ER26-3380-000 · 2026-08-21 · East Kentucky Power Cooperative, Inc.

Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal

Text extracted from the eLibrary original (SHA-256 1bfba97402f4c05e…). Download the original from the official source.

Contents · 88 sections
  1. I. Background p. 2
  2. A. RBP Overview p. 2
  3. A. The Stakeholder Process and Coalition RBP Proposal p. 8
  4. II. Protest p. 10
  5. A. The PJM RBP Proposal is Not Just and Reasonable. p. 15
  6. B. The Role of Electric Distributors, States, and RERRAs in PJM’s RBP p. 35
  7. C. PJM’s RBP Proposal is Inconsistent with the Boundaries of Federal and State p. 41
  8. D. PJM’s Proposed FRR Exemption and Treatment of RPM Capacity Market p. 45
  9. E. PJM’s Proposed FRR Exemption Creates Ambiguity and Disadvantages p. 47
  10. F. PJM’s Proposal Is Inconsistent with Ratepayer Protection and the p. 48
  11. III. Conclusion p. 50
  12. I. Introduction and Qualifications p. 52
  13. II. Summary of Opinions p. 53
  14. III. Background p. 53
  15. IV. Reliability Neutrality and Large-Load Growth p. 54
  16. V. Cost Causation and Section 205 Burden p. 56
  17. VI. Cost and Risk Allocation Effects Created by the RBP p. 57
  18. VII. Effects on LSEs, Electric Distributors, and States p. 60
  19. VIII. Hedgeability, Traceability, and Collateral Risk p. 63
  20. IX. FRR and RPM Self-Supply Asymmetry p. 66
  21. X. Application to EKPC p. 67
  22. XI. Conclusion p. 68
  23. I. INTRODUCTION AND QUALIFICATIONS p. 72
  24. II. PURPOSE AND SUMMARY OF OPINIONS p. 73
  25. III. THE ROLE OF COLLATERAL p. 74
  26. IV. PARTIES AND EXPOSURES UNDER THE RBP p. 76
  27. A. Parties with obligations p. 77
  28. B. Parties without obligations p. 77
  29. C. The residual tier p. 77
  30. D. How a default travels p. 77
  31. E. Which party is harmed by which failure p. 78
  32. F. Application to EKPC p. 78
  33. V. THE PROPOSED CREDIT CONSTRUCT p. 79
  34. A. Seller collateral p. 79
  35. B. The cumulative buyer requirement p. 79
  36. C. The individual LSE posting p. 79
  37. D. Acceptable forms p. 79
  38. E. PJM’s stated derivation p. 80
  39. VI. OPINION 1 — The magnitude has no precedent in PJM p. 80
  40. VII. WHETHER THE REQUIREMENT SECURES A MEASURED EXPOSURE p. 82
  41. A. The requirement is absent during the period of greatest uncertainty p. 82
  42. B. The requirement is not measured against the contract it secures p. 83
  43. C. The requirement departs from every methodology PJM applies elsewhere p. 84
  44. D. The seller requirement is deficient by the same standard p. 85
  45. E. Neither requirement is measured against the party that bears it p. 86
  46. VIII. THE QUANTITY OF MW TO WHICH THE CREDIT RATE APPLIES IS p. 86
  47. A. The three quantities p. 86
  48. B. Committed MW and the Final RBP Target will not be the same p. 87
  49. C. Committed MW is not in-service MW p. 87
  50. D. Consequence p. 87
  51. IX. THE REDUCTION OF THE REQUIREMENT OVER THE TERM IS UNDEFINED p. 88
  52. A. How PJM releases collateral elsewhere p. 88
  53. B. How the RBP releases collateral p. 88
  54. C. Absent reduction, the requirement exceeds the obligation it secures p. 89
  55. D. Consequence p. 90
  56. X. THE COST OF CARRYING THE REQUIREMENT IS MATERIAL AND IS NOT p. 90
  57. A. Only two forms of collateral are permitted p. 90
  58. B. Cash p. 90
  59. C. Letter of credit p. 90
  60. D. The rate PJM selected is not the rate applicable to load p. 91
  61. E. In aggregate p. 91
  62. F. The cost is not recovered and is not disclosed p. 92
  63. XI. THE REQUIREMENT CREATES SYSTEMIC LIQUIDITY RISK AMONG THE ENTITIES p. 92
  64. A. The requirement falls at one moment, in two instruments p. 92
  65. B. The obligation is concentrated and is not adjusted for the financial capacity of the obligor p. 93
  66. C. The NOVEC zone p. 93
  67. D. Letter of credit capacity is concentrated p. 95
  68. E. The failure mode is correlated, and PJM has handled the same structure differently p. 95
  69. F. Conclusion p. 96
  70. XII. THE SOCIALIZATION OF A DEFAULT INCREASES THE OBLIGATION OF THE p. 97
  71. A. Section 18.9(a) does not expressly require collateral to be applied before reallocation p. 97
  72. B. Two reallocation mechanisms of different scope p. 97
  73. C. Where the load does not appear, the obligation reaches native load p. 97
  74. D. The NOVEC zone p. 98
  75. E. The NOVEC zone does not satisfy the conditions for the opt-out p. 99
  76. F. The residual reaches Members with no allocation p. 100
  77. G. The seller side runs the same direction p. 100
  78. H. Conclusion p. 101
  79. XIII. THE FILED CREDIT CONSTRUCTS WERE NOT EXAMINED IN THEIR FINAL FORM p. 101
  80. A. PJM proposed using its existing credit framework for LSEs p. 101
  81. B. Other stakeholder proposals addressed buyer credit differently p. 102
  82. C. The seller requirement was materially revised in the final stakeholder proposal p. 102
  83. D. The LSE requirement changed after the final stakeholder proposal p. 103
  84. E. The filed methodologies departed from the exposure-based criteria considered during the process p. 103
  85. F. PJM considered adjustment mechanisms for sellers that were not included for load p. 104
  86. G. PJM states that the filed proposal was not stakeholder-endorsed p. 105
  87. H. Conclusion p. 105
  88. XIV. CONCLUSION p. 105

