ER26-3380-000 · 2026-08-21 · Northern Virginia Electric Cooperative, Inc.
Protest of Northern Virginia Electric Cooperative, Inc. to the PJM Reliability Backstop Procurement Proposal
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
)
PROTEST OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric Cooperative, Inc. (“NOVEC”) respectfully submits this protest to aspects of the July 31, 2026, filing by PJM Interconnection, L.L.C. (“PJM”) to revise its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).2 For the reasons set forth herein, the Commission should reject the RBP as unjust and unreasonable. If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, and to eliminate the resulting subsidization of the PJM capacity market by NOVEC and a relatively small number of the other Load Serving Entities (“LSEs”) that would be primarily responsible for providing financial security for the contracts that PJM would enter into with RBP Resources.
I. INTRODUCTION
NOVEC recognizes the importance of bringing online more new capacity quickly to ensure system reliability and the fair assignment of associated costs. Even before the recent
1 18 C.F.R. § 385.211. NOVEC filed a doc-less motion to intervene in this proceeding on August 10, 2026. NOVEC, (doc-less) Motion to Intervene, Docket No. ER26-3380-000 (Aug 10, 2026) (Accession No. 20260810-5101).2 PJM Interconnection, L.L.C., Reliability Backstop Procurement, Docket No. ER26-3380-000 (July 31, 2026) (Accession No. 20260731-5214) (“RBP Proposal”).
PDF page 2
2
exponential nationwide expansion of data centers and other large loads, significant numbers of data centers had already been locating in NOVEC’s service territory.
NOVEC has a longstanding practice of taking steps to appropriately assign costs to large- load customers. NOVEC developed and received state regulatory approval for, and then began utilizing, a data-center-specific rate class that has been in place since the 1990’s. Additionally, NOVEC has directly assigned more than $1.7 billion in costs directly to data-center customers to help ensure they pay upfront for their dedicated substations and other infrastructure. NOVEC is also concerned about supply-demand imbalances and the resulting cost increases impacting customers large and small throughout the region.
As a result, NOVEC was encouraged by, and participated in, the PJM stakeholder process that utilized PJM’s Critical Issue Fast Path (“CIFP”) to address the issue of large-load additions. That stakeholder process successfully culminated in a coalition proposal that received more than two-thirds member endorsement in a sector-weighted vote. That consensus proposal “would have created greater stability and certainty while shielding homes and businesses from bearing the costs of serving large loads.”3 The coalition proposal was a bottom-up structure that relied on a voluntary subscription model to maintain LSEs’ authority to negotiate with large-load customers and only take on obligations for which it had signed contracts or otherwise secured a pathway for directly assigning the resulting costs to the data center causing the costs. Despite the strong stakeholder support, PJM rejected the consensus proposal and instead filed its RBP Proposal, a top-down approach that is fundamentally flawed and was not fully vetted through the stakeholder process. Notably, the details and full implications of the mandatory credit and collateral requirements were never explained.
3 East Kentucky Power Cooperative, Letter of EKPC President and CEO Don Mosier, Docket No. ER26-3380-000, at 2 (filed Aug. 11, 2026) (Accession No. 20260811-4003) (“EKPC Letter”).
PDF page 3
3
The as-filed RBP Proposal is not just and reasonable. The accelerated schedule prevents the RBP from achieving the aims of mutually agreed-upon cost-causation principles. The cost allocation of the RBP violates the Commission’s cost-causation principle because it does not recognize that neither load growth of large-load customers, nor load growth in general, are the sole cause of the capacity shortfall. PJM’s proposal is also not just or reasonable because it unreasonably causes entities like NOVEC to secure and subsidize the capacity market as RBP buyers. Although the RBP allows RBP buyers to offset their obligations, the time allotted to do so is unreasonably short and the RBP requires that customers procure more MWs than they would otherwise be responsible for, design choices that should be rejected. Having put this burden on NOVEC and other RBP buyers, PJM is also proposing to impose collateral requirements on them that are excessive, onerous, and not commensurate with the actual RBP Charges that need to be collateralized.
The Commission should reject the filing as unjust and unreasonable. If the Commission does not reject the filing, it should accept PJM’s invitation4 to require changes to the RBP to rectify the flaws discussed below, including extending the effective date to allow for the RBP to have a chance of success, revising the cost-allocation structure to recognize the benefits derived from RBP Resources by non-RBP buyers, adjusting the amount of MWs needed to offset RBP cost responsibility, requiring additional paths to mitigation, and reducing the collateral requirements as discussed below. At a minimum, the Commission should issue a deficiency letter and require PJM to better explain both its rejection of the coalition proposal and clarify PJM’s as-filed RBP design.
4 RBP Proposal at 3 (“…PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”) (internal citation omitted).
PDF page 4
4
II. PROTEST
A. There is a material mismatch in the timing required by PJM’s proposed RBP
obligation and the decisions of state regulators on allocation process requirements as PJM laid them out prior to the auction.
Recognizing that the justness and reasonableness of the RBP hinges on the ability of the LSEs to directly assign the RBP costs imposed on them to large loads that the LSEs serve, PJM states that the success of the RBP relies on state participation to “refine, for purposes of cost allocation, which retail loads — including which ‘large loads,’ as each state defines such loads
— should be allocated the costs of resources procured through the RBP.”5 The success, then, of the RBP relies on the coordination of a multidimensional amalgam of state regulatory commissions, legislatures, governors, local governments, and utilities across thirteen states and the District of Columbia. Notwithstanding that Herculean challenge, PJM plans for the procurement phase of the RBP to conclude less than six weeks from today’s comment date (specifically, within three weeks of September 30, 2026).6 In principle, NOVEC supports PJM’s efforts to quickly address its lack of capacity and the allocation of costs, as appropriate, directly to large loads but is concerned that the pace of the RBP process as PJM has proposed it will not afford NOVEC and others the necessary time for either RBP-obligation mitigation or completion of necessary regulatory proceedings to assign costs fairly and accurately to the cost-causing customers, to develop customer-level allocation rules, to make necessary modifications to billing and settlement processes, to address phased, delayed, reduced, or canceled load, and to implement appropriate audit and control procedures for substantial obligations lasting up to 15
5 RBP Proposal at 11 (citing Statement of Principles Regarding PJM, National Energy Dominance Council, at 2 (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ Principles”)).6 RBP Proposal at 3, n.5 (“To the extent the RBP framework is accepted by September 29, 2026, and absent significant revisions or developments, PJM intends to open the procurement window on September 30, 2026.”); id., Attachment A at § 18.4 (“The Reliability Backstop Procurement offer submission window for RBP Sell Offers shall open for three weeks in 2026.”).
