ER26-3380-000 · 2026-08-21 · Constellation Energy Generation, LLC
Limited Protest of Constellation Energy Generation, LLC re PJM Interconnection, L.L.C.’s 07/31/2026 filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
)
LIMITED PROTEST OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC” or
“Commission”) Rules of Practice and Procedure,1 Constellation Energy Generation, LLC
(“Constellation”) hereby submits this limited protest of the revisions PJM Interconnection, L.L.C. (“PJM”) submitted on July 31, 2026, to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).2
Constellation has serious concerns with several elements of the RBP, including its new- resource limitations, pay-as-bid procurement structure, and cost-allocation consequences. Given the need for prompt action, however, this limited protest seeks four targeted modifications and/or clarifications. The first and most important is for the Commission to reject PJM’s proposal that “Available RBP UCAP” 3 participate in Reliability Pricing Model (“RPM”) Auctions as a price taker for the duration of the RBP commitment.4 PJM suggests that RBP resources must be offered
1 18 C.F.R. § 385.211.2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (the “PJM Proposal”). Capitalized terms used but not otherwise defined herein have the meaning as defined in the Tariff, the RAA, or the PJM Proposal, as applicable. 3 “Available RBP UCAP” means committed RBP UCAP that, for the applicable Delivery Year, is accredited, has satisfied the applicable commercial-operation or registration requirements, is deliverable where required, and is available to provide capacity.4 See PJM Proposal at 56.
PDF page 2
2
into RPM as a price-taker to ensure load does not “double pay” for capacity. PJM’s proposal will do more harm than good, however, because it will undermine RPM’s ability to send accurate resource adequacy price signals in the future.5 As explained in Section I and the accompanying Affidavit of Roy J. Shanker, Ph.D., included here as Appendix A, PJM’s proposed requirement is not a just and reasonable means of addressing PJM’s asserted duplicate-procurement concern. Instead, Section I herein outlines why the Commission should direct PJM to exclude Available RBP UCAP from RPM price formation with a matched exclusion of RBP-Related Load.6 Such an annual isolation mechanism that adjusts both RBP supply and the matched quantity of RBP- Related Load while preserving the RBP resources’ compensation and physical obligations is reflected in the Tariff language contained in Appendix B to this limited protest. 7 This modest adjustment to PJM’s proposal will allow the RBP to procure the megawatts needed to address PJM’s immediate resource adequacy shortfall, while preserving RPM’s effectiveness for price formation in support of long-term resource adequacy.
Sections II through IV describe three additional changes that FERC must make to render the filing just and reasonable: (1) the deletion of the “new Maximum Facility Output” requirement in Tariff section 18.5(b)(i) and inclusion of qualifying Energy Resources in section 18.5(b)(iii);
(2) the addition of a meaningful cure period for Qualifying RBP Offset UCAP MW submissions; and (3) clarification and revision of certain credit and collateral provisions.
5 Id. at 57.6 “RBP-Related Load” means the portion of the incremental-load cohort used to establish or allocate the RBP that PJM includes in the planning parameters for the applicable RPM Auction. 7 The proposed, illustrative language in Appendix B regarding the isolation mechanism is provided to assist the Commission in exercising its authority (to which PJM consented) to modify the proposed Tariff pursuant to the FPA and NRG Power Marketing in order to resolve the issues raised in this limited protest. See, e.g., PJM Proposal at 3-4 and 130-131. No severance is recommended and effectuating Appendix B may be done and meshed with the other parts of the Tariff without causing delay in the commencement of the RBP in September 2026.
PDF page 3
3
Accordingly, consistent with NRG Power Marketing, LLC v. FERC,8 the Commission
should accept the RBP subject to the exercise of its authority to modify the proposed Tariff language in order to effectuate the four targeted Tariff and RAA modifications set forth herein and in Appendix B.
I. LIMITED PROTEST OF REQUIREMENT THAT AVAILABLE RBP UCAP
MUST OFFER INTO RPM AS A PRICE TAKER
A. Introduction and Summary
The capacity challenge facing the PJM Region is serious.9 While PJM’s filing includes several imperfections, Constellation does not oppose PJM’s use of a one-time RBP to address the shortfall in the 2028/2029 Base Residual Auction (“BRA”), reduced as applicable for accepted offsets and opt-outs.10
Although PJM frames the RBP as a one-time stopgap measure, the zero-offer obligation will affect repeated RPM Auctions for as long as fifteen years.11 The RBP may address an immediate procurement need, but without modification it can weaken the market’s ability to attract and retain the capacity PJM will need in later years. PJM’s price-taker requirement is unsupported and potentially harmful because it impairs RPM as a credible price-forming market. Such degradation to RPM could result in resources deferring market entry or capital expenditures, exporting to other markets, or accelerating retirements—undermining the express resource adequacy purpose of PJM’s RBP proposal.128 NRG Power Mktg., LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017).9 This limited protest does not challenge PJM’s decision to procure needed capacity or to impose enforceable physical performance obligations on selected resources.10 See PJM Proposal at 7–9.11 See id. at 5, 7.12 PJM itself has said RPM pricing below the value placed on capacity by other regions incents generators to export to neighboring regions. See PJM Interconnection, L.L.C, 2027/2028 Base Residual Auction Reserve Target Shortfall
PDF page 4
4
As Dr. Roy Shanker—an economist with more than 50 years of electric-industry
experience and approximately 30 years of competitive-market-design experience, including participation in PJM market design since RPM’s inception—explains: When Available RBP UCAP precedes or exceeds the RBP-Related Load reflected in an RPM Auction, the mandatory zero-offer rule can cause RPM to signal excess supply to the residual market.13 Distorting the RPM price signal threatens increased retirement risk, incents resources to export to other markets,14 and delays market entry and capital investment—leaving PJM short yet again when delayed load arrives.15 The risk of delayed load is real and looming, so ensuring RPM sends correct price signals, rather than promoting the exit of existing generation, is of critical importance to reliability.
PJM has not addressed the foreseeable mismatch between supply and load timing. PJM has supported the physical retention and compensation of RBP resources, but it has not shown that requiring those resources to offer at zero in RPM auctions will support resource adequacy in PJM beyond covering the most immediate shortfall. That omission is the heart of this limited protest, and the solution lies in conditioning approval of PJM’s FPA 205 filing on the annual isolation mechanism that excludes the RBP resources and a matched quantity of RBP Load from RPM Auctions as set forth in Section I.D.
Report 12 (Feb. 9, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027- 2028/2027-2028-bra-reserve-target-shortfall-report.pdf.
13 See Shanker Aff. ¶¶ 9, 1414 See, e.g., Cordova Energy Company LLC, 194 FERC 61,108 (2026) (authorizing a 611.2 MW natural-gas fueled, combined-cycle electric generating facility located in PJM to sell its capacity to an affiliate in MISO during the 2028/2029 Delivery Year after already receiving approvals for similar sales during the 2027/2028 Delivery Year); Dairyland Power Coop., 194 FERC ¶ 61,133, at P 5 (2026) (explaining that Dairyland acquired PJM units for the purpose of exporting energy and capacity to fulfill Dairyland’s capacity obligations to its distribution cooperative members located in MISO).15 See Shanker Aff. ¶¶ 13–16.
PDF page 5
5
The PJM proposal aims to implement the Statement of Principles Regarding PJM issued on January 16, 2026, by the National Energy Dominance Council and the 13 governors of the PJM states.16 The NEDC/PJM Governors’ Principles called both for prompt procurement and a return to market fundamentals.17 But mandatory zero offers for separately compensated RBP capacity frustrates that objective by causing RPM to signal excess supply when Available RBP UCAP exceeds RBP-Related Load that actually materializes. The RBP proposed by PJM is not a return to market fundamentals but rather a retreat from them.
It is wholly inconsistent with market fundamentals for the main capacity market, RPM, to falsely signal excess supply on the heels of a supplemental procurement due to a serious resource adequacy shortfall. As Dr. Shanker explains, PJM’s proposed treatment of that capacity undermines the same resource-adequacy objective PJM aims to solve with the RBP.18
B. PJM Has Not Shown That Mandatory Zero Offers Are Just and Reasonable
PJM has shown why RBP resources should be retained for resource adequacy and why selected sellers should receive their accepted RBP compensation. PJM has not shown why a zero price is the appropriate representation of those resources in the supply stack when RPM is intended to establish the marginal value of capacity.
Whether an RBP resource should count toward reliability, whether it should receive its promised compensation, and whether its mandatory offer should affect the market price paid to non-RBP resources are distinct questions. PJM’s filing conflates them in the name of guarding load against facing risk of double payment for capacity. A mandatory $0/MW-day offer is not the
16 PJM Proposal at 2 (citing National Energy Dominance Council, Statement of Principles Regarding PJM (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm) (“NEDC/PJM Governors’ Principles”).17 NEDC/PJM Governors’ Principles at 1.18 See Shanker Aff. ¶¶ 14–15.
PDF page 6
6
reasonable or just way to address that risk because such mandate does more harm than good by signaling excess supply if anticipated load is delayed or does not show up, thereby encouraging departure of existing generation—recreating the very reliability problems that spurred the RBP in the first place. This problem can be eliminated, and load still protected from double payment, if instead PJM removes RBP supply while also removing the actual new load that the RBP resources were procured to supply. That way, if anticipated load is delayed, the market will not signal excess supply and encourage retirement of the existing fleet.
As Dr. Shanker explains, RPM price signals guide both new-entry and resource-retention decisions.19 When a large block of capacity procured under long-term, out-of-market commitments is required to offer at zero, prospective entrants may defer merchant investment in anticipation of lower-risk contractual opportunities, while existing resources may accelerate exit or decline to commit additional capital.
Those responses can occur substantially faster than replacement generation can be developed. An inappropriate signal today can therefore leave the competitive fleet smaller when forecast load ultimately arrives. 20 Indeed, Constellation suspects this phenomenon (lack of new entry and instead waiting for out-of-market compensation) was reflected in the last RPM auction, as the instant filing providing for an out-of-market auction opportunity was widely-discussed and expected.
PJM’s own contemporaneous analysis corroborates Dr. Shanker. PJM describes a
“credibility trap” in which scarcity triggers price caps, emergency backstop procurements, or other
19 Id. 20 Id.
PDF page 7
7
administrative interventions. Investors then discount the durability of the revenue signal, capital remains on the sidelines, and the shortage persists.21
PJM states that the RBP should not subsume the broader review of market fundamentals and that the RBP should permit PJM to return to competitive resource-adequacy markets as soon as possible.22 Yet, the mandatory zero-offer requirement moves in the opposite direction by allowing the financial terms of a separate backstop procurement to determine the price signal received for the next 15 years by the residual competitive market, which could undermine the resource adequacy objective of that market.
The challenged proposal is not transitory merely because PJM calls the RBP a “one-time” procurement. The Initial RBP Target is 6,831.3 MW UCAP before accepted offsets and opt-outs. As selected resources become operational and accredited, PJM will require their committed, available RBP UCAP to offer at $0/MW-day in each applicable RPM Auction through the end of the applicable commitment (i.e., up to 15 years). The procurement can create a potentially multi- gigawatt block of mandatory zero-priced capacity in repeated RPM Auctions over many years. PJM supplies no sensitivity analysis evaluating whether its mandatory zero-offer rule will preserve appropriate entry and retention signals under plausible variations in timely load realization, resource commercial-operation dates, annual accreditation, resource exit or retirement, or updated Incremental Auction parameters. Nor does PJM analyze the later resource-adequacy effect if delayed load arrives after the auction signal has induced exit or deferred entry. PJM’s
21 PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability 5–6, 26, 29–30 (May 6, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability- through-market-design.pdf.22 PJM Interconnection, L.L.C., Critical Issue Fast Path–Reliability Backstop Procurement PJM Proposal 1(June 30, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a--- pjm-reliability-backstop-procurement-proposal---paper.pdf (“PJM Paper”).
PDF page 8
8
section 205 showing therefore does not address the central price-formation and resource-adequacy consequences of the rule it proposes.
C. The Risk Is Most Acute When Available RBP UCAP Precedes or Exceeds
Timely RBP-Related Load
The price-formation and reliability risks are most acute when Available RBP UCAP exceeds the RBP-Related Load included in the Planning Parameters for the applicable RPM Auction. That mismatch does not require long-term load growth to disappear—a delay alone is sufficient. Even if all forecast load ultimately connects, a multi-year delay can cause RPM to signal reduced need for resource retention and new entry before the load arrives. Dr. Shanker uses a simplified example in which the full Initial RBP Target is available in the relevant auction but load is delayed.23 This delayed-load example shows the resulting problem.24 Assume, for illustration, that approximately 6.8 GW of RBP capacity becomes available and must enter RPM at a zero price, but only 3 GW of RBP-Related Load is reflected in the applicable auction parameters due to large load delays. RPM would then reflect 3.8 GW of unmatched zero-offer RBP supply without the corresponding RBP-Related Load. That clearing outcome can signal reduced need for retention or entry in the RPM market. If the remaining load arrives several years later, some existing capacity may already have retired (or otherwise exited PJM), and prospective new entry may have stayed on the sidelines. Because retirement/exit can occur faster than replacement capacity can be developed, PJM may again face a shortfall and pressure for another out-of-market procurement.2523 In operation, the quantity of Available RBP UCAP subject to the isolation mechanism would vary by Delivery Year based on commercial-operation timing, accreditation, and availability, as described above.24 Shanker Aff. ¶¶ 13–14.25 Id. ¶¶ 14–16.