Read topic-matched comments in ER26-3380

Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

PJM proposes the RBP to be a one-time procurement of new capacity resources intended to address previously identified resource adequacy challenges that have arisen as a result of insufficient capacity commitments in the 2027/2028 and 2028/2029 Reliability Pricing Model (“RPM”) Capacity Market…
Read this passage Filed comments: Cost allocation

I. Background

printed heading

I.
Read this passage

A. RBP Overview

printed heading · Topic match: Cost allocation

If an RBO is not reported by an Electric Distributor to PJM, the cost allocation will default to applying a back-up cost allocation methodology based on “PJM’s status quo method for allocating capacity costs pursuant to RAA, Schedule 8.”26 Overall, PJM claims that its proposed cost allocation…
Read this passage Filed comments: Cost allocation

A. The Stakeholder Process and Coalition RBP Proposal

printed heading · Topic match: Credit and exit

The Stakeholder Process and Coalition RBP Proposal PJM claims that “the RBP reflects the input of stakeholders, as well as PJM’s judgment and analyses in shaping the specific means to implement the Principles document.”36 During the stakeholder process intended to consider options to address the…
Read this passage Filed comments: Credit and exit

II. Protest

printed heading · Topic match: Credit and exit

Coscia (“Coscia Affidavit”). 55 Coscia Affidavit at PP 7, 120. 13 based on the Tariff language proposed.56 Also, PJM proposes to reduce the applicable collateral requirements over time, but does not propose a schedule or precise method for doing so.57 And if there is no reduction, the posted…
Read this passage Filed comments: Credit and exit

A. The PJM RBP Proposal is Not Just and Reasonable.

printed heading · Topic match: Credit and exit

Corp., 88 FERC ¶ 61,249, 61,795 (1999). 16 PX argued that it was “impossible to be more explicit about the methodologies for allocating specific costs” because the Block-Forward Market was “in [its] infancy,” but the Commission was “not persuaded by PX’s unsupported claim” and directed the PX to…
Read this passage Filed comments: Credit and exit

B. The Role of Electric Distributors, States, and RERRAs in PJM’s RBP

printed heading · Topic match: Cost allocation

Electric Distributors must specify the MW quantity of load to be decremented where the Electric Distributor’s zone/area has rates that are not regulated by the states and is unable to address cost allocation associated with capacity procured in the backstop.
Read this passage Filed comments: Cost allocation