PDF page 5
5
years. NOVEC is a prime example of this conundrum because its nature, as a not-for-profit electric cooperative, is to set up allocations before assuming obligations, but PJM is mandating that it assume a large obligation that it has no way to opt out of.
PJM’s timeline raises additional concerns that adversely affect the market. The success of the RBP depends on generators offering in sufficient quantities and at competitive prices. With only three weeks to make informed decisions based on the final, effective version of the RBP, some participants may not be able to prepare offers in time to participate. Indeed, PJM has requested FERC approval by September 29 so it can begin the RBP auction on September 30, which means that participants are expected to make decisions with impacts that last the better part of two decades in a span of a few weeks and without knowing what the actual rules or approved state regulator allocations will be. The companies with the wherewithal to prepare offers on an expedited basis and accept the uncertainty risk are likely to be staffed sufficiently to gamble on whatever the RBP might turn out to be without detracting from their established sources of revenue and have significant market share of PJM’s existing generation. From the customer’s perspective, there is a risk that a paucity of true competition will result in much of the RBP Resources receiving guaranteed payments at the cap of $555/MW-day when, if more time were afforded, more participants might think through ways to offer at lower rates and still be profitable. Not many developers will have proposed generation sitting on the shelf ready to deploy into the RBP auction within such a short window. PJM’s expedited process thus risks unnecessarily increasing costs on the customers who will be supporting RBP Resources and undermines the purpose of the RBP.
The expedited process also effectively forecloses NOVEC’s ability to procure Qualifying RBP Offset UCAP MW. As PJM explains in the transmittal letter, Qualifying RBP Offset UCAP
PDF page 6
6
MW “is new capacity voluntarily brought on to the PJM system by new load… [and] [w]here Electric Distributors…report Qualifying RBP Offset UCAP MW to PJM with the requisite supporting evidence, PJM may reduce the region-wide Initial RBP Target by the quantity of Qualifying RBP Offset UCAP MW, where appropriate.”7 In addition to reducing the region-wide RBP Target, “the pro-rata allocation of RBP UCAP MW to each Electric Distributor’s zone/area, and the Final RBP Target, will be further adjusted to reflect reductions for Qualifying RBP Offset UCAP MW and UCAP MW representing successfully supported opt-outs from RBP in each zone/area.”8 Thus, RBP buyers can benefit in two ways from Qualifying Offset UCAP MW: by a reduction to the Initial Load Adjustment MW, and by reducing the Final RBP Target, thus reducing the pro-rata share of RBP UCAP MW from that Final RBP Target allocated to each Electric Distributor’s zone.
The ability to procure Qualifying RBP Offset UCAP MW is important to managing RBP costs for all RBP buyers, but particularly for NOVEC given the size of its obligation and the need to address the appropriate allocation and recovery of these new and substantial RBP costs from the cost-causing data centers. Despite that importance, RBP buyers have only the imminent and brief RBP bid-submission window in which to procure new generation.9 Just as supply-side participants are likely to encounter difficulties preparing offers for the RBP, NOVEC and other buyers will experience difficulty securing new generation by the third week of October. PJM’s proposed schedule provides RBP buyers an exceptionally limited period to identify and procure qualifying capacity. The result is an offset mechanism that may exist under the Tariff but cannot reasonably be utilized at the scale required.
7 RBP Proposal at 35.8 Id., Attachment C, Affidavit of Ms. Danielle Croop at P 44 (“Croop Affidavit”).9 See RBP Proposal, Attachment A at § 18.2(c).
PDF page 7
7
NOVEC in particular is prejudiced because the Initial Load Adjustment MW that it would need to offset to eliminate its obligation in the RBP auction is so high (1,619.2 MW) that NOVEC is unlikely to be able to secure bilateral contracts with new generators for anything approaching that amount. The only other Electric Distributor who exceeds NOVEC’s initial allocation is in a retail-choice state where the LSEs it serves take on the obligation.10 As a rural, not-for-profit cooperative and a transmission-dependent distribution utility, NOVEC faces a procurement challenge that is unusual both in magnitude and structure. A prudent procurement of more than 1,600 MW cannot reasonably be completed within the period PJM proposes. A procurement of this magnitude would likely require multiple counterparties and transactions, each involving counterparty and credit diligence, commercial and risk analysis, contract negotiations, internal approvals, and potentially regulatory review. A conventional physical bilateral capacity transaction may require approximately two to four months once qualifying capacity has been identified, while more complex structured transactions, including power purchase agreements or tolling arrangements, may require four to twelve months or more to negotiate. PJM’s proposed schedule does not provide a commercially reasonable opportunity to undertake those activities, particularly for an Electric Distributor seeking capacity on the scale required here.
The compressed procurement period is especially problematic because the universe of resources capable of qualifying as RBP offsets is itself constrained. The applicable qualification window limits the capacity that can serve as an offset, and PJM’s schedule provides no realistic opportunity to develop new generation specifically for that purpose. RBP buyers therefore are not entering an unrestricted capacity market with sufficient time to develop alternatives. They are
10 RBP Proposal, Attachment C, Croop Affidavit at P 46.
PDF page 8
8
competing within a limited pool of qualifying resources under an unusually compressed deadline.
