ER26-3380-000 · 2026-08-21 · East Kentucky Power Cooperative, Inc.

Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000

)

PROTEST OF
EAST KENTUCKY POWER COOPERATIVE, INC.

Pursuant to Rule 211 of the Commission’s Rules of Practice and Procedure1 and the Commission’s August 3, 2026 “Combined Notice of Filings #1,” East Kentucky Power Cooperative, Inc. (“EKPC”)2 hereby protests the July 31, 2026 filing3 of PJM Interconnection, L.L.C. (“PJM”) proposing revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”). PJM proposes the RBP to be a one-time procurement of new capacity resources intended to address previously identified resource adequacy challenges that have arisen as a result of insufficient capacity commitments in the 2027/2028 and 2028/2029 Reliability Pricing Model (“RPM”) Capacity Market Auctions (“RBP Proposal”).   EKPC shares the concern that PJM is attempting to address; however, this is not the right fix.  The PJM RBP Proposal is unjust and unreasonable, improperly expands the role of an Electric Distributor in PJM, and is inconsistent with the boundaries of federal and state jurisdiction.  Despite its claims to the contrary, PJM’s RBP Proposal also fails to address concerns raised by the Commission and the Governors of the 13 PJM states regarding the impacts of large loads, specifically ratepayer protection. Indeed, EKPC is significantly concerned about the potential cost shifting that could

1 18 C.F.R. § 385.211 (2026).
2 EKPC filed a doc-less motion to intervene in this proceeding on August 7, 2026.
3 PJM Interconnection L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads,” (filed July 31, 2026) (“PJM RBP Filing”).

PDF page 2

2
occur, and possibly even defaults that may result from, the inability of any Load Serving Entity (“LSE”) to know with certainty its ultimate cost exposure, which may be exacerbated should the realization of the large load itself be affected by the potential exposure to these costs. The Commission should therefore reject PJM’s proposed Tariff revisions.

I. Background
A. RBP Overview
As proposed by PJM, the RBP is a one-time capacity procurement targeting an Unforced Capacity (“UCAP”) shortfall identified in the 2027/2028 and 2028/2029 RPM Capacity Market Auctions. PJM claims that “[t]o mitigate the potential reliability risks associated with resource adequacy shortfalls, PJM is proposing this RBP as a supplementary mechanism to procure additional supply to meet the resource adequacy needs of the PJM Region.”4 PJM asserts that “[t]he RBP proposal is a just and reasonable means to address the influx of large loads while maintaining resource adequacy, reliability, and affordability in a manner that respects the divide between state and federal authorities and avoids disrupting existing commercial arrangements.”5 Fundamentally, according to PJM, the RBP has the “goal of obtaining commitments of new RBP UCAP MW from eligible resources, called RBP Resources, for a fixed term of up to 15 years, starting with the 2028/2029 Delivery Year and ending with the 2042/2043 Delivery Year.”6 The RBP intends to accomplish this goal by conducting a one-time auction to procure new capacity equal to the identified “RBP Target.” The RBP Target is equal to the “Initial RBP Target,” which is the region-wide 2028/2029 Delivery Year reliability shortfall observed in the July 2026 Base Residual Auction (“BRA”) for Delivery Year 2028/2029, i.e., 6,831.3 MW UCAP, minus

4 PJM RBP Filing at 7.
5 PJM RBP Filing at 2.
6 PJM RBP Filing at 8.

PDF page 3

3
Qualifying RBP Offset UCAP MW and Opt-Out UCAP MW.7 Qualifying RBP Offset UCAP MW is “new capacity voluntarily brought on to the PJM system by new load” that must meet certain specified criteria.8 And Opt-Out UCAP MW will reflect the associated MW quantity of load in the zone/area that will be opted-out of the Initial RBP Target. To qualify for this opt-out, the request must be supported by documentation demonstrating an inability to address cost allocation associated with capacity procured in the backstop, along with written support for such opt-out from the relevant state governor, Relevant Electric Retail Regulatory Authority (“RERRA”), and interconnection customers.9 PJM is also proposing another narrow opt-out to permit Electric Distributors to decrement the Initial RBP Target by up to the associated MW quantity of load that participates in a peak shaving adjustment program codified in state law.10 Notably, Fixed Resource Requirement (“FRR”) Entities as of the 2028/2029 Delivery Year also will be excluded from the RBP.

Importantly, PJM is not proposing to match specific supply to specific demand.11 In other words, PJM is not utilizing a register or other means to ensure specific LSEs serving large loads throughout the 15-year duration are appropriately charged the costs associated with the procurement or credited with the RBP MW secured on their behalf (to offset any potential for curtailments under the Interim Resource Adequacy Service (“IRAS”) PJM has proposed in Docket

7 PJM RBP Filing at 31.
8 PJM RBP Filing at 35.
9 Proposed Tariff, Attachment DD, Section 18.1(d).
10 PJM BRP Filing at 45.
11 PJM RBP Filing at 33; PJM RBP Filing, Attachment C, “Affidavit of Ms. Danielle Croop,” at P 7 (“Croop Affidavit”).

PDF page 4

4
No. ER26-3515.)12 This is a duration 15-times greater than the commitment secured through any of the other markets PJM administers.

Nor is PJM applying any locational constraints in determining which resources to select for 15-year commitments.  PJM claims that “locational parameters based on today’s conditions would inevitably skew the results and lead to either over-procurement or under-procurement in given zones based on nothing more than speculation as to the state of the system ten and fifteen years from now.”13 As PJM asserts, “inclusion of a speculative 15-year forward locational capacity requirement at this point in time would simply ignore the role of PJM’s interconnection and planning process as the means to ensure deliverability of capacity resources to load throughout the PJM Region.”14

According to PJM, the RBP is designed to attract new supplies of capacity.15 Under PJM’s proposal, resources procured through the RBP must demonstrate a high degree of certainty of achieving commercial operation within the next few years and be available to provide capacity until the end of a fixed, 15-year term.16 Sellers eligible to participate in the RBP, i.e., RBP Resources or Market Participants selling RBP UCAP MW of RBP Resources, must: “(1) meet collateral requirements prior to participating in the RBP; (2) support eligibility to provide capacity;

(3) provide capacity; (4) cover penalties for any capacity shortfalls; and (5) bear responsibility for defaults.”17 Similarly, buyers, i.e., LSEs, must: “(1) meet collateral requirements immediately

12 PJM Interconnection, L.L.C., “Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy and a Large Load Registry to Address System Reliability,” Docket No. ER26-3515-000 (filed Aug. 13, 2026).
13 PJM RBP Filing at 34.
14 PJM RBP Filing at 34.
15 PJM RBP Filing at 51; Croop Affidavit at P 9.
16 PJM RBP Filing at 51; Croop Affidavit at P 15.
17 PJM RBP Filing at 49-51.

PDF page 5

5
prior to each relevant Delivery Year; (2) cover the cost of RBP UCAP MW in accordance with the allocation of RBP Charges in each Delivery Year covered by the 15-year resource commitments; and (3) bear responsibility for defaults.”18

The RBP will use a pay-as-bid clearing structure with a MW-weighted average levelized procurement cost cap of $555/MW-day UCAP, which is based on Point 1 of the Variable Resource Requirement (“VRR”) curve for the 2028/2029 BRA.19 Resources selected through the RBP are committed for a fixed 15-year term, commencing with the 2028/2029 Delivery Year and extending through the 2042/2043 Delivery Year.20 PJMSettlement acts as the counterparty to RBP commitments, and RBP Resources must offer as price takers ($0/MW-day) in RPM Capacity Market auctions. PJM proposes to commit resources in the RBP using a pay-as-bid approach, which PJM explains is more appropriate for a one-time backstop procurement than the single- clear-price approach used in the RPM Capacity Market.21

As proposed by PJM, cost allocation under the RBP flows first to Electric Distributor zones/areas based on Load Adjustments per RAA Schedule 8, then to LSEs based on state- or RERRA-determined RBP Obligations (“RBOs”). In the absence of reported RBOs, PJM’s backup methodology uses Daily Unforced Capacity Obligation ratios. Costs will be allocated to PJM zones based on their pro rata share of the procurement target and then allocated to utilities and other LSEs within the zones. As explained by PJM, it “is proposing to allocate daily RBP Charges to relevant Electric Distributor zones/areas, pro rata, based on the zone/area’s assigned share of the total, region-wide Final RBP Target MW, floored at zero,” incorporating certain Load

18 PJM RBP Filing at 51.
19 PJM RBP Filing at 61-62.
20 PJM RBP Filing at 8.
21 PJM RBP Filing at 65; Croop Affidavit at PP 22-25.

PDF page 6

6
Adjustments.22 Costs allocated to a zone/area may be further adjusted where a zone/area is recognized by PJM as having Qualifying RBP Offset UCAP MW or Opt-Out UCAP MW that qualifies for an opt-out.23 PJM is proposing that cost allocation to LSEs within an Electric Distributor’s zone/area be based on “the state and/or RERRA-determined allocation of cleared RBP UCAP MW to LSEs within each Electric Distributor’s zone/area, as reported by each Electric Distributor to [PJM].”24 However, should there be no state- or RERRA-determined RBO allocation methodology, PJM will require the Electric Distributor to further assign the costs that PJM assigned to the zone/area to the LSEs in that zone/area according to their Daily Unforced Capacity Obligation (which commonly is referred to as their “Peak Load Contribution” or “PLC”). PJM’s cost allocation proposal relies heavily on the role of Electric Distributors, requiring them to report to PJM, “the state and/or RERRA-determined allocations of RBP UCAP MW to LSEs in their zone(s)/area(s).”25  Without PJM providing the linkage between RBP MW procured to specific LSEs, the Electric Distributor must determine how any zone/area offset or opt-out MW PJM accepted affects individual LSE obligations. PJM provides no details in the proposed Tariff or RAA revisions for how the Electric Distributor must execute upon this responsibility. If an RBO is not reported by an Electric Distributor to PJM, the cost allocation will default to applying a back-up cost allocation methodology based on “PJM’s status quo method for allocating capacity costs pursuant to RAA, Schedule 8.”26 Overall, PJM claims that its proposed cost allocation method “recognizes and respects” the division of responsibilities between PJM and states.27  PJM

22 PJM RBP Filing at 97.
23 Croop Affidavit at PP 43-46. 24 PJM RBP Filing at 97-98 (quoting Proposed Tariff, Attachment DD, Section 18.3(b)(iii)).
25 PJM RBP Filing at 98. 26 PJM RBP Filing at 98-99.
27 PJM RBP Filing at 99.

PDF page 7

7
also claims, without adequate support, that its proposal is consistent with the Ratepayer Protection Pledge.28

PJM proposes to align an LSE’s RBP credit requirement with its cost allocation. Therefore, the extensive role PJM has proposed for Electric Distributors also impacts credit requirements and the collateral an LSE will be required to post. As PJM explains, “for LSEs serving load in an Electric Distributor zone/area in which no RBOs have been reported, an LSE’s ‘allocated RBP UCAP MW shall equal the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.’”29 If an LSE is serving load in an “Electric Distributor zone/area in which RBOs have been reported, the LSE will be required to post RBP Collateral for its RBO MW (i.e., its allocated RBP UCAP MW amount).”30 PJM has proposed that collateral must be posted 45 days before the starts of the Delivery Year, which is intended to give Electric Distributors sufficient time to specify the RBO MW for the applicable zone/area.31 If an LSE were to default on RBP Charges, any defaulted amount is allocated among the LSEs with RBP Charges “based on [the LSE’s] proportional share.”32 However, the amount to be reallocated will be offset by collateral posted by the defaulting LSE.33 In the event that an RBP Resource defaults on the payment of RBP shortfall charges, the LSE which anticipated receiving

28See
THE
WHITE
HOUSE,
Ratepayer
Protection
Pledge,
(Mar.
4,
2026),
https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. As of August 18, 2026, more than 300 organizations across every stakeholder in the power system has signed on to the Ratepayer Protection Pledge, including Governors of 23 states and more than 250 utilities and cooperatives, including EKPC (see https://www.whitehouse.gov/ratepayer-protection-pledge/#commitments for a list of entities that have signed the Pledge).

29 PJM RBP Filing at 118 (quoting Proposed Tariff, Attachment DD, Section 18.8(b)(i)(B)(1)).
30 PJM RBP Filing at 119.
31 PJM RBP Filing at 120.
32 PJM RBP Filing at 122.
33 PJM RBP Filing at 122.

PDF page 8

8
credits will not receive such credits unless there is posted collateral that PJM could provide to the LSE.34

PJM has also proposed to restrict an FRR entity’s use of bilateral contracts to satisfy its FRR obligation. PJM’s proposed language in RAA Section 8.1.D.1.1 states that “[a]n FRR Entity may not use an Existing Generation Capacity Resource not owned by such FRR Entity as of June 1, 2027 or any resource committed through the Reliability Backstop Procurement to satisfy its Capacity FRR Plan.”35 With this proposal, PJM has created ambiguity with respect to the role of bilateral contracts for FRR entities while still allowing the potential for existing resources to be removed from the RPM Capacity Market.

A. The Stakeholder Process and Coalition RBP Proposal
PJM claims that “the RBP reflects the input of stakeholders, as well as PJM’s judgment and analyses in shaping the specific means to implement the Principles document.”36 During the stakeholder process intended to consider options to address the identified capacity shortfall, PJM considered 13 proposals that were voted on June 30, 2026, through the Critical Issue Fast Path (“CIFP”) process. Of those proposals, only the Coalition RBP Proposal, discussed in more detail below, received the required two-thirds sector-weighted member support. The PJM Board, in its July 27, 2026 decisional letter, rejected this voluntary, stakeholder-supported proposal and instead directed PJM to file the mandatory procurement framework at issue here.37 PJM acknowledges that only the Coalition RBP Proposal received the required two-thirds sector-weighted member

34 PJM RBP Filing at 122-123.
35 Proposed RAA, Schedule 8.1.D.1.1 (emphasis added).
36 PJM RBP Filing at 9.
37 See Paula Conboy, PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and Connect and Manage, (July 27, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement-and-connect-and- manage.pdf.