C. PJM’s RBP Proposal is Inconsistent with the Boundaries of Federal and State

printed heading · Topic match: Cost allocation

Power Supply Ass’n, 577 U.S. 260, 277-78 (2016). 159 Id. at 279-80. 160 See PJM Interconnection, L.L.C., PJM Manual 19: Load Forecasting and Analysis, at Attachment B: Load Forecast Adjustment Guidelines (effective June 30, 2026); PJM Interconnection, L.L.C., Presentation to Load Analysis…
Read this passage Filed comments: Cost allocation

D. PJM’s Proposed FRR Exemption and Treatment of RPM Capacity Market

printed heading · Topic match: Cost allocation

Yet, that is what [the Utility] effectively asks us to do, i.e., to delegate to state commissions and to [the Utility] itself the determination of the reasonableness of [the Utility’s] Commission-jurisdictional rates.”). 172 Bednarczyk Affidavit at P 60. 173 Bednarczyk Affidavit at P 60. 46 to meet…
Read this passage Filed comments: Cost allocation

E. PJM’s Proposed FRR Exemption Creates Ambiguity and Disadvantages

printed heading

See RAA, Schedule 8.1.D.4. 181 Proposed RAA, Schedule 8.1.D.1. (emphasis added). 182 See RAA, Schedule 8.1.D.4. 48 effort to ensure that FRR Entities do not enter into bilateral agreements with resources that have been committed to serve load under the RPM Capacity Market and further challenge the…
Read this passage

F. PJM’s Proposal Is Inconsistent with Ratepayer Protection and the

printed heading · Topic match: Cost allocation

Thus, advancing the goal of ratepayer protection necessarily depends on the ability to assign costs to 183 See THE WHITE HOUSE, Ratepayer Protection Pledge, (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/.
Read this passage Filed comments: Cost allocation

III. Conclusion

printed heading · Topic match: Cost allocation

Conclusion Wherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the Commission reject the PJM RBP Proposal because the PJM RBP Proposal is unjust and unreasonable, improperly expands the role of an Electric Distributor in PJM, and is inconsistent with the boundaries of…
Read this passage Filed comments: Cost allocation

I. Introduction and Qualifications

printed heading · Topic match: Credit and exit

Based on that experience, I am familiar with how Commission staff evaluate whether a proposed RTO or ISO tariff change is supported by the filing utility’s Section 205 showing, whether the filed provisions are sufficiently specific and administrable, and whether the resulting rate design is…
Read this passage Filed comments: Credit and exit

II. Summary of Opinions

printed heading · Topic match: Credit and exit

PJM must demonstrate that the specific tariff provisions governing RBP offsets, cost allocation, resource commitments, collateral requirements, RBP Charges, RBP Obligations (“RBO MW”), and Electric Distributor reporting satisfy the standards of a just and reasonable rate design.
Read this passage Filed comments: Credit and exit

III. Background

printed heading · Topic match: Credit and exit

PJM’s proposed Reliability Backstop Procurement (“RBP”) is a one-time, PJM-administered capacity procurement intended to address the 6,831 MW resource adequacy shortfall identified in the 2028/2029 Base Residual Auction.
Read this passage Filed comments: Credit and exit

IV. Reliability Neutrality and Large-Load Growth

printed heading · Topic match: Cost allocation

As a result, the proposal may encourage parties to focus on allocation outcomes rather than on actions that reduce the reliability impacts of adding large loads without corresponding resources or curtailment arrangements. 13.
Read this passage Filed comments: Cost allocation

V. Cost Causation and Section 205 Burden

printed heading · Topic match: Registry access

Similarly, PJM capacity-market reforms have sought to align accreditation, testing requirements, must-offer obligations, and performance consequences with actual resource-adequacy value.
Read this passage Filed comments: Registry access

VI. Cost and Risk Allocation Effects Created by the RBP

printed heading · Topic match: Credit and exit

Section 18.4 offers commitments "for a fixed period of fifteen (15) Delivery Years," while section 18.5(g) provides that each committed RBP Resource "shall be individually settled as a contract for difference." These provisions create a valuable administrative procurement pathway that is distinct…
Read this passage Filed comments: Credit and exit