PDF page 9
9
PJM’s implementation design confirms that the relevant supply and demand quantities will vary across auctions. Available RBP UCAP may ramp across several Delivery Years, while PJM will continue to update its load forecasts through later RPM Auctions. PJM’s August 10 example, for instance, shows an illustrative 6,800 MW portfolio providing 3,900 MW in 2028/2029, 6,750 MW in 2029/2030, 6,800 MW in 2030/2031, and 6,850 MW in 2031/2032. PJM’s example is illustrative rather than predictive, but it confirms that the filed selection architecture permits RBP quantities to vary materially across Delivery Years and that RBP supply may exceed the target in a particular year.26
Incremental Auctions do not cure this problem. They update the competitive market around the RBP commitments; they do not true up or unwind the underlying backstop procurement. If PJM lowers the load reflected in the planning parameters (even temporarily) while Available RBP UCAP remains subject to the zero-offer requirement, the forecast correction is borne by the existing resources participating in the RPM market rather than by the out-of-market procurement based on the earlier forecast.27
The supply-load timing risk is not merely conceptual. ERCOT has reported approximately 8,900 MW of large load approved for energization, of which more than 5,000 MW had not yet energized, while significant new generation and storage capacity was being added.28 While ERCOT’s market design differs materially from PJM’s, this example illustrates an underlying factual risk: large-load projects and new supply do not necessarily become operational on the
26 See PJM Interconnection, L.L.C and Charles River Associates, Reliability Backstop Procurement Execution Presentation, 44–45 (Aug. 10, 2026). Slides 44-45 show 3,900 MW in 2028/2029, 6,750 MW in 2029/2030, 6,800 MW in 2030/2031, and 6,850 MW in 2031/2032, and explain that full, indivisible offers may exceed the remaining target).27 Shanker Aff. ¶ 17.28 Electric Reliability Council of Texas, Large Load Interconnection Status Update, Large Load Integration Team 8– 9 (June 19, 2026), https://www.ercot.com/files/docs/2026/06/18/June-19-LLWG-Report.pptx.
PDF page 10
10
same schedule. Based on the ERCOT example, it is not a hypothetical that new supply may enter service prior to when the corresponding large load enters service. PJM’s RBP design should not assume otherwise.
PJM’s own recent downward revisions to its near-term load growth forecasts confirms that large-load forecasts are not static and that the amount reflected in successive RPM Auctions can change materially. The downward revision for peak annual load in 2027 was trimmed by 3,735 MW.29 The point is not that PJM’s long-term load growth will necessarily fail to appear. The point is that the timing of supply and load can diverge long enough for a temporary RBP supply surplus to produce durable entry, exit, and retirement consequences in RPM.30
When timely RBP-Related Load is below Available RBP UCAP, mandatory zero-offer
RBP supply can cause RPM to signal excess supply to the RPM market before the forecast load has arrived, even as PJM expects delayed load to require additional capacity. That signal bears directly on entry, retention, and capital-investment decisions and can leave PJM short precisely when PJM continues to forecast substantial future demand.
D. Annual RBP Isolation and a Matched Demand Adjustment Will Preserve the
Competitive Integrity of RPM While Avoiding Duplicate Procurement
To prevent the adverse impacts described above, while still protecting customers from
double payment for capacity, Dr. Shanker recommends isolation through an annual, auction- specific mechanism. Dr. Shanker recommends removing the separately procured RBP supply and
29 PJM Interconnection, L.L.C., PJM’s Updated 20-Year Forecast Continues to See Significant Long-Term Load Growth (Jan. 14, 2026), https://insidelines.pjm.com/pjms-updated-20-year-forecast-continues-to-see-significant- long-term-load-growth/.30 Goldman Sachs reports that historically approximately 72% of data centers scheduled for activation within the following four quarters came online on time and forecasts on-time realization of approximately 60% over the next year and approximately 50% over the next two years. See Goldman Sachs, US Data Center Power Demand Projected to Double by 2027 (May 20, 2026), https://www.goldmansachs.com/insights/articles/us-data-center-power-demand- projected-to-double-by-2027.
PDF page 11
11
the corresponding RBP-related demand from RPM price formation.31 This isolation mechanism eliminates the threat of any double payment and removes the deleterious impact on RPM. The Tariff language in Appendix B implements Dr. Shanker’s core isolation recommendation through an annual, auction-specific mechanism.
The revisions in Appendix B translate that economic recommendation into the filed RBP design by accounting for annual accreditation, availability, commercial-operation timing, and the conduct of both Base Residual Auctions and Incremental Auctions. For each Delivery Year and each applicable RPM Auction, PJM should: (1) exclude Available RBP UCAP from the RPM price-forming supply stack; and (2) reduce the applicable RPM reliability requirement by the lesser of Available RBP UCAP and RBP-Related Load included in the Planning Parameters for that auction, with both quantities expressed in UCAP terms.32
The adjustment concerns price formation only. The revisions in Appendix B preserve the RBP resources’ physical and performance obligations and the two-sided economics of the RBP settlement.
PJM argues that zero-price participation is necessary because responsible LSEs already are paying for RBP capacity and another resource might otherwise be procured via RPM if the RBP resources are not entered as price-takers, resulting in a double payment for capacity by load.33 That concern assumes RBP supply is removed while the entire associated demand requirement remains in RPM. Constellation’s proposal does not do that. For the matched quantity—the lesser of Available RBP UCAP and RBP-Related Load—the mechanism adjusts both supply and
31 Shanker Aff. ¶¶ 25–30.32 Id. ¶ 25.33 PJM Proposal at 57.
PDF page 12
12
demand. RPM therefore does not procure replacement capacity for load already covered through the RBP.34
Dr. Shanker also explains why all RBP resources must be excluded, as price-taker offers cannot readily be prorated among individual large-load projects. RBP resources are not physically matched to particular loads, and individual generating units cannot be divided among varying levels of realized load without creating another administrative allocation mechanism.35 The more workable design is to isolate all the RBP supply while adjusting demand by the amount of timely RBP-Related Load.
Where Available RBP UCAP exceeds timely RBP-Related Load, Constellation recognizes that isolation may temporarily preserve more total physical capacity than the updated RPM requirement alone would procure. Constellation proposes that result as a safeguard against allowing a potentially temporary, forecast-created mismatch to trigger exit and deferred investment before the load arrives. The relevant comparison is intertemporal: temporary additional capacity versus premature exit, later replacement, another capacity shortfall, and another backstop procurement.
PJM itself evaluated carving RBP supply and demand out of RPM.36 It anticipated that the capacity-cost outcomes of the zero-offer and carve-out approaches would be largely the same and that neither would materially change costs to the remaining RPM load. PJM rejected isolation
34 Even excluding the RBP supply and associated load as proposed here does not completely neutralize the out-of- market effects on RPM, as RPM is deprived of the RBP resources that would sit at the top of the supply stack, providing upward pressure on RPM price signals. See ISO New England Inc., 138 FERC ¶ 61,027 at PP 72–75 (2012); see also ISO New England Inc., 135 FERC ¶ 61,029 at PP 230, 232 (2011). By this measure, the isolation methodology is a conservative solution, yet is significantly more effective at reducing any out-of-market pricing impact as compared to the mandatory zero offer proposal, and without creating any risk of double payment.35 Shanker Aff. ¶ 29.36 PJM Paper at 11.
PDF page 13
13
principally because it believed the approach would differentiate large load from other load and require additional changes to RPM.37
That concession substantially narrows the dispute. The RBP already creates a separately compensated supply cohort associated with a separately identified increment of forecast load for terms lasting as long as fifteen years. Isolating that cohort from RPM price formation better preserves the competitive integrity of the residual market than requiring it to participate at zero in every applicable RPM Auction.
RBP isolation and the matched demand adjustment therefore preserve the RBP
procurement and the physical availability of RBP resources without representing separately compensated capacity as though its competitive RPM offer were zero.
II. THE PHRASE “MAXIMUM FACILITY OUTPUT” IN TARIFF SECTION
18.5(b)(i) SHOULD BE DELETED, AND ENERGY RESOURCES SHOULD BE
INCLUDED IN SECTION 18.5(b)(iii).
The Commission should condition acceptance of PJM’s Proposal on (A) revising proposed Tariff section 18.5(b)(i) from “new Installed Capacity and new Maximum Facility Output” to “new Installed Capacity” and (B) revising proposed Tariff section 18.5(b)(iii)(2) to include an Energy Resource seeking new Capacity Interconnection Rights. As drafted, section 18.5(b) excludes an existing Energy Resource that has Maximum Facility Output but no Capacity Interconnection Rights and is seeking new Capacity Interconnection Rights through an Interconnection Request, even if the resource otherwise satisfies the RBP eligibility criteria.
To qualify as an RBP Resource, a generation resource must meet the requirements of sections 18.5(a) and 18.5(b) of the proposed Tariff. Such generation resources must have a
37 Id.
PDF page 14
14
commercial operation date prior to June 1, 2032, not otherwise have an RPM commitment for a future delivery year, and be:
(i) Composed of new Installed Capacity and new Maximum Facility Output;
(ii) Supported by new Capacity Interconnection Rights (if located in the
PJM Region) or Capacity Interconnection Rights transferred from a
deactivated resource or a resource that announced deactivation as of April 10, 2026; and
(iii) Consist of (1) new build; (2) incremental capacity created by an uprate of an existing Generation Capacity Resource’s or Energy Storage
Resource’s installed capacity and associated level of Capacity
Interconnection Rights; or (3) repowering of a generation resource that had deactivated, or announced deactivation, on or before April 10, 2026.38
An existing Energy Resource necessarily has Maximum Facility Output; obtaining new Capacity Interconnection Rights does not create a new Maximum Facility Output. The relevant attribute from a resource adequacy perspective is the new Capacity Interconnection Rights. Excluding an otherwise eligible resource solely because its Maximum Facility Output is not “new” and because it is currently not a capacity resource but is seeking to obtain new Capacity Interconnection Rights is unjust and unreasonable where the resource will provide new capacity, satisfy the applicable commercial-operation requirements, and bear its share of any required Network Upgrade costs associated with securing its new Capacity Interconnection Rights. Accordingly, the Commission should exercise its authority to modify the proposed Tariff language to delete the phrase “and new Maximum Facility Output” in proposed Tariff section 18.5(b)(i) and add Energy Resources seeking new Capacity Interconnection Rights as a category of resource eligible under section 18.5(b)(iii)(2).
38 See PJM Proposal, attach. A § 18.5(b).
PDF page 15
15
III. QUALIFYING RBP OFFSET UCAP MW SUBMISSIONS SHOULD RECEIVE A
MEANINGFUL CURE PERIOD
Constellation requests clarification that PJM will provide a submitting entity five calendar days from notice to cure a deficiency in a Qualifying RBP Offset UCAP MW submission, provided that the cure is completed before the close of the bid submission window of the Reliability Backstop Procurement. If PJM does not confirm that interpretation, the Commission should condition acceptance on Tariff revisions expressly providing that cure opportunity. New Section 18.2(c) requires entities to report the Qualifying RBP Offset UCAP MW during the RBP bid submission window with accompanying listed evidence, but does not explicitly provide for a cure period upon a finding of deficiency by PJM.39 PJM has indicated in stakeholder workshops that it would initiate discussions with any parties where there are questions regarding the submission of evidence of Qualifying RBP Offset UCAP MW. Further, PJM’s recently- proposed draft Manual 18 Attachment F confirms that PJM contemplates that there will be some level of communication with participants regarding clarification of evidence submitted by participants seeking to establish Qualifying RBP Offset UCAP MW.40 However, given the impact of Qualifying RBP Offset UCAP MW on the RBP’s total procurement target and the procurement assignment and allocation of charges to specific EDC zones/areas, a more formal and explicit cure process is warranted.
RBP Sell Offers receive a five-calendar-day cure opportunity after notice of a deficiency.41 Qualifying RBP Offset UCAP MW submissions should receive the same substantive protection. The Commission should therefore exercise its authority to modify the proposed Tariff language to
39 See id.40 PJM Interconnection, L.L.C., Draft Manual Language for Reliability Backstop Procurement (Aug. 10, 2026), 20260810-draft-manual-language-for-reliability-backstop-procurement.pdf.41 See PJM Proposal, attach. A § 18.5(f)(i).
PDF page 16
16
provide for five calendar days from notice to cure a curable deficiency, subject to completion before the close of the bid submission window of the Reliability Backstop Procurement. This treatment will prevent minor, curable errors from unnecessarily increasing the procurement target or shifting cost responsibility.
IV. LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS
The Commission should exercise its authority to modify the proposed Tariff language to clarify two aspects of the credit and collateral provisions in the proposed Tariff. First, the Commission should clarify that, for purposes of proposed Tariff section 18.8, reference to “the first Delivery Year” means the 2028/2029 Delivery Year. As written, the phrase is ambiguous and does not provide affected Load Serving Entities sufficient certainty regarding the date on which the initial collateral obligation attaches.
Second, in section 18.3(b)(iii) of the proposed Tariff, the Commission should replace the phrase “no later than sixty (60) days prior to the 2028/2029 Delivery Year” with “no later than three-hundred sixty-five (365) days prior to the 2028/2029 Delivery Year.” This would allow market participants to have a clear understanding of how the initial allocation determination under section 18.3 will be effectuated, and perhaps equally important, how any default amounts that result from the failure of expected large loads to materialize will also be allocated. This timeline would give the states over a year to conduct proceedings to finalize these determinations and the entire market will benefit from increased certainty. PJM’s proposed schedule gives the State Commissions over two years to determine their proposed cost allocation and only fifteen days between the allocation determination and the collateral deadline. That period is not reasonably practicable and creates an unnecessary risk of credit default and resulting cost reallocation. The revisions to the Tariff proposed here provide those with collateral obligations a reasonable
PDF page 17
17
opportunity to quantify their final exposure, obtain necessary internal approvals, arrange potentially substantial collateral, and make the required posting.
Accordingly, the Commission should therefore condition acceptance of PJM’s Proposal on replacing the phrase “no later than sixty (60) days prior to the 2028/2029 Delivery Year” with “no later than three-hundred sixty-five (365) days prior to the 2028/2029 Delivery Year” in revised Tariff section 18.3(b)(iii).
V. THE MODIFICATIONS PROPOSED HEREIN COMPLY WITH NRG POWER
MARKETING
Under NRG Power Marketing, the Commission may condition acceptance of a section 205 filing where the filing utility has consented to the modification and the condition does not transform the proposal into an entirely different rate design.