PDF page 9

9
support.38 The Coalition RBP Proposal represented the consensus of PJM’s diverse stakeholder body, including the LSEs that will bear the financial consequences of the RBP. At the same time the Commission is questioning whether the PJM membership can come to a consensus on

proposals to address the most pressing challenge facing the PJM region, the membership did, in fact, come to agreement.39

The Commission should give significant weight to the fact that the stakeholder body—
which includes the LSEs that will bear the costs—did not support a mandatory procurement, especially one that did not identify or track with specificity who would bear the costs of, or who receives the RBP MW credit resulting from, the procurement. With respect to the Coalition RBP Proposal, a coalition of entities, including EKPC,40 put forward a proposed registry-based subscription model that would have allowed large loads and their LSEs to secure bilateral contracts to manage the risks associated with large loads.41 In the subscription-based model, LSEs would

38 See PJM RBP Filing at 20 (citing PJM Members Committee, MC Voting Results for RBP Proposals Agenda Items 3L through 3X (June 30, 2026), https://www.pjm.com/committees-and-groups/committees/mc [https://perma.cc/5CSQ-DP4K] (scroll to “Meeting Materials” and search for 2026, click on link for “6.30.2026 Special Meeting,” scroll to MC Voting Results – Agenda Items 3L to 3X and click on each to view the PDF)).
39 The Commission has an open docket addressing PJM governance and the stakeholder process, and the Commission recently held a Commission-led technical conference to discuss these issues. See PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, “Notice of Commission-Led Technical Conference” (May 12, 2026). And, starting September 1, 2026, the Commission’s Director of Dispute Resolution Services “will convene a forum to facilitate interest-based discussions on proposed reforms to PJM’s governance and stakeholder processes” intended “to gather feedback from PJM members and stakeholders, identify areas of consensus and divergence, and evaluate actionable reforms to inform a future filing.” See PJM Governance and Stakeholder Reforms, Docket No. AD26-6-000, “Notice Regarding Dispute Resolution Procedures” (Aug. 10, 2026). As noted by Chairman Swett, “PJM is facing a grave legitimacy crisis, frustrations are mounting, the collaborative spirit that underpinned the market’s formation is fracturing, and some transmission owners are openly discussing leaving the RTO altogether. Put plainly, market participants have lost confidence in PJM’s decision-making abilities.” PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, Transcript, 8:25-9:6.
40 Along with EKPC, the Coalition also included Buckeye Power, Dominion Energy, Duke Energy Ohio, Duke Energy Kentucky, Duquesne Light Company, Exelon, Old Dominion Electric Cooperative, PPL Electric Utilities Corp., Southern Maryland Electric Cooperative, and the Data Center Coalition.
41 PJM Critical Issue Fast Path – Reliability Backstop Procurement / Connect & Manage, Joint EDCs & Data Center Coalition Reliability Backstop Procurement Package (June 30, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02f---joint-edcs-and-data-center- coalition---rbp---executive-summary.pdfbp---executive-summary.pdf

PDF page 10

10
opt into the procurement on behalf of their large load customers, bear associated credit and collateral obligations, and prevent cost-shifting to unrelated retail customers.  Importantly, those elements worked together to create a just and reasonable proposal.  Despite PJM’s claims that certain elements were adopted from the Coalition RBP Proposal,42 they were altered and applied to a fundamentally different approach, and thus will have a significantly different effect than they would under the Coalition RBP Proposal.43

For the reasons explained herein, EKPC urges the Commission to reject the PJM RBP
Proposal as unjust, unreasonable, and unduly discriminatory.44 EKPC also urges the Commission to clarify the revision proposed to FRR will not preclude the ability of any entity electing to utilize the FRR alternative in the future to satisfy its PJM capacity obligations to rely upon existing bilateral contracts in its long-standing supply portfolio.

II. Protest
PJM claims that the RBP is “a critical safety net designed to address current resource
adequacy shortfalls.”45 EKPC shares PJM’s concern about resource adequacy and the reliability challenges facing the PJM region, and EKPC supports measures that maintain resource adequacy

42 PJM RBP Filing at 22 (“[T]he PJM Board adopted various concepts from the Coalition RBP Proposal that received a sector-weighted majority of stakeholder support. Specifically, the proposed (1) maximum volume weighted average of all selected RBP Sell Offers, (2) credit requirement for Load Serving Entities, and (3) opt-out from the RBP Initial Procurement Target all had their roots in the Coalition RBP Proposal.”).
43 The Coalition proposed a Large Load Registry maintained by PJM, through which the Large Load or its designated LSE would report the MW quantity of Large Load assigned to a specific LSE in a specific zone and the identity of the Large Load (not necessarily meter-level data at time of procurement). At the start of each Delivery Year, the registry would capture Large Load meter-level information to facilitate billing and collateral tracking, accommodate LSE switching in retail choice states, and address corporate ownership changes. The Coalition RBP Proposal’s cost allocation method was based on assigning costs and collateral obligations to the cost-causing parties at the time the bilateral commitments are made. The Coalition RBP Proposal fixed the RBP commitment at the time of procurement. While MW quantities could vary over time based on varying in-service dates of committed resources, the obligation to pay is fixed at procurement. RBP obligations would be settled separately from RPM Capacity Market but structured to net appropriately to avoid double payment for overlapping capacity obligations.
44 The Commission should reject PJM’s suggestion that the Commission make changes to the as-filed Proposal to remedy the fact that the RBP Proposal is unjust, unreasonable, and unduly discriminatory.
45 PJM RBP Filing at 26.

PDF page 11

11
and recognizes the urgency of PJM’s reliability concerns. But as filed, the PJM RBP Proposal will fail to achieve its objectives in a manner consistent with the requirements of the Federal Power Act (“FPA”). The PJM RBP Proposal assigns long-term costs and collateral obligations through a framework that lacks the specificity necessary to be just and reasonable. In particular, PJM’s RBP Proposal does not sufficiently identify the LSE responsible for causing the capacity shortage, ensure that any offsets or opt-outs follow the entity that secured them, or protect LSEs whose existing resource portfolios already support their expected load obligations from incurring additional costs. PJM’s RBP Proposal may attempt to address a legitimate reliability need. But simply attempting to address a legitimate need is not enough to make the RBP Proposal just and reasonable, especially where the resulting costs are not reasonably tied to cost causation, and the cost allocation and credit and collateral obligations are not knowable, hedgeable, or administrable. These uncertainties, in turn, will frustrate PJM’s stated purpose and serve to actually increase the default risk that has broader implications for the PJM region. That risk extends to entities like EKPC whose supply portfolio contains sufficient resources to serve the load underlying PJM’s forecast that was the basis for its calculation of the shortfall the RBP is attempting to address.46 For example, in his Affidavit,47 Mr. Bednarczyk explains that the PJM RBP Proposal is not just and reasonable because, as proposed, the RBP “creates cost, credit, collateral, and risk- allocation obligations that do not consistently satisfy the principles of transparency, traceability, and cost causation.”48  He also provides an analysis as to why the RBP’s cost-and-risk allocation

46 See PJM Interconnection, L.L.C., Presentation to Post-CIFP Workshop, Reliability Backstop Procurement Execution, at 11 (Aug. 10, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260810/20260810-pjm-and-cra-reliability-backstop-procurement-presentation.pdf (showing Table B9b from the 2026 PJM Load Forecast, which shows EKPC’s initial share of RBP Charges and Allocation to be “0”).
47 Attachment 1, Affidavit of Adam Bednarczyk (“Bednarczyk Affidavit”).
48 Bednarczyk Affidavit at P 7.

PDF page 12

12
mechanism fails because a “generalized showing of regional reliability need” is insufficient to support the “particular RBP rate design” under FPA section 205,49 and the zonal or Electric Distributor cost allocation process does not ensure the assignment of RBP obligations to the specific LSE responsible for supplying the large load. Moreover, he explains why Electric Distributors are not the same as RAA load-serving parties, and therefore, the conventional role for Electric Distributors does not appropriately extend to assigning wholesale cost responsibility.50 Mr. Bednarczyk explains how the RBP converts what should be a targeted, incremental large-load cost-causation problem into a generalized load-ratio obligation that penalizes self-supply LSEs that acted prudently and rewards policies that incentivize inadequate resource planning.51 Additionally, the RBP as proposed “does not directly assign RBP obligations to the LSE responsible for serving the large load that creates the procurement need.”52 This may create an incentive, as Mr. Bednarczyk explains, that will “encourage parties to focus on allocation outcomes rather than on actions that reduce the reliability impacts of adding large loads without corresponding resources or curtailment arrangements.”53

The Affidavit of Mr. Carl Coscia further elaborates on the concerns with PJM’s credit and collateral elements of the RBP proposal. The credit and collateral requirements also fail to satisfy the Commission’s just and reasonable standard.54 The proposed collateral requirements do not secure a measured exposure,55 and an LSE cannot calculate its collateral posting requirements 49 Bednarczyk Affidavit at P 7.

50 Bednarczyk Affidavit at P 42.
51 Bednarczyk Affidavit at PP 7, 9, 12, 18.
52 Bednarczyk Affidavit at P 12.
53 Bednarczyk Affidavit at P 12.
54 Attachment 2, Affidavit of Carl F. Coscia (“Coscia Affidavit”).
55 Coscia Affidavit at PP 7, 120.

PDF page 13

13
based on the Tariff language proposed.56 Also, PJM proposes to reduce the applicable collateral requirements over time, but does not propose a schedule or precise method for doing so.57 And if there is no reduction, the posted collateral amount may exceed exposure by the 2036/2037 delivery year.58 Moreover, that approximately $10.2 billion “becomes due at a single moment, from a single class of participants, in two instruments,” creates a systemic liquidity risk, which could be managed by proper sequencing, but is not managed by the RBP proposal.59

PJM also performed its own exposure analysis before filing and then departed from it. In the Credit and Securitization Overview presented March 4, 2026, PJM modeled the procurement as a fixed-for-float swap and produced a potential future exposure curve that begins at zero, peaks below $1.2 million per MW within roughly the first third of the term, and then amortizes to zero by expiration.60 PJM then filed a flat $1.5 million per MW Credit Rate.61 This is not a case in which PJM lacked analysis regarding credit exposure; it is a case in which PJM had analysis and did not use it.

The RBP Proposal also creates an unjustified distinction among entities that have taken similar resource adequacy actions with respect to the exclusion of FRR entities but not RPM self- supply entities.62 As proposed, PJM allows an FRR entity that satisfies its resource adequacy obligations through qualifying owned and some portion of existing resources to be “insulated from

56 Coscia Affidavit at PP 7, 108.
57 Coscia Affidavit at PP 109-121.
58 Coscia Affidavit at PP 116.
59 Coscia Affidavit at PP 136-153.
60 PJM Interconnection, L.L.C., Presentation to Reliability Backstop Procurement Workshop, Credit and Securitization Overview, at 12 (Mar. 4, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm- presentation.pdf (“PJM March 4 Credit Overview Presentation”).
61 PJM RBP Filing at 116-117.
62 Bednarczyk Affidavit at PP 59-60.

PDF page 14

14
RBP exposure.”63 In contrast, an RPM Capacity Market LSE that has likewise prudently planned to serve its load does not receive comparable treatment under the proposed RBP cost-allocation framework.64 As explained in Mr. Bednarczyk’s Affidavit, this raises comparability concerns65 and results in undue discrimination between similarly situated participants in the PJM market. Moreover, the ambiguity PJM has introduced with respect to what qualifies as an existing resource for an FRR entity creates additional market design concerns, particularly for entities that rely heavily on long-term, bilateral contracts.66

The PJM RBP Proposal creates unmitigable financial and reliability risk for LSEs that prudently planned for their load or otherwise did not cause the residual RBP procurement need. It also creates a potential significant burden for those LSEs that may not have sufficiently planned and may have anticipated costs from RBP associated with only their contribution to the need. If the weight of the imposed burden causes defaults, that increases risk for the entire market. The financial and reliability risks and burdens imposed on all market participants will inhibit growth and ultimately discourage investment in the PJM region. Moreover, and most strikingly, the RBP Proposal also undermines the Administration’s and PJM state Governor’ ratepayer-protection objectives because it has the potential to shift large-load-driven costs to customers and LSEs that did not create the need for those costs. Indeed, the default allocation provision explicitly would assign costs to all LSEs in a zone/area without regard to whether those affected zones/aeras serve a new large load.  Therefore, the Commission should reject the RBP Proposal.

63 Bednarczyk Affidavit at P 60.
64 Bednarczyk Affidavit at P 60.
65 Bednarczyk Affidavit at P 60.
66 Bednarczyk Affidavit at P 63.

PDF page 15

15
A. The PJM RBP Proposal is Not Just and Reasonable.
a. PJM’s RBP Proposal is Unjust and Unreasonable Because the Resulting
Rate Impact is Uncertain.
Under section 205 of the FPA, rates must be “just and reasonable.”67 Section 205(c) of the FPA “requires rate filings to recite ‘the … practices … affecting such rates and charges.’” The Commission’s regulations also require rate schedules to set forth “clearly and specifically … the classifications, practices, rules and regulations affecting such rates, charges, classifications, services … ”68 The PJM RBP Proposal does not provide sufficiently bounded and causation-based inputs for determining which LSE is responsible for RBP charges. The PJM RBP Proposal does not explain how qualifying offsets or opt-outs follow the responsible LSE such that its allocation appropriately can be calibrated or reduced to zero. Nor does it make clear when collateral obligations attach. Relying on the Electric Distributor and RERRA to make determinations or otherwise effectuate downstream processes does not replace the need to ensure the appropriate wholesale entity is allocated the costs. Therefore, the cost allocation put forward as part of the PJM RBP Proposal fails to meet this standard, and is not just and reasonable.

The Commission has rejected proposed cost allocations when the proposals, like the PJM RBP Proposal here, lack specificity or do not allow impacted customers to be able to estimate the cost impact. In California Power Exchange Corp., for example, the Commission rejected the cost allocation plan of the California Power Exchange Corporation (“PX”) for its Block-Forward Market because the plan “lack[ed] specificity with regard to items which will not be directly assigned” and “ha[d] not linked the allocation methodologies to particular costs to be allocated.”69

67 16 U.S.C. § 824d (2018). 68 18 C.F.R. § 35.1(a). See also City of Cleveland v. FERC, 773 F.2d 1,368, 1,376 (D.C. Cir. 1985) (citing 18 C.F.R. §§ 35.1(a), 35.2(b)).
69 Cal. Power Exch. Corp., 88 FERC ¶ 61,249, 61,795 (1999).

PDF page 16

16
PX argued that it was “impossible to be more explicit about the methodologies for allocating specific costs” because the Block-Forward Market was “in [its] infancy,” but the Commission was “not persuaded by PX’s unsupported claim” and directed the PX to “clarify and support which cost allocation methodology is applicable to each particular cost category.”70 As with the PX cost allocation proposal, the cost allocation proposed in the PJM RBP Proposal lacks specificity and does not provide sufficiently bounded and causation-based inputs for determining which LSE is responsible for RBP charges. Therefore, the Commission should similarly reject the PJM RBP Proposal.