VII. Effects on LSEs, Electric Distributors, and States

printed heading · Topic match: Cost allocation

More broadly, all LSEs face risk under proposed Tariff section 18.3 and proposed RAA Articles 7.2B and 7.2C if Adam Bednarczyk Affidavit 10 PJM ultimately relies on its default allocation mechanism, which assigns RBP Charges to all LSEs within a zone or area based on Daily Unforced Capacity…
Read this passage Filed comments: Cost allocation

VIII. Hedgeability, Traceability, and Collateral Risk

printed heading · Topic match: Credit and exit

Section 18.8 applies its credit provisions to “LSEs allocated costs for RBP UCAP MW procured through the Reliability Backstop Procurement, as determined in accordance with Tariff, Attachment DD, section 18.3,” and makes clear that RBP credit requirements are “separate from and additional to” credit…
Read this passage Filed comments: Credit and exit

IX. FRR and RPM Self-Supply Asymmetry

printed heading · Topic match: Reliability and curtailment

PJM proposes to exclude “Fixed Resource Requirement (‘FRR’) Entities as of the 2028/2029 Delivery Year” from the Reliability Backstop Procurement, including both the Initial and Final RBP Targets, while continuing to hold an Electric Distributor zone or area responsible for RBP UCAP MW if that zone…
Read this passage Filed comments: Reliability and curtailment

X. Application to EKPC

printed heading · Topic match: Cost allocation

That concern is particularly relevant because proposed Tariff section 18.9(a) provides that, if an LSE defaults and fails to pay an RBP Charge, “the defaulted amount will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share of the…
Read this passage Filed comments: Cost allocation

XI. Conclusion

printed heading · Topic match: Credit and exit

Rather, the specific design choices reflected in proposed Tariff sections 18.1, 18.2, 18.3, 18.4, 18.5, and 18.8, together with proposed RAA Articles 7.2B and 7.2C, do not adequately align responsibility for the procurement with responsibility for the resulting costs, credit exposure, and…
Read this passage Filed comments: Credit and exit

I. INTRODUCTION AND QUALIFICATIONS

printed heading · Topic match: Credit and exit

Based on that experience I am familiar with how collateral requirements in the organized markets are derived from measured exposure, administered as that exposure changes, and released as it declines, and with the liquidity consequences of collateral calls for the participants subject to them.
Read this passage Filed comments: Credit and exit

II. PURPOSE AND SUMMARY OF OPINIONS

printed heading · Topic match: Credit and exit

Attachment Q provides that collateral no longer required “shall be returned at the request of a Participant” within two Business Days, and Attachment Q, Section VI.B.3 sets out a mandatory, participant-initiated schedule reducing RPM auction credit across five stated milestones.
Read this passage Filed comments: Credit and exit

III. THE ROLE OF COLLATERAL

printed heading · Topic match: Credit and exit

Attachment Q, Section V.A provides that collateral no longer required “shall be returned at the request of a Participant no later than two Business Days” following PJMSettlement’s determination; that a Participant may substitute one approved form of collateral for another absent a default; and that…
Read this passage Filed comments: Credit and exit

IV. PARTIES AND EXPOSURES UNDER THE RBP

printed heading · Topic match: Credit and exit

That question is prior to any judgment about whether the credit requirement is correctly sized, because collateral secures a party against a loss, and one cannot evaluate the amount without first knowing whose loss it is and who is protected from it.
Read this passage Filed comments: Credit and exit

A. Parties with obligations

printed heading · Topic match: Credit and exit

RBP Sellers submit Sell Offers, receive commitments for a fixed fifteen-year term, and post collateral under section 18.8(a) equal to 20% of the offer price times committed UCAP MW times 365 days, for the first three Delivery Years. 29.
Read this passage Filed comments: Credit and exit

B. Parties without obligations

printed heading · Topic match: Credit and exit

They incur no payment obligation and post no collateral.
Read this passage Filed comments: Credit and exit

C. The residual tier

printed heading · Topic match: Cost allocation

That exposure extends to Members with no Load Adjustment and no RBP Charge allocation.
Read this passage Filed comments: Cost allocation

D. How a default travels

printed heading · Topic match: Cost allocation

On an LSE default, section 18.9(a) provides that the defaulted RBP Charge “will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share,” and that such amounts “may be offset by the RBP Collateral posted by the defaulting Load Serving…
Read this passage Filed comments: Cost allocation