The modifications of the Tariff and RAA provisions proposed herein are consistent with NRG Power Marketing. PJM expressly consents to Commission modification or severance of individual Tariff and RAA provisions where the modification is consistent with the filing’s overarching objectives.42 PJM also asks the Commission to prescribe any replacement rule with sufficient specificity for immediate implementation, states that a compliance filing implementing prescribed changes would constitute further consent, and distinguishes this proposal from the stakeholder compromise at issue in NRG Power Marketing.43 PJM’s consent therefore satisfies the threshold requirement for conditional acceptance.
42 See PJM Proposal at 3 (“PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing”).43 See PJM Proposal at 3–4, 131–33; NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017).
PDF page 18
18
The requested modifications to the Tariff here do not create an “entirely different rate design.”44 The isolation condition preserves the RBP solicitation, target determination, offsets and opt-outs, seller eligibility, selection process, resource-specific compensation, commitment terms, cost allocation, credit requirements, and physical performance obligations. It modifies the representation and settlement of RBP capacity in subsequent RPM Auctions to preserve competitive price formation and RPM’s resource-adequacy function.
As explained in Section I.D, PJM itself evaluated the same basic supply-and-demand carve-out, confirming that the requested condition falls within the range of design alternatives considered during development of the RBP.45 The proposed modification therefore is neither foreign to the filed design nor beyond the range of alternatives of which stakeholders had notice. Appendix B provides the framework for the Commission to use in the exercise of its authority to modify the proposed Tariff to implement the annual formula, continuing resource obligations, settlement treatment, and locational requirements.
The remaining requested revisions are narrower still and do not alter the RBP’s core procurement, compensation, allocation, or performance design. The Commission may therefore condition acceptance without leaving PJM discretion to devise a materially different replacement rate.
VI. CONCLUSION
For the foregoing reasons, the Commission should accept the RBP subject to the Commission exercising its authority to modify the proposed Tariff to effectuate the revisions described herein and in Appendix B. The annual RBP isolation mechanism and matched demand
44 NRG Power Mktg., 862 F.3d at 115.45 PJM Paper at 11.
PDF page 19
19
adjustment preserve the competitive integrity and resource-adequacy function of RPM, address PJM’s asserted duplicate-procurement concern, and preserve the RBP resources’ promised compensation and physical obligations.
The Commission should also exercise of its authority to modify the proposed Tariff language to: (1) delete the phrase “new Maximum Facility Output” in Tariff section 18.5(b)(i) and include qualifying Energy Resources in section 18.5(b)(iii); (2) provide a five-calendar-day cure opportunity for curable deficiencies in Qualifying RBP Offset UCAP MW submissions; and (3) clarify and revise the credit and collateral provisions in proposed Tariff sections 18.3 and 18.8.
Respectfully submitted,
Dated: August 21, 2026
/s/
Carrie Hill Allen
Sr. Vice President & Deputy General
Counsel
John M. White
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
john.white@constellation.com
Christopher A. Wilson
Vice President, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Kenneth W. Irvin
Alexandra K. Calabro
Sidley Austin LLP
1501 K Street, N.W.
Washington, DC 20005
Phone: (202) 736-8256
kirvin@sidley.com
alexandra.calabro@sidley.com
Terence T. Healey
Sidley Austin LLP
60 State Street, 37th Floor
Boston, MA 02109
Phone: (617) 223-0306
thealey@sidley.com
Counsel for Constellation Energy Generation,
LLC
PDF page 20
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C. this 21 day of August 2026.
/s/
Alexandra K. Calabro
Sidley Austin LLP
1501 K Street, N.W.
Washington, DC 20005
PDF page 21
Appendix A
PDF page 22
UNITED STATES OF AMERICA
BEFORE
THE FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3380-000
AFFIDAVIT OF ROY J. SHANKER, PH.D., IN SUPPORT OF
CONSTELLATION ENERGY GENERATION, LLC’S
LIMITED PROTEST
I. Qualifications and Purpose of Affidavit
1. My name is Roy J. Shanker. My address is P.O. Box 1480, Pebble Beach,
California, 93953. I have a bachelor’s degree from Swarthmore College and both a master’s degree and a doctorate degree from Carnegie Mellon University.
2. My resume, Attachment A hereto, summarizes my experience in numerous
regulatory proceedings before state commissions and the Federal Energy Regulatory Commission (“FERC” or “Commission”). As detailed therein, I have over 50 years of experience covering a broad range of issues in the electric utility/power generation/energy sectors for a broad range of clients. I have been involved in competitive market design for approximately 30 years, and specifically for PJM from the inception of the market. I contributed to some of the fundamental design elements for the capacity market and its evolution over the years.
3. The purpose of my affidavit is to assist the Commission with its decision-making process as it evaluates PJM’s proposal in this docket as filed on July 31, 2026.1 I specifically address the interaction of the Reliability Backstop Procurement (“RBP”) and the subsequent offer requirements proposed for such capacity in future Reliability Planning Model (“RPM”) auctions.
1 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (the “PJM Proposal”).
PDF page 23
2
I was retained by Constellation Energy Generation, LLC to offer an independent opinion regarding these issues.
II. Background
4. In May of this year PJM released a white paper entitled Powering Reliability Through Market Design.2 In this paper PJM candidly discussed what it calls the “credibility trap”
– the idea that properly functioning markets need to be able to signal scarcity, but investors have little confidence that the market will actually produce the appropriate price signal due to political interference. As PJM noted:
The result is what might be called a credibility trap: high scarcity prices that are economically necessary to signal the need for investment become, in this
environment, the trigger for governmental intervention that undermines the
credibility of those same prices. When prices spike and unhedged load is
immediately exposed, policymakers face intense pressure to intervene through
price caps, emergency backstop procurements, or other administrative actions that signal to investors that the revenue they are counting on to recover their costs may not materialize. Investors, anticipating further intervention, discount the durability of the price signal. Capital stays on the sidelines; the shortage persists.3
5. This concern is more relevant than ever. PJM’s recently concluded Base Residual Auction (“BRA”) for the 2028/29 Delivery Year cleared over approximately 6.8 GW (6,831.3 MW)4 short of the reliability requirement. The BRA for the 2027/28 Delivery Year, conducted last year, cleared similarly short. These unprecedented shortfalls are a clear signal of scarcity, though market clearing prices have been administratively capped at well below the price needed
2 PJM Interconnection, L.L.C., Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability (May 6, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability- through-market-design.pdf (“PJM White Paper”).3 Id. at 5–6.4 PJM Proposal at 7.
PDF page 24
3
to attract new supply. PJM itself recognizes the conflict between capped prices and encouraging new market entry for capacity.5 Meanwhile, the problem only appears to be getting worse. PJM estimates 32 GW (virtually all attributable to large loads) of growth in peak load from 2024 to 2030, and supply, at least to date, has failed to keep up.6
6. Against this backdrop, in this proceeding PJM has proposed a one-time,7 out-of- market intervention, the RBP, which aims to procure new capacity to fill the gap as established by the 2028/29 BRA. Capacity procured through the RBP auction would assume a long-term capacity obligation for a term of up to 15 years at a “pay-as-bid” price.8
7. While the RBP proposal is complex and has many different features worth
discussing, I focus my affidavit chiefly on one element of the proposal: the requirement that all capacity resources committed through the RBP central procurement must offer that capacity into future RPM Auctions at a $0/MW-day price for the entire term of the RBP commitment (i.e., up to 15 years).9 Getting this aspect of the proposal right is critical to address the “credibility trap” problem PJM has correctly identified and to promote resource adequacy both near- and long-term. It is a vital element to PJM’s self-proclaimed intent of returning to a market-based paradigm.10
III. PJM Must Isolate the Impact of the RBP Central Procurement
8. For all its faults and imperfections, RPM has delivered on its central mission— resource adequacy. But now, facing some of the most difficult challenges in its history, the future
5 PJM White Paper at 5–6, 26.6 PJM Proposal at 6.7 Id. at 6–7.8 Id. at 7–8, 42.9 Id. at attach. A § 6.6(j) (“An RBP Resource committed through the Reliability Backstop Procurement must offer all available committed RBP UCAP MW as a price-taker (i.e., $0/MW-day) into the applicable RPM Auctions pursuant to the capacity must offer requirements and exceptions set forth in Tariff, Attachment DD, sections 6.6 and 6.6A.”).10 PJM Proposal at 6.
PDF page 25
4
of RPM is at stake. The RBP represents a point of inflection that may determine the success or failure of PJM’s resource adequacy construct going forward.
9. While PJM has correctly identified the “credibility trap” issue, the RBP proposal does not inspire confidence that PJM is ready and able to tackle the problem and escape the trap. Indeed, the representation of new supply from the RBP as “price takers” in RPM is one of the most significant and farthest-reaching of any market intervention by PJM to date. As proposed, this price-taking offer requirement will have a material, one-sided bias to reduce future capacity prices below the necessary levels required to attract new entry and retain needed existing supply. This type of market intervention will further damage confidence in the robustness of RPM going forward, limiting its ability to attract and retain the supply needed to reliably serve PJM’s rapidly expanding load. It would be the antithesis of “returning PJM to market fundamentals.”
10. The current challenge facing PJM and its stakeholders is twofold: First, how do we maintain reliability when facing a perceived supply shortage? And second, how do we preserve a viable competitive market for Capacity Resources?
11. As I note above PJM’s proposed RBP will fail to achieve these objectives. PJM’s proposal, if left unchanged, (a) will drive near-term exit of resources that will be needed if load growth materializes and (b) would be a one-sided intervention that depresses the market below where it would otherwise clear under a competitive outcome, further entrenching the “credibility trap” problem and leading to stagnation, shortfall, and ultimately market failure.
12. I propose, below, a change to the RBP design to reduce its impact on the broader competitive capacity market structure, thereby preserving proper investment signals and ultimately resource adequacy.
PDF page 26
5
13. The key problem with PJM’s proposal is best illustrated with an example. Assume the RBP procures approximately 6,800 MW of new capacity. Under PJM’s proposal this capacity would then be required to offer into RPM Auctions for the entire RBP commitment period at a price of $0/MW-day. But now assume that only 3,000 MW of RBP-related load materializes on schedule as forecasted.
Figure 1.
14. As shown in Figure 1, the addition of the full 6.8 GW of supply at $0, combined with a demand curve only reflecting a portion (3 GW) of the previously expected load, results in a material surplus of supply. The resulting price signal will indicate to investors that there is no need for new entry, and, in fact, that many existing resources should retire or seek other markets. Further investment in new resources will be chilled, and many aging thermal capacity resources are likely to exit the market.
15. Clearly that is not the right price signal. If the rest of that originally-expected load later materializes, the market will be even worse off than it is today. The market will be short because the low prices encouraged additional existing resources to exit while also not supporting new entry. This scenario is represented below in Figure 2, where the expected load eventually arrives, but supply is deficient due to the increase in exits and inadequate new entry. The result,
PDF page 27
6
based on recent behavior, is that PJM is likely to once again face political pressure to intervene administratively to maintain reliability. And developers of new capacity will build the expectation of future interventions into their decision-making framework. Investment will be further chilled by repeated market intervention, and the “credibility trap” cycle will continue. Figure 2.
16. This risk of load delay is not merely hypothetical. We have already seen real-life examples of forecasted data center load failing to materialize as scheduled.11 Goldman Sachs Research reports that despite surging AI-driven demand, grid constraints and project attrition mean that only 50% to 72% of planned U.S. data center capacity will likely materialize on time.12 There is no reason to assume that such delays will not persist over the next few years at least.
17. This reality underscores the need to consider the impact of the RBP on the
competitive capacity market’s clearing mechanism going forward. The basic link between the RBP capacity and the competitive market is that (i) the targeted out-of-market RBP procurement
11 ERCOT has reported approximately 8,900 MW of large load approved for energization, of which more than 5,000 MW had not yet energized. Electric Reliability Council of Texas, Large Load Interconnection Status Update, Large Load Integration Team 8–9 (June 19, 2026), https://www.ercot.com/files/docs/2026/06/18/June-19-LLWG- Report.pptx.12 See US Data Center Power Demand Projected to Double by 2027, Goldman Sachs (May 20, 2026), https://www.goldmansachs.com/insights/articles/us-data-center-power-demand-projected-to-double-by-2027.
PDF page 28
7
quantity is fixed, (ii) this quantity remains fixed regardless of whether or not and when the forecast demand is realized, and (iii) as proposed, subsequently, that RBP capacity quantity will be entered into the competitive RPM process as price takers regardless of the level of load.
18. Notably, PJM has indicated via its August 13, 2026 IRAS Filing that it will exclude the representation of new large loads in the RPM demand curve in the future unless and until such loads bring their own new capacity supply or an allocated portion of the RBP supply.13
19. While the purpose of this Affidavit is not to address the IRAS Filing, and I take no position here on the IRAS Filing generally, this aspect of PJM’s IRAS proposal is worth highlighting given how it informs elements within the RBP proposal.
20. In the RBP filing PJM proposes that all RBP supply be represented as price takers in RPM Auctions. It ignores whether the underlying load is realized or not or when it is realized. Thus, RBP supply can exceed the linked demand and lower market prices for other existing supply via the out-of-market actions.
21. While PJM includes RBP generation regardless of whether the associated load is realized in the capacity auction, it takes the opposite approach with respect to when it includes new large load in the capacity auction in the IRAS proposal. Specifically, in the IRAS proposal, PJM only includes new large load in the capacity auction when it can be offset by either new generation (BYONC) or an allocation of RBP capacity. In other words, PJM only includes this balanced amount of New Large Load and generation (which may be partially made up of RBP generation) in the RPM auctions. Any additional load is not represented in these auctions. This is
13 See PJM Proposal at n.9; see also PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No. ER26-3515-000 (filed Aug. 13, 2026) (“IRAS Filing”).