Similarly, in Tri-State, the Commission issued a show cause order finding Tri-State Generation and Transmission Association Inc.’s (“Tri-State”) Contract Termination Payment (“CTP”) calculations were impermissibly vague.71 The Commission held that Tri-State’s Open Access Transmission Tariff, Bylaws, and Rate Schedules (“Tri-State Tariff”) was “impermissibly vague because it lack[ed] detailed procedures governing when and how a utility member may obtain a CTP methodology calculation.”72 The Commission found that since the CTP methodology relied on information proprietary to Tri-State, “utility members cannot estimate their own CTP payments or reasonably predict the impacts of a membership withdrawal.”73 The Commission reasoned that the failure to provide “clear and transparent procedures” makes it “difficult, if not impossible, for Tri-State’s members to make a reasoned assessment as to whether to terminate their membership.”74

70 Id.
71 Tri-State Generation & Transmission Ass’n, 175 FERC ¶ 61,229 (2021).
72 Id. at P 12.
73 Id.
74 Id. at P 13.

PDF page 17

17
As was the case in Tri-State, PJM has failed to provide “clear and transparent procedures” to allow an LSE to determine the amount of costs it may be allocated under the PJM RBP Proposal. As Mr. Bednarczyk explains, the RBP cost allocation process proposed by PJM “does not provide a transparent means for an LSE to assess its wholesale RBP exposure, evaluate the benefits of qualifying offsets or opt-outs, understand its related credit obligations, or determine whether its actions will make it reliability neutral.”75 Pursuant to the PJM RBP Proposal, only certain LSEs in the zone/area may be charged, or all LSEs in a zone/area will be charged.76 But, the responsible LSE is not known with sufficient specificity based on the PJM RBP Proposal. It both depends on the Electric Distributor RBO allocation determinations, possibly informed by the RERRA, and the Delivery Year to Delivery Year changes to large load growth over the 15-year duration. PJM has not proposed to lock in the allocation in the first Delivery Year in which the costs will be allocated. LSEs will be assigned costs each Delivery Year over the 15-year duration.  Moreover, PJM does not propose to insulate any LSE that provided Qualifying RBP Offset UCAP MW or accepted Opt-Out to decrement the procurement target from costs associated from the RBP procurement. The RBP Proposal is silent in this regard.  Most concerning, PJM’s proposal for a default allocation methodology, should the Electric Distributor not report an RBO, is that all LSEs in the zone/area will be held accountable to pay the costs PJM assigns to the zone/area, regardless of whether they serve any large load or contributed to the need for backstop procurement.  The uncertainty of being assigned costs, as well as the magnitude of the costs that may be assigned, should the large loads not materialize in each zone/area as PJM anticipated in establishing the procurement target, will itself impact whether large loads materialize as forecasted.77  It is nearly impossible for an LSE,

75 Bednarczyk Affidavit at P 14.
76 PJM RBP Filing at 96-100; Croop Affidavit at 41 (costs are allocated based on RBO).
77 Bednarczyk Affidavit at PP 52-53.

PDF page 18

18
based on the information available to it in PJM’s RBP Proposal, to determine the amount of costs it may be allocated. Therefore, the Commission should reject the RBP Proposal.

The PJM RBP Proposal is also distinguishable from Commission-approved formula rates in which the resulting rate may not be known with exact precision at the time of filing or in future years as the formula rate is implemented.  But the PJM RBP Proposal lacks the important guardrails that make formula rates acceptable. For example, the D.C. Circuit has noted that “the Commission’s acceptance of formula rates is premised on the rate design’s ‘fixed, predictable nature,’ which both allows a utility to recover costs that may fluctuate over time and prevents a utility from utilizing excessive discretion in determining the ultimate amounts charged to customers.”78 The D.C. Circuit acknowledged that “there is undoubtedly some irreducible minimum of detail needed for a valid formula rate.”79 However, the court emphasized that “the amount of the detail in a formula rate is not the dispositive consideration.”80 The key question is not whether a rate filing falls short “of some absolute prescribed standard literally set forth in the statute and regulations,” but “of the minimum specificity that the Commission could reasonably require.”81

Here, PJM’s proposed cost allocation is neither fixed nor predictable. The problem is not merely that the final dollar amount to be allocated may be calculated later; formula rates often involve later inputs and the Commission has found that may be just and reasonable. The PJM RBP Proposal does not adequately define who is responsible for the charges (which affects how much

78 Pub. Utils. Comm’n of Cal. v. FERC, 254 F.3d 250, 254 (D.C. Cir. 2001) (citing Ocean State Power II, 69 FERC 61,146, 61,552 (1994)) (“PUC”).
79 PUC, 254 F.3d at 255 (citing City of Cleveland v. FERC, 773 F.2d 1368, 1376–77 (D.C. Cir. 1985)).
80 Id.
81 Id.

PDF page 19

19
of the zone/area assigned costs any individual LSE may receive) or how the charges are tied to incremental cost causation.

PJM’s RBP Proposal also lacks critical details regarding how changes that could impact cost allocation will be accounted for. For example, EKPC presumes that PJM will not bill for the costs associated with generators that do not come online and therefore have not satisfied their requirements to be eligible for payment. But, that is not specified anywhere in the PJM RBP Proposal.  EKPC also presumes that the zone/area allocation will change Delivery Year to Delivery Year because large loads are projected to continue growing. PJM’s proposal is silent as to how load growth between Delivery Years over the 15-year horizon of the RBP obligation will be handled.  Certainly, under the proposed default allocation methodology, LSE obligations would change Delivery Year to Delivery Year.  It is unclear how LSEs could discern their obligation, and it is unclear how PJM would manage the credit obligation in such situations.82 PJM appears to assume, based on its proposed credit provisions, that the obligation is fixed in the first Delivery Year during which costs would be assigned, and can only decrement at some point, without explaining how, in the future.

PJM assumes that a RERRA can determine a cost allocation methodology that fixes the concerns caused by PJM’s decision to allocate costs to zone/areas and not directly to LSEs causing the need for the RBP procurement.  However, PJM has not explained the impact on a cost allocation if a zone crosses state boundaries. States or RERRAs must be able to ensure that costs are appropriately allocated to the correct entities. But, that assumes that the costs are correctly allocated in the first instance at the PJM level. If a zone/area crosses state or RERRA boundaries (for example, the Dominion Energy zone, which is in both Virginia and North Carolina), under the

82 See Coscia Affidavit at P 47.

PDF page 20

20
PJM RBP Proposal, a state may not be able to fully assign the costs to the correct entities because it will not know who is responsible for the charges (since PJM is not tracking that large load information), and the state will only be able to determine the cost allocation and assignment to the customers in its state. It is also unclear whether PJM is properly using the information from Table B9b from the 2026 PJM Load Forecast to ensure Electric Distributor zone/areas receive correct allocations from PJM.83 For example, North Carolina Electric Membership Corporation (“NCEMC”) is located in the Dominion Energy zone. But, the NCEMC area is not currently reflected as “0” in PJM’s Initial Allocation to Electric Distributor zone/area table. Therefore, as initially presented by PJM, NCEMC could be subject to some kind of cost allocation if the cross- state cost allocation is not appropriately determined.

Moreover, PJM’s proposal to use a default allocation based on Daily Unforced Capacity Obligation if the more targeted allocation process does not produce an LSE-specific result is also unjust and unreasonable. When a state or RERRA has not determined an RBO for LSEs within a zone/area, PJM defaults to allocating costs based on each LSE’s Daily Unforced Capacity Obligation ratio share. This backup methodology socializes RBP costs across all load within the zone – including LSEs serving customer bases that contributed nothing to the capacity shortfall. This violates the fundamental principle that “costs must be allocated to entities that cause them.”84 As explained in the Bednarczyk Affidavit, the “Daily Unforced Capacity Obligation is a broad capacity allocation metric,” and “it does not identify the LSEs that created the residual procurement need.”85 Reliance on a preexisting cost allocation methodology that may have been

83 See PJM Interconnection, L.L.C., Presentation to Post-CIFP Workshop, Reliability Backstop Procurement Execution, at 10, (Aug. 10, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260810/20260810-pjm-and-cra-reliability-backstop-procurement-presentation.pdf.
84 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254. at 1260 (D.C. Cir. 2018).
85 Bednarczyk Affidavit at P 17.

PDF page 21

21
approved as just and reasonable in a different context does not provide justification to use it as the default methodology in this case. And hoping that the Electric Distributor or state/RERRA determines an appropriate allocation methodology such that PJM’s proposed default methodology may be avoided is clearly insufficient too.

The Commission must support its rate design decisions with “substantial evidence.”86 PJM has offered no evidence that allocating costs based on total zonal load obligations bears any reasonable relationship to the load growth that caused the shortfall. LSEs with no or minimal large load growth may nonetheless be allocated disproportionate costs due to improper accounting of the offsets and opt-outs or the use of the default allocation methodology. The vagueness inherent in PJM’s proposal virtually assures this. PJM’s proposal provides no clear nexus between cost causation and cost allocation. For example, even where an LSE such as EKPC has not been shown to cause or contribute to the RBP procurement target, PJM’s RBP Proposal will leave EKPC exposed to other LSEs’ payment default risk, and potential associated collateral requirement risk, because PJM has proposed mechanisms that do not reliably assign costs to the LSEs that caused the incremental need. PJM’s RBP Proposal is unjust and unreasonable.

b. The Proposed Collateral Requirements are Unjust and Unreasonable.
PJM’s proposed collateral requirements further exacerbate the unjustness and
unreasonableness of PJM’s RBP Proposal’s cost allocation because an LSE’s RBP credit requirement will be aligned with its cost allocation.87 If an LSE’s cost allocation cannot be determined with specificity based on PJM’s RBP Proposal, its credit requirement will also be

86 See, e.g., Elec. Consumers Res. Council v. FERC, 407 F.3d 1232, 1233 (D.C. Cir. 2005) (“Upon applying the usual APA standard, we conclude that the Commission’s approval of the rate design is supported by substantial evidence in the record and is not otherwise arbitrary and capricious.”).
87 PJM RBP Filing at 118. See also Bednarczyk Affidavit at P 26.

PDF page 22

22
uncertain. A collateral requirement may only be just and reasonable if it stems from “clear and consistent credit policies.”88 Under PJM’s RBP Proposal, PJM will first calculate an aggregate collateral requirement.89 Then, PJM will allocate that collateral requirement to individual LSEs.90 An LSE should not have to post substantial RBP collateral for an obligation that PJM has not properly linked to exposure. As Mr. Coscia notes, there is a timing gap evident in the load requirement that demonstrates that this requirement is not tied to exposure.91 Mr. Coscia explains that “[c]ommitments bind when results post on December 2, 2026,” and the first Delivery Year’s exposure is known at the moment the commitment binds because the “2028/2029 [BRA] has already cleared at $325.00/MW-day.”92 Then, “[t]he 2029/2030 results post on December 22, 2026.”93 Therefore, within three weeks of commitment (i.e., December 2, 2026), “two Delivery Years are priced, and on the adjusted target of approximately 6,000 MW the exposure they represent is approximately $1.0 billion, taking the 2029/2030 year at the $333.44 proxy” defined in Mr. Coscia’s Affidavit. This is exposure that has been quantified, yet PJM requires no collateral at all until roughly April 17, 2028.94 Rather, PJM requires “approximately $9.1 billion on the same target against an exposure it has never quantified, beginning at the point when a substantial part of the position has become knowable and is no longer in doubt.”95

88 Credit Reforms in Organized Wholesale Electric Markets, 133 FERC ¶ 61,060, P 2 (2010), order on reh’g, 134 FERC ¶ 61,126 (2011).
89 PJM RBP Filing at 118. 90 PJM RBP Filing at 115.
91 Coscia Affidavit at P 204.
92 Id. 93 Id. 94 Id.
95 Id.

PDF page 23

23
Moreover, it is clear from PJM’s proposal with respect to collateral requirements for sellers that neither the seller’s collateral requirement nor the LSE/buyer collateral requirement was derived from measured exposure. The two requirements imply contradictory RPM price paths. As explained by Mr. Coscia, the RBP Proposal’s proposed seller collateral is adequate only if RPM averages at or above $532.80/MW-day, and above $564 across the thirteen unpriced and uncollared years.96 But, the LSE figure corresponds to the exposure only if RPM averages at or below $281.03.97 No single price path satisfies both. This shows that neither figure was derived from measured exposure and are irreconcilably in conflict – the exact opposite of just and reasonable.

In addition, the same obligation is also collateralized twice. The RBP Charge is secured in advance by the Credit Rate, and once the Delivery Year begins and RBP Charges are billed, those same charges enter the LSE’s Peak Market Activity through the ordinary operation of Attachment Q and are secured again. Proposed Section 18.8(b) does not net the two collateral requirements.98 Moreover, an LSE should not have to post a collateral requirement based on a default allocation rather than the LSE’s own load-serving obligation and its inability or failure to provide Qualifying RBP Offset UCAP MW or Opt-Out UCAP MW.99 Nor should an LSE have to post collateral for an obligation that may be resolved later through an Electric Distributor or state/RERRA cost allocation determination. Requiring an LSE to post collateral based on any of the foregoing is unjust and unreasonable.

96 Coscia Affidavit at P 203. 97 Coscia Affidavit at P 203.
98 Coscia Affidavit at P 98.
99 Coscia Affidavit at P 51 (“[S]ection 18.8(b)(i)(B)(2) provides that the LSE ‘may be required to post’ collateral based on ‘the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.’”).

PDF page 24

24
 Section 18.8, as proposed, requires an LSE to post collateral prior to the start of a delivery year.  However, it is not just and reasonable to require an LSE to post collateral before PJM has calculated the zone/area initial allocation, applied all recognized offsets and opt-outs, finalized the zone/area LSE-specific cost allocation, and provided sufficient transparency for the LSE to understand and, if warranted, challenge the obligation. The LSE credit requirement alone is $1.5 million per committed RBP MW.100 This means LSEs could collectively face credit requirements exceeding $10 billion.101 Applying the credit requirement ahead of those steps most certainly will result in a significant credit burden being placed on LSEs that had no role in creating the reliability shortfall. What is worse, those LSEs may lack the financial capacity to absorb such obligations, leaving other LSEs in PJM to face allocations caused by an LSE defaulting on its payment obligations.