The consequences of the compressed schedule extend beyond NOVEC. It is worth noting that NOVEC will not be the only Electric Distributor harmed by the constraints on NOVEC’s ability to assess and obtain Qualifying RBP Offset UCAP MW. In her affidavit, Ms. Croop walks through an example that shows how one Electric Distributor obtaining Qualifying RBP Offset UCAP MW reduces the final allocation of RBP UCAP MW for all RBP buyers.11 That is, when one RBP buyers procures some Qualifying RBP Offset UCAP MW, that act also reduces the final amount of RBP MW allocated to other RBP buyers as well.12 Thus, an Electric Distributor’s ability to obtain qualifying offsets affects the residual RBP allocation borne by other RBP buyers. PJM’s compressed timetable therefore does not merely impair an individual participant’s opportunity to mitigate its own costs. It can affect the ultimate allocation of RBP obligations across multiple participants.
NOVEC is also concerned that, given the limited timeframe to choose between
participating in the RBP auction or signing a bilateral contract, the compressed schedule and limited pool of qualifying resources may materially disadvantage RBP buyers in bilateral negotiations. Potential counterparties will know that RBP buyers face a fixed and imminent deadline to obtain qualifying capacity and that the alternative is exposure to an RBP allocation. Those circumstances reduce the ability of RBP buyers to solicit competing offers, develop alternative transaction structures, and negotiate from a commercially reasonable position,
11 Id. PP 47-50.12 This is because, per the example in Croop’s affidavit, when an Electric Distributor procures generation to be Qualifying RBP Offset UCAP MW, it reduces both the MW load adjustment column and the Final Allocation of RBP UCAP MW column such that all Electric Distributor areas are allocated fewer RBP MWs. In Croop’s example, ODEC procuring 130 MW entitles them to 122.2 MW, but also reduces (in combination with REC’s 673.8 MW) NOVEC’s allocation to 1,271.6 MW from 1,302.6 MW. See id., Attachment C, Croop Affidavit at PP 47-50.
PDF page 9
9
potentially resulting in higher bilateral prices or less favorable contractual terms. PJM cannot reasonably rely on Qualifying RBP Offset UCAP MW as a meaningful mechanism for mitigating RBP obligations while establishing a schedule that prevents affected Electric Distributors from having a commercially reasonable opportunity to use that mechanism. The problem is particularly acute where, as here, PJM proposes to impose substantial long-term financial obligations based, in part, on whether an Electric Distributor succeeds in procuring qualifying offsets during this abbreviated period.
The Commission should therefore reject PJM’s proposed implementation schedule or require PJM to provide RBP buyers sufficient time to conduct a commercially reasonable procurement of Qualifying RBP Offset UCAP MW before their final RBP obligations are established. At a minimum, the schedule should provide no less than four months for conventional bilateral capacity transactions after the universe of qualifying resources and applicable offset requirements are sufficiently known, with additional time where structured transactions are necessary. Without such an opportunity, the offset mechanism does not provide a meaningful means of mitigating RBP exposure, and PJM’s resulting allocation may reflect the constraints of its accelerated implementation schedule rather than the amount of capacity RBP buyers reasonably could procure.
B. The RBP violates the Commission’s cost-causation principle because it does not recognize the structural causes of the capacity shortfall beyond load growth and improperly assigns all RBP costs based only on projected load growth of large-load customers.
Section 205 requires rates to be just and reasonable.13 That standard incorporates “a ‘cost- causation principle’—the rates charged for electricity should reflect the costs of providing it.”1413 16 U.S.C. § 824d(a).14 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018).
PDF page 10
10
The cost-causation principle “add[s] flesh to the[] bare statutory bones” of the just and reasonable standard.15 But while cost allocation is not a matter for the “slide-rule”16 and does not require “exacting precision,”17 the cost-causation principle does require the Commission to have “an articulable and plausible reason” to believe that the benefits are roughly commensurate with the costs.18 A rate that assigns all the costs to a cause only partly responsible for the costs does not satisfy the cost-causation principle because as a “kind of equity,” the principle matches burden with benefit.19
The RBP violates the Commission’s cost-causation principle because it assigns the costs of the RBP Charge and the collateral requirements to one cause without recognition of other significant causes of the capacity shortfall, and because it results in an improper subsidy of PJM’s Reliability Pricing Model (“RPM”) auction by RBP buyers for the benefit of other Market Participants that are not RBP buyers.
The RBP process is a one-time mechanism designed to address resource-adequacy challenges arising from the capacity shortfall that occurred in the 2028/2029 Base Residual Auction (“BRA”).20 Ms. Croop explains that the “RBP will function as a safety net to address the shortfall MW from the 2028/2029 BRA that has not been addressed by new load bringing their own new capacity through bilateral agreements or otherwise.”21
The RBP attributes the shortfall to load growth.22 PJM argues that, despite the addition of 1,294.4 MW ICAP between the 2027/2028 and 2028/2029 BRA, the shortfall has grown.2315 K N Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).16 United Distribution Cos. v. FERC, 88 F.3d 1105, 1167 (D.C. Cir. 1996). 17 Coalition of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1017 (D.C. Cir. 2022).18 Illinois Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).19 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).20 RBP Proposal at 25-26.21 Id., Attachment C, Croop Affidavit at P 5.22 RBP Proposal at 6-7.23 Id.
PDF page 11
11
PJM’s proposed RBP cost-allocation mechanism assigns costs only to those Electric Distribution zones where load growth is forecasted, as measured by load adjustments between 2026 and 2028.24 This allocation is particularly problematic because it remains fixed for the entire 15-year RBP commitment term. If forecasted large load is delayed, reduced, canceled, or never materialized, the RBP obligation assigned based on that forecast could remain with the Electric Distributor and ultimately be borne by its remaining retail customers. PJM has not adequately explained how a fixed allocation continues to reflect cost causation when the load on which it was based materially changes or fails to materialize.