PDF page 29
8
done, as PJM states to “prevent[s] artificial price shifts, [thus] resulting in an effectively price- neutral outcome for the rest of the market.”14
22. PJM ignores that its logic in the IRAS Filing must mean there can, at times, be unrealized (delayed or cancelled) load. This will result in “extra” RBP generation, which, in turn, will depress prices due to the “artificial shifts.” This outcome occurs whenever the RBP load has not yet arrived or is delayed. When this happens the excess RBP supply will depress RPM prices and will not be price neutral for the existing market supply. Out-of-market actions will distort prices and exacerbate the “credibility trap” in just the manner that PJM has so well described.
23. Despite this rationale in the IRAS filing, and without any explanation or mitigation, PJM is apparently satisfied in the instant filing to require all RBP capacity to offer into RPM as price takers, with no guarantee that the forecasted load forming the basis for the procurement will actually materialize as scheduled.
IV. Recommendation
24. The preferred approach for any market design would be to adopt a design that works without the need for ad-hoc interventions and stick with that design—both when prices rise and when they fall. The dislocation caused by the combination of large new loads, regulatory and political intervention, and the continued erosion of true market-based pricing makes that solution very unlikely. But if PJM must intervene now with an ad-hoc intervention such as the RBP out- of-market procurement, a top priority of the intervention should be to preserve resource adequacy by maintaining the competitive integrity of the overall market going forward to the greatest extent possible. Without that focus it is very likely that PJM will see increased exits of existing resources (which will only exacerbate resource adequacy issues in the region) and be right back at the
14 IRAS Filing at 58.
PDF page 30
9
drawing board in a few short years, and even sooner if the RBP does not clear the needed quantity of capacity.
25. To that end, my recommendation is to modify the RBP proposal to include a
mechanism that will appropriately isolate the effect of the RBP and maintain appropriate investment signals for the remainder of the capacity market. There is a very simple way to accomplish this objective. Rather than requiring all RBP supply to offer into RPM at $0/MW-day, PJM should remove all RBP supply and RBP-related demand from the RPM Auctions going forward. Specifically, PJM should exclude from RPM Auctions both (a) the cleared RBP capacity and (b) the lower of (i) the actual large load that is in the applicable auction Planning Parameters and (ii) an amount of load equal to the RBP generation.
26. This representation is as neutral as possible with respect to price formation for the “rest” of the market, and allows PJM to return to market fundamentals, market-based procurement, and rates and avoid unnecessary exits of existing resources. With this adjustment in place the rest of the market sees the “right” representation of supply and demand. And in this manner the market can adjust going forward independently of PJM’s “one-time” RBP purchases. In turn, regardless of the rate of arrival of the 6,800 MW of demand (the forecasted deficiency), there will be no price distortion for the rest of the market. The RBP capacity will operate as intended, as a separate out- of-market procurement to assure reliability.
27. When seen in light of PJM’s removal of future large loads, my recommendation to simply remove both the RBP supply and the lower of (i) the actual large load that is in the applicable auction Planning Parameters and (ii) an amount of load equal to the RBP generation becomes almost obvious in terms of logical consistency. Failing to make the adjustment discussed herein leaves the PJM proposal fundamentally discriminatory against existing suppliers who
PDF page 31
10
will face the distorted market signal when the RBP deficiency load either is delayed or fails to arrive completely.
28. In this context it is illogical to not remove all out-of-market RBP supply and the associated demand. Doing so removes the asymmetry and any associated price distortion. With this proposal the RBP procurement exists and continues to address reliability. But my recommended adjustment prevents delays in the arrival of the forecast demand or the failure of the forecast demand (the 6,800 MW) to enter at all from artificially shifting prices. The rest of the market therefore sees accurate price signals.
29. It is important to understand that this must be achieved by isolating this RBP load and generation. This is because the RBP generation is not readily divisible, e.g. it cannot be reasonably pro-rated for participation vis-a-vis any specific load. It must be either in or out. There is not a simple way to pro-rate a half of such a unit’s participation in the context of varying levels of realized load. Thus, the correct approach is to simply remove both the out-of-market supply and the realized portion of the load it was intended to serve. Modifying the demand curve by the same (reliability adjusted) amount in either direction does not distort prices. There is no reason to retain the one-way bias that PJM has built into the representation of the RBP supply when the bias and price distortion can be so easily fixed.
30. As a practical matter my recommendation is very simple to implement. PJM will have to clearly identify the supply identified in the RBP procurement in the very near future. PJM will also be tracking the actual realization of the 6,800 MW deficiency. This direct empirical information is easily represented in RPM Auction parameters and offering generation. The new large load registry PJM is instituting in the IRAS Filing has exactly the detailed information to accomplish this objective. Similarly, via the criteria for the submission of the RBP for sale, PJM’s
PDF page 32
11
proposal elicits all the necessary information to identify and remove the RBP supply from the RPM Auctions.
31. Similarly, my proposal stands independent of any other details of the operation of the RBP procurement process, either as proposed or as potentially modified. If there is to be such a procurement, this type of isolation is necessary to protect the markets and stands independently as a required feature.
32. This concludes my affidavit.
PDF page 33
[No extractable text on this page.]
PDF page 34
[No extractable text on this page.]
PDF page 35
Roy J. ShankerPage 1
Attachment A
QUALIFICATIONS
AND
EXPERIENCE OF
DR. ROY J. SHANKER
EDUCATION:
Swarthmore College, Swarthmore, PA
A.B., Physics, 1970
Carnegie-Mellon University, Pittsburgh, PA
Graduate School of Industrial Administration
MSIA Industrial Administration, 1972
Ph.D., Industrial Administration, 1975
Doctoral research in the development of new non-parametric multivariate techniques for data analysis, with applications in business, marketing and finance.
EXPERIENCE:
1981 -
Independent Consultant
Present
P.O. Box 1480
Pebble Beach, CA 93953
Providing management and economic consulting services in
natural resource-related industries, primarily electric
and natural gas utilities.
1979-81 Hagler, Bailly & Company
2301 M Street, N.W.
Washington, D.C.
Principal and a founding partner of the firm; director of electric utility practice area. The firm conducted economic, financial, and technical management consulting analyses in the natural resource area.
1976-79 Resource Planning Associates, Inc.
1901 L Street, N.W.
PDF page 36
Roy J. ShankerPage 2
Washington, D.C.
Principal of the firm; management consultant on resource problems, director of the Washington, D.C. utility practice. Direct supervisor of approximately 20 people.
1973-76 Institute for Defense Analysis
Professional Staff
400 Army-Navy Drive
Arlington, VA
Member of 25 person doctoral level research staff
conducting economic and operations research analyses of military and resource problems.
RELEVANT EXPERIENCE:
2025
271—On behalf of Vistra Corporation. Before the Federal Energy Regulatory Commission Docket EL25-49-000. Affidavit addressing properties of co-location of generation and new load and the proper comparison of the impacts of such arrangements versus behind the meter generation of in general, Network Load.
2024
270—On behalf of PJM Power Providers. EL24-148-000. Testimony regarding reliability must run designation and price formation for energy and capacity in the context of the development of the PJM Reliability Pricing Model.
269—On behalf of Constellation Energy Generation LLC, Before the Federal Energy Regulatory Commission Dockets No. ER24-2172-000 Affidavit addressing the proper comparison of impacts of co-located load behind a generator to Network Load or behind the meter generation in the PJM Interconnection markets. Conclusions addressing the specific business configuration of interest.
268—On behalf of Constellation Energy Generation LLC, Before the Federal Energy Regulatory Commission Dockets No. El24-2888 et al. Affidavit addressing the proper comparison of impacts of co-located load behind a generator to Network Load or behind the meter generation in the PJM Interconnection markets. Conclusions addressing the specific business configuration of interest.
267—On behalf of Kiewit Power Constructors. AAA CASE NO. 01-23- 0000-2706. Analyses of the proper comparison of alternatives to estimate
PDF page 37
Roy J. ShankerPage 3
damages related to the performance of an electric generator during Winter Storm Elliott.
2023
266—On behalf of the PJM Power Providers. Before the Federal Energy Regulatory Commission. Docket No. EL 23-19-000 and Docket ER23-729 Affidavit regarding the calculation of the Capacity Emergency Transfer Objective and model properties and how they interact with the Reliability Requirements for a Locational Deliverability Area. Explanation of the role of offer options in degrading information in the Capacity Auctions.
265—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket EL23-13. Answer ing statements to intervenors regarding Dr. Shanker’s complaint.
2022
264—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket EL23-13. An FPA Section 206 complaint for violating its Tariff via over accreditation of certain Variable Capacity Resoruces.
263—On Dr. Shanker’s own behalf. Before the Federal Energy Regulatory Commission, Docket RM22-14. Comments and reply comments regarding the Notice of Proposed Rulemaking Improvements to Generator Interconnection Procedures and Agreements.
262—On behalf of the Energy Trading Institute. Before the Federal Energy Regulatory Commission, Docket No. ER22-797. Affidavit in support of PJM LLC proposals for modifications to the Auction Revenue Rights/Financial Transmission Rights Market. Preparation of extensive general regulatory and PJM history regarding the formation of such rights over time.
2021
261—On behalf of the PJM Power Producers Group (P3) before the Federal Energy Regulatory Commission Docket No. ER21-2582-000. Affidavit addressing PJM’s proposed modification of the Minimum Offer Price Rule and problems related to the economic justification of the proposed narrowing of the applicability of the rule.
PDF page 38
Roy J. ShankerPage 4
260—On behalf of LS Power Associates L.P. before the Federal Energy Regulatory Commission Docket No. ER21-2043. Affidavit discussing PJM’s revised Effective Load Carrying Capability proposal, its limitations and associated PJM responses to previous comments regarding its initial proposal.
259—On behalf of Indicated Suppliers before the Federal Energy Regulatory Commission in Dockets No. EL19-47-000 and EL19-63-000 comments regarding the PJM proposed modification to its Market Seller Offer Cap in the Reliability Planning Model Base Residual Auction for Capacity Resources.
258—Written post conference comments in Federal Energy Commission Docket No. AD21-10. Discussion of the appropriate scope and range of actions for the Commission with respect to the PJM Minimun Offer Price Rate. Similar considerations of the legal scope of the Commission under the Federal Power Act.
257—Invited Speaker before the Federal Energy Energy Regulatory Commission Docket No. AD21-10. Comments before the Commissioners related to the role of subsidies and their impact in terms of the determination of satisfaction of just and reasonable rates under the Federal Power Act.
256—On behalf of LS Power Associates L.P. before the Federal Enegy Regulatory Commission Docket No. ER21-278-001. Affidavit discussing PJM’s Effective Load Carrying Capability proposal, its limitations and associated PJM responses to the Commission’s deficiency notice.
2020
256—On behalf of Cricket Valley Energy Center and Empire Generating Company before the Federal Energy Commission Docket EL21-7. Affidavit addressing the appropriate design of offer price floors in the NYISO Capacity market and associated mitigation and extension of the related rules to the entire state.
255—Invited speaker and written submission before the Federal Energy Regulatory Commission Docket AD20-14. Comments about the legal issues under the Federal Power Act relevant to the implementation of carbon pricing within the wholesale regional transmission organizations.
254—On behalf of Shell Energy North America before the Federal Energy Regulatory Commission, Docket EL20-49. Affidavit addressing bilateral trading of FTRs, associated agreements and the interaction with PJM’s FTR Center reporting and Tariff.
PDF page 39
Roy J. ShankerPage 52019
253—On behalf of White Oak Power Constructors before the United States District Court for the Eastern District of Virginia (Richmond Division). Expert report on proper calculation of damages and costs associated with the delay in commercial operations of a new electric power generation facility.
252—On behalf of the Public Service Companies before the Federal Energy Regulatory Commission, Docket ER19-1486. Affidavit regarding the PJM proposed operating reserve demand curve and other modifications to the reserve products market. Comments on missing elements within the proposal.
251—On behalf of Indicated Parties, (Calpine, Vestra, and Electric Power Supply Association) before the Federal Energy Regulatory Commission. Docket EL19-63. Affidavit regarding the complaint of the Joint Consumer Advocates regarding PJM’s market seller offer cap, the potential exercise of market power in the capacity market and appropriate market design adjustments under the Capacity Performance paradigm.
250—On behalf of Indicated Parties, (Calpine, Vestra, and Electric Power Supply Association) before the Federal Energy Regulatory Commission. Docket EL19-47. Affidavit regarding the appropriate adjustment of penalties and the Market Seller Offer Cap within the PJM Capacity Performance paradigm.
249—Supreme Court of the United States. Brief of Energy Economists as Amici Curiae in Support Of Petitioners, Nos. 18-868 & 18-879. Discussion of the impact of subsidies in electric energy market structures and the relationship of the instant cases where a Writ of Certiorari is being sought to previous Supreme Court precedent regarding state actions that effect Federal Energy Regulatory Commission jurisdictional rates.
2018
248—On behalf of PJM Power Providers (P3). Federal Energy Regulatory Commission. Docket EL18-178. Affidavit addressing the appropriate mechanisms to address state/public policy subsidies in the PJM Reliability Planning Model capacity construct. Related comments with respect to a “Clean” Minimum Price Offer Rule.
247—On behalf of Calpine Corporation, Eastern Generating and CPV Power Holdings. Federal Energy Regulatory Commission. Docket No.
PDF page 40
Roy J. ShankerPage 6
EL18-169. Affidavit addressing the the establishment of a “clean” Minimum Offer Price Rule for capacity offers in the PJM markets.
246—On behalf of DC Energy LLC and Vitol Inc. Federal Energy Regulatory Commission. Docket No. ER18-1334. Affidavit on the CAISO proposals to limit source and sink pairs in its annual and monthly CRR auctions, as well as comments addressing appropriate coordination of transmission outage and constraint information.
245—On behalf of the PJM Power Providers. Federal Energy Regulatory Commission Docket No. ER18-1314-000. Affidavit on the PJM proposed mitigation alternatives for addressing out of market subsidies either by Repricing or a modified Minimum Offer Price Rule.
244—On behalf of Joint Commentors. Federal Energy Regulatory Commission Docket EL18-34. Participation in the preparation of comments addressing PJM’s proposed fast start pricing modifications and related price formation issues.