PJM’s own analysis underscores that this is not a theoretical concern. Before filing, PJM identified 105 LSEs, only 24 of which were investment grade with 81 sub-investment grade, and reported that 46 percent of LSEs had tangible net worth below $5 million and 30 percent below $1 million.102 PJM stated before filing that those figures indicated limited financial capacity. Nonetheless, PJM selected a collateral rate that would impose substantial liquidity pressure on that same population.

This risk of picking up a collateral obligation is particularly acute for smaller LSEs that do not serve a large load. Absent separate collateral support from a large load customer under a supply agreement, the required collateral could be significant relative to the LSE’s financial resources and could impose material financial harm. The disproportion is evident on either measure of the

100 PJM RBP Filing, Attachment D, “Affidavit of Ms. Gwen Kelly” at P 33.
101 See Coscia Affidavit at PP 7, 62-71.
102 Coscia Affidavit at PP 138, 192. See also PJM March 4 Credit Overview Presentation at 7.

PDF page 25

25
obligation secured. The RBP settles as a contract for differences, meaning that in each Delivery Year, load pays the difference between the RBP price and the RPM clearing price, not the RBP price itself.103 Measured against the maximum gross annual commitment value before any offset for RPM revenues – approximately $1.38 billion at the $555 maximum willingness to pay and the Initial RBP Target – the proposed collateral requirement of approximately $10.2 billion is approximately 740% of one year’s gross commitment value.104 But that gross figure is not the amount billed to load. At the 2028/2029 Base Residual Auction clearing price of $325.00/MW- day, the amount billed to load in the first Delivery Year is approximately $573 million, against which the collateral requirement is approximately 1,790%.105 PJM has thus sized collateral as though load owed the full contract price, when the Tariff obligates load to pay only a difference between two prices.

That burden is particularly stark in the zones receiving the largest allocations. Under PJM’s own allocation, the NVEC zone is assigned 1,302.6 RBP UCAP MW, translating into approximately $1.954 billion of collateral at the proposed $1.5 million Credit Rate.106 For the cooperative serving that zone, the requirement exceeds total assets of roughly $1.716 billion, total equity and margins of approximately $920 million, and cash and temporary investments of only about $243 million.107 Even at a carrying cost of just 100 basis points, maintaining that collateral would consume roughly 94% of a year’s operating margins, with the burden rising substantially at higher financing costs.108 If a requirement of this magnitude strains the balance sheet of an

103 Coscia Affidavit at P 67.
104 Id. 105 Id.
106 Coscia Affidavit at P 140.
107 Coscia Affidavit at P 141.
108 Coscia Affidavit at P 142.

PDF page 26

26
investment-grade, member-owned cooperative operating without a parental guarantee, PJM’s own data raise serious concerns about its impact on the broader LSE population, 77% of which PJM classified as sub-investment grade and 46% of which have tangible net worth below $5 million.109 Neither figure bears any relation to PJM’s own practice. PJM’s collateral across every market it operates and every class of participant in them has run between approximately nine and thirteen percent of annual market activity. The proposed requirement is therefore between approximately fifty-seven and eighty-five times that intensity measured against gross commitment value, and between approximately 138 and 206 times measured against the amount actually billed to load. The magnitude of this proposed collateral requirement “stands apart from anything in PJM's experience.”110 An unprecedented collateral requirement with such significant uncertainty cannot be just and reasonable.

While PJM consents in advance to the Commission modifying or severing any element of the proposed Tariff and RAA language,111 there is an insufficient basis for the Commission to provide a substitute collateral requirement that is justifiable and reasonable. PJM’s consent supplies authority to modify; it does not supply a record to modify on. As Mr. Coscia explains, the appropriate requirement cannot be determined from the filed formula alone, the analysis on which any rate would rest was never performed, and the present record does not contain the participant- specific financial and liquidity information needed to perform it.112 Selecting a substitute figure on

109 PJM March 4 Credit Overview Presentation at 7.
110 Coscia Affidavit at P 61.
111 PJM RBP Filing at 3.
112 Coscia Affidavit at PP 209-210.

PDF page 27

27
this record would repeat the defect rather than cure it. There is no support for the Commission to make such a determination off.113

The RBP Proposal collateral requirements are also unjust and unreasonable because the requirement is not distributed evenly but instead is concentrated among LSEs that receive RBP Obligations.114 This creates systemic liquidity risk among the entities required to post collateral at the proposed levels. In an example prepared by Mr. Coscia, the Northern Virginia Electric Cooperative (“NOVEC”) Zone illustrates this risk.115 Based on PJM’s RBP Proposal, NOVEC’s initial allocation (RBP UCAP MW) is 1302.6 MW, and a Zonal Collateral Obligation at $1.5 million per MW results in a $1.954 billion collateral requirement.116 The cooperative serving this zone has $1.716 billion of total assets, $243.2 million of cash and temporary investments, and $34.4 million of cash collateral already posted to PJM, which continues to be required.117 Considering the most favorable assumptions available, the cost to maintain a letter of credit in these circumstances could be approximately $19.5 million annually (or much more, as explained by Mr. Coscia) and that cost would have to be borne by the cooperatives’ customers.118 This example is illustrative of the systemic risk but “is not the limit of the problem.”119 The concentration problem also extends to the instruments PJM expects LSEs to use. As of July 30, 2026, PJM held approximately $6.87 billion in letters of credit issued by 43 institutions,

113 PJM distinguishes NRG Power Marketing LLC v. FERC, 862 F.3d 108 (D.C. Cir. 2017) on the grounds that the RBP Proposal was Board-authorized and not stakeholder-endorsed. See PJM RBP Filing at 3, n.8. However, here, the PJM Board rejected a stakeholder-endorsed proposal that received the only sector-weighted supermajority, the Coalition RBP Proposal.
114 Coscia Affidavit at P 139.
115 Mr. Coscia prepared this example based on publicly available data in a federal regulatory filing.
116 Coscia Affidavit at PP 140-41.
117 Coscia Affidavit at P 141.
118 Coscia Affidavit at PP 142-43.
119 Coscia Affidavit at P 144.

PDF page 28

28
with the ten largest accounting for approximately 65 percent and two individual institutions each exceeding 10 percent.120 Satisfying the RBP requirement predominantly through letters of credit would more than double PJM’s letter-of-credit exposure, drawn substantially from the same institutions.

It is important to note that if the collateral obligation cannot be met, as proposed by PJM, it would not be extinguished.121 Instead, Tariff Section 18.9(a) reallocates the defaulted charge pro rata to the remaining LSEs, and Operating Agreement (“OA”) Section 15.2.2 extends what remains to Members in the residual tier with no RBP allocation at all, like EKPC. Therefore, an entity like EKPC, which is not anticipating any RBP Obligation in its zone/area,122 is still at risk and no party is posting collateral against that exposure. This astonishing misalignment of collateral obligations and cost causation severely runs afoul of the Ratepayer Protection Pledge and is plainly unreasonable and unjust.

c. PJM’s Proposal with respect to Decrementing the Procurement Target and
Crediting Offsets Is Unjust and Unreasonable.
PJM’s proposed RBP uses “decrementing” in two primary contexts. First, the Initial RBP Target is decremented pre-procurement by Qualifying RBP Offset UCAP MW and opt-out MW to arrive at the Final RBP Target.123 Second, post-procurement, committed RBP UCAP MW may be effectively reduced through generation rescission for failure to materialize, changes in ELCC- based accreditation, or Transmission Owner exit scenarios, each of which carries distinct financial

120 Coscia Affidavit at P 146 (citing PJM Interconnection, L.L.C., Presentation to Risk Management Committee, Credit Risk Metrics, 4 (Aug. 18, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/rmc/2026/20260818/20260818-informational-only---credit-metrics---august-2026.pdf).
121 See Coscia Affidavit at P 153.
122 Coscia Affidavit at PP 169-70.
123 PJM RBP Filing at 35; Proposed Tariff Section 18.1(b).

PDF page 29

29
and credit consequences.124 PJM’s RBP Proposal does not, however, adequately distinguish between reducing the aggregate procurement target for any of those reasons and shielding LSEs whose qualifying supply offsets reduced the procurement target amount. There is no provision in the proposal that requires such LSEs to be insulated from RBP charges. A reduction in the regional or zonal procurement target is not equivalent to an LSE-specific cost-allocation credit.  As noted by Mr. Bednarczyk, “reducing the aggregate procurement target is not the same as protecting the LSE that supplied or sponsored the offset from RBP Charges, collateral obligations, or default- allocation risk,” and therefore, “[t]he tariff should clearly state whether, and how, a recognized offset follows the associated LSE or load when PJM calculates LSE-specific RBO MW, RBP Charges, and collateral requirements.”125

Additionally, PJM’s failure to explicitly shield LSEs from cost assignment is especially problematic for LSEs who did not contribute to the need for the RBP procurement. There is no provision that insulates them from RBP charges either. And given the duration of the obligations imposed by the RBP – obligations that could last as long as 15 years – the risk is more significant than a standard double payment. As Mr. Bednarczyk highlights, “an LSE that has already planned prudently and secured adequate resources could nonetheless incur a second long-term obligation that provides little or no additional reliability benefit. That outcome weakens incentives for proactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning LSE exposed to residual charges, collateral obligations, and default-allocation risk.”126 PJM is allowing decrementing of the procurement target only for providing qualifying new generation supply, while failing to provide comparable recognition for existing owned resources,

124 PJM RBP Filing at 55, 60-61, 94-95.
125 Bednarczyk Affidavit at P 27.
126 Bednarczyk Affidavit at P 34.

PDF page 30

30
long-term bilateral contracts, or other forward actions that may already support an LSE’s incremental load obligations.127 That restriction ignores prudent planning and ignores the Commission’s cost-causation principles.

To be just and reasonable and not unduly discriminatory or preferential under FPA section 205,128 rates must reflect the cost causation principle that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.”129 The Commission analyzes compliance with the cost causation principle “by comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party.”130 Courts have held that to “the extent that a utility benefits from the costs of new facilities, it may be said to have ‘caused’ a part of those costs to be incurred, as without the expectation of its contributions the facilities might not have been built, or might have been delayed.”131 The courts have emphasized that the Commission must have an “articulable and plausible reason to believe that the benefits are at least roughly commensurate with” the allocation of the costs.”132 And it is the Commission’s fundamental mission to ensure that rates satisfy that standard.133

PJM’s RBP Proposal with respect to decrementing fails to meet this cost causation requirement in numerous ways. For example, even where PJM recognizes Qualifying RBP Offset UCAP MW, the proposed Tariff revisions do not clearly require the corresponding benefit to reduce the RBO MW, RBP charge, or collateral exposure of the LSE or load that supplied the

127 PJM RBP Filing at 35-36. 128 16 U.S.C. § 824d (2018).
129 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).
130 Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004).
131 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).
132 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).
133 See, e.g., FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277 (2016).

PDF page 31

31
offset. Under either the Electric Distributor (with state/RERRA support) allocation determinations, or the PJM default allocation mechanism, an LSE that supplied qualifying offsets or already has sufficient existing capacity resources may still pay RBP costs and be required to post collateral because it is not guaranteed it will receive the benefit of any offsetting decrement. As explained by Mr. Bednarczyk, “[i]f the benefit of a Qualifying RBP Offset UCAP MW is applied only at a zonal or Electric Distributor level and is not traced to the LSE that undertook the mitigation action, the proposal weakens the incentive for voluntary forward procurement and load-management measures.”134 Without a rule requiring offsets and existing-supply recognition to follow the responsible LSE or load, the RBP unfairly socializes the benefit of prudent resource planning while leaving those LSEs that adequately covered their load obligations exposed to residual charges and collateral. That result violates the Commission’s cost-causation principles because costs may be assigned to loads that did not cause the need for those costs. Therefore, the PJM RBP Proposal is also unjust and unreasonable for yet another reason.

d. PJM’s RBP Proposal is Not Just and Reasonable Because it Lacks a
Locational Requirement.
PJM seeks approval of a 15-year, region-wide backstop procurement but has not shown that the procured capacity will be deliverable to, or operationally useful for, the loads identified as driving the need for the procurement and responsible for its costs. Under FPA section 205, that showing is an important element of establishing that the proposal is just and reasonable. The fact that a procurement adds capacity somewhere in the PJM region does not, by itself, demonstrate that it will address the specific reliability concern identified by PJM or that the allocation of costs is reasonably aligned with expected benefits. The filing does not provide sufficient support on

134 Bednarczyk Affidavit at P 38.

PDF page 32

32
these points. PJM proposes to allow resources that satisfy the eligibility criteria to locate anywhere in the PJM region without regard to the Capacity Emergency Transfer Objective/Capacity Emergency Transfer Limit analysis that underlies the RPM Capacity Market Locational Deliverability Areas (“LDAs”). However, the existence of LDAs under Tariff Attachment DD reflects that there are load pockets and constrained areas in PJM where transmission import capability limits the operational value of remote capacity. Capacity that is not deliverable to constrained load areas may not solve the reliability need that PJM invokes to justify the RBP, even though LSEs and customers may still be charged for it.

PJM’s explanation that it does not project and calculate locational parameters 15 years into the future does not satisfy its burden under FPA section 205. The question is not whether PJM can forecast every future constraint with precision; it is whether PJM has provided substantial evidence that a non-locational, region-wide procurement is a just and reasonable means of addressing the stated reliability need. PJM has not done so. Ms. Croop acknowledges that PJM “does not project and calculate” locational parameters “15-years out” and therefore cannot apply locational constraints in the RBP.135 However, that asserted forecasting limitation does not justify eliminating locational analysis altogether, particularly where PJM already recognizes persistent constraints through existing LDA constructs and where the Coalition RBP Proposal included an element designed to account for the locational benefits of offered capacity resources. PJM’s own 2028/2029 BRA Report confirms that locational scarcity is not speculative. In the uncapped auction results reported shortly before PJM filed, the auction cleared at

135 Croop Affidavit at P 8.

PDF page 33

33
$554.72/MW-day except for ComEd, which cleared at $776.69/MW-day.136 The prior delivery year similarly showed Dominion clearing separately.137 The reason no LDA appeared constrained in the filed auction results was not that location had ceased to matter; it was that the collar and overall shortage produced a flat result. PJM should not be permitted to rely on a capped auction result to prove that location is irrelevant when its own uncapped run of that auction showed the opposite.