A central flaw of this paradigm is that the shortfall’s cause is not solely large-load customer growth. Even PJM recognizes that “it is well-documented and recognized that supply and demand in the PJM Region have converged, as a significant portion of PJM’s thermal generation fleet have retired while replacement resources are arriving at a slower pace….”25 PJM acknowledges that: “Together, these factors have strained the RPM Auction’s ability to procure sufficient capacity to meet the PJM Region Reliability Requirement in recent capacity auctions.”26 Thus, as PJM itself explains, the shortfall in the capacity market arose not only from large-load growth but also from a reduction in supply and the inability to bring new generation online.
Those retirements did not occur in a vacuum, nor did they occur suddenly. Many of them were precipitated by the policies of states whose Electric Distributors will not be bearing costs associated with the RBP as PJM has proposed it. The reduction in supply is a PJM-wide phenomenon that PJM had been warning stakeholders and the Commission about long before the
24 RBP Proposal, Attachment C, Croop Affidavit at PP 41, 43.
25 RBP Proposal at 28.
26 Id. (emphasis added).
PDF page 12
12
unexpected surge in load growth. As early as PJM’s February 24, 2023, report Energy Transition in PJM: Resource Retirements, Replacements & Risks, PJM noted that significant amounts of generation had retired and was slated to retire.27 Between 2012 and 2022, 47.2 GW ICAP retired.28 Figure 1 of the 4R Report highlights that PJM was projecting 40 GW of retirements by 2030, composed of “12 GW of announced retirements, 25 GW of potential policy-driven retirements and 3 GW of potential economic retirements. Combined, this represents 21% of PJM’s current installed capacity.”29 The Independent Market Monitor for PJM echoed those concerns in its 2023 State of the Market Report for PJM, commenting that “an estimated total of between 24,000 MW and 58,000 MW of thermal resources are at risk of retirement, including 4,285 MW of announced retirements, 19,635 MW of retirements as a result of state and federal environmental regulations, and 33,744 MW of retirements for economic reasons, based on expected forward prices.”30 So PJM’s recognition 1,294.4 MW ICAP added between the 2027/2028 and 2028/2029 BRA fails to also recognize the removal of 47,200 MW ICAP over a little more than the past decade.
The renewables that replaced the retiring thermal generation could replace the energy, but not the capacity, and the interconnection queue could not proceed efficiently enough to bring new generation online.31 The shortfall is, to a significant degree, as much the product of state policy choices as it is large-load growth. As Commissioner Christie articulated in the transmission context:
27 Energy Transition in PJM: Resource Retirements, Replacements & Risks at 6-7 (dated Feb. 24, 2023) (Available at: https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/energy-transition-in-pjm- resource-retirements-replacements-and-risks.ashx) (“4R Report”).28 Id. at 6.29 Id. at 5 (internal citations omitted).30 IMM, 2023 State of the Market Report for PJM Volume I at 1 (March 14, 2024) (https://www.monitoringanalytics.com/reports/pjm_state_of_the_market/2023.shtml) (“2023 State of the Market”).31 Id. at 2.
PDF page 13
13
Let me emphasize that the State of Maryland, within its sovereign police
powers, clearly has the authority to mandate any particular mix of
generating resources it prefers. Maryland's new climate law is well within
its inherent authority to enact. Such policies are for Marylanders to choose, not RTOs or FERC. But if the resulting transmission projects under protest
in this RTEP filing are caused more by Maryland's policy choices than by
organic load growth and economic resource retirements, then a salient
question that may be asked is whether these transmission projects are more
accurately categorized as public policy projects, essentially the same as the transmission upgrades caused by New Jersey's offshore wind projects?
And if they are more accurately categorized as public policy projects,
should such projects be regionally cost-allocated, potentially to consumers
in Pennsylvania, West Virginia, Ohio, et al.? For example, the State of
Illinois has a law similar to Maryland's that PJM has already estimated will cause $2 billion in transmission upgrades, costs that will be allocated to
consumers in other states under PJM's existing cost-allocation formula.32
It is an equally salient question as to how the RBP is just and reasonable when it attributes, contrary to even PJM’s admission, all the costs associated with the shortfall to large-load growth during a PJM-wide phenomenon of supply constriction.
The RBP is not just and reasonable because it does not match cost and causation. Large- load growth is a cause, certainly, but not the only cause. The truth is that causation also is attributable to the diffuse effect of state environmental policies and the interconnection queue. The fact that the problem ballooned to this extent is because of the fundamental dysfunction of the PJM RPM, which has been unable to respond effectively to either an increase in demand or a decrease in supply. Although characterized as a reaction to load growth, the RBP is, in reality, another iteration of the “perpetual tweaking”33 needed to keep the PJM RPM wheezing along, in the same tradition as the Minimum Offer Price Rule34 and the price collar.3532 PJM Interconnection, L.L.C., 185 FERC ¶ 61,107, PP 7-8 (2023) (Christie, Comm’r, concurring).33 Mark C. Christie, It’s Time to Reconsider Single-Clearing Price Mechanisms in U.S. Energy Markets, 44 Energy L.J. 1, 26 (2023).34 Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236 (2018).35 PJM Interconnection, L.L.C., 191 FERC ¶ 61,066 (2025).
