. IV. Recommendation p. 29
  15. Attachment A p. 35

Read topic-matched comments in ER26-3380

Topics in the text: Reliability and curtailment · Credit and exit · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 33, 34.

Opening text

opening text · Topic match: Reliability and curtailment

The first and most important is for the Commission to reject PJM’s proposal that “Available RBP UCAP” 3 participate in Reliability Pricing Model (“RPM”) Auctions as a price taker for the duration of the RBP commitment.4 PJM suggests that RBP resources must be offered 1 18 C.F.R. § 385.211. 2 PJM…
Read this passage Filed comments: Reliability and curtailment

I. LIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP

printed heading

LIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP MUST OFFER INTO RPM AS A PRICE TAKER
Read this passage

A. Introduction and Summary

printed heading · Topic match: Reliability and curtailment

Such degradation to RPM could result in resources deferring market entry or capital expenditures, exporting to other markets, or accelerating retirements—undermining the express resource adequacy purpose of PJM’s RBP proposal.12 8 NRG Power Mktg., LLC v.
Read this passage Filed comments: Reliability and curtailment

B. PJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable

printed heading · Topic match: Reliability and curtailment

PJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable PJM has shown why RBP resources should be retained for resource adequacy and why selected sellers should receive their accepted RBP compensation.
Read this passage Filed comments: Reliability and curtailment

C. The Risk Is Most Acute When Available RBP UCAP Precedes or Exceeds

printed heading

Shanker uses a simplified example in which the full Initial RBP Target is available in the relevant auction but load is delayed.23 This delayed-load example shows the resulting problem.24 Assume, for illustration, that approximately 6.8 GW of RBP capacity becomes available and must enter RPM at a…
Read this passage

D. Annual RBP Isolation and a Matched Demand Adjustment Will Preserve the

printed heading

Shanker also explains why all RBP resources must be excluded, as price-taker offers cannot readily be prorated among individual large-load projects.
Read this passage

II. THE PHRASE “MAXIMUM FACILITY OUTPUT” IN TARIFF SECTION

printed heading · Topic match: Cost allocation

To qualify as an RBP Resource, a generation resource must meet the requirements of sections 18.5(a) and 18.5(b) of the proposed Tariff.
Read this passage Filed comments: Cost allocation

III. QUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A

printed heading

QUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A MEANINGFUL CURE PERIOD Constellation requests clarification that PJM will provide a submitting entity five calendar days from notice to cure a deficiency in a Qualifying RBP Offset UCAP MW submission, provided that the cure is completed…
Read this passage

IV. LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS

printed heading · Topic match: Credit and exit

LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS The Commission should exercise its authority to modify the proposed Tariff language to clarify two aspects of the credit and collateral provisions in the proposed Tariff.
Read this passage Filed comments: Credit and exit

V. THE MODIFICATIONS PROPOSED HEREIN COMPLY WITH NRG POWER

printed heading · Topic match: Cost allocation

Cir. 2017). 18 The requested modifications to the Tariff here do not create an “entirely different rate design.”44 The isolation condition preserves the RBP solicitation, target determination, offsets and opt-outs, seller eligibility, selection process, resource-specific compensation, commitment…
Read this passage Filed comments: Cost allocation

VI. CONCLUSION

printed heading · Topic match: Credit and exit

The Commission should also exercise of its authority to modify the proposed Tariff language to: (1) delete the phrase “new Maximum Facility Output” in Tariff section 18.5(b)(i) and include qualifying Energy Resources in section 18.5(b)(iii); (2) provide a five-calendar-day cure opportunity for…
Read this passage Filed comments: Credit and exit

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 21 day of August 2026. /s/ Alexandra K.
Read this passage

I. Qualifications and Purpose of Affidavit

printed heading · Topic match: Reliability and curtailment

The purpose of my affidavit is to assist the Commission with its decision-making process as it evaluates PJM’s proposal in this docket as filed on July 31, 2026.1 I specifically address the interaction of the Reliability Backstop Procurement (“RBP”) and the subsequent offer requirements proposed…
Read this passage Filed comments: Reliability and curtailment

II. Background

printed heading · Topic match: Reliability and curtailment

While the RBP proposal is complex and has many different features worth discussing, I focus my affidavit chiefly on one element of the proposal: the requirement that all capacity resources committed through the RBP central procurement must offer that capacity into future RPM Auctions at a $0/MW-day…
Read this passage Filed comments: Reliability and curtailment

III. PJM Must Isolate the Impact of the RBP Central Procurement

printed heading · Topic match: Reliability and curtailment

PJM Must Isolate the Impact of the RBP Central Procurement 8.
Read this passage Filed comments: Reliability and curtailment

IV. Recommendation

printed heading · Topic match: Reliability and curtailment

But if PJM must intervene now with an ad-hoc intervention such as the RBP out- of-market procurement, a top priority of the intervention should be to preserve resource adequacy by maintaining the competitive integrity of the overall market going forward to the greatest extent possible.
Read this passage Filed comments: Reliability and curtailment

Attachment A

printed heading · Topic match: Reliability and curtailment

Resource- or customer-specific confidential information may be omitted from the public posting but shall be made available to the Market Monitoring Unit. (i) Effect Limited to RPM Price Formation The exclusion of Available RBP UCAP MW under this section shall not relieve an RBP Resource of any…
Read this passage Filed comments: Reliability and curtailment