The same locational disconnect is particularly harmful when viewed with PJM’s
companion IRAS proposal in Docket No. ER26-3515. IRAS would curtail large loads when the region is short, and curtailment necessarily turns on local system conditions. A resource electrically remote from the constrained pocket does not relieve the local condition that triggers curtailment there. Thus, an LSE could pay RBP charges and post collateral for 15 years and still face curtailment because the RBP resource procured with those payments is not deliverable to the location where the need arises. That is a concrete injury, not a theoretical objection. Nor does PJM’s forecasting objection withstand scrutiny. PJM says a 15-year locational requirement would be speculative, but the proposal fixes the quantity at 6,831.3 MW for 15 years, fixes each zone’s share based on the 2026 Load Forecast, and fixes the conversion factor at 0.9401 under proposed section 18.3(a).138 Even that conversion factor did not remain stable for three weeks: after filing, PJM asked stakeholders to endorse a 0.9232 conversion factor for the next

136 PJM Interconnection, L.L.C., 2028/2029 Base Residual Auction Report, at 17 (July 14, 2026) available at: https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra-results- report.pdf (“2028/2029 BRA Report”).
137 2028/2029 BRA Report at 17.
138 Croop Affidavit at PP 46-47.

PDF page 34

34
delivery year.139 If a 15-year horizon is too speculative to site supply, it is too speculative to freeze who pays and in what amount.

Without a locational requirement or comparable deliverability showing, the RBP may procure capacity that is concentrated in areas that do not address localized reliability needs. That outcome would leave the Commission approving a charge for capacity that may not mitigate the locational RPM Capacity Market impacts, reliability risks, or operational constraints that PJM cites as the basis for the proposal. Worse, if RBP resources are electrically distant from constrained load pockets, PJM may later need to rely on out-of-market actions or additional Regional Transmission Expansion Plan transmission projects to make those resources useful to the load that allegedly caused the need. In that circumstance, unrelated LSEs and customers could be required to pay twice: first through RBP charges for capacity that is not deliverable where needed, and later through transmission-related cost allocation to address the transmission constraints the RBP failed to account for. That result is inconsistent with the Commission’s cost-causation principles and would expose the Commission to approving a rate design that imposes substantial long-term costs without substantial evidence that the procurement will produce commensurate reliability benefits. PJM’s RBP Proposal therefore fails to establish the required nexus among the identified reliability need, the location and deliverability of procured resources, and the LSEs and customers assigned the resulting costs. For these reasons, the Commission should find PJM’s RBP Proposal unjust and unreasonable.

139 PJM Interconnection, L.L.C., Presentation to Markets & Reliability Committee, Installed Reserve Margin (IRM), Forecast Pool Requirement (FPR), and Effective Load Carrying Capability (ELCC) for 2029/2030 BRA, at 11 (Aug. 19, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260819/20260819- item-03---2029-2030-bra-irm-fpr---presentation.

PDF page 35

35
B. The Role of Electric Distributors, States, and RERRAs in PJM’s RBP
Proposal Is Improper, Administratively Incomplete, and Not a Substitute for
a Just and Reasonable Rate Design.
Electric Distributors’ Commission-approved function in the PJM market is limited. An Electric Distributor’s function largely consists of managing meter-data and administrative, technical functions. The previously determined role of an Electric Distributor is limited and fundamentally different than assigning wholesale cost responsibility for a long-term backstop procurement.

In its RBP Proposal, PJM assigns to Electric Distributors the performance of functions that go well beyond ordinary meter-data or administrative responsibilities.140 Electric Distributors are assigned responsibility for requesting the MW quantity of load in the zone/area that will be decremented from the Initial RBP Target and opted-out of the Final RBP Target. Electric Distributors must specify the MW quantity of load to be decremented where the Electric Distributor’s zone/area has rates that are not regulated by the states and is unable to address cost allocation associated with capacity procured in the backstop. As part of such a request, Electric Distributors must include “written support for such opt-out from the relevant state governor, RERRA, and interconnection customer(s).”141 Electric Distributors may also request the Initial RBP Target be further decremented by up to the associated MW quantity of load that participates in a peak shaving adjustment program codified in state law.142

 PJM’s RBP Proposal requires Electric Distributors to effectively set allocation inputs for a Commission-jurisdictional charge. The allocation of these inputs impacts cost allocation and credit requirements. PJM’s RBP Proposal also requires Electric Distributors to coordinate state or

140 See Bednarczyk Affidavit at P 42 (summarizing the traditional role of Electric Distributors).
141 See Proposed Tariff, Attachment DD, Section 18.3(b)(iii).
142 Id.

PDF page 36

36
RERRA determinations, and it delegates the allocation of certain costs even though it may not be known – by PJM or the Electric Distributor – which LSEs serve the relevant large loads that should be held accountable to pay the RBP costs. In doing so, PJM shifts a significant responsibility and considerable degree of discretion to Electric Distributors.

PJM relies on OA Section 11.3 to support its proposed role for Electric Distributors. However, that OA section did not envision the Electric Distributor playing a rate-making role. OA Section 11.3 sets out a specific set of tasks for Electric Distributors in the PJM market. These include mostly technical tasks such as metering reading, providing for and arranging reactive capability and voltage control facilities, coordinating load shedding with the PJM Office of Interconnection in emergencies, maintaining and arranging control center services,  and engaging in the tasks specifically enumerated in the OA.143 That provision also requires Electric Distributors to “[p]rovide to the Office of the Interconnection all System, accounting, customer tracking, load forecasting (including all load to be served from its System) and other data necessary or appropriate to implement or administer this [OA], and the [RAA].”144 But that “catch all” provision does not justify imposing on Electric Distributors a new rate-design and cost-allocation function. This is particularly true where many entities that PJM appears to treat as “Electric Distributors” (or similarly situated distribution-level entities) may not be PJM Members or may not have contractual privity with PJM.

Under PJM’s RBP Proposal, PJM will first assign RBP costs to zones, but the Electric Distributor is then given the responsibility for translating those costs into LSE-level RBO MW. That step is not merely administrative; it is the step that determines which LSEs bear the

143 See OA, Section 11.3.3. 144 OA, Section 11.3.3(h).

PDF page 37

37
Commission-jurisdictional charge and associated collateral obligation. Under PJM’s RBP Proposal, each Electric Distributor is required to report to PJM the state- and/or RERRA- determined allocations of RBP UCAP MW to LSEs in the Electric Distributors zone/area or the “RBO.”145 The RBP Charge assessed daily to an LSE in the relevant zone will equal the LSE’s daily reported RBO MW in the zone/area divided by the total daily RBO MW in the zone, and multiplied by the total, daily RBP Charges allocated to the zone/area.146 Thus, the allocation determination sets the rate paid. The fewer the number of LSEs assigned costs, the greater an individual LSE’s proportional assignment of zone/area allocation may be.  Conversely, the larger the number of LSEs assigned costs, the lower the individual LSE’s proportional assignment of the zone/area allocation may be.

PJM proposes that the Electric Distributors would allocate the costs by LSEs’ PLC (Peak Load Contribution) if no allocation is reported by the Electric Distributor with allocated RBP UCAP MW. The intent is to allocate costs to the LSEs serving large loads. But this is an impossible task in the RBP as PJM has proposed. PJM is not tracking which large loads were in the forecast used to set the procurement target. Therefore, there is currently no way for an Electric Distributor to know which LSE should be charged.

PJM cannot make an otherwise insufficient federal rate design just and reasonable by requiring Electric Distributors, states, or RERRAs to supply the missing cost-causation analysis.147 If PJM cannot identify the responsible LSE (the entity that is the PJM wholesale customer) with sufficient specificity, shifting that task downstream to an Electric Distributor does not solve a cost

145 PJM RBP Filing at 98.
146 Id.
147 See La. Pub. Serv. Comm’n v. FERC, 337 F.3d 1066, 1077 (D.C. Cir. 2003) (“FERC may not brandish a state’s prior approval of a set of existing rates as if it were independently sufficient to satisfy the Commission’s own regulatory obligations.”).

PDF page 38

38
allocation problem that ultimately sits with PJM.148 And because PJM cannot identify the responsible LSE, the costs cannot be allocated in a way that is consistent with the Commission’s cost causation policy.149 As noted above, the Commission’s cost causation policy requires that those who cause costs to be incurred should pay for those costs, and, conversely, that those who benefit from costs should pay a portion of the costs that is roughly commensurate with the benefits received.150 PJM has not made a sufficient showing that the proposed allocations will assign costs in all circumstances to the LSEs that caused the costs to be incurred, or that LSEs that benefit from the costs will pay an amount that is roughly commensurate with the allocated costs. Rather, under PJM’s RBP Proposal, the Electric Distributor must apply judgment and gather information (or speculate about such information if no such information is available) from customers and work with the state and/or RERRAs to determine an allocation methodology. This is far beyond the scope of the OA’s intended role of an Electric Distributor. There is no precedent to support an Electric Distributor having such a role. Nor is there any indication in PJM’s original filing or the Commission’s approval of the OA that it intended Electric Distributors to be able to have such an expanded role. Therefore, PJM’s RBP Proposal has not been shown to be just and reasonable yet again.

Moreover, this is vastly different from the role the Electric Distributor plays in determining PLC associated with each LSE in its zone/area for purposes of PJM charging RPM Capacity Market costs to LSEs. In that circumstance, the Electric Distributor performs a meter-reading function to calculate all of the end-use, consumer loads served by an LSE contribution at peak, and then the RPM Capacity Market clearing prices (combination of BRA and Incremental

148 See Bednarczyk Affidavit at PP 45-46.
149 See Bednarczyk Affidavit at P 46.
150 See, e.g., Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).

PDF page 39

39
Auctions for a Delivery Year) are applied. Simply stated, this is a mathematical, mechanical exercise: in the RPM Capacity Market, the price to be assigned is known and the PLC determines the quantity against which the price is applied. All loads pay for capacity in the RPM Capacity Market. In contrast, here the Electric Distributor effectively is tasked with determining the rate each LSE pays for the RBP.  The rate may vary both by the allocation of the procurement target PJM assigns to each zone area after decrementing the procurement target,151 and further by the number of LSEs receiving a portion of the allocation based on the state/RERRA determination. And in cases in which all loads in a zone are required to pay on a Daily Unforced Capacity obligation basis (the default allocation methodology PJM proposes to use should an Electric Distributor not have an allocation method), this will spread costs across all LSEs in the zone. This expansive role assigned to Electric Distributors in PJM’s RBP Proposal thus contravenes the Ratepayer Protection Pledge and violates the Commission’s cost causation policy. As PJM acknowledges, the Commission has previously held that an Electric Distributor serves as “the party with the distribution and metering facilities defining a zone/area and responsible for reporting load information to PJM.”152 EKPC does not dispute that Electric Distributors have a role to play in the PJM market. However, reporting PLC load data to PJM, which is the role the Commission has previously recognized,153 is far different than being charged with implementing a cost allocation which has the functional effect of determining the rate of a Commission-jurisdictional product. PJM’s attempt to present this role proposed here for an

151 See Bednarczyk Affidavit at PP 26-35 (explaining, in part the impacts of PJM’s proposed decrementing). See also Proposed Tariff Sections 18.1 and 18.2 (recognize Qualifying RBP Offset UCAP MW for purposes of reducing the aggregate procurement target).
152 PJM RBP Filing at 101 (quoting PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, P 40 (2024)).
153 See PJM Interconnection, L.L.C., 188 FERC ¶ 61,200, P 40, n.65 (2024).

PDF page 40

40
Electric Distributor to be the same as the role for an Electric Distributor with respect to supporting the PLC calculation should be rejected.

The Commission lacks jurisdiction to impose such obligations on Electric Distributors directly. Additionally, Electric Distributors are defined by the OA as

a Member that: 1) owns or leases with rights equivalent to
ownership electric distribution facilities that are used to provide
electric distribution service to electric load within the PJM Region;
or 2) is a generation and transmission cooperative or a joint
municipal agency that has a member that owns electric distribution
facilities used to provide electric distribution service to electric load
within the PJM Region.154
They may or may not also engage in Commission-jurisdictional activities, i.e., wholesale sales and transmission of electric energy in interstate commerce. Accordingly, in the absence of further information, there is no way to know whether they are “public utilities” over which the Commission may exercise plenary jurisdiction under Part II of the FPA.155 And if they are not “public utilities,” then the Commission may not exercise such authority over them. Indeed, many entities that engage solely in electric distribution activities are expressly exempt from the Commission’s “public utility” regulatory authority by virtue of FPA section 201(f).156 In any event, any argument that they may have agreed to take on this role based on vague, catch-all language in the Operating Agreement should be rejected.

Additionally, under FPA section 201(b), the Commission is explicitly precluded from exercising jurisdiction over “facilities used in local distribution or only for the transmission of electric energy in intrastate commerce.”157 The FPA limits the Commission’s jurisdiction to

154 OA Definitions.
155 16 U.S.C. § 824(e).
156 See 16 U.S.C. § 824(f).
157 16 U.S.C. § 824(b)(1). See also Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 695 (D.C. Cir. 2000) aff'd sub nom. New York v. FERC, 535 U.S. 1 (2002).

PDF page 41

41
wholesale sales in interstate commerce, which includes only those rules or practices that “directly affect the wholesale rate.”158 The Commission does not have the authority to directly regulate retail sales “no matter how direct, or dramatic, its impact on wholesale rates.”159

While determination of PLCs for capacity is a meter reading function that may be appropriately delegated to an Electric Distributor, allocating RBP costs will require the exercise of discretion. This will require Electric Distributors to have knowledge of, or speculate in the absence of knowledge of, which LSE is serving large load and whether that load has resources that allowed the RBP target to be decremented. The load forecast that the RBP Target is based upon, while including information from the Electric Distributor, also will be adjusted by PJM applying its “independent judgement.”160  As a result, for several zone/areas there is no direct linkage to specific end-use consumers in that forecast that an Electric Distributor may apply. Therefore, the Electric Distributor is making an allocation decision based on knowledge outside of its control. Such an allocation cannot be just and reasonable.

C. PJM’s RBP Proposal is Inconsistent with the Boundaries of Federal and State
Jurisdiction.
PJM claims that the RBP Proposal is “the result of a carefully considered effort to respect the line between federal and state jurisdiction while simultaneously embracing PJM’s significant role in (1) meeting the region’s resource adequacy needs and (2) supporting the reliable and orderly interconnection of large loads in the region.”161 But PJM’s RBP Proposal is inconsistent with the

158 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277-78 (2016).
159 Id. at 279-80.
160 See PJM Interconnection, L.L.C., PJM Manual 19: Load Forecasting and Analysis, at Attachment B: Load Forecast Adjustment Guidelines (effective June 30, 2026); PJM Interconnection, L.L.C., Presentation to Load Analysis Subcommittee, Load Adjustment Requests Summary for 2026 Load Forecast – Preliminary, (Nov. 24, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03--- large-load-adjustment-requests-summary.pdf.
161 PJM RBP Filing at 10.