PDF page 14
14
PJM has acknowledged that the RPM is ill-suited for it purpose, and indeed has not allowed the RPM to work as it’s designed. Rather than allow the RPM to clear at a price intended to spur the entry of new generation, PJM entered a settlement agreement to “cap [] power plant capacity prices.”36 Mr. Mosier is correct that suppressing the market signals to enter the market undermines investor confidence in the markets – “credibility trap” is PJM’s phrase for it.37 There is also likely merit to his assertion that “the ability to obtain 15-year price certainty in a backstop procurement likely chilled new entry in PJM’s most recent capacity auction.”38 NOVEC should also point out that there is a mechanism in the PJM RPM -- the Reliability Backstop Auction -- specifically to address consecutive capacity shortfalls which PJM is also preempting in favor of yet another temporary “fix.”39
If NOVEC (or others) cannot assign these costs directly to large loads, then the results should be viewed through the lens of whether the actual cost allocation is just and reasonable, and not whether a hypothetical allocation occurred. Viewed through that lens, the proposal does not satisfy the cost-causation principle because it does not match even one iota of the burden of the shortfall to the rest of PJM, notwithstanding the policy-driven retirements of generation that contributed to the shortfall. Unless the Commission revises the effective date or PJM voluntarily agrees to, the Commission should reject the RBP as a violation of the cost-causation principle.
36 EKPC Letter at 2.37 PJM, Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment to Support Durable Reliability at 5-6 (May 6, 2026) (https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf).38 EKPC Letter at 2.39 RBP Proposal at 123-125.
PDF page 15
15
C. The RBP improperly concentrates the incremental costs of RBP Resources on RBP buyers while allowing the resulting capacity-market benefits to accrue more
broadly.
PJM’s proposed RBP framework does not adequately account for the market-wide benefits that RBP Resources may provide. RBP buyers would bear the incremental RBP Charges and associated credit obligations attributable to the RBP Resources allocated to them. Yet those resources would participate in the same RPM Auctions that establish capacity prices paid by load throughout the relevant capacity market. To the extent RBP Resources increase available supply and reduce RPM clearing prices, those benefits are not confined to the LSEs assigned RBP cost responsibility. They accrue to other capacity purchasers as well.
The RBP framework requires RBP Resources to offer their committed capacity into the RPM Auctions as price takers at $0. PJM explains that this requirement is appropriate because the RBP Resources are already being paid for by the responsible LSEs and because it ensures that an RBP Resource clears the RPM Auction, thereby avoiding the potential for load to pay twice for the same capacity. NOVEC does not dispute the objective of preventing duplicative payment obligations, but PJM’s solution has an important cost-allocation consequence that its proposal does not adequately address requiring RBP-supported capacity to offer at $0 can affect RPM clearing outcomes for market participants that bear no corresponding share of the incremental RBP costs. The significance of that requirement follows from the operation of RPM. Adding RBP Resources at a mandatory $0 offer increases the quantity of capacity offered at the bottom of the supply curve. Depending on market conditions, locational constraints, and the position of the marginal resource, those offers can reduce the RPM clearing price that otherwise would have resulted. Where that occurs, the resulting reduction in capacity prices benefits capacity purchasers generally, not merely the RBP buyers that financially support the RBP Resources.
PDF page 16
16
The incremental financial obligations associated with those resources, however, remain concentrated on the LSEs assigned RBP cost responsibility. Those LSEs must fund applicable RBP Charges and support those obligations through PJM’s proposed collateral requirements, while other market participants may receive lower capacity prices resulting from the same resources without bearing a corresponding share of those incremental costs.
The RBP’s contract-for-differences settlement structure compounds this mismatch. RBP Resources receive RPM revenues that offset their RBP commitment payments. If the mandatory $0 offers of RBP Resources contribute to a lower RPM clearing price, those resources receive less RPM revenue and the corresponding RBP settlement obligation increases. RBP buyers therefore may bear a larger RBP Charge at the same time that the lower RPM price produces savings for capacity purchasers more broadly. In that circumstance, the same market effect that benefits non- RBP buyers increases the incremental obligation imposed on RBP buyers.
This allocation raises concerns under the Commission’s cost-causation principles. Although cost allocation need not correspond precisely to benefits received, the Commission has required costs to bear a reasonable relationship to the burdens imposed and benefits received and has recognized that substantial departures from that principle can create inappropriate cross- subsidization. PJM has not adequately demonstrated why the incremental costs and substantial credit obligations associated with RBP Resources should be concentrated on designated RBP buyers without accounting for material capacity-market benefits those resources may provide to other PJM load.
At a minimum, the Commission should require PJM to demonstrate that its proposed allocation of RBP costs is roughly commensurate with the benefits attributable to the RBP Resources. If PJM’s mandatory $0 offer requirement produces material market-wide capacity-
PDF page 17
17
price benefits, PJM should explain why those benefits do not warrant broader allocation of at least some portion of the incremental RBP costs or another mechanism that recognizes the value received by non-RBP buyers.
The potential effect of such offers on RPM clearing prices is not merely theoretical. In considering the operation of PJM’s capacity market in another context, the Third Circuit recognized that artificially low capacity offers can “crowd out other capacity that is priced at a higher, cost-based rate” and thereby produce a lower clearing price.40 NOVEC does not contend that RBP Resources are similarly situated to the state-supported resources at issue in New Jersey BPU. The relevant point is narrower: PJM’s requirement that RBP Resources offer at $0 can affect the RPM clearing price, and any resulting price reduction benefits capacity purchasers beyond the LSEs required to bear the incremental costs of supporting those resources.
D. The RBP framework is not just and reasonable because it requires too many MW to offset the RBP Target and encourages free riding.