243—On behalf of the PJM Power Providers Group. Federal Energy Regulatory Commission Dockets EL17-32 and EL17-36. Pre-Technical Conference Comments and participant technical conference regarding seasonal capacity products and specific related reliability and forecasting questions from Commission Staff.
(2018) Non-public reports regarding potential market manipulation within ISO NE markets.
2017
242—On behalf of the PSEG Companies. Federal Energy Regulatory Commission Docket No. ER13-535-000. Affidavit regarding
implementation of Court of Appeals remand to FERC of the PJM capacity market Minimum Offer Price Rule.
241-- In the United States Court of Appeals for the Second Circuit. Case No. 17-2654.Co-writer/sponsor of the Brief of Energy Economists as Amici Curiae in Support of Plaintiffs-Appealants-Reversal. Comments regarding the impacts of subsidies on the operation of organized electric markets.
240—In the United States Court of Appeals for the Seventh Circuit. No. 17-2433.Co-writer/sponsor of the Brief of Energy Economists as Amici Curiae in Support of Plaintiffs-Appealants. Comments regarding the impacts of subsidies on the operation of organized electric markets.
PDF page 41
Roy J. ShankerPage 7
239—Invited speaker Federal Energy Regulatory Commission technical session, Docket AD17-11. Comments on the appropriate incorporation of state policies in wholesale electric markets. Submission of post technical session comments.
238—On behalf of PJM Power Providers. Federal Energy Regulatory Commission Dockets EL17-36 and EL17-32 addressing the current Capacity Performance design and criticisms related to the exclusion of an inferior seasonal capacity product. Explanation of how PJM establishes its adequacy targets and whether or not the asserted criticisms were valid.
2016
237- On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. Federal Energy Regulatory Commission Dockets EL16-6, ER16-121. Submission of post technical session statement regarding PJM FTR market “netting” proposal.
236-On behalf of DC Energy, Vitol, Intertia Power, Saracen Energy East. Federal Energy Regulatory Commission Dockets EL16-6, ER16-121. Participant in two Technical Session Panels addressing PJM FTR market design and deficiency in the pending proposal to remove netting in the market settlement.
2015
235- On behalf of the Electric Power Supply Associaton. Federal Energy Regulatory Commission Dockets EL15-70, 71, 72, 82. Affidavit regarding MISO capacity market design and also addressing use of opportunity costs in offers.
234-On behalf of the Electric Power Supply Associaton. Federal Energy Regulatory Commission Dockets EL15-70, 71, 72, 82. Discussant in technical session addressing the establishment of opportunity costs as the basis for capacity reference pricing in the MISO Planning Resource Auctions.
233-On behalf of Dominion Virginia Power. Federal Energy Regulatory Commission Docket ER15-1966. Affidavit regarding changing economic incentives for suppliers associated with the modification of PJM’s calculation of Lost Opportunity Costs.
PDF page 42
Roy J. ShankerPage 8
232-On behalf of “Indicated Suppliers” Federal Energy Regulatory Commission Docket No. EL15-64-000. Testimony addressing the appropriateness of proposed changes to the NYISO buyer side mitigation exemptions.
231-On behalf of Hydro Quebec, Energy Services U.S. Federal Energy Regulatory Commission Docket No. ER15-623. Affidavit addressing the consistent treatment of energy imports under PJM’s Capacity Performance proposal.
230-Before the Supreme Court of the United States, No. 14-995, On Petition for a Writ of Certiorari to the United States Court of Appeals for the Third Circuit. Brief of electrical engineers, scientists and economists as amici curiae in support of petitioners. Metropolitan Edison et al. versus Pennsylvania Public Utility Commission et al., http://www.americanbar. org/content/dam/aba/publications/supreme_court_preview/briefs_2015_20 16/14-840_Borlick_et_al.pdf.
2014
229-On behalf of Benton County Wind Farm. United States District Court Southern District of Indiana, Indianapolis Division, Civil Action No. 1:13- cv-1984-SEB-TAB. Expert Reports addressing custom and practice in electric power purchase agreements.
228-On behalf of FirstEnergy Services. FERC Docket EL14-55. Affidavit related to the appropriate characterization of Demand Response in Capacity Markets reflecting performance as the reduction of retail energy consumption.
227-Federal Energy Regulatory Commission. Docket RM10-17. On my own behalf, a statement regarding the ability of the PJM capacity and energy markets to clear in the transition from any determination that demand response would be excluded jurisdictionally from wholesale markets. This could in turn result in a more appropriate representation of retail demand response.
226-Illinois Commerce Commission. Matter: No. 13-0657. On behalf of Commonwealth Edison Company. Testimony regarding the operation of the PJM regional transmission expansion planning process in general and particularly with regards to the preservation of long-term transmission rights (Stage 1A Auction Revenue Rights), and the consequences that occur when such mandated rights are infeasible.
225-Federal Energy Regulatory Commission. Docket ER14-1579. On behalf of H-P Energy. Affidavit explaining importance of property rights
PDF page 43
Roy J. ShankerPage 9
and associated contracts within the PJM transmission planning process, particularly as they pertain to Upgrade Construction Service Agreements.
2013
224-Federal Energy Regulatory Commission. Docket No. ER14-456. On behalf of NextEra Energy to analyze a proposed modification to the PJM Tariff allowing for “easily resolved constraints” to be address by transmission upgrades without any analyses of benefits.
223-Federal Energy Regulatory Commission. Docket No. ER14-504. Affidavit on behalf of PJM Power Producers addressing the interaction between the PJM adequacy planning processes and the formulation of saturation constraints on Limited and Extended Summer Demand Response products.
222-Federal Energy Regulatory Commission. Docket AD13-7. Invited speaker on the Commission’s technical session regarding capacity markets in RTO’s. Comments addressed basic principles of market design, market features, and consequences of market failures and deviations from design principles.
221-Federal Energy Regulatory Commission. Docket No. EL13-62 on behalf of TC Ravenswood LLC. Two affidavits addressing the treatment of reliability support services agreements and associated capacity in the NYISO capacity market design.
2012
220-Federal Energy Regulatory Commission. Docket No. ER12-715-003. On behalf of First Energy Services Company. An affidavit and testimony addressing the appropriateness of the application of a proposed new MISO tariff provision after the fact to a withdrawing MISO member.
219-Federal Energy Regulatory Commission. Docket ER13-335. On behalf of Hydro Quebec U.S. Affidavit addressing appropriate application of ISO-NE Market Rule 1/ Tariff with respect to the qualification of new external capacity to participate in the Forward Capacity Market.
218-Federal Energy Regulatory Commission. Docket IN12-4. On behalf of Deutsche Bank Energy Trading. Affidavit regarding a review of specific transactions, related congestion revenue rights, and deficiencies in CAISO tariff implementation during periods when market software produces multiple feasible pricing solutions.
PDF page 44
Roy J. ShankerPage 10
217-Federal Energy Regulatory Commission. Docket No. ER12-715-003. On behalf of FirstEnergy Services Company. Affidavit regarding implementation of the MISO Tariff with respect to the determination of appropriate exit fees and charges related to certain transmission facilities.
216-Federal Energy Regulatory Commission. Docket No. IN12-11. On behalf of Rumford Paper Company. Affidavit regarding free riding behavior in the design of demand response programs, and its relationship to accusations of market manipulation.
215-Federal Energy Regulatory Commission. Docket No. IN12-10. On behalf of Lincoln Paper and Tissue LLC. Affidavit regarding relationship of demand response behavior and value established in Order 745 to claimed market impacts associated with accusations of market manipulation.
214-Federal Energy Regulatory Commission. Docket No. AD12-16-000. On behalf of PJM Power Providers, testimony regarding deliverability of capacity between the MISO and PJM RTO’s and associated basic adequacy planning concepts.
213-United States Court Of Appeals, District of Columbia Circuit. Electric Power Supply Asociation, et al (Petitioners) v. Federal Energy Regulatory Commission et al (Respondents) Nos. 11-1486. Amici Curiae brief regarding the appropriate pricing of demand reduction services in wholesale markets vis a vis the FERC determinations in Order 745.
212-United States Supreme Court. Metropolitan Edison Company and Pennsyvalnia electric Company (Petitioners), Pennsylvania Public Utility Commission (Respondent) (No. 12-4) Amici Curiae brief regarding the nature of physical losses in electric transmission and relationship to proper marginal cost pricing of electric power and the marginal cost of transmission service.
2011
211-Federal Energy Regulatory Commission Docket No. ER12-513-000. On behalf of PJM Power Providers, testimony regarding the establishment of system wide values for the net cost of new entry related to modifications of the Reliability Planning Model.
210-Federal Energy Regulatory Commission Docket No. EL11-56-000, on behalf of First Energy Services. Affidavit regarding the appropriateness of proposed transmission cost allocation of Multi-Value Projects to an exiting member of the Midwest Independent System Operator.
PDF page 45
Roy J. ShankerPage 11
209-Federal Energy Regulatory Commission Docket No. ER11-4081-000, on behalf of “Capacity Suppliers”. Affidavit addressing correct market design elements for Midwest Independent System Operator proposed resource adequacy market.
208-Public Utility Commission of Ohio, Case Nos. 11-346-EL-SSO,11- 348-EL-SSO,Nos. 11-349-EL-AAM, 11-350-EL-AAM, on behalf of First Energy Services. Testimony regarding the interaction between the capacity default rates for retail access under the PJM Fixed Resource Requirement and the PJM Reliability Planning Model valuations.
207-Federal Energy Regulatory Commission Dockets No. ER11-2875, EL11-20, Staff Technical Conference on behalf of PJM Power Providers, addressing self supply and the Fixed Resource Requirement elements of PJM’s capacity market design.
206-New Jersey Board of Public Utilities, Docket Number EO11050309 on behalf of PSEG Companies. Affidavit addressing the implications of markets and market design elements, and regulatory actions on the relative risk and trade-offs between capital versus energy intensive generation investments.
205-Federal Energy Regulatory Commission Docket No. ER11-2875. Affidavit and supplemental statement on behalf of PJM Power Providers addressing flaws in the PJM tariff’s Minimum Offer Price Rule regarding new capacity entry and recommendations for tariff revisions.
204-Federal Energy Regulatory Commission Docket No. EL11-20. Affidavit on behalf of PJM Power Providers addressing flaws in the PJM tariff’s Minimum Offer Price Rule regarding new capacity entry.
203-Federal Energy Regulatory Commission Docket Nos. ER04-449. Affidavit and supplemental statement on behalf of New York Suppliers addressing the appropriate criteria for the establishment of a new capacity zone in the NYISO markets.
2010
202-New Jersey State Assembly and Senate. Statements on behalf of the Competitive Supplier Coalition addressing market power and reliability impacts of proposed legislation, Assembly Bill 3442 and Senate Bill 2381.
201-Federal Energy Reglatory Commission. Docket ER11-2183. Affidavit on behalf of First Energy Services Company addressing default capacity charges for Fixed Resource Requirement participants in the PJM Reliability Pricing Model capacity market design.
PDF page 46
Roy J. ShankerPage 12
200-Federal Energy Regulatory Commission. Docket ER11-2059 Affidavit on behalf of First Energy Services Company addressing deficiencies and computational problems in the proposed “exit charges” for transmission owners leaving the MISO RTO related to long term transmission rights.
199-Federal Energy Regulatory Commission Docket RM10-17. Invited panelist addressing metrics for cost effectiveness of demand response and associated cost allocations and implications for monopsony power.
198-Federal Energy Regualtory Commission Consolidated Dockets ER10- 787-000, EL10-50-000, and EL10-57-000. Two affidavits on behalf of the New England Power Generators Association regarding ISO-NE modified proposals for alternative price rule mitigation and zonal definitions/functions of locational capacity markets.
197-Federal Energy Regulatory Commission Docket No. ER10-2220-000. Affidavit on behalf of the Independent Energy Producers of New York. Addressing rest of state mitigation thresholds and procedures for adjusting thresholds for frequently mitigated units and reliability must run units.
196-Federal Energy Regulatory Commission Docket PA10-1. Affidavit on behalf of Entergy Services related to development of security constrained unit commitment software and its performance.
195-Federal Energy Regulatory Commission Docket No. ER09-1063-004. Testimony on behalf of the PJM Power Providers Group (P3) regarding the proposed shortage pricing mechanism to be implemented in the PJM energy market. Reply comments related to a similar proposal by the independent market monitor.
194-PJM RTO. Statement regarding the impact of the exercise of buyer market power in the PJM RPM/Capacity market. Panel discussant on the issue at the associated Long Term Capacity Market Issues Sympossium.
193-Federal Energy Regulatory Commission Docket No. ER10-787-000. Affidavit on behalf of New England Power Generators Association addressing proper design of the alternative price rules (APR) for the ISO- NE Forward Capacity Auctions. Second affidavit offered in reply. Supplemental affidavit also submitted
192-Federal Energy Regulatory Commission Docket No. RM10-17-000. Affidavit on behalf of New England Power Generators Association addressing proper pricing for demand response compensation in organized wholesale regional transmissiom organizations.
PDF page 47
Roy J. ShankerPage 13
191-Federal Energy Regulatory Commission Docket No. RM10-17-000, Affidavit on my on behalf regarding inconsistent representations made between filings in this docket and contemporaneous materials presented in the PJM stakeholder process.
2009
190-Federal Energy Regulatory Commission Docket No. ER09-1682. Two affidavits on behalf of an un-named party regarding confidential treatment of market data coupled with specific market participant bidding, and associated issues.
189-American Arbitration Assoication, Case No. 75-198-Y-00042-09 JMLE, on behalf of Rathdrum Power LLC. Report on the operation of specific pricing provision of a tolling power purchase agreement.
188-Federal Energy Regulatory Commission. Docket No. IN06-3-003. Analyses on behalf of Energy Transfer Partners L.P. regarding trading activity in physical and financial natural gas markets.
187-Federal Energy Regulatory Commission. Docket No. ER08-1281- 000. Analyses on behalf of Fortis Energy Trading related to the impacts of loop flow on trading activities and pricing.