E. Which party is harmed by which failure

printed heading · Topic match: Cost allocation

Under section 18.9(a) the defaulted RBP Charge is allocated among the remaining Load Serving Entities responsible for paying RBP Charges; because RBP Charges are assessed against every zone/area holding a share of the RBP Target, that population is footprint-wide rather than confined to the zone in…
Read this passage Filed comments: Cost allocation

F. Application to EKPC

printed heading · Topic match: Credit and exit

EKPC would therefore not be allocated RBP Charges on those figures, and would not post RBP Collateral.
Read this passage Filed comments: Credit and exit

V. THE PROPOSED CREDIT CONSTRUCT

printed heading

This section describes the proposed provisions without evaluating them.
Read this passage

A. Seller collateral

printed heading · Topic match: Credit and exit

Section 18.8(a) requires each RBP Resource seeking to submit a Sell Offer to post collateral equal to the sum, over the first three Delivery Years, of 20% of the RBP Sell Offer price times the offered UCAP MW times 365.
Read this passage Filed comments: Credit and exit

B. The cumulative buyer requirement

printed heading · Topic match: Cost allocation

The RBP Credit Rate “shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an amount sufficient…
Read this passage Filed comments: Cost allocation

C. The individual LSE posting

printed heading · Topic match: Credit and exit

Section 18.8(b)(i)(B)(1) requires each LSE with an RBP Obligation, “prior to forty-five (45) days before the start of the Delivery Year,” to “post, or maintain an existing, RBP Collateral equal to $1.5 million x the allocated RBP Obligation MW.” The obligation recurs in advance of each Delivery…
Read this passage Filed comments: Credit and exit

D. Acceptable forms

printed heading · Topic match: Credit and exit

RBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a letter of credit issued for the benefit of PJM or PJMSettlement, in an amount and form determined by and acceptable to PJM or PJMSettlement as credit support.” Surety bonds, which PJM accepts elsewhere…
Read this passage Filed comments: Credit and exit

E. PJM’s stated derivation

printed heading · Topic match: Credit and exit

PJM states that it is proposing to address RBP credit “through rules outside of its Credit Risk Management Policy,” and that the LSE requirement is intended to mitigate potential defaults from non-payment of RBP Charges.
Read this passage Filed comments: Credit and exit

VI. OPINION 1 — The magnitude has no precedent in PJM

printed heading · Topic match: Credit and exit

The Commission’s standard has two sides: an RTO must minimize the risk that a default is socialized among non-defaulting participants, while “ensuring that the credit or collateral requirements are not so stringent that they unnecessarily inhibit access to the marketplace.” Sw.
Read this passage Filed comments: Credit and exit

VII. WHETHER THE REQUIREMENT SECURES A MEASURED EXPOSURE

printed heading · Topic match: Credit and exit

This section evaluates whether the proposed collateral secures a measured risk position, and whether the amount is sufficient or deficient under plausible future price outcomes.
Read this passage Filed comments: Credit and exit

A. The requirement is absent during the period of greatest uncertainty

printed heading · Topic match: Credit and exit

Those parties bear both the reassigned collateral requirement and, under section 18.9(a), the reallocated RBP Charges, “based on their pro-rata share of the total RBP Charges for all such Load Serving Entities.” 12
Read this passage Filed comments: Credit and exit

B. The requirement is not measured against the contract it secures

printed heading · Topic match: Credit and exit

It also proposes at section 16.2 to reinstate the existing Tariff provisions establishing a Reliability Backstop Auction — a mechanism distinct from the RBP proposed here — beginning with the 2032/2033 Delivery Year, so that from that point forward a clearing shortfall against the Reliability…
Read this passage Filed comments: Credit and exit

C. The requirement departs from every methodology PJM applies elsewhere

printed heading · Topic match: Credit and exit

It provides no unsecured credit allowance and accepts only two forms of collateral. 88.
Read this passage Filed comments: Credit and exit

D. The seller requirement is deficient by the same standard

printed heading · Topic match: Credit and exit

The two requirements — the LSE collateral requirement and the seller collateral requirement — rest on opposite assumptions about the same variable.
Read this passage Filed comments: Credit and exit