The RBP framework is unjust and unreasonable because the Qualifying RBP Offset UCAP MW to offset each Electric Distributor’s zone is too high relative to their pro rata share of the Initial RBP Target. The initial allocation of the RBP UCAP MW is based on each Electric Distributor’s zone’s share of the Initial RBP Target of 6,831.3 MW.41 NOVEC, for example, is assigned 1,302.6 MW.42 Even though NOVEC’s “share” of the shortfall is 1,302.6 MW, PJM’s proposal would require NOVEC to procure approximately 1,619 MW to fully offset 1,302.6 MW.43 If the Initial RBP Target of 6,831.3 MW is the goal to offset, it is unjust and unreasonable to force RBP buyers to procure an excess of that target MW amount. The excess MW provide
40 New Jersey Board of Public Utilities v. FERC, 744 F.3d 74, 85 (3d Cir. 2014).41 RBP Proposal, Attachment C, Croop Affidavit at P 46.42 Id.43 Id. P 47 (“Note: The qualifying RBP Offset UCAP MW is represented by load*FPR for the 2028/2029 BRA (0.9401). This is representative of the self-supply obligation.”).
PDF page 18
18
additional value to the PJM capacity market for which the RBP buyer is not compensated. Similarly, the RBP reduces other buyers’ obligations when a single buyer procures Qualifying RBP Offset UCAP MW, which creates a perverse incentive for buyers willing to risk assignment of the RBP Charges to do nothing with the hope that other RBP buyers enter bilateral arrangements and reduce the Final RBP Target.
E. The RBP is not just and reasonable because it relies on load forecasts that were prepared without knowledge or consideration of PJM’s newly proposed RBP
paradigm.
The RBP is intended to address the shortfall that occurred in the 2028/2029 BRA, but it assigns responsibility to that shortfall using the load adjustments from 2026 to 2028 submitted by LSEs. NOVEC has reservations about the use of the load adjustments “to ultimately determine the initial allocated pro-rata share to each relevant Electric Distributor zone/area.”44 PJM has not explained why this snapshot in time is appropriate beyond references to Schedule 8 of the RAA, which does not suffice.45 The load adjustments set forth in PJM Table B9b from the 2026 PJM Load Forecast are something of a black box.46
The problem with relying on the load adjustments is, even if they are “firm,” all the load indicated interest based on economic circumstances that no longer exist.47 The RBP will raise costs of data center loads, which will either prompt marginal data center projects to withdraw or cause data centers to relocate to areas that are not assessed RBP Charges so that they can avoid these additional costs. If loads had known about the RBP, their plans would be different, they
44 RBP Proposal, Attachment C, Croop Affidavit at P 43.45 Id.46 2026 PJM Load Forecast Report Data Tables, PJM Interconnection, L.L.C., Tab Table B9b (Feb. 2026), https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx [https://perma.cc/SST2-EGUZ]; 2026 PJM Load Forecast Report, PJM Interconnection, L.L.C., 5-6 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf [https://perma.cc/J24E-7CV7] (describing Table B9b results).47 See Coscia Affidavit at P 22 (explaining that no participant in the load forecast process knew that the figures would be used in an RBP process).
PDF page 19
19
would have made different representations to their LSEs, and the load adjustments would be different. As a consequence of the increased costs, PJM will reduce the actual load that materializes. In order to account for this effect, the Commission should either reject the filing or reduce the amount of RBP MWs that are allocated to NOVEC and other RBP buyers.
F. The RBP’s collateral requirements on RBP buyers are unjust and unreasonable because it is unduly burdensome, excessive, and has not been shown to be necessary.
PJM “is proposing to require that those LSEs allocated RBP cost responsibility for a given Delivery Year must post credit associated with such obligation.”48 PJM argues that this credit obligation is just and reasonable because “it is designed [to prevent] those LSEs not allocated cost responsibility for RBP Resources from having to pay for such resources” notwithstanding the benefit those LSEs derive from the new generation themselves.49 The RBP credit requirement “is a function of two inputs: the RBP Credit Rate and RBP UCAP MW committed.”50 The RBP UCAP MW input is the total amount of RBP UCAP MW committed through the RBP, as adjusted for resources that do not come online.51
PJM is proposing to set the RBP Credit Rate at $1.5 million per MW initially, but it can be reduced to reflect a reduction in the total RBP UCAP MW or when total posted RBP Collateral exceeds the total RBP Charges obligation.52 PJM states that it set the credit rate at $1.5 million based on an estimate of “the contractual value associated with a 1-MW RBP commitment using conservative assumptions, including a 15-year commitment term application of the RBP price throughout that commitment period.”53 Assuming the RBP clearing price is at the price cap of $555/MW-day, PJM estimated the contractual value of a 1-MW RBP commitment at $3.04
48 RBP Proposal at 114.49 Id. at 114 (emphasis in original).50 Id. at 115.51 Id. at 115-116.52 Id. at 116.53 Id., Attachment D, Affidavit of Ms. Gwen Kellyat P 25 (“Kelly Affidavit”).
PDF page 20
20
million.54 PJM then reduced the $3.04 million to $1.5 million so that PJM would hold “sufficient collateral to cover approximately 50% of the notional value of all RBP commitments….”55
As set forth in Mr. Rollins’ affidavit, NOVEC estimates that its collateral requirement under PJM’s proposed regime would be approximately $1.95 billion.56 The collateral requirement is an extraordinary imposition on NOVEC. Indeed, the collateral requirement exceeds NOVEC’s total assets.57 NOVEC is uncertain whether it would even be able to secure $2 billion in collateral.58 As Mr. Rollins explains, the collateral requirement will disrupt NOVEC’s ordinary business operations.59 The Commission should not approve a collateral requirement that is an impossibility, a hindrance to an entity’s ability to operate, and an injustice.