PDF page 42

42
boundaries of federal and state jurisdiction because it inappropriately places obligations on Electric Distributors and states or RERRAs. PJM’s cost allocation methodology relies on states and RERRAs to determine appropriate RBOs in order to allocate RBP to LSEs within each Electric Distributor zone/area. This “cooperative federalism” approach improperly delegates a critical component of rate design to entities that may not be parties to this proceeding and whose actions are not subject to Commission review.

PJM relies on the Commission’s determination in its order accepting Midcontinent Independent System Operator, Inc.’s (“MISO”) Revised Expedited Resource Addition Study (“ERAS”) Proposal.162 In the ERAS proceeding, the Commission found that RERRA participation in the ERAS process was permissible and not an improper delegation of federal authority to the states.163 The delegation of ratemaking authority that PJM has proposed here is distinguishable from the RERRA participation in the MISO ERAS process. The RERRA’s role in the MISO ERAS process was “limited to assessing and verifying non-speculative interconnection requests.”164 This is much more limited than the RERRA’s role in the PJM RBP Proposal where states or RERRAs are determining cost allocations to LSEs – which is within the Commission’s primary regulatory authority.

Additionally, federal agencies cannot delegate “decision-making authority … to outside entities – private or sovereign – absent affirmative evidence of authority to do so.”165 The Commission found that the MISO ERAS proposal was distinguishable from U.S. Telecom because

162 PJM RBP Filing at 105 (citing Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064, at P 99 (2025), order addressing arguments raised on reh’g, 194 FERC ¶ 61,050 (2026)).
163 Midcontinent Indep. Sys. Operator, Inc., 192 FERC ¶ 61,064, at P 99 (2025) (“MISO ERAS Order”), order addressing arguments raised on reh’g, 194 FERC ¶ 61,050 (2026).
164 MISO ERAS Order at P 101.
165 U.S. Telecom Ass’n v. FCC, 359 F.3d 554, 566 (D.C. Cir. 2004).

PDF page 43

43
“it does not subdelegate the Commission’s authority but simply creates a role for RERRAs in a Commission-jurisdictional process.”166 Here, PJM is not “simply” creating a role for RERRAs. Rather, PJM’s RBP Proposal gives significant decision-making authority and discretion to states or RERRAs through Electric Distributors by delegating the Commission’s authority over jurisdictional rates.

PJM’s RBP Proposal requires Electric Distributors to determine how to allocate RBO among the LSEs in a zone, which in turn requires states or RERRAs to play a role in establishing a Commission-jurisdictional rate. This is also true of the credit requirement associated with the procurement obligation. Collateral determination responsibilities should be reserved for entities regulated by the Commission.167 Entities imposing credit requirements or obligations are “public utilities” regulated by the Commission because these entities engage in practices that directly affect rates, terms and conditions, and therefore they should be subject to Commission regulation.168 But PJM’s RBP Proposal skirts that regulation by assigning the role of establishing credit requirements to non-jurisdictional entities by virtue of requiring the Electric Distributor to determine the LSE RBO. Technically, PJM will implement the credit requirement, but it will do so based on the Electric Distributor determinations. Therefore, PJM’s proposed delegation is inappropriate and inconsistent with the requirements of the FPA.

Moreover, not all electric distribution companies (or similar distribution-level utilities that might qualify as “Electric Distributors”) are Members of PJM. There are multiple transmission

166 MISO ERAS Order at P 101.
167 See generally Credit Reforms in Organized Wholesale Electric Markets, 133 FERC ¶ 61,060 (2010), order on reh’g, 134 FERC ¶ 61,126 (2011) (rulemaking order regarding risk and credit procedures in Commission-jurisdictional markets). See also Policy Statement on Credit-Related Issues for Electric OATT Transmission Providers, Independent System Operators and Regional Transmission Organizations, 109 FERC ¶ 61,186, P 1 (2004) (“credit policies of regulated utilities have always been a component of the Commission’s regulatory agenda”).
168 See FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277-78 (2016).

PDF page 44

44
dependent cooperatives and municipalities throughout the PJM region. Therefore, an attempt to delegate such a role to distribution-level utilities creates jurisdictional overreach by bringing such entities into a Commission-jurisdictional ratemaking role.

In an attempt to present the RBO as “flexible” and consistent with the boundaries of federal and state jurisdiction over cost allocation, PJM is proposing that “cost allocation to LSEs within an Electric Distributor’s zone/area be based on ‘the state and/or RERRA-determined allocation of cleared RBP UCAP MW to LSEs within each Electric Distributor’s zone/area, as reported by each Electric Distributor to [PJM].’”169 Basing the cost allocation on a state or RERRA determined allocation of RBP UCAP MW to LSEs within each zone/area is inconsistent with the intended role of states/RERRAs with respect to rates under the Commission’s jurisdiction. It would be appropriate and indeed consistent with retail jurisdiction for states and RERRAs to develop and charge retail rates that are based upon Commission-jurisdictional rates. However, here, because the states/RERRAs must determine the cost allocations in the first instance, they are determining Commission-jurisdictional rates. As explained by Mr. Bednarczyk, “the market-design concern is that PJM has not first established a sufficiently specific wholesale framework that identifies the responsible LSE, records the relevant large-load obligation, tracks offsets and mitigation measures associated with that obligation, and maintains a clear connection between cost responsibility and cost causation.”170 PJM is effectively improperly pushing its rate-making role onto other entities and impermissibly blurring the line between federal and state jurisdiction.  This delegation is not

169 PJM RBP Filing at 97-98.
170 Bednarczyk Affidavit at P 46. Additionally, as explained by Mr. Bednarczyk, the Coalition RBP Proposal “established responsibility first and then used retail or administrative processes to implement that responsibility,” which would be an appropriate market design that incorporated Electric Distributor, state, and RERRA processes. Bednarczyk Affidavit at P 45.

PDF page 45

45
appropriate,171 and at a minimum, it is not clear that Electric Distributors agreed to such a role by executing the OA. Delegating this role to Electric Distributors does not make PJM’s RBP Proposal consistent with the boundaries of federal and state jurisdiction.

PJM’s RBP Proposal also has not been shown to be just and reasonable because it leaves out much of the implementation details. For example, if PJM’s RBP Proposal is accepted, will Electric Distributors then become Commission-jurisdictional? And, how will PJM’s RBP Proposal be implemented in zones where not all of the load is served by Electric Distributors? Rather than leave open the possibility of this jurisdictional overreach, the Commission should reject PJM’s RBP Proposal.

D. PJM’s Proposed FRR Exemption and Treatment of RPM Capacity Market
Self-Supply Are Unduly Discriminatory.
PJM’s RBP Proposal’s treatment of FRR entities and the use of existing resources to satisfy FRR plans creates comparability concerns and unduly discriminates against RPM Capacity Market LSEs in several ways. First, as proposed, PJM allows an FRR entity that satisfies its resource adequacy obligations through qualifying owned and some portion of existing resources to be “insulated from RBP exposure”172 In contrast, an RPM Capacity Market LSE that has likewise prudently planned to serve its load does not receive comparable treatment under the proposed RBP cost-allocation framework.173 PJM’s RBP Proposal allows FRR entities to use existing resources

171 See, e.g., Entergy Servs., Inc., 120 FERC P 61,020, at P 28 (2007) (“The Commission’s ratemaking obligations under the FPA cannot be delegated to a state commission.  Similarly, as a general matter, a state commission cannot set Commission-jurisdictional rates nor direct the filing of Commission-jurisdictional rates. Likewise, the Commission cannot delegate to jurisdictional utilities its obligation to ensure the justness and reasonableness of jurisdictional rates. Yet, that is what [the Utility] effectively asks us to do, i.e., to delegate to state commissions and to [the Utility] itself the determination of the reasonableness of [the Utility’s] Commission-jurisdictional rates.”).
172 Bednarczyk Affidavit at P 60.
173 Bednarczyk Affidavit at P 60.

PDF page 46

46
to meet their FRR plans so long as those resources are locked in by June 1, 2027,174 while RPM Capacity Market LSEs with owned or contracted resources may not receive comparable protection from RBP cost assignment. PJM’s proffered explanation is that “FRR load has already paid for resource adequacy through the FRR Plan. Allocating RBP Charges to FRR load, in essence, require that they pay twice for capacity it has already procured.”175 But PJM offers no explanation as to why LSEs that similarly have existing resources paid for by the load they serve should be exposed to RBP costs. As explained by Mr. Bednarczyk,

An FRR entity that satisfies its resource adequacy obligation
through qualifying owned resources, and at least some categories of
existing resources, is effectively insulated from RBP exposure. By
contrast, an RPM LSE that has prudently developed, retained, or
contracted for sufficient resources to serve all or part of its
incremental load does not appear to receive comparable treatment
under the RBP cost-allocation framework. If PJM recognizes
resource adequacy actions taken under the FRR construct for
purposes of avoiding RBP exposure, principles of comparability and
cost causation suggest that it should similarly recognize owned
resources,
bilateral
contracts,
and
comparable
resource
commitments maintained by RPM LSEs when determining RBO
MW, RBP Charges, and collateral obligations.176
RPM Capacity Market LSEs that have sufficient capacity, whether owned or contracted for, are similarly situated to FRR entities, because both have sufficient capacity. Therefore, neither has caused any costs to be incurred or gained any benefits from the RBP. Yet as proposed, only RPM Capacity Market LSEs have exposure under RBP. This is inconsistent with the Commission’s cost- causation principles. And, this distinction, without justification, is unduly discriminatory.177 As

174 Proposed RAA, Schedule 8.1.D.1.1.
175 PJM RBP Filing at 31-32, n.92.
176 Bednarczyk Affidavit at P 60.
177 City of Anaheim, Opinion No. 483, 113 FERC ¶ 61,091, P 130 (2005) (“Discrimination is undue when there is a difference in rates or services among similarly situated customers that is not justified by some legitimate factor.”); PacifiCorp Elec. Operations, 54 FERC ¶ 61,296, 61,855 (“undue discrimination can occur only when two similarly situated customers are treated differently, and there is no justification for the differing treatment”); Puget Sound Energy, Inc. v. All Jurisdictional Sellers of Energy, Opinion No. 537, 151 FERC ¶ 61,173, P 43, n.105 (quoting Energy

PDF page 47

47
explained by Mr. Bednarczyk, “an LSE’s choice between the RPM construct and the FRR alternative should not determine whether its resource position receives recognition under the RBP.”178 Instead, the focus should be on whether an LSE has mitigated or eliminated the incremental reliability need.179

E. PJM’s Proposed FRR Exemption Creates Ambiguity and Disadvantages
Entities that May Elect FRR in the Future.
PJM’s RBP Proposal is unclear with respect to the extent to which a future FRR entity may rely on existing resources, including bilateral contracts associated with existing resources, to satisfy FRR obligations. PJM’s proposed language creates ambiguity about whether an FRR entity may use capacity resources it does not own to satisfy its FRR plan, despite other RAA provisions allowing bilateral contracts.180 PJM’s proposed language in RAA Section 8.1.D.1.1 states that “[a]n FRR Entity may not use an Existing Generation Capacity Resource not owned by such FRR Entity as of June 1, 2027 or any resource committed through the Reliability Backstop Procurement to satisfy its Capacity FRR Plan.”181 Thus, according to PJM’s proposal, an FRR entity is limited to relying upon its “owned” (not purchased via bilateral contract with the generation owner) capacity. Yet elsewhere in the RAA,182 bilateral contracts are clearly permitted. PJM’s proposed language was not explained in its RBP Filing Transmittal Letter, so its purpose and likely impacts have not been presented to the Commission. But it appears to be an

Transfer, 120 FERC ¶ 61,086, P 169), rev’d on other grounds, 157 FERC ¶ 61,026 (2016) (“It is well established that a finding of undue discrimination requires a showing that ‘(1) two classes of customers are treated differently; and (2) the two classes of customers are similarly situated.’”); Midwest Indep. Transmission Sys. Operator, Inc., 155 FERC ¶ 61,082, P 31 (2016) (“there is no undue discrimination or preference because we have identified appropriate reasons for it”).

178 Bednarczyk Affidavit at P 62.
179 Bednarczyk Affidavit at P 62.
180 Bednarczyk Affidavit at P 63. See RAA, Schedule 8.1.D.4.
181 Proposed RAA, Schedule 8.1.D.1. (emphasis added).
182 See RAA, Schedule 8.1.D.4.

PDF page 48

48
effort to ensure that FRR Entities do not enter into bilateral agreements with resources that have been committed to serve load under the RPM Capacity Market and further challenge the resource adequacy of entities who rely on the RPM Capacity Market.  However, as drafted the provision would privilege ownership over bilateral (contract) supply arrangements for satisfying FRR plans. However, LSEs may have long-standing bilateral contracts. To the extent that this language would restrict an entity newly electing the FRR alternative from being able to rely upon a long-standing bilateral contract to satisfy its FRR plan, it is an unjust and unreasonable provision.  This revision would unnecessarily constrain the ability of other entities to consider use of the FRR alternative in the future if their full portfolio of resources could not be used to satisfy an FRR plan. The revision is unexplained by PJM, is unjustified for the reasons discussed herein, and therefore has not been shown to be just and reasonable and should be rejected by the Commission.

F. PJM’s Proposal Is Inconsistent with Ratepayer Protection and the
Administration’s Policy Objectives Because It May Shift Large-Load-Driven
Costs to LSEs and Customers That Did Not Cause Them to Be Incurred.
PJM wraps its RBP Proposal in the claim that it addresses concerns raised by the Administration, the Commission, and PJM states with respect to large loads and ratepayer protection.183 But advancing the policy goal of rate payer protection184 depends on assigning reliability-related costs to the entities whose incremental large load growth creates the need for those costs, in a manner consistent with the Commission’s cost-causation principles. Thus, advancing the goal of ratepayer protection necessarily depends on the ability to assign costs to

183 See THE WHITE HOUSE, Ratepayer Protection Pledge, (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. As of August 18, 2026, more than 300 organizations across every stakeholder in the power system have signed on to the Ratepayer Protection Pledge, including Governors of 23 states and more than 250 utilities and cooperatives, including EKPC (see https://www.whitehouse.gov/ratepayer-protection-pledge/#commitments for a list of entities that have signed the Pledge).
184 See National Energy Dominance Counsel, Statement of Principles Regarding PJM (Jan. 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm).

PDF page 49

49
entities that either cause the costs to be incurred or benefit from the RBP in a manner roughly commensurate with the costs assigned.

