Protest of Northern Virginia Electric Cooperative, Inc. to the PJM Reliability Backstop Procurement Proposal
Text extracted from the eLibrary original (SHA-256 26b0d3d0a6397eb5…). Download the original from the official source.
Contents · 10 sections
- I. INTRODUCTION
- II. PROTEST
- A. There is a material mismatch in the timing required by PJM’s proposed RBP
- B. The RBP violates the Commission’s cost-causation principle because it does not
- C. The RBP improperly concentrates the incremental costs of RBP Resources on RBP
- D. The RBP framework is not just and reasonable because it requires too many MW to
- E. The RBP is not just and reasonable because it relies on load forecasts that were
- F. The RBP’s collateral requirements on RBP buyers are unjust and unreasonable
- III. STAKEHOLDER PROCESS
- IV. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Credit and exit
If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, and to eliminate the resulting subsidization of the PJM capacity market by NOVEC and a…Read this passage Filed comments: Credit and exit
I. INTRODUCTION
printed heading · Topic match: Credit and exit
Notably, the details and full implications of the mandatory credit and collateral requirements were never explained. 3 East Kentucky Power Cooperative, Letter of EKPC President and CEO Don Mosier, Docket No.Read this passage Filed comments: Credit and exit
II. PROTEST
printed heading
II.Read this passage
A. There is a material mismatch in the timing required by PJM’s proposed RBP
printed heading
A prudent procurement of more than 1,600 MW cannot reasonably be completed within the period PJM proposes.Read this passage
B. The RBP violates the Commission’s cost-causation principle because it does not
printed heading · Topic match: Cost allocation
PJM has not adequately explained how a fixed allocation continues to reflect cost causation when the load on which it was based materially changes or fails to materialize.Read this passage Filed comments: Cost allocation
C. The RBP improperly concentrates the incremental costs of RBP Resources on RBP
printed heading · Topic match: Cost allocation
Those LSEs must fund applicable RBP Charges and support those obligations through PJM’s proposed collateral requirements, while other market participants may receive lower capacity prices resulting from the same resources without bearing a corresponding share of those incremental costs.Read this passage Filed comments: Cost allocation
D. The RBP framework is not just and reasonable because it requires too many MW to
printed heading · Topic match: Cost allocation
Similarly, the RBP reduces other buyers’ obligations when a single buyer procures Qualifying RBP Offset UCAP MW, which creates a perverse incentive for buyers willing to risk assignment of the RBP Charges to do nothing with the hope that other RBP buyers enter bilateral arrangements and reduce the…Read this passage Filed comments: Cost allocation
E. The RBP is not just and reasonable because it relies on load forecasts that were
printed heading · Topic match: Cost allocation
The RBP is not just and reasonable because it relies on load forecasts that were prepared without knowledge or consideration of PJM’s newly proposed RBP paradigm.Read this passage Filed comments: Cost allocation
F. The RBP’s collateral requirements on RBP buyers are unjust and unreasonable
printed heading · Topic match: Credit and exit
Kelly testifies that PJM’s Tariff provision “permit[s]” reductions to the RBP credit rate when “changes in the underlying RBP commitment portfolio demonstrate that previously required collateral exceeds the remaining expected payment exposure.”73 According to the proposed Tariff, “the RBP Credit…Read this passage Filed comments: Credit and exit
III. STAKEHOLDER PROCESS
printed heading · Topic match: Reliability and curtailment
ER26-3515 (the Interim Resource Adequacy Service or “IRAS”).Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading · Topic match: Credit and exit
CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the Commission reject the RBP Filing.Read this passage Filed comments: Credit and exit
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 21st day of August, 2026. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.comRead this passage