The need to reject or modify the collateral obligation is heightened by the calculation’s obvious defects. PJM “conservatively” requires the collateral obligation of the buyers to span the entire 15-year period.60 This expansive requirement simply is not necessary, as the risk could be significantly mitigated by a shorter period, such as three years. As Mr. Rollins discusses, the most significant obstacle to NOVEC fulfilling its RBP obligations is, ironically, the size of the RBP collateral obligation itself and not the RBP Charges.61 Indeed, PJM does not believe that a 15-year collateral obligation on sellers is appropriate, noting that it limited the sellers’ collateral obligation to three years to avoid making the collateral requirement “onerous.”62 NOVEC does not see why it is just and reasonable for buyers to suffer under what even PJM deems an
54 Id. P 25. 55 RBP Proposal at 116.56 Rollins Affidavit at 2.57 Id. at 3; see also Coscia Affidavit at PP 13, 58-61.58 Rollins Affidavit at 3.59 Id. at 3-4.60 See Coscia Affidavit at PP 48-50; id. P 51 (“The observation that matters is that the filed requirement exceeds the exposure at every path in the range.”).61 See generally Rollins Affidavit.62 RBP Proposal at 109-110.
PDF page 21
21
“onerous” requirement while sellers are limited to a three-year period – as if the potential impossibility of a $2-billion collateral obligation was not onerous enough.
Ms. Kelly states in her affidavit for PJM that the collateral requirement assumes that the RBP clearing price is at the price cap of $555/MW-day,63 and PJM sets forth the calculation as an “application of a simple formula based on the RBP Charge obligation over 15 years, i.e., the commitment term, and a conservative assumption that all RBP commitments are — on average
— at the maximum willingness to pay, i.e.,15 years * 365 days * $555/MW-Day =
$3,038,625.”64 There are two problems with this calculation. First, it assumes that the clearing prices of the RBP are $555/MW-day, which is not guaranteed — if the price clears lower than that, the proposed Tariff revisions still fix the RBP Credit Rate at $1.5 million, even though PJM’s own methodology could support a lower price.65
Second, the calculation assumes that the RBP buyers have to collateralize the entire $555/MW-day. In actuality, the RBP Charges will be the RBP clearing-price average (which can be less than $555/MW-day) net of revenues from the capacity auction.66 Effectively, RBP buyers are providing collateral to ensure that everyone in PJM pays the capacity costs associated with the RBP Resources. RBP buyers themselves already provide PJM collateral to ensure that they pay their capacity rates under Attachment Q, and so do all other capacity buyers.67 PJM is
63 Id., Attachment D, Kelly Affidavit at P 25. 64 RBP Proposal at 116-117; see also Coscia Affidavit at P 39.65 Coscia Affidavit at P 38 (“The RBP settles as a contract for differences. In each Delivery Year the cooperative pays the difference between the RBP price and the RPM clearing price for that year, multiplied by its allocated RBP UCAP MW. It does not pay the RBP price. Where RPM clears above the RBP price the payment runs in the opposite direction.”); id. P 46 (“If the RBP clears below $555.00 the exposure falls and the ratio of collateral to exposure rises, so this assumption is conservative against the conclusion I reach.”).66 Id. P 40 (“Because the Credit Rate makes no reference to RPM, the requirement bears no stable relationship to what the cooperative will owe. Where RPM clears close to the RBP price the difference approaches zero while the collateral does not move. Where RPM clears far below it the difference widens and the collateral is unchanged again. A requirement calibrated to exposure would vary with the second price; this one is fixed against the first.”).67 Id. P 26 (noting that PJM already holds collateral from NOVEC).
PDF page 22
22
requiring duplicative collateral — at the most, RBP buyers should only have to provide collateral for the incremental cost of the RBP clearing price above the weighted RPM clearing price for the relevant delivery year. That is the only cost that RBP buyers will actually have to pay, and thus the only payments that need to be collateralized.68
It is unnecessary to require that 50% of the total payments be held as collateral. Although PJM contends that this provides “commensurate” protection against non-payment,69 NOVEC has demonstrated that the actual RBP Charges will be less than $555/MW-day. The total amount held as collateral could exceed the ultimate payments made by the RBP buyers.70 The collateral amount should not exceed a level that is commensurate with actual RBP obligations. PJM asserts that to test the reasonableness of the $1.5 million per MW figure, PJM used a 9.5% discount rate developed by consultants from The Brattle Group based on the average weighted cost of capital for participants in the RPM.71 PJM’s reliance on calculations from a Brattle report does not substantiate PJM’s assertion that its figure is just and reasonable. For one, it was developed for another purpose and does not necessarily translate to a risk of non-payment. The figure is designed for ordinary generators, not generators who will have a guaranteed revenue stream for 15 years. Those generators face much lower risk and do not need as high a return.
The Tariff is ambiguous as to when the collateral obligation will be reduced and does not appear to properly reduce it over time. Ms. Kelly states that “PJM concluded that the remaining payment exposure naturally declines as remaining, forward RBP payment obligations are satisfied and as committed RBP Resources are removed from the portfolio through rescinded
68 Id. P 41 (“A collateral requirement is ordinarily derived from an identified position, a price at which that position would be replaced, and a period over which the exposure is held before replacement is complete.”).69 RBP Proposal, Attachment D, Kelly Affidavit at P 24.70 Indeed, Mr. Coscia shows that the collateral could be as much as 9 times the amount of exposure it is securing. Coscia Affidavit at P 49.71 RBP Proposal, Attachment D, Kelly Affidavit at PP 27-28.
PDF page 23
23
commitments or other changes affecting the remaining payment obligations.”72 PJM is vague about whether such reductions will occur — Ms. Kelly testifies that PJM’s Tariff provision “permit[s]” reductions to the RBP credit rate when “changes in the underlying RBP commitment portfolio demonstrate that previously required collateral exceeds the remaining expected payment exposure.”73 According to the proposed Tariff, “the RBP Credit Rate shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an amount sufficient to cover the total existing RBP Charges obligations….”74 It is not just and reasonable to grant PJM the discretion to determine whether RBP buyers should be required to post more collateral than the total existing RBP Charges obligations, especially given that their calculation already overstates the likely RBP Charges.