PJM’s RBP Proposal is inconsistent with the objectives expressed by the Administration, the Commission, and the PJM Governors because, as proposed, the RBP will inevitably allocate costs to LSEs that prudently managed their resource positions and did not contribute to the need for the RBP and therefore, do not benefit from the costs arising under the RBP. PJM’s RBP Proposal allows for this improper cost allocation in multiple ways, as recounted above. First, PJM’s RBP Proposal fails to account for existing resources in an LSE’s supply portfolio. The RBP Proposal also fails to ensure that applicable offsets and opt-outs decrement any obligation of LSEs who supplied them. Additionally, relying on Electric Distributors and state or RERRA cost allocation methods, or defaulting to a cost allocation method adopted and approved for a very different purpose (i.e., the RPM Capacity Market), may shift costs away from the entities that have caused the costs. This is inconsistent with the Commission’s cost causation principles and produces an unjust and unreasonable result. Therefore, the Commission should reject PJM’s RBP Proposal.

PDF page 50

50
III. Conclusion
Wherefore, East Kentucky Power Cooperative, Inc. respectfully requests that the Commission reject the PJM RBP Proposal because the PJM RBP Proposal is unjust and unreasonable, improperly expands the role of an Electric Distributor in PJM, and is inconsistent with the boundaries of federal and state jurisdiction. PJM’s RBP Proposal also fails to address concerns raised by the Commission and the governors of the 13 PJM states regarding the impacts of large loads, specifically ratepayer protection.

Respectfully submitted,
Denise R. Foster Cronin
Chief Compliance Officer and Senior Vice
President
East Kentucky Power Cooperative, Inc.
4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Tel.: 859-745-9615
Email: denise.cronin@ekpc.coop
On Behalf of
East Kentucky Power Cooperative, Inc.
/s/ Daniel E. Frank
Daniel E. Frank
Allison E. S. Salvia
Kelly A. Cuthbertson
Adriana J. Santana
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Tel.: 202-383-0100
Email: danielfrank@eversheds-sutherland.com
allisonsalvia@eversheds-sutherland.com
kellycuthbertson@eversheds-sutherland.com
anasantana@eversheds-sutherland.com
Counsel for
East Kentucky Power Cooperative, Inc.
Dated: August 21, 2026

PDF page 51

Attachment 1
Affidavit of Adam Bednarczyk

PDF page 52

DAYMARK ENERGY ADVISORS |370 MAIN STREET, SUITE 325 |  WORCESTER, MA 01608
TEL: (617) 778-5515 | DAYMARKEA.COM

AFFIDAVIT OF ADAM BEDNARCZYK
Prepared for East Kentucky Power Cooperative, Inc. in connection with PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing

AFFIDAVIT
I. Introduction and Qualifications
1. My name is Adam Bednarczyk. I am a Lead Consultant with Daymark Energy Advisors. I work with market participants, regulators, utilities, and developers to provide actionable insights regarding power market design, FERC policy, and transmission economics. I submit this affidavit on behalf of East Kentucky Power Cooperative, Inc. (“EKPC”) in connection with PJM Interconnection, L.L.C.’s proposed Reliability Backstop Procurement (“RBP”).

2. I have approximately 17 years of experience at the Federal Energy Regulatory Commission (“FERC” or the “Commission”) in roles of progressive responsibility.

3. During my tenure at FERC, I served in the Office of Energy Market Regulation, the Office of Policy and Innovation, and the Office of Enforcement. Most germane here, I advised senior agency management and Commissioners on matters arising under the Federal Power Act, including wholesale energy, capacity, and ancillary services market rules in the Eastern RTOs and ISOs. My experience includes Section 205 and Section 206 proceedings, tariff compliance, rulemaking implementation, natural gas- electric coordination, fuel security, market power mitigation, market-based rate authority, and affiliate sales restrictions.

4. Based on that experience, I am familiar with how Commission staff evaluate whether a proposed RTO or ISO tariff change is supported by the filing utility’s Section 205 showing, whether the filed provisions are sufficiently specific and administrable, and whether the resulting rate design is reasonably aligned with cost causation, market incentives, and comparability among similarly situated market participants.

5. My affidavit examines whether the specific design elements of PJM’s proposed Reliability Backstop Procurement (“RBP”) appropriately align procurement obligations, cost responsibility, collateral requirements, and associated risks with the entities whose incremental load growth creates the need for

PDF page 53

Adam Bednarczyk Affidavit
2

additional capacity. I address market-design, cost-causation, incentive, hedgeability, collateral, and administrability issues arising under proposed Tariff sections 18.1, 18.2, 18.3, 18.4, 18.5, 18.8, and 18.9, as well as proposed RAA Articles 7.2B and 7.2C. My review focuses not on whether PJM has identified a legitimate reliability concern, but on whether the specific rate design and allocation provisions filed under Section 205 are sufficiently transparent, traceable, administrable, and consistent with cost- causation principles.

II. Summary of Opinions
6. PJM has identified a real and urgent resource adequacy challenge, and nothing in my testimony suggests that PJM should be prohibited from addressing that challenge. Rather, my testimony examines whether the specific mechanisms PJM selected to procure capacity, recognize offsets, allocate costs, impose collateral requirements, and assign related risks appropriately align those obligations with the entities whose incremental demand creates the need for the procurement. These questions are particularly important because the proposal contemplates long-term financial commitments and credit obligations that may remain in place for as many as fifteen Delivery Years.

7. In my opinion, the Commission should not treat a generalized showing of regional reliability need as sufficient to support the particular RBP rate design filed under Section 205. PJM must demonstrate that the specific tariff provisions governing RBP offsets, cost allocation, resource commitments, collateral requirements, RBP Charges, RBP Obligations (“RBO MW”), and Electric Distributor reporting satisfy the standards of a just and reasonable rate design. The proposal creates cost, credit, collateral, and risk- allocation obligations that do not consistently satisfy the principles of transparency, traceability, and cost causation. In particular, the proposal does not consistently identify the entities responsible for the incremental reliability need, track mitigation measures taken by those entities, or ensure that resulting costs, credits, collateral obligations, and associated risks remain aligned with the parties whose actions create, increase, or mitigate the need for backstop procurement.

III. Background
8. PJM’s proposed Reliability Backstop Procurement (“RBP”) is a one-time, PJM-administered capacity procurement intended to address the 6,831 MW resource adequacy shortfall identified in the 2028/2029 Base Residual Auction. Under the proposal, PJM would procure new capacity resources through a competitive process and provide successful resources with commitments of up to fifteen Delivery Years. The procurement target would be reduced by certain qualifying new capacity arrangements and limited opt-outs, but PJM would not require a direct matching of specific resources to specific loads. The costs of the procurement would be allocated first to Electric Distributor zones and areas based on load-growth-

PDF page 54

Adam Bednarczyk Affidavit
3

related allocation factors and then further allocated to Load Serving Entities through a combination of state-, RERRA-, or Electric Distributor-reported assignments, with a default PJM allocation mechanism if no such assignments are provided. PJM’s proposal therefore combines a centralized procurement mechanism with a largely downstream allocation process for costs and obligations, placing substantial reliance on subsequent state, RERRA, and Electric Distributor actions to identify the ultimate beneficiaries and cost-responsible parties.

9. PJM’s proposal reflects a market-design choice to address the identified resource adequacy shortfall through a centralized procurement mechanism combined with a multi-layered allocation framework. Under the filing, qualifying offsets and opt-outs may reduce the overall procurement target, while responsibility for the resulting obligations is assigned through Electric Distributor zones and areas and ultimately translated into Load Serving Entity (“LSE”)-level obligations through Electric Distributor, state, RERRA, or default PJM allocation processes. The proposal also includes associated settlement, collateral, and default-allocation provisions intended to support the financial administration of the procurement. Accordingly, evaluating the proposal requires consideration not only of how PJM procures resources, but also of how procurement obligations, offsets, cost responsibility, collateral requirements, and associated risks are assigned and tracked after the procurement occurs. The remainder of my affidavit evaluates whether those mechanisms provide a sufficiently transparent, traceable, and administrable framework for ensuring that responsibility for the procurement remains aligned with the parties whose actions create, increase, or mitigate the underlying reliability need.

IV. Reliability Neutrality and Large-Load Growth
10. The Commission can apply an affirmative principle that improves reliability while preserving cost- causation discipline: new large loads should be expected to remain reliability neutral, or as close to reliability neutral as reasonably practicable, before their incremental demand imposes long-term costs on customers that did not create the need.

11. A reliability neutral design principle is not an anti-growth or anti-data-center concept; it is a governance and cost-allocation principle. It recognizes that large loads may produce economic benefits and that PJM may need additional resources to serve them reliably. At the same time, it requires PJM to link, as directly as practicable, the incremental reliability consequences of serving those loads to the LSEs that supply them.

12. The RBP proposal does not adequately implement this principle. A load-serving entity, or a self- supplying large-load customer, should know that bringing capacity, demand response, curtailability, or another recognized mitigation measure will reduce its own RBP exposure. PJM's proposed zonal and

PDF page 55

Adam Bednarczyk Affidavit
4

Electric Distributor allocation framework does not directly assign RBP obligations to the LSE responsible for serving the large load that creates the procurement need. As a result, the proposal may encourage parties to focus on allocation outcomes rather than on actions that reduce the reliability impacts of adding large loads without corresponding resources or curtailment arrangements.

13. PJM's allocation framework does not provide sufficient LSE-specific information for an LSE to determine, before completion of the Electric Distributor process, whether it will be assigned RBP costs. Nor does the filing include a registry or MW opt-in mechanism that would allow an LSE or self-supplying large load to identify responsibility at the outset, associate qualifying mitigation measures with that responsibility, and determine whether its actions satisfy a reliability-neutral standard.

14. Proposed Tariff section 18.1(b) provides that the Final RBP Target equals the Initial RBP Target less the total PJM-wide Qualifying RBP Offset UCAP MW and the unforced capacity obligation value of load that successfully opts out under section 18.1(d). Proposed section 18.3 similarly reduces the Electric Distributor zone/area calculation for qualifying offsets and opt-outs before calculating that zone's or area's share of the Final RBP Target MW. These provisions reduce a PJM-wide or zone-specific procurement target, but they do not expressly provide that the LSE supplying the offset or associated with the opt-out receives a corresponding reduction in its own RBO MW, RBP Charges, or collateral requirements. Instead, the Electric Distributor allocates the remaining obligation through the RAA framework. That process does not provide a transparent means for an LSE to assess its wholesale RBP exposure, evaluate the benefits of qualifying offsets or opt-outs, understand its related credit obligations, or determine whether its actions will make it reliability neutral.

15. The significance of a registry extends beyond administrative tracking. The Coalition proposal that EKPC co-sponsored was designed to establish an opt-in mechanism under which an LSE or associated large-load customer could identify the RBP MW for which it accepted responsibility and allow those MW to be tracked and cost responsibility assigned to the correct LSE. The Coalition proposal did not itself require tracking of qualifying offsets by the LSE. Rather, in combination with a separate Connect and Manage framework, the registry would have linked procurement responsibility, cost allocation, collateral requirements, and operational consequences.

16. By contrast, PJM's filed proposal largely treats procurement, cost allocation, and the forthcoming IRAS process as separate constructs. PJM states that the RBP does not depend on the IRAS framework. That separation breaks the direct connection between the entity creating the incremental reliability need and the consequences of failing to mitigate that need. Unlike the Coalition proposal, the filing does not establish a unified framework that carries responsibility from procurement through settlement and

PDF page 56

Adam Bednarczyk Affidavit
5

operational consequences. As a result, it does not provide the same transparent and traceable path for ensuring that large-load customers and their suppliers remain reliability neutral.

V. Cost Causation and Section 205 Burden
17. Proposed Tariff section 18.3 is the central cost-allocation provision. Section 18.3(a) allocates the Initial RBP Target MW to each Electric Distributor zone or area based on that zone's or area's pro rata share of the increase in forecasted Load Adjustments between the 2026/2027 and 2028/2029 Delivery Years. Section 18.3(b) then allocates daily RBP Charges to LSEs based on each LSE's assigned RBO MW. Critically, section 18.3(b)(iii) provides that, if no RBO MW are reported, "PJM will allocate the RBP Charges for that zone/area to all load in the zone/area using each LSE's ratio share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8."1 That default raises a significant just-and-reasonable concern because Daily Unforced Capacity Obligation is a broad capacity- allocation metric. By itself, it does not identify the LSEs that created the residual procurement need, nor does it provide a mechanism to ensure that recognized offsets, opt-outs, or mitigation actions reduce the exposure of the LSE that supplied them.

18. Section 18.3 therefore risks transforming an incremental large-load cost-causation issue into a generalized load-ratio allocation. A simple example illustrates the concern. Assume one LSE's new large load creates an incremental need for RBP procurement, while another LSE in the same zone experiences only ordinary load growth and has already secured sufficient owned or contracted resources to meet its obligations. Under a default zonal or load-ratio allocation, the second LSE could still bear a portion of the costs caused by the first. In that circumstance, the filed rate would not distinguish between an LSE that created, or failed to mitigate, the incremental procurement need and an LSE that prudently planned for its resource requirements. By blurring that distinction, the proposal weakens the forward-planning incentives that PJM asserts the RBP is intended to create.

19. This concern is consistent with principles the Commission has accepted in other PJM market-design contexts. PJM credit and collateral requirements have generally been tied to measurable participant- specific exposure and structured to reduce mutualized default risk. Similarly, PJM capacity-market reforms have sought to align accreditation, testing requirements, must-offer obligations, and performance consequences with actual resource-adequacy value. Those same principles underscore the importance of the alternative framework reflected in the Coalition proposal that EKPC co-sponsored. Under that approach, obligations would be identified when procurement responsibility is established, tied to a party that affirmatively accepts responsibility, and paired with a mechanism that associates

1 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.3(b)(iii).

PDF page 57

Adam Bednarczyk Affidavit
6

qualifying offsets with the entity that supplied them. PJM's filed proposal does not provide the same level of upfront traceability.

20. The Coalition proposal that EKPC co-sponsored addresses many of these concerns through a registry or MW opt-in framework. Under that approach, the large-load-driven need, the LSE or supplier associated with that need, the MWs for which that party accepted responsibility, and the qualifying resources or mitigation measures used to reduce that responsibility would all be identified at the time of procurement. That framework differs materially from PJM's proposal, which reduces the procurement target through offsets and opt-outs but does not comparably ensure that the resulting credit follows the responsible LSE into the cost-allocation, settlement, and collateral calculations.