186-American Arbitration Association. Report on behalf of PEPCO Energy Services regarding several trading transactions related to the purchase and sale of Installed Capacity under the PJM Reliability Pricing Model.
185-Federal Energy Regulatory Commission Docket No. EL-0-47. Analyses on behalf of HQ Energy services (U.S.) regarding pricing and sale of energy associated with capacity imports into ISO-NE.
184-Federal Energy Regulatory Commission Docket No. ER04-449 019, Affidavit on behalf of HQ Energy Services (U.S.) regarding the implementation of the consensus deliverability plan for the NYISO, and associated reliability impacts of imports.
183-Federal Energy Regulatory Commission Docket ER09-412-000, ER05-1410-010, EL05-148-010. Affidavit and Reply Affidavit on behalf of PSEG Companies addressing proposed changes to the PJM Reliability Pricing Model and rebuttal related to other parties’ filings.
2008
PDF page 48
Roy J. ShankerPage 14
182-Pennsylvania Public Service Commission. En Banc Public Hearing on "Current and Future Wholesale Electricity Markets", comments regarding the design of PJM wholesale market pricing and state restructuring.
181-Maine Public Utility Commission. Docket No. 2008-156. Testimony on behalf of a consortium of energy producers and suppliers addressing the potential withdrawal of Maine from ISO New England and associated market and supplier response.
180-Federal Energy Regulatory Commission. Docket No. EL08-67-000. Affidavit on behalf of Duke Energy Ohio and Reliant Energy regarding criticisms of the PJM reliability pricing model (RPM) transitional auctions.
179-Federal Energy Regulatory Commission. Docket AD08-4, on behalf of the PJM Power Providers. Statement and participation in technical session regarding the design and operation of capacity markets, the status of the PJM RPM market and comments regarding additional market design proposals.
178-Federal Energy Regulatory Commission. Docket ER06-456-006, Testimony on behalf of East Coast Power and Long Island Power Authority regarding appropriate cost allocation procedures for merchant transmission facilities within PJM.
2007
177-FERC Docket No. EL07-39-000. Testimony on behalf of Mirant Companies and Entergy Nuclear Power Marketing regarding the operation of the NYISO In-City Capacity market and the associated rules and proposed rule modifications.
176-FERC Dockets: RM07-19-000 and AD07-7-000, filing on behalf of the PJM Power Providers addressing conservation and scarcity pricing issues identified in the Commission’s ANOPR on Competition.
175-FERC Docket No. EL07-67-000. Testimony and reply comments on behalf of Hydro Quebec U.S. regarding the operation of the NYISO TCC market and appropriate bidding and competitive practices in the TCC and Energy markets.
174-FERC Docket Nos. EL06-45-003. Testimony on behalf of El Paso Electric regarding the appropriate interpretation of a bilateral transmission and exchange agreement.
2006
PDF page 49
Roy J. ShankerPage 15
173-United States Bankruptcy Court for the Southern District of New York. Case No. 01-16034 (AJG). Report on Behalf of EPMI regarding the properties and operation of a power purchase agreement.
172-FERC Docket No. EL05-148-000. Testimony regarding the proposed Reliability Pricing Model settlement submitted for the PJM RTO.
171-FERC Docket No. ER06-1474-000, FERC. Testimony on behalf othe PSEG Companies regarding the PJM proposed new policy for including “market efficiency” transmission upgrades in the regional transmission expansion plan.
170-FERC Docket No. EL05-148-000, FERC. Participation in Commission technical sessions regarding the PJM proposed Reliability Pricing Model.
169-FERC Docket No. EL05-148-000, FERC. Comments filed on behalf of six PJM market participants concerning the proposed rules for participation in the PJM Reliability Pricing Model Installed Capacity market, and related rules for opting out of the RPM market.
168-FERC Docket No. ER06-407-000. Testimony on behalf of GSG, regarding interconnection issues for new wind generation facilities within PJM.
2005
167-FERC Docket No. EL05-121-000, Testimony on behalf of several PJM Transmission Owners (Responsible Pricing Alliance) regarding alternative regional rate designs for transmission service and associated market design issues.
166-FERC Technical Conference of June 16, 2005. (Docket Nos. PL05-7- 000, EL03-236-000, ER04-539-000). Invited participant. Statement regarding the operation of the PJM Capacity market and the proposed new Reliability Pricing Model Market design.
165-American Arbitration Association Nos. 16-198-00206-03 16-198- 002070.On behalf of PG&E Energy Trading. Analyses related to the operation and interpretation of power purchase and sale/tolling agreements and electrical interconnection requirements.
164-Arbitration on behalf of Black Hills Power, Inc. Expert testimony related to a power purchase and sale and energy exchange agreement, as
PDF page 50
Roy J. ShankerPage 16
well as FERC criteria related to the applicable code and standards of conduct.
2004
163-Federal Energy Regulatory Commission Docket No. EL03-236-003. Testimony on behalf of Mirant companies relating to PJM proposal for compensation of frequently mitigated generation facilities.
162-Federal Energy Regulatory Commission. Docket No. ER03-563-030. Testimony on behalf of Calpine Energy Services regarding the development of a locational Installed Capacity market and associated generator service obligations for ISO-NE. Supplemental testimony filed 2005.
161-Federal Energy Regulatory Commission. Docket No. EL04-135-000. Testimony on behalf on the Unified Plan Supporters regarding implications of using a flow based rate design to allocate embedded costs.
160-Federal Energy Regulatory Commission. Docket No. ER04-1229- 000. Testimony on behalf of EME Companies regarding the allocation and recovery of administrative charges in the NYISO markets.
159-Federal Energy Regulatory Commission. Dockets No. EL01-19-000, No. EL01-19-001, No. EL02-16-000, EL02-16-000. Testimony on behalf of PSE&G Energy Resources and Trade regarding pricing in the New York Independent System Operator energy markets.
158-Federal Energy Regulatory Commission. Invited panelist regarding performance based regulation (PBR) and wholesale market design. Comments related to the potential role of PBR in transmission expansion, and its interaction with market mechanisms for new transmission.
157-Federal Energy Regulatory Commission. Docket No. ER04-539-000 Testimony on behalf of EME Companies regarding proposed market mitigation in the energy and capacity markets of the Northern Illinois Control Area.
156-Federal Energy Regulatory Commission. Standardization of Generator Interconnection Agreements and Procedures Docket No. RM02- 1-001, Order 2003-A, Affidavit on Behalf of PSEG Companies regarding the modifications on rehearing to interconnection crediting procedures.
155-Federal Energy Regulatory Commission. Dockets ER03-236- 000,ER04-364-000,ER04-367-000,ER04-375-000. Testimony on behalf of
PDF page 51
Roy J. ShankerPage 17
the EME Companies regarding proposed market mitigation measures in the Northern Illinois Control Area of PJM.
154-Federal Energy Regulatory Commission. Dockets PL04-2-000, EL03- 236-000. Invited panelist, testimony related to local market power and the appropriate levels of compensation for reliability must run resources.
2003
153-American Arbitration Association. 16 Y 198 00204 03. Report on behalf of Trigen-Cineregy Solutions regarding an energy services agreement related to a cogeneration facility.
152-Federal Energy Regulatory Commission. Docket No. EL03-236-000. Testimony on behalf of EME Companies regarding the PJM proposed tariff changes addressing mitigation of local market power and the implementation of a related auction process.
151-Federal Energy Regulatory Commission. Docket No. PA03-12-000. Testimony on behalf of Pepco Holdings Incorporated regarding transmission congestion and related issues in market design in general, and specifically addressing congestion on the Delmarva Peninsula.
150-Federal Energy Regulatory Commission. Docket Nos. ER03-262-007, Affidavit on behalf of EME Companies regarding the cost benefit analysis of the operation of an expanded PJM including Commonwealth Edison.
149-Supreme Court of the State of New York, Index No. 601505/01. Report on behalf of Trigen-Syracuse Energy Corporation regarding energy trading and sales agreements and the operation of the New York Independent System Operator.
148-Federal Energy Regulatory Commission. Docket No. ER03-262-000. Affidavit on behalf of the EME Companies regarding the issues associated with the integration of the Commonwealth Edison Company into PJM.
147-Federal Energy Regulatory Commission. Docket No. ER03-690-000. Affidavit on behalf of Hydro Quebec US regarding New York ISO market rules at external generator proxy buses when such buses are deemed non- competitive.
146-Federal Energy Regulatory Commission. Docket RT01-2-006,007. Affidavit on behalf of the PSEG Companies regarding the PJM Regional Transmission Expansion Planning Protocol, and proper incentives and structure for merchant transmission expansion.
PDF page 52
Roy J. ShankerPage 18
145-Federal Energy Regulatory Commission. Docket No. ER03-406-000. Affidavit on behalf of seven PJM Stakeholders addressing the appropriateness of the proposed new Auction Revenue Rights/Financial Transmission Rights process to be implemented by the PJM ISO.
144-Federal Energy Regulatory Commission. Docket No. ER01-2998- 002. Testimony on behalf of Pacific Gas and Electric Company related to the cause and allocation of transmission congestion charges.
143-Federal Energy Regulatory Commission. Docket No. RM01-12-000. On behalf of six different companies including both independent generators, integrated utilities and distribution companies comments on the proposed resource adequacy requirements of the Standard Market Design.
142-United States Bankruptcy Court, Northern District of California, San Francisco Division, Case No. 01-30923 DM. On behalf of Pacific Gas and Electric Dr. Shanker presented testimony addressing issues related to transmission congestion, and the proposed FERC SMD and California MD02 market design proposals.
2002
141-Arbitration. Testimony on behalf of AES Ironwood regarding the operation of a tolling agreement and its interaction with PJM market rules.
140-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Dr. Shanker was asked by the three Northeast ISO’s to present a summary of his resource adequacy proposal developed in the Joint Capacity Adequacy Group. This was part of the Standard Market Design NOPR process.
139-Federal Energy Regulatory Commission. Docket No. ER02-456-000. Testimony on behalf of Electric Gen LLC addressing comparability of a contract among affiliates with respect to non-price terms and conditions.
138-Circuit Court for Baltimore City. Case 24-C-01-000234. Testimony on behalf of Baltimore Refuse Energy Systems Company regarding the appropriate implementation and pricing of a power purchase agreement and related Installed Capacity credits.
137-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Comments on the characteristics of capacity adequacy markets and alternative market design systems for implementing capacity adequacy markets.
PDF page 53
Roy J. ShankerPage 192001
136-Federal Energy Regulatory Commission. Docket ER02-456-000. Testimony on behalf of Electric Gen LLC regarding the terms and conditions of a power sales agreement between PG&E and Electric Generating Company LLC.
135-Delaware Public Service Commission. Docket 01-194. On behalf of Conectiv et al. Testimony relating to the proper calculation of Locational Marginal Prices in the PJM market design, and the function of Fixed Transmission Rights.
134-Federal Energy Regulatory Commission. Docket No. IN01-7-000 On behalf of Exelon Corporation . Testimony relating to the function of Fixed Transmission Rights, and associated business strategies in the PJM market system.
133-Federal Energy Regulatory Commission. Docket No. RM01-12-000. Comments on the basic elements of RTO market design and the required market elements.
132-Federal Energy Regulatory Commission. Docket No. RT01-99-000. On behalf of the One RTO Coalition. Affadavit on the computational feasibility of large scale regional transmission organizations and related issues in the PJM and NYISO market design.
131-Arbitration. On behalf of Hydro Quebec. Testimony related to the eligibility of power sales to qualify as Installed Capacitywithin the New York Independent system operator.
130-Virginia State Corporation Commission. Case No. PUE000584. On behalf of the Virginia Independent Power Producers. Testimony related to the proposed restructuring of Dominion Power and its impact on private power contracts.
129-United States District Court, Northern District of Ohio, Eastern Division, Case: 1:00CV1729. On behalf of Federal Energy Sales, Inc. Testimony related to damages in disputed electric energy trading transactions.
128-Federal Energy Regulatory Commission. Docket Number ER01- 2076-000. Testimony on behalf of Aquila Energy Marketing Corp and Edison Mission Marketing and Trading, Inc. relating to the implementation of an Automated Mitigation Procedure by the New York ISO.
PDF page 54
Roy J. ShankerPage 202000
127-New York Independent System Operator Board. Statement on behalf of Hydro Quebec, U.S. regarding the implications and impacts of the imposition of a price cap on an operating market system.
126-Federal Energy Regulatory Administration. Docket No. EL00-24-000. Testimony on behalf of Dayton Power and Light Company regarding the proper characterization and computation of regulation and imbalance charges.
125-American Arbitration Association File 71-198-00309-99. Report on behalf of Orange and Rockland Utilities, Inc. regarding the estimation of damages associated with the termination of a power marketing agreement.
124-Circuit Court, 15th Judicial Circuit, Palm Beach County, Florida. On behalf of Okeelanta and Osceola Power Limted Partnerships et. al. Analyses related to commercial operation provisions of a power purchase agreement.
1999
123-Federal Energy Regulatory Commission. Docket No. ER00-1-000. Testimony on behalf of TransEnergie U.S. related to market power associated with merchant transmission facilities. Also related analyses regarding market based tariff design for merchant transmission facilities.
122-Federal Energy Regulatory Commission. Docket RM99-2-000. Analyses on behalf of Edison Mission Energy relating to the Regional Transmission Organization Notice of Proposed Rulemaking.
121-Federal Energy Regulatory Commission. Docket No. ER99-3508- 000. On behalf of PG&E Energy Trading, analyses associated with the proposed implementation and cutover plan for the New York Independent System Operator.
120-Federal Energy Regulatory Commission. Docket No. EL99-46-000. Comments on behalf of the Electric Power Supply Association relating to the Capacity Benefit Margin.
119-New York Public Service Commission, Case 97-F-1563. Testimony on behalf of Athens Generating Company describing the impacts on pricing and transmission of a new generation facility within the New York Power Pool under the new proposed ISO tariff.