The circumstances in which the collateral obligation is reduced are too few. The RBP Credit Rate should be reduced to account for the remaining term over which RBP Charges will be paid. If 50% of the total RBP Charges is the standard (and it should be lower for the reasons discussed in prior paragraphs), then it should be 50% or less of the remaining RBP Charges in each year. If PJM believes that 50% of the total payment obligations at the start of the 15-year term is sufficient, then the same percentage of the total remaining payment obligations should be the cap for each year.
If the Commission does not reject the filing, then it should require revisions on compliance to reduce the collateral obligation so that it corresponds to the actual risk imposed on
72 RBP Proposal, Attachment D, Kelly Affidavit at P 29.73 Id. P 30. 74 RBP Proposal, Attachment A at § 18.8(b)(i)(A) (emphasis added).
PDF page 24
24
PJM’s markets. The Commission should require PJM to allow other methods to demonstrate creditworthiness besides posting the full collateral or a letter of credit. NOVEC maintains an investment-grade credit rating and has met its obligations to PJM. Given NOVEC’s investment- grade credit rating, financial condition, and established record of satisfying its PJM obligations, PJM should permit NOVEC to satisfy all or a substantial portion of the requirement through unsecured credit or another demonstration of creditworthiness rather than requiring cash collateral or a letter of credit for the full notional amount. If the Commission does not allow alternative demonstrations of creditworthiness, the Commission should correct PJM’s defective collateral calculations. The Commission should require the collateral calculation to reflect the actual clearing price of the RBP auction. Instead of providing for an “onerous” 15-year term, the Commission should limit the period collateralized to three years, just as PJM proposes to do for generators. Additionally, the Commission should also limit the collateral amount to the expected incremental amount between the RBP clearing price and the expected capacity-market revenue to avoid duplicative collateral requirements.
III. STAKEHOLDER PROCESS
Rather than attempt to salvage the RBP Proposal, the Commission should exercise its authority under NRG to implement the voluntary subscription model the stakeholders approved as part of the CIFP process. PJM’s CIFP process is intended to expedite resolution of issues critical to PJM. As such, while decisions from it are ultimately the Board’s to make, PJM members and other stakeholders play a key advisory role by signaling solutions they agree with through a four-stage proposal-development and voting process. Indeed, members have been criticized in past iterations of the CIFP for not coming to clear consensus. Members sent the Board a clear message in this CIFP by supporting one proposal from more than a dozen
PDF page 25
25
considered. That proposal included an interconnected package of reforms that were carefully balanced to address the issue while maintaining mitigation options for LSEs, all headlined by a version of the RBP auction that would have required LSEs to “subscribe” to obligations, i.e. they had control to mitigate their forecasted growth by committing to curtail it instead of accepting a capacity obligation and resulting costs. NOVEC supported that proposal and still does.
The Board clearly appreciated members’ message by adopting portions of the proposal that it found favorable but rejecting those it did not, including the key tool for LSEs to mitigate their potential obligations in the auction: the subscription-based auction. By pulling out that component of the proposal, PJM effectively stripped LSEs of their control over accepting RBP obligations. In NOVEC’s view, that control was critical to the success of the RBP process, which should embody a bottom-up, rather than a top-down approach. The bottom-up process gives truly interested developers the option to subscribe to pay the RBP costs rather than accept an interruptible form of service which PJM has proposed in Docket No. ER26-3515 (the Interim Resource Adequacy Service or “IRAS”). Contrary to the PJM Board’s determination, the voluntary subscription framework would provide sufficient assurance that capacity equal to the identified near-term shortfall would actually be procured.75 Paired with IRAS, committed load is adequately incentivized to participate to avoid an interruptible service—their business models rely on reliable service.
Although NOVEC rejects the premise that the voluntary subscription process would fail, even if it procured less than the total shortfall, that should not be considered a failure when considered in the context of the package of reforms the stakeholders proposed. The IRAS effectively mitigates any reliability harm, and if load prefers to avoid IRAS through bringing its
75 RBP Proposal at 21.
PDF page 26
26
own generation rather than participating in the RBP, it makes sense to allow that option. Either way, PJM obtains the generation it needs, and the large load is better situated to make that determination. More to the point, the subscription process avoids many of the issues discussed above because it allows LSEs to make arrangements directly with willing participants. FERC should order PJM to revise its RBP auction structure to be subscription-based with the load growth that is not subscribed being subject to curtailment by default, as contemplated by the stakeholder proposal.
IV. CONCLUSION
WHEREFORE, for the foregoing reasons, NOVEC respectfully requests that the
Commission reject the RBP Filing. If the Commission does not reject the filing, it should accept PJM’s invitation76 to require changes to the RBP to rectify the mistakes discussed above, including extending the effective date to allow for the RBP to have a chance of success, revising the cost-allocation structure to recognize the benefits derived from RBP Resources by non-RBP buyers, adjusting the amount of MW needed to offset RBP cost responsibility, shifting the auction to a subscription-based model, and reducing the collateral requirements as discussed above. At a minimum, the Commission should issue a deficiency letter and require PJM to better explain both its rejection of the coalition proposal and the as-filed RBP’s design.
76 Id. at 3 (“…PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”) (internal citation omitted).
PDF page 27
27
Respectfully submitted,
//s// Alan I. Robbins
Alan I. Robbins
Debra D. Roby
Thomas B. Steiger III
Washington Energy Law LLP
900 17th Street. N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9313
Email: arobbins@washingtonenergylaw.com
droby@washingtonenergylaw.com
tsteiger@washingtonenergylaw.com
Counsel to Northern Virginia Electric Cooperative, Inc.
Dated: August 21, 2026.
PDF page 28
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
Dated at Washington, D.C. this 21st day of August, 2026.
//s// Jessika Dziechciowska
Jessika Dziechciowska
Energy Practice Analyst
Washington Energy Law LLP
900 17th Street, N.W., Suite 500-A
Washington, D.C. 20006
Tel: (202) 326-9308
Email: jdziechciowska@washingtonenergylaw.com