Affidavit of Cosica_NOVEC Protest ER26-3380
Text extracted from the eLibrary original (SHA-256 38dd2039ada5930c…). Download the original from the official source.
Contents · 16 sections
- I. QUALIFICATIONS AND ASSIGNMENT
- II. SUMMARY OF OPINIONS
- III. THE COOPERATIVE, THE ZONE, AND THE OBLIGATION
- IV. THE ALLOCATION IS DERIVED FROM A PLANNING SUBMISSION
- V. PJM ALREADY MEASURES THIS COUNTERPARTY
- VI. THE CONSTRUCT ADDRESSES ONE RISK AND PJM DESCRIBED ANOTHER
- VII. THE EXPOSURE CAN BE MEASURED
- A. The instrument is a contract for differences
- B. The exposure that can be measured
- C. Assumptions stated
- D. The full term
- VIII. THE OPT-OUT WAS WRITTEN FOR THIS COOPERATIVE AND EXCLUDES IT
- IX. WHO BEARS THE OBLIGATION
- X. THE REQUIREMENT CANNOT BE MET
- XI. THE CONSEQUENCE IS NOT CONFINED TO THE COOPERATIVE
- XII. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
I. QUALIFICATIONS AND ASSIGNMENT
printed heading · Topic match: Credit and exit
Based on that experience I am familiar with how collateral requirements in the organized markets are derived from measured exposure, administered as that exposure changes, and released as it declines.Read this passage Filed comments: Credit and exit
II. SUMMARY OF OPINIONS
printed heading · Topic match: Credit and exit
PJM has sized collateral for a fixed-price contract and filed a contract for differences. 8. (b) The exposure can be measured.Read this passage Filed comments: Credit and exit
III. THE COOPERATIVE, THE ZONE, AND THE OBLIGATION
printed heading · Topic match: Credit and exit
The obligation is a function of what is projected to be built in the territory, not of the entity that must pay for it. 19.Read this passage Filed comments: Credit and exit
IV. THE ALLOCATION IS DERIVED FROM A PLANNING SUBMISSION
printed heading · Topic match: Credit and exit
No participant in that process was told, and none could have known, that the figures submitted would be used to allocate a collateral obligation.Read this passage Filed comments: Credit and exit
V. PJM ALREADY MEASURES THIS COUNTERPARTY
printed heading · Topic match: Credit and exit
Under Attachment Q, PJM measures the cooperative's credit exposure continuously through Peak Market Activity, calculated on actual observed billings, and adjusts the collateral required as that measurement changes.Read this passage Filed comments: Credit and exit
VI. THE CONSTRUCT ADDRESSES ONE RISK AND PJM DESCRIBED ANOTHER
printed heading · Topic match: Cost allocation
The first is counterparty credit risk: that a Load Serving Entity fails to pay the RBP Charge.Read this passage Filed comments: Cost allocation
VII. THE EXPOSURE CAN BE MEASURED
printed heading
VII.Read this passage
A. The instrument is a contract for differences
printed heading · Topic match: Credit and exit
Where RPM clears close to the RBP price the difference approaches zero while the collateral does not move.Read this passage Filed comments: Credit and exit
B. The exposure that can be measured
printed heading · Topic match: Credit and exit
A collateral requirement is ordinarily derived from an identified position, a price at which that position would be replaced, and a period over which the exposure is held before replacement is complete.Read this passage Filed comments: Credit and exit
C. Assumptions stated
printed heading · Topic match: Credit and exit
I adopt it because it is the only period for which the record supplies prices that are established or will be established before any collateral is due.Read this passage Filed comments: Credit and exit
D. The full term
printed heading · Topic match: Credit and exit
RPM, Delivery Years 2030/31–2042/43 13-year exposure Lifetime exposure Collateral as multiple $550.00 — Net CONE-based cap, PJM estimate $30.9M $246M 8.0× $500.00 $339.9M $555M 3.5× $450.00 $649.0M $864M 2.3× $400.00 $958.0M $1,173M 1.7× $350.00 $1,267.1M $1,482M 1.3× $325.00 — collared level…Read this passage Filed comments: Credit and exit
VIII. THE OPT-OUT WAS WRITTEN FOR THIS COOPERATIVE AND EXCLUDES IT
printed heading
THE OPT-OUT WAS WRITTEN FOR THIS COOPERATIVE AND EXCLUDES IT 52.Read this passage
IX. WHO BEARS THE OBLIGATION
printed heading · Topic match: Credit and exit
A collateral obligation of approximately $1.954 billion is 2.4 times all patronage capital on the books, and equal to some 109 years of capital credit retirements at the 2025 rate.Read this passage Filed comments: Credit and exit
X. THE REQUIREMENT CANNOT BE MET
printed heading · Topic match: Credit and exit
Measure (December 31, 2025) Amount Collateral as multiple Cash and temporary investments $243.2M 8.0× Total current and accrued assets $575.4M 3.4× Total long-term debt $69.2M 28× Total margins and equities $919.7M 2.12× Net utility plant $983.6M 2.0× Total assets $1,716.5M 1.14× Cash collateral…Read this passage Filed comments: Credit and exit
XI. THE CONSEQUENCE IS NOT CONFINED TO THE COOPERATIVE
printed heading · Topic match: Credit and exit
Section 18.9(a) provides that a defaulted RBP Charge is socialized pro rata across the remaining Load Serving Entities.Read this passage Filed comments: Credit and exit
XII. CONCLUSION
printed heading · Topic match: Credit and exit
PJM took the gross contractual value of a fifteen-year commitment, halved it, and called the result collateral.Read this passage Filed comments: Credit and exit