PDF page 55
Roy J. ShankerPage 21
118-JAMS Arbitration Case No. 1220019318 On behalf of Fellows Generation Company. Testimony related to the development of the independent power and qualifying facility industry and related industry practices with respect to transactions between cogeneration facilities and thermal hosts.
117-Court of Common Pleas, Philadelphia County, Pennsylvania. Analyses on behalf of Chase Manhattan Bank and Grays Ferry Cogeneration Partnership related to power purchase agreements and electric utility restructuring.
1998
116-Virginia State Corporation Commission. Case No. PUE 980463. Testimony on behalf of Appomattax Cogeneration related to the proper implementation of avoided cost methodology.
115-Virginia State Corporation Commission. Case No. PUE980462 Testimony on behalf of Virginia Independent Power Producers related to an applicaton for a certificate for new generation facilities.
114-Federal Energy Regulatory Commission. Analyses related to a number of dockets reflecting amendments to the PJM ISO tariff and Reliability Assurance Agreement.
113-U.S. District Court, Western Oklahoma. CIV96-1595-L. Testimony related to anti-competitive elements of utility rate design and promotional actions.
112-Federal Energy Regulatory Commission Dockets No. EL94-45-001 and QF88-84-006. Analyses related to historic measurement of spot prices for as available energy.
111-Circuit Court, Fourth Judicial Circuit, Duval County, Florida. Analyses related to the proper implementation of a a power purchase agreement and associated calculations of capacity payments. (Testimony 1999)
1997
110-United States District Court for the Eastern District of Virginia, CA No. 3:97CV 231. Analyses of the business and market behavior of Virginia Power with respect to the implementation of wholesale electric power purchase agreements.
PDF page 56
Roy J. ShankerPage 22
109-United States District Court, Southern District of Florida, Case No. 96-594-CIV, Analyses related to anti-competitive practices by an electric utility and related contract matters regarding the appropriate calculation of energy payments.
108-Virginia State Corporation Commission. Case No. PUE960296. Testimony related to the restructuring proposal of Virginia Power and associated stranded cost issues.
107-Federal Energy Regulatory Commission. Dockets No. ER97-1523- 000 and OA97-470-000, Analyses related to the restructuring of the New York Power Pool and the implementation of locational marginal cost pricing.
106-Federal Energy Regulatory Commission Dockets No. OA97-261-000 and ER97-1082-000 Analyses and testimony related to the restructuring of the PJM Power Pool and the implementation of locational marginal cost pricing.
105-Missouri Public Service Commission. Case No. ET-97-113. Testimony related to the proper definition and rate design for standby, supplemental and maintenance service for Qualifying facilities.
104-American Arbitration Association. Case 79 Y 199 00070 95. Testimony and analyses related to the proper conditions necessary for the curtailment of Qualifying Facilities and the associated calculations of negative avoided costs.
103-Virginia State Corporation Commission. Case Number PUE960117 Testimony related to proper implementation of the differential revenue requirements methodology for the calculation of avoided costs.
102-New York Public Service Commission. Case 96-E-0897, Analyses related to the restructuring of Consolidated Edison Company of New York and New York Power Pool proposed Independent System Operator and related transmission tariffs.
1996
101-Florida Public Service Commission. Docket No. 950110-EI. Testimony related to the correct calculation of avoided costs using the Value of Deferral methodology and its implementation.
100-Federal Energy Regulatory Commission Dockets No. EL94-45-001 and QF88-84-006. Testimony and Analyses related to the estimation of historic market rates for electricity in the Virginia Power service territory.
PDF page 57
Roy J. ShankerPage 23
99-Circuit Court of the City of Richmond Case No. LA-2266-4. Analyses related to the incurrence of actual and estimated damages associated with the outages of an electric generation facility.
98-New Hampshire Public Utility Commission, Docket No. DR96-149. Analyses related to the requirements of light loading for the curtailment of Qualifying Facilities, and the compliance of a utility with such requirements.
97-State of New York Supreme Court, Index No. 94-1125. Testimony related to system planning criteria and their relationship to contract performance specifications for a purchased power facility.
96-United States District Court for the Western District of Pennsylvania, Civil Action No. 95-0658. Analyses related to anti-competitive actions of an electric utility with respect to a power purchase agreement.
95-United States District Court for the Northern District of Alabama, Southern Division. Civil Action Number CV-96-PT 0097-S. Affadavit on behalf of TVA and LG&E Power regarding displacement in wholesale power transactions.
1995
94-American Arbitration Association. Arbitration No. 14 198 012795 H/K. Report concerning the correct measurement of savings resulting from a commercial building cogeneration system and associated contract compensation issues.
93-Circuit Court City of Richmond. Law No. LX-2859-1. Analyses related to IPP contract structure and interpretation regarding plant compensation under different operating conditions.
92-Federal Energy Regulatory Commission. Case EL95-28-000. Affidavit concerning the provisions of the FERC regulations related to the Public Utility Regulatory Policies Act of 1978, and relationship of estimated avoided cost to traditional rate based recovery of utility investment.
91-New York Public Service Commission, Case 95-E-0172, Testimony on the correct design of standby, maintenance and supplemental service rates for qualifying facilities.
90-Florida Public Service Commission, Docket No. 941101-EQ. Testimony related to the proper analyses and procedures related to the
PDF page 58
Roy J. ShankerPage 24
curtailment of purchases from Qualifying Facilities under Florida and FERC regulations.
89-Federal Energy Regulatory Commission, Dockets ER95-267-000 and EL95-25-000. Testimony related to the proper evaluation of generation expansion alternatives.
1994
88-American Arbitration Association, Case Number 11 Y198 00352 94 Analyses related to contract provisions for milestones and commercial operation date and associated termination and damages related to the construction of a NUG facility.
87-United States District Court, Middle District Florida, Case No. 94-303 Civ-Orl-18. Analyses related to contract pricing interpretation other contract matters in a power purchase agreement between a qualifying facility and Florida Power Corporation.
86-Florida Public Service Commission Docket 94037-EQ. Analyses related to a contract dispute between Orlando Power Generation and Florida Power Corporation.
85-Florida Public Service Commission Docket 941101-EQ. Testimony and analyses of the proper procedures for the determination and measurement for the need to curtail purchases from qualifying facilities.
84-New York Public Service Commission Case 93-E-0272, Testimony regarding PURPA policy considerations and the status of services provided to the generation and consuming elements of a qualifying facility.
83-Circuit Court for the City of Richmond. Case Number LW 730-4. Analyses of the historic avoided costs of Virginia Power, related procedures and fixed fuel transportation rate design.
82-New York Public Service Commission, Case 93-E-0958 Analyses of Stand-by, Supplementary and Maintenance Rates of Niagara Mohawk Power Corporation for Qualifying Facilities .
81-New York Public Service Commission, Case 94-E-0098. Analyses of cost of service and rate design of Niagara Mohawk Power Corporation.
80-American Arbitration Association, Case 55-198-0198-93, Arbitrator in contract dispute regarding the commercial operation date of a qualifying small power generation facility.
PDF page 59
Roy J. ShankerPage 251993
79-U.S. District Court, Southern District of New York Case 92 Civ 5755. Analyses of contract provisions and associated commercial terms and conditions of power purchase agreements between an independent power producer and Orange and Rockland Utilities.
78-State Corporation Commission, Virginia. Case No. PUE920041. Testimony related to the appropriate evaluation of historic avoided costs in Virginia and the inclusion of gross receipt taxes.
77-Federal Energy Regulatory Commission. Docket ER93-323-000. Evaluations and analyses related to the financial and regulatory status of a cogeneration facility.
76-Federal Energy Regulatory Commission. Docket EL93-45-000; Docket QF83-248-002. Analyses related to the qualifying status of cogeneration facility.
75-Circuit Court of the Eleventh Judicial Circuit, Dade County, Florida. Case No. 92-08605-CA-06. Analyses related to compliance with electric and thermal energy purchase agreements. Damage analyses and testimony.
74-Board of Regulatory Commissioners, State of New Jersey. Docket EM 91010067. Testimony regarding the revised GPU/Duquesne 500 MW power sales agreement and associated transmission line.
73-State of North Carolina Utilities Commission. Docket No. E-100 Sub
67. Testimony in the consideration of rate making standards pursuant to Section 712 of the Energy Policy Act of 1992.
72-State of New York Public Service Commission. Cases 88-E-081 and 92-E-0814. Testimony regarding appropriate procedures for the determination of the need for curtailment of qualifying facilities and associated proper production cost modeling and measurement.
71-Pennsylvania Public Utility Commission. Docket No. A-110300f051. Testimony regarding the prudence of the revised GPU/Duquesne 500 MW power sales agreement and associated transmission line.
1992
70-Pennsylvania Public Service Commission. Dockets No. P-870235,C- 913318,P-910515,C-913764. Testimony regarding the calculation of avoided costs for GPU/Penelec.
PDF page 60
Roy J. ShankerPage 26
69-Public Service Commission of Maryland. Case No. 8413,8346. Testimony on the appropriate avoided costs for Pepco, and appropriate procedures for contract negotiation.
1991
68-Board of Regulatory Commissioners, State of New Jersey. Docket EM- 91010067. Testimony regarding the planned purchase of 500 MW by GPU from Duquesne Light Company.
67-Public Service Commission of Wisconsin. Docket 05-EP-6. State Advance Plan. Testimony on the calculation of avoided costs and the structuring of payments to qualifying facilities.
66-State Corporation Commission, Virginia. Case No. PUE910033. Testimony on class rate of return and rate design for delivery point service. Northern Virginia Electric Cooperative.
65-State Corporation Commission, Virginia. Case No. PUE910048 Testimony on proper data and modeling procedures to be used in the evaluation of the annual Virginia Power fuel factor.
64-State Corporation Commission, Virginia. Case No. PUE910035. Evaluation of the differential revenue requirements method for the calculation of avoided costs.
63-Public Service Commission of Maryland. Case Number 8241 Phase II. Testimony related to the proper determination of avoided costs for Baltimore Gas and Electric.
62-Public Service Commission of Maryland. Case Number 8315. Evaluation of the system expansion planning methodology and the associated impacts on marginal costs and rate design, PEPCO.
1990
61-Public Utility Commission, State of California, Application 90-12-064. Analyses related to the contractual obligations between San Diego Gas and Electric and a proposed QF.
60-Montana Public Service Commission. Docket 90.1.1 Testimony and analyses related to natural gas transportation, services and rates.
59-State Corporation Commission, Virginia. Case No. PUE890075. Testimony on the calculation of full avoided costs via the differential revenue requirements methodology.
PDF page 61
Roy J. ShankerPage 27
58-District of Columbia Public Service Commission. Formal Case 834 Phase II. Analyses and development of demand side management programs and least cost planning for Washington Gas Light.
57-State Corporation Commission, Virginia. Case No. PUE890076. Analyses related to administratively set avoided costs. Determination of optimal expansion plans for Virginia Power.
56-State Corporation Commission, Virginia. Case No. PUE900052. Analyses supporting arbitration of a power purchase agreement with Virginia Power. Determination of expansion plan and avoided costs.
55-Public Service Commission of Maryland. Case Number 8251. Analyses of system expansion planning models and marginal cost rate design for PEPCO.
54-State Corporation Commission, Virginia. Case No. PUE900054. Evaluation of fuel factor application and short term avoided costs.
53-Federal Energy Regulatory Commission. Northeast Utilities Service Company Docket Nos. EC90-10-000, ER90-143-000, ER90-144- 000,ER90-145-000 and El90-9-000. Analyses of the implications of Northeast Utilities and Public Service Company of New Hampshire merger on electric supply and pricing.
52-Public Service Commission of Maryland. Re: Southern Maryland Electric Cooperative Inc. Contract with Advanced Power Systems, Inc. and PEPCO.
51-Puerto Rico Electric Power Authority, Office of the Governor of Puerto Rico. Independent evaluation for PREPA of avoided costs and the evaluation of competing QF's.
50-State Corporation Commission, Virginia. Case No. PUE890041. Testimony on the proper determination of avoided costs with respect to Old Dominion Electric Cooperative.
1989
49-Oklahoma Corporation Commission. Case Number PUD-000586. Analyses related to system planning and calculation of avoided costs for Public Service of Oklahoma.
PDF page 62
Roy J. ShankerPage 28
48-Virginia State Corporation Commission. Case Number PUE890007. Testimony relating to the proper determination of avoided costs to the certification evaluation of new generation facilities.
47-Federal Energy Regulatory Commission. Docket RP85-50. Analyses of the gas transportation rates, terms and conditions filed by Florida Gas Transmission.
46-Circuit Court of the Fifth Judicial Circuit, Dade County, Florida. Case No. 88-48187. Analyses related to compliance with electric and thermal energy purchase agreements.
45-Florida Public Service Commission. Docket 880004-EU. Analysis of state wide expansion planning procedures and associated avoided unit.
1988
44-Virginia State Corporation Commission. Case No. PUE870081. Testimony on the implementation of the differential revenue requirements avoided costmethodology recommended by the SCC Task Force.
43-Virginia State Corporation Commission. Case No. PUE880014. Testimony on the design and level of standby, maintenance and supplemental power rates for qualifying facilities.
42-Virginia State Corporation Commission. Case No. PUE99038. Testimony on the natural gas transportation rate design and service provisions.
41-Montana Public Service Commission. Docket 87.8.38. Testimony on Natural Gas Transmission Rate Design and Service Provisions.
40-Oklahoma Corporation Commission. Cause Pud No. 00345. Testimony on estimation and level of avoided cost payments for qualifying facilities.
39-Florida Public Service Commission. Docket No.8700197-EI. Testimony on the methodology for establishing non-firm load service levels.
38-Arizona Corporation Commission. Docket No. U-1551-86-300. Analysis of cost-of-service studies and related terms and conditions for material gas transportation rates.
1987
PDF page 63
Roy J. ShankerPage 29
37-Virginia State Corporation Commission. Case No. PUE870028. Analysis of Virginia Power fuel factorapplication and relationship to avoided costs.