E. Neither requirement is measured against the party that bears it

printed heading · Topic match: Cost allocation

The RBP Charge is secured in advance by the Credit Rate, and once the Delivery Year begins and RBP Charges are billed, those same charges enter the LSE’s Peak Market Activity through the ordinary operation of Attachment Q and are secured again by the financial security that Peak Market Activity…
Read this passage Filed comments: Cost allocation

VIII. THE QUANTITY OF MW TO WHICH THE CREDIT RATE APPLIES IS

printed heading · Topic match: Cost allocation

The amount an LSE must post is therefore the product of that rate and a quantity of MW.
Read this passage Filed comments: Cost allocation

A. The three quantities

printed heading

Section 18.8(b)(i)(A) provides that the cumulative requirement “shall be equivalent to the product of the RBP Credit Rate multiplied by RBP UCAP MW committed,” 16 defined as “the amount of RBP UCAP MW that receives a commitment through the Reliability Backstop Procurement minus each commitment of…
Read this passage

B. Committed MW and the Final RBP Target will not be the same

printed heading

Section 18.5(f) provides that “RBP Resources shall not be partially cleared,” and that “[i]n the event that the Reliability Backstop Procurement cannot meet the Final RBP Target, the Reliability Backstop Procurement shall clear short of the Final RBP Target.” The same section permits PJM to “commit…
Read this passage

C. Committed MW is not in-service MW

printed heading

A resource committed for a first Delivery Year of 2032/2033 is therefore included in committed MW from the 2028/2029 Delivery Year, when it is neither in service nor generating any RBP Charge.
Read this passage

D. Consequence

printed heading · Topic match: Credit and exit

An LSE cannot compute the collateral it would be required to post from the tariff.
Read this passage Filed comments: Credit and exit

IX. THE REDUCTION OF THE REQUIREMENT OVER THE TERM IS UNDEFINED

printed heading · Topic match: Credit and exit

This section addresses the release of collateral as exposure declines.
Read this passage Filed comments: Credit and exit

A. How PJM releases collateral elsewhere

printed heading · Topic match: Credit and exit

Attachment Q, Section V provides that Collateral which may no longer be required to be maintained under provisions of the Agreements “shall be returned at the request of a Participant, no later than two (2) Business Days following determination by PJM within a commercially reasonable period of time…
Read this passage Filed comments: Credit and exit

B. How the RBP releases collateral

printed heading · Topic match: Credit and exit

Section 18.8(b)(i)(A) provides that the Credit Rate “shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the…
Read this passage Filed comments: Credit and exit

C. Absent reduction, the requirement exceeds the obligation it secures

printed heading · Topic match: Cost allocation

The RBP Charge is a differential between the RBP price and the RPM clearing price, and for the first two Delivery Years that differential is measurable rather than forecast.
Read this passage Filed comments: Cost allocation

D. Consequence

printed heading · Topic match: Credit and exit

PJM adopted a mandatory, participant-initiated, milestone-based release mechanism for sellers in the capacity market five months before this filing, and a mandatory two-business-day return obligation for collateral generally.
Read this passage Filed comments: Credit and exit

X. THE COST OF CARRYING THE REQUIREMENT IS MATERIAL AND IS NOT

printed heading · Topic match: Credit and exit

This section addresses the cost to a Load Serving Entity of holding the required collateral.
Read this passage Filed comments: Credit and exit

A. Only two forms of collateral are permitted

printed heading · Topic match: Credit and exit

RBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a letter of credit issued for the benefit of PJM or PJMSettlement.” Surety bonds are excluded, although PJM accepts them elsewhere subject to per-issuer limits, and section 18.8 provides no unsecured…
Read this passage Filed comments: Credit and exit

B. Cash

printed heading · Topic match: Credit and exit

As explained at paragraphs 129 through 132, that figure describes the cost of capital for merchant generation investment, not the cost of funds of the load-serving entities required to post the collateral.
Read this passage Filed comments: Credit and exit

C. Letter of credit

printed heading · Topic match: Credit and exit

PJM presently observes a mix of approximately thirty-five percent cash and sixty-five percent letters of credit across its markets, but that mix is observed against a total collateral balance that has never exceeded approximately $13.1 billion across every market and every participant, and against…
Read this passage Filed comments: Credit and exit

D. The rate PJM selected is not the rate applicable to load

printed heading

The rate PJM selected is not the rate applicable to load 129.
Read this passage

E. In aggregate

printed heading · Topic match: Credit and exit

The per-MW-day figure does not depend on the size of the procurement: because both the collateral and the MW-days scale with committed UCAP MW, the quantity cancels.
Read this passage Filed comments: Credit and exit

F. The cost is not recovered and is not disclosed

printed heading · Topic match: Credit and exit

As set out above, the Commission established Regional Transmission Organizations to promote efficiency in wholesale electricity markets and to ensure that consumers pay the lowest price possible for reliable service, and has held that credit and collateral requirements must not be “so stringent…
Read this passage Filed comments: Credit and exit

XI. THE REQUIREMENT CREATES SYSTEMIC LIQUIDITY RISK AMONG THE ENTITIES

printed heading · Topic match: Credit and exit

The standard is the one set out in Section III: credit requirements must not be so stringent that they unnecessarily inhibit access to the marketplace, and the Commission has identified cascading default as the consequence it guards against.
Read this passage Filed comments: Credit and exit

A. The requirement falls at one moment, in two instruments

printed heading · Topic match: Credit and exit

RBP Collateral is defined as either a cash deposit or a letter of credit.
Read this passage Filed comments: Credit and exit

B. The obligation is concentrated and is not adjusted for the financial capacity of the obligor

printed heading

The obligation is concentrated and is not adjusted for the financial capacity of the obligor 137.
Read this passage

C. The NOVEC zone

printed heading · Topic match: Credit and exit

It therefore both makes the RBP Obligation MW assignment under proposed Reliability Assurance Agreement, section 7.2C and bears the resulting RBP Charge and collateral obligation under Tariff, Attachment DD, section 18.8(b). 23 Table 1.
Read this passage Filed comments: Credit and exit

D. Letter of credit capacity is concentrated

printed heading · Topic match: Credit and exit

PJM measures that concentration every month because it bears directly on the quality of the collateral PJM holds.
Read this passage Filed comments: Credit and exit

E. The failure mode is correlated, and PJM has handled the same structure differently

printed heading · Topic match: Credit and exit

Neither is a means by which a Load Serving Entity holding an assigned obligation can reduce that obligation once the commitment binds, which is the period during which the collateral is required.
Read this passage Filed comments: Credit and exit

F. Conclusion

printed heading · Topic match: Credit and exit

The NOVEC zone shows that the question is not hypothetical: an obligation of approximately $1.95 billion is allocated to a footprint served by a cooperative reporting approximately $1.716 billion in total assets, whose customers have no general right to select an alternative Load Serving Entity…
Read this passage Filed comments: Credit and exit

XII. THE SOCIALIZATION OF A DEFAULT INCREASES THE OBLIGATION OF THE

printed heading · Topic match: Credit and exit

The Commission has identified the prevention of socialization as the function collateral performs: where collateral posted by a defaulting party is insufficient, the remaining exposure and costs are socialized across the membership.
Read this passage Filed comments: Credit and exit

A. Section 18.9(a) does not expressly require collateral to be applied before reallocation

printed heading · Topic match: Credit and exit

Section 18.9(a) provides that a defaulted RBP Charge “will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share,” and that such amounts “may be offset by the RBP Collateral posted by the defaulting Load Serving Entity.” Reallocation to…
Read this passage Filed comments: Credit and exit

B. Two reallocation mechanisms of different scope

printed heading · Topic match: Cost allocation

Where an allocated Load Serving Entity fails to pay, section 18.9(a) reallocates the defaulted charge to “all remaining Load Serving Entities responsible for paying RBP Charges,” language that on its face reaches the entire footprint rather than the zone.
Read this passage Filed comments: Cost allocation

C. Where the load does not appear, the obligation reaches native load

printed heading · Topic match: Credit and exit

Section 18.8(b)(i)(B)(2) addresses a Load Serving Entity for which the Electric Distributor reports no obligation at all, providing that such an entity “may be required to post” collateral determined by its “pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in…
Read this passage Filed comments: Credit and exit