36-District of Columbia Public Service Commission. Formal Case No. 834 Phase II. Analysis of the theory and empirical basis for establishing cost effectiveness of natural gas conservation programs.
35-Virginia State Corporation Commission. Case No. PUE860058. Testimony on the relationship of small power producers and cogenerators to the need for power and new generation facilities.
34-Virginia State Corporation Commission. Case No. PUE870025. Testimony addressing the proper design of rates for standby, maintenance and supplement power sales to cogenerators.
33-Florida Public Service Commission. Docket No. 860004 EU. Testimony in the 1986 annual planning hearing on proper system expansion planning procedures.
1986
32-Florida Public Service Commission. Docket No. 860001 EI-E. Testimony on the proper methodology for the estimation of avoided O&M costs.
31-Florida Public Service Commission. Docket No. 860786-EI. Testimony on the proper economic analysis for the evaluation of self- service wheeling.
30-U.S. Bankruptcy Court, District of Ohio. Testimony on capabilities to develop and operate wood-fired qualifying facility.
29-Public Utility Commission, New Hampshire Docket No. DR-86-41. Testimony on pricing and contract terms for power purchase agreement between utility and QFs. (Settlement Negotiations)
28-Florida Public Service Commission, Docket No. 850673-EU. Testimony on generic issues related to the design of standby rates for qualifying facilities.
27-Virginia State Corporation Commission. Case No. 860024. Generic hearing on natural gas transportation rate design and tariff terms and conditions.
PDF page 64
Roy J. ShankerPage 30
26-Virginia State Corporation Commission. Commonwealth Gas Pipeline Corporation. Case No. 850052. Testimony on natural gas transportation rate design and tariff terms and conditions.
25-Bonneville Power Administration. Case No. VI86. Testimony on the proposed Variable Industrial Power Rate for Aluminum Smelters.
24-Virginia Power. Case No. PUE860011. Testimony on the proper ex post facto valuation of avoided power costs for qualifying facilities.
23-Florida Public Service Commission. Docket No. 850004 EU. Testimony on proper analytic procedures for developing a statewide generation expansion plan and associated avoided unit.
1985
22-Virginia Natural Gas. Docket No. 85-0036. Testimony and cost of service procedures and rate design for natural gas transportation service.
21-Arkansas Louisiana Gas. Louisiana Docket No. U-16534. Testimony on proper cost of service procedures and rate design for natural gas service.
20-Connecticut Light and Power. Docket No. 85-08-08.
Assist in the development of testimony for industrial natural gas transportation rates.
19-Oklahoma Gas and Electric. Cause 29727. Testimony and system operations and the development of avoided cost measurements as the basis for rates to qualifying facilities.
18-Florida Public Service Commission. Docket No. 840399EU. Testimony on self-service wheeling and business arrangements for qualifying facilities.
17-Virginia Electric and Power Company. General Rate application No. PUE840071. Testimony on proper rate design procedures and computations for development of supplemental, maintenance and standby service for cogenerators.
16-Virginia Electric and Power Company. Fuel Factor
Proceeding No. PUE850001. Testimony on the proper use of the PROMOD model and associated procedures in setting avoided cost energy rates for cogenerators.
PDF page 65
Roy J. ShankerPage 31
15-New York State Public Service Commission. Case No. 28962. Development of the use of multi-area PROMOD models to estimate avoided energy costs for six private utilities in New York State.
14-Vermont Rate Hearings on Payments to Small Power Producers. Case No. 4933. Testimony on proper assumptions, procedures and analysis for the development of avoided cost rates.
1984
13-Northern Virginia Electric Cooperative. Case No. PUE840041. Testimony on class cost-of-serviceprocedures, class rate of return and rate design.
12-BPA 1985 Wholesale Rate Proceedings. Analysis of Power 1985 Rate Directives. Testimony on theory and implementation of marginal cost rate design.
11-Virginia Electric Power Company. Application to Revise Rate Schedule 19 -- Power Purchases from Cogeneration and Small Power Production Qualifying Facilities. Case No. PUE830067. Testimony on proper PROMOD modeling procedures for power purchases and properties of PROMOD model.
10-Northern Virginia Electric Cooperative. Case No. PUE840041. Testimony on class cost-of-service procedures, class rate of return and rate design.
9-BPA 1985 Wholesale Rate Proceedings. Analysis of Power 1985 Rate Directives. Testimony on the theory and implementation of marginal cost rate design, financial performance of BPA; interactions between rate design, demand, system expansion and operation.
1983
8-Northern Virginia Electric Cooperative. Case No. PUE830040. Testimony on class cost-of-service procedures, class rate of return and rate design.
7-Vermont Rate Hearings to Small Power Producers. No.4804. Testimony on proper use and application of production costing analyses to the estimation of avoided costs.
6-BPA Wholesale Rate Proceedings. Testimony on the theory and implementation of marginal cost rate design; financial performance of
PDF page 66
Roy J. ShankerPage 32
BPA; interactions between rate design, demand, system expansion and operation.
5-Idaho Power Company, PUC-U-1006-185. Analysis of system planning/production costing model play of hydro regulation and associated energy costs.
1982
4-Generic Conservation Proceedings, New York State. Case No. 18223. Testimony on the economic criteria for the evaluation of conservation activities; impacts on utility financial performance and rate design.
3-PEPCO, Washington Gas Light. DCPSC-743. Financial evaluation of conservation activities; procedures for cost classification, allocation; rate design.
2-PEPCO, Maryland PSC Case Nos. 7597-I, 7597-II, and 7652. Testimony on class rates of return, cost classification and allocation, power pool operations and sales.
1981
1-Pacific Gas and Electric. California PSC Case No. 60153. Testimony on rate design; class cost-of-service and rate of return.
Previous testimony before the District of Columbia
Public Service Commission, Maryland PSC, New York Public Service Commission, FERC; Economic Regulatory Administration
PDF page 67
Appendix B
PDF page 68
1
18.10 Annual RBP Isolation and Matched Demand Adjustment
(a) Applicability
For each Delivery Year during the Reliability Backstop Procurement commitment period, and for each Base Residual Auction and Incremental Auction conducted after the Office of the Interconnection commits RBP UCAP MW through the Reliability Backstop Procurement, the Office of the Interconnection shall apply the RBP isolation and matched demand adjustment set forth in this section.
(b) Determination of Available RBP UCAP MW
Before posting the Planning Parameters for each applicable RPM Auction, the Office of the Interconnection shall determine Available RBP UCAP MW for the applicable Delivery Year on a resource-specific and aggregate basis. The determination shall account for the RBP Resource’s committed RBP UCAP MW, applicable Accredited UCAP, expected commercial-operation or registration status, deliverability, any notice submitted pursuant to Tariff, Attachment DD, section 5.5, approved replacement capacity, and any rescission pursuant to Tariff, Attachment DD, section 18.6(e).
The Office of the Interconnection shall determine Available RBP UCAP MW for the PJM Region and by Zone and modeled Locational Deliverability Area.
(c) Determination of RBP-Related Load UCAP MW
Before posting the Planning Parameters for each applicable RPM Auction, the Office of the Interconnection shall determine the portion of the incremental-load cohort used to establish or allocate the Reliability Backstop Procurement that is included in the Planning Parameters for the applicable RPM Auction. The Office of the Interconnection shall convert such load to UCAP MW using the Forecast Pool Requirement and the existing methodologies used to determine the applicable PJM Region and LDA Reliability Requirements.
The determination shall exclude load associated with Qualifying RBP Offset UCAP MW, approved opt-outs, FRR Entities, and load not included in the applicable RPM Auction Planning Parameters. Load shall not be counted more than once under this section or under any other Tariff provision providing for exclusion or matched treatment of New Large Load.
(d) RTO-Wide RBP Demand Adjustment
For each applicable RPM Auction, the RBP Demand Adjustment for the PJM Region shall equal the lesser of:
1. Available RBP UCAP MW; and
2. RBP-Related Load UCAP MW included in the Planning Parameters for such RPM Auction.
PDF page 69
2
Solely for purposes of clearing and price formation in the applicable RPM Auction, the Office of the Interconnection shall reduce the PJM Region Reliability Requirement by the RBP Demand Adjustment.
(e) Exclusion of Available RBP UCAP MW
Available RBP UCAP MW shall not be included in any Sell Offer, price-forming supply curve, or optimization used to determine the Capacity Resource Clearing Price in an applicable RPM Auction. Available RBP UCAP MW shall not clear such RPM Auction and shall not receive RPM Auction capacity credits.
Any UCAP MW of an RBP Resource above its committed RBP UCAP MW may participate in RPM Auctions pursuant to otherwise applicable Tariff and RAA requirements. To the extent Available RBP UCAP MW exceeds RBP-Related Load UCAP MW, such excess shall remain excluded from RPM Auction price formation and shall not produce an additional reduction in any RPM reliability requirement.
(f) Incremental Auctions
For each Incremental Auction, the Office of the Interconnection shall recalculate Available RBP UCAP MW, RBP-Related Load UCAP MW, and the RBP Demand Adjustment using the updated Planning Parameters for the applicable Delivery Year. The RBP-Adjusted Reliability Requirement used in the Incremental Auction shall reflect the recalculated RBP Demand Adjustment and all RPM commitments established in prior RPM Auctions for the same Delivery Year. Available RBP UCAP MW shall not be included as an RPM commitment established in a prior auction.
(g) Locational Treatment
The Office of the Interconnection shall allocate the RBP Demand Adjustment among Zones based on the location of RBP-Related Load included in the applicable Planning Parameters. For each modeled LDA, the reduction in the LDA Reliability Requirement shall not exceed:
1. RBP-Related Load UCAP MW located in such LDA; or
2. Available RBP UCAP MW located in, or determined under the same CETO and CETL assumptions used in the applicable RPM Auction to be deliverable to, such LDA. The Office of the Interconnection shall not count the same RBP Demand Adjustment more than once among nested LDAs and their parent LDAs. Any portion of the RTO-wide RBP Demand Adjustment that cannot support an LDA adjustment under this subsection shall not reduce the reliability requirement for that LDA.
PDF page 70
3
(h) Publication
With the Planning Parameters for each applicable RPM Auction, the Office of the Interconnection shall post the aggregate Available RBP UCAP MW, RBP-Related Load UCAP MW, RBP Demand Adjustment, and resulting RBP-Adjusted Reliability Requirements for the PJM Region and each affected Zone and LDA. Resource- or customer-specific confidential information may be omitted from the public posting but shall be made available to the Market Monitoring Unit.
(i) Effect Limited to RPM Price Formation
The exclusion of Available RBP UCAP MW under this section shall not relieve an RBP Resource of any accreditation, deliverability, registration, testing, outage-reporting, energy- market must-offer, Capacity Performance, replacement-capacity, Non-Performance Charge, deficiency-charge, RBP shortfall, or other physical or performance obligation applicable to the committed RBP UCAP MW.
Recommended new and revised defined terms
“Available RBP UCAP MW” shall mean, for an RPM Auction for a Delivery Year, the aggregate UCAP MW of RBP Resources committed for such Delivery Year that the Office of the Interconnection determines, using the accreditation, commercial-operation or registration, deliverability, and availability standards that otherwise would apply in determining the quantity of such resources eligible to participate in that RPM Auction, are expected to be available to provide capacity during such Delivery Year; provided that Available RBP UCAP MW shall not exceed the RBP UCAP MW committed for such Delivery Year and shall exclude any commitment rescinded pursuant to Tariff, Attachment DD, section 18.6(e).
“RBP-Related Load UCAP MW” shall mean, for an RPM Auction for a Delivery Year, exclusive of any load associated with Qualifying RBP Offset UCAP MW, an approved opt-out, an FRR Entity, or load otherwise excluded from the applicable RPM Auction Planning Parameters, the sum of all Large Loads across the PJM region in the load forecast for the relevant Delivery Year minus the sum of all Large Loads across the PJM region that were forecasted to be on the system for the 2026/27 delivery year using the load forecast that was used for the 2028/29 Base Residual Auction. Peak-load megawatts shall be converted to UCAP MW using the Forecast Pool Requirement and the applicable existing zonal and LDA methodologies for such Delivery Year.
“RBP Demand Adjustment” shall mean, for an RPM Auction for a Delivery Year, the lesser of Available RBP UCAP MW and RBP-Related Load UCAP MW, as determined and allocated to the PJM Region, Zones, and affected Locational Deliverability Areas in accordance with Tariff, Attachment DD, section 18.10.
PDF page 71
4
“RBP-Adjusted Reliability Requirement” shall mean, solely for purposes of clearing and price formation in an RPM Auction, the applicable PJM Region Reliability Requirement or LDA Reliability Requirement, as applicable, reduced by the RBP Demand Adjustment determined pursuant to Tariff, Attachment DD, section 18.10. The RBP-Adjusted Reliability Requirement shall not modify the applicable reliability criterion, Forecast Pool Requirement, or physical resource-adequacy requirement.
“Daily RBP Settlement Quantity” shall mean, for an RBP Resource and Operating Day, the lesser of the RBP Resource’s daily committed RBP UCAP MW and daily owned UCAP MW. “RBP Market Revenue Offset” shall mean, for a Delivery Year and Electric Distributor zone/area, the daily dollar value of the final RBP Demand Adjustment allocated to such zone/area multiplied by the applicable Final Zonal Capacity Price, subject to interim calculation and true-up as set forth in Tariff, Attachment DD, section 18.5(g).
“RBP Settlement Credits” shall mean the daily dollar amount payable to an RBP Resource pursuant to Tariff, Attachment DD, section 18.5(g), before application of any RBP shortfall charge, Non-Performance Charge, deficiency charge, or other applicable charge. “RBP Charges” shall mean the daily positive or negative net amount determined pursuant to Tariff, Attachment DD, sections 18.3 and 18.5(g), consisting of RBP Settlement Credits allocated to an Electric Distributor zone/area, less the RBP Market Revenue Offset applicable to such zone/area, together with any other adjustment expressly included pursuant to Tariff, Attachment DD, section 18.