D. The NOVEC zone

printed heading · Topic match: Credit and exit

As set out in the preceding section, the NOVEC zone carries an initial allocation of 1,302.6 UCAP MW and a collateral obligation of approximately $1.95 billion.
Read this passage Filed comments: Credit and exit

E. The NOVEC zone does not satisfy the conditions for the opt-out

printed heading

The NOVEC zone does not satisfy the conditions for the opt-out 166.
Read this passage

F. The residual reaches Members with no allocation

printed heading · Topic match: Credit and exit

That provision is not limited to Members allocated RBP Charges. 169.
Read this passage Filed comments: Credit and exit

G. The seller side runs the same direction

printed heading · Topic match: Credit and exit

Section 18.9(b) provides that where an RBP Resource defaults on payment of shortfall charges, “the corresponding credits will not be allocated to the Load Serving Entities that would otherwise receive the RBP shortfall credits.” There is no reallocation among sellers and no provision applying the…
Read this passage Filed comments: Credit and exit

H. Conclusion

printed heading · Topic match: Cost allocation

The collateral posting is mandatory, while section 18.9(a) states its application to a defaulted RBP Charge in permissive terms.
Read this passage Filed comments: Cost allocation

XIII. THE FILED CREDIT CONSTRUCTS WERE NOT EXAMINED IN THEIR FINAL FORM

printed heading · Topic match: Credit and exit

The Commission has held that credit requirements emerging from an RTO stakeholder process must still be reviewed for whether they are unduly burdensome.
Read this passage Filed comments: Credit and exit

A. PJM proposed using its existing credit framework for LSEs

printed heading · Topic match: Credit and exit

In the Design Presentation, PJM stated that upon notification by the Load Serving Entity of known changes to its load, “the credit, and collateral requirements for LSEs are expected to be managed by the current credit processes,” and that those processes “include, but are not limited to, credit…
Read this passage Filed comments: Credit and exit

B. Other stakeholder proposals addressed buyer credit differently

printed heading · Topic match: Credit and exit

Their final recommendations to the Board again called for PJM to “[e]stablish demand-side credit and collateral prior to procurement.” They recorded PJM staff’s position on that issue as “collateral timing/assignment is later,” and identified as a source of stranded cost risk the absence of any…
Read this passage Filed comments: Credit and exit

C. The seller requirement was materially revised in the final stakeholder proposal

printed heading

The seller requirement was materially revised in the final stakeholder proposal 182.
Read this passage

D. The LSE requirement changed after the final stakeholder proposal

printed heading · Topic match: Credit and exit

PJM’s final June 30 proposal continued to state that LSE credit and collateral requirements were expected to be managed through existing credit processes, including credit evaluation, Peak Market Activity recalculation and other mitigation tools.
Read this passage Filed comments: Credit and exit

E. The filed methodologies departed from the exposure-based criteria considered during the process

printed heading · Topic match: Credit and exit

The Joint Consumer Advocates emphasized establishing the credit and collateral requirement before the procurement occurred. 190.
Read this passage Filed comments: Credit and exit

F. PJM considered adjustment mechanisms for sellers that were not included for load

printed heading · Topic match: Credit and exit

The June Design Presentation also demonstrates that PJM considered mechanisms for adjusting seller collateral over the term.
Read this passage Filed comments: Credit and exit

G. PJM states that the filed proposal was not stakeholder-endorsed

printed heading · Topic match: Credit and exit

The absence of stakeholder endorsement does not itself determine whether a credit requirement is reasonable.
Read this passage Filed comments: Credit and exit

H. Conclusion

printed heading · Topic match: Credit and exit

The stakeholder process provided no opportunity to examine the $1.5 million per MW methodology against the matters addressed in this affidavit: its relationship to measured exposure; the quantity to which the Credit Rate applies; the availability and cost of permitted collateral; the mechanism by…
Read this passage Filed comments: Credit and exit

XIV. CONCLUSION

printed heading · Topic match: Credit and exit

Item Amount NVEC initial allocation 1,302.6 UCAP MW Share of Initial RBP Target 19.07% Collateral at $1.5 million per MW $1.954 billion Total assets (FY2025) $1.716 billion Total equities and margins (FY2025) $919.7 million Total long-term debt (FY2025) $69.2 million Cash collateral posted to PJM…
Read this passage Filed comments: Credit and exit