21. In my view, the absence of a transparent registry or opt-in mechanism is significant because it eliminates a practical tool for linking RBP MW and related cost recovery responsibility to the LSE serving the large load. The Coalition proposal treated the registry as a means of identifying the responsible LSE and tracking the RBP MW to that entity. The registry, together with the Connect and Manage framework co-sponsored by EKPC would have provided a transparent mechanism linking procurement responsibility, cost responsibility, settlement outcomes, and operational consequences.

22. PJM has since proposed registry-related elements through its separate IRAS filing. In this RBP filing, however, PJM expressly treats the RBP and IRAS frameworks as independent constructs. As a result, the filing does not establish a unified framework that carries responsibility from procurement through cost allocation, settlement, collateral requirements, and operational reliability obligations. The proposal therefore does not provide the same direct and transparent connection between the entity creating the incremental reliability need and the consequences of failing to mitigate that need.

VI. Cost and Risk Allocation Effects Created by the RBP
23. The proposed RBP would create a new administrative procurement opportunity for new generation developers, including independent power producers. A long-term RBP commitment may be valuable because it provides revenue certainty and a risk profile that differs from traditional RPM participation or bilateral contracting. That distinction matters because the RBP's long-term contract structure may shield selected generators from certain RPM market risks, while performance, load-realization, and stranded- cost risks do not disappear. Instead, the tariff shifts those risks to the LSEs and large-load customers expected to bear RBP Charges. Because the proposed allocation framework does not fully ring-fence those costs and risks to the entities that created the procurement need, LSEs that do not require RBP resources to serve large loads may nonetheless assume long-term financial obligations, even in the absence of a payment default.

PDF page 58

Adam Bednarczyk Affidavit
7

24. Proposed Tariff sections 18.4 and 18.5 are central to this concern because they establish the terms under which new RBP Resources may be selected and compensated. Section 18.4 offers commitments "for a fixed period of fifteen (15) Delivery Years," while section 18.5(g) provides that each committed RBP Resource "shall be individually settled as a contract for difference." These provisions create a valuable administrative procurement pathway that is distinct from traditional RPM participation. The concern is not that new resources receive backstop compensation. Rather, if PJM creates a payment stream with a different and potentially more favorable risk profile for selected resources, the tariff should also clearly identify who bears the associated performance, revenue-sufficiency, load-realization, and stranded-cost risks. Unless the cost-allocation and collateral provisions are equally specific and traceable, the RBP may procure supply through one set of rules while allocating the resulting costs and risks through another set of rules that does not clearly identify the responsible LSE or load.

25. Existing resources receive materially different treatment. An LSE that prudently has planned, built, or contracted for resources to meet future load obligations generally cannot access the RBP revenue stream. That distinction may be reasonable if PJM intends to reserve RBP compensation for new backstop resources. It becomes problematic, however, if the tariff fails to recognize those same existing resource commitments when determining which LSEs caused, mitigated, or avoided the residual need for RBP procurement.

26. A related but distinct concern involves the LSEs that procured, developed, or retained those resources. For vertically integrated utilities, cooperatives, and other self-supply LSEs, the key question is whether their resource-adequacy actions reduce their own RBP exposure. Proposed Tariff sections 18.1 and 18.2 appear to recognize Qualifying RBP Offset UCAP MW for purposes of reducing the aggregate procurement target. However, the tariff must distinguish between reducing a zonal or system-wide procurement target and reducing the obligation of the LSE that supplied the offset. If an offset reduces only the aggregate target and does not follow the LSE or load responsible for the mitigation, the tariff may still assign RBP costs and collateral requirements, and impose risks on an entity that prudently acted to reduce the need for procurement.

27. My concern with proposed section 18.2 is not simply that it may exclude certain categories of potential Qualifying RBP Offset UCAP MW. Rather, the more fundamental issue is that reducing the aggregate procurement target is not the same as protecting the LSE that supplied or sponsored the offset from RBP Charges, collateral obligations, or default-allocation risk. The tariff should clearly state whether, and how, a recognized offset follows the associated LSE or load when PJM calculates LSE- specific RBO MW, RBP Charges, and collateral requirements.

PDF page 59

Adam Bednarczyk Affidavit
8

28. The distinction can be illustrated through a simple example. Assume LSE A serves a new 500 MW large load that contributes to the need for Reliability Backstop Procurement capacity. LSE B serves existing native load and has already developed or contracted sufficient resources to support its forecasted load growth. Further assume that LSE B sponsors a qualifying offset that PJM recognizes under proposed sections 18.1 and 18.2, thereby reducing the overall procurement target.

29. Section 18.2 defines Qualifying RBP Offset UCAP MW as capacity that has not previously supported a capacity commitment or been committed in an FRR Plan and that is supported by specified evidence, including certain bilateral contracts, RERRA-approved or accepted self-supply generation, or demand- side commitments. Yet PJM's proposal does not expressly provide that the offset secured by LSE B will reduce LSE B's own RBO MW, cost assignment, or related collateral obligation. Instead, the offset appears to reduce the aggregate or zonal procurement target, after which either the Electric Distributor determines the downstream allocation or PJM defaults to a zonal allocation methodology.

30. The problem becomes most apparent under the default-allocation approach. LSE B is not necessarily insulated from RBP Charges or collateral obligations merely because its actions reduced the procurement target. Because the tariff does not clearly provide that the offset will flow through to LSE B's own obligation before costs and collateral are assigned, LSE B may remain exposed to RBP costs and credit obligations despite having taken the very actions that reduced the need for procurement.

31. An even more direct example illustrates the concern. Assume an LSE has a 1,000 MW resource portfolio and serves 900 MW of existing load. The LSE then adds a 100 MW large load that is fully covered by its existing owned resources or bilateral contracts. Under a reliability-neutral framework, that LSE has not created an incremental need for additional backstop procurement. Yet PJM's proposal does not clearly ensure that the LSE's existing resource position will eliminate its RBP exposure. If the LSE nevertheless receives an RBP cost allocation, it effectively pays twice: first for the resources it already secured to serve the load and again for a long-term RBP obligation imposed through PJM's allocation process.

32. The incentive issue is particularly important because the Coalition proposal, in combination with a Connect and Manage framework, would have tied procurement obligations to corresponding operational consequences. Under that combined approach, a large load that failed to bring sufficient capacity, self- supply resources, bilateral contracts would remain subject to curtailment per the proposed Connect and Manage provisions. The possibility of curtailment served as a practical forcing mechanism that encouraged reliability-neutral behavior. PJM's RBP filing does not establish the same connection between procurement responsibility and operational consequences. As filed, an LSE may face

PDF page 60

Adam Bednarczyk Affidavit
9

uncertainty regarding its ultimate cost exposure while lacking a clear and predictable mechanism through which reliability-neutral actions eliminate that exposure.

33. This outcome creates both a cost-causation problem and an incentive problem. An LSE may have sufficient owned resources, bilateral capacity contracts, demand response, curtailment commitments, or other qualifying portfolio assets to satisfy its load obligations, including all or part of the large load that PJM seeks to address through the RBP. If PJM does not ensure that those LSE-specific resource positions reduce that LSE's own RBO MW, charges, and collateral requirements, the proposal risks requiring the LSE to pay twice for capacity: once through resources or contracts it already secured and again through an RBP allocation.

34. The concern extends beyond ordinary double payment. The RBP may impose obligations lasting as long as fifteen years, together with substantial collateral and credit requirements. As a result, an LSE that has already planned prudently and secured adequate resources could nonetheless incur a second long- term obligation that provides little or no additional reliability benefit. That outcome weakens incentives for proactive resource planning, socializes the benefits of prudent mitigation, and leaves the planning LSE exposed to residual charges, collateral obligations, and default-allocation risk.

35. This concern extends beyond self-supply LSEs. Any LSE considering bilateral contracts, demand response, curtailment commitments, or self-supply resources faces uncertainty if the tariff does not clearly provide that the resulting credit will reduce that LSE's own RBO MW, RBP Charges, and collateral exposure. The issue is particularly significant for self-supply LSEs because they may already have substantial resource commitments in place that mitigate or eliminate the need for RBP procurement, yet the proposal does not clearly ensure that those commitments will be recognized throughout the procurement, allocation, settlement, and collateral framework.

VII. Effects on LSEs, Electric Distributors, and States
36. For purposes of this affidavit, I use the term “LSE” to mean a load-serving entity that bears wholesale obligations under the PJM governing documents. The RAA defines a Load Serving Entity as an entity serving end users in the PJM Region that has authority or an obligation under state or local law, regulation, or franchise to sell electric energy to those end users, and includes certain end-use customers that manage their own supply. This category includes self-supply LSEs, such as vertically integrated utilities and cooperatives, as well as LSEs that serve load through market purchases or bilateral arrangements. The concerns raised by the RBP are not identical for every LSE. Self-supply LSEs face particular risk if the tariff does not recognize their owned or contracted resource positions. More broadly, all LSEs face risk under proposed Tariff section 18.3 and proposed RAA Articles 7.2B and 7.2C if

PDF page 61

Adam Bednarczyk Affidavit
10

PJM ultimately relies on its default allocation mechanism, which assigns RBP Charges to all LSEs within a zone or area based on Daily Unforced Capacity Obligation MW when no Electric Distributor allocation is reported. That approach risks assigning costs through a broad load-ratio methodology rather than tracing them to the incremental reliability need that gave rise to the procurement.

37. For LSEs serving new large loads, the RBP may create perverse incentives. PJM appears to intend that large-load customers and their serving LSEs bring qualifying capacity or accept curtailment to mitigate the need for backstop procurement. That incentive, however, is effective only if the LSE can determine in advance that those actions will reduce its own RBP obligation. The Coalition proposal addressed this issue through a mandatory Connect and Manage framework that coupled procurement responsibility with operational consequences. By contrast, PJM's current proposal relies in part on the separate and voluntary IRAS framework and does not provide the same clear forcing mechanism.

38. If the benefit of a Qualifying RBP Offset UCAP MW is applied only at a zonal or Electric Distributor level and is not traced to the LSE that undertook the mitigation action, the proposal weakens the incentive for voluntary forward procurement and load-management measures. Under those circumstances, an LSE may not know whether self-supply, bilateral contracts, demand response, or curtailment commitments will reduce its own RBP exposure. That uncertainty may encourage reliance on ex post allocation outcomes rather than proactive actions that reduce future resource-adequacy needs.

39. LSEs serving existing native load face a different concern. This issue relates specifically to PJM's proposed default allocation methodology rather than to the self-supply example discussed above. If PJM's section 18.3 process does not result in an Electric Distributor or state/RERRA allocation mechanism that identifies the responsible LSEs, PJM may allocate residual RBP obligations across LSEs in the zone using Daily Unforced Capacity Obligation MW or another load-ratio proxy. In that circumstance, an LSE may bear costs associated with large loads served by other LSEs in the same zone despite having taken no action that contributed to the procurement need.

40. For example, assume LSE B has a 1,000 MW resource portfolio and serves 900 MW of existing load. If a new 100 MW large load is also served from that existing portfolio, LSE B has not created an incremental resource shortfall requiring RBP procurement. If PJM nevertheless allocates RBP costs to LSE B through a zonal load-ratio mechanism rather than recognizing that LSE B's resource position already covers the incremental load, LSE B could incur RBP charges despite having acted in a reliability-neutral manner. That outcome would not send an efficient planning signal because the LSE already procured the resources necessary to serve the load and may have no practical means of avoiding the costs assigned through the default mechanism.

PDF page 62

Adam Bednarczyk Affidavit
11

41. Proposed RAA Articles 7.2B and 7.2C raise a separate administrability concern because they establish the framework through which Electric Distributors communicate and report RBO MW for purposes of allocating RBP Charges and credits. Article 7.2B provides that when an Electric Distributor reports RBO MW for each LSE within its zone or area, PJM will allocate RBP Charges and shortfall credits in accordance with that notification. If no such notification is provided, PJM will allocate those charges and credits based on each LSE's share of Daily Unforced Capacity Obligation MW. Article 7.2C further requires Electric Distributors to provide PJM, no later than 36 hours before each Operating Day, any RBO MW associated with each RAA party serving load in the applicable zone or area.

42. Electric Distributors are not the same entities as RAA load-serving parties, and their traditional role is generally associated with metering, customer data, and distribution system functions rather than assigning wholesale cost responsibility. If PJM intends Electric Distributors to identify or communicate RBO MW, coordinate with state or RERRA allocation processes, and translate those determinations into wholesale settlement consequences, the federal tariff should clearly specify the mechanics of that process and explain how it produces just and reasonable wholesale charges.

43. PJM's attempt to analogize these responsibilities to obligations imposed on Transmission Owners in other proceedings does not resolve that concern. Transmission Owners and Electric Distributors perform different functions and are separately defined under the PJM governing documents. A requirement that a Transmission Owner identify network upgrades associated with serving large-load customers is directly related to the Transmission Owner's facilities and planning responsibilities. By contrast, the proposed RBP requires Electric Distributors to provide or convey allocation inputs that determine LSE-specific wholesale obligations and collateral requirements. Even if PJM is correct that the information sought is "in connection with" or "directly affects" wholesale rates, that observation does not explain why Electric Distributors are the appropriate entities to provide the information or why a wholesale cost-allocation framework should depend on that process.

44. The Coalition proposal demonstrates that a more traceable and administrable alternative is available. Under that framework, PJM would identify responsibility at the wholesale level through a registry and subscription process that associated specific RBP MW with specific LSEs and loads before assigning costs, credits, offsets, and collateral requirements. The Coalition RBP proposal did not impose curtailment consequences. Rather, in combination with a Connect and Manage framework, the registry could have enabled the transparent implementation of curtailment actions by PJM, TO, EDC, and LSE.

45. By contrast, PJM's proposal relies heavily on downstream Electric Distributor, state, and RERRA processes to determine how obligations ultimately flow to individual LSEs. This distinction is important because the Coalition proposal established responsibility first and then used retail or administrative

PDF page 63

Adam Bednarczyk Affidavit
12

processes to implement that responsibility. PJM's proposal reverses that sequence by relying on downstream processes to determine critical wholesale allocation outcomes.

46. This distinction does not suggest that states or RERRAs lack an appropriate role in addressing retail allocation or retail-rate consequences. Rather, the market-design concern is that PJM has not first established a sufficiently specific wholesale framework that identifies the responsible LSE, records the relevant large-load obligation, tracks offsets and mitigation measures associated with that obligation, and maintains a clear connection between cost responsibility and cost causation. Had PJM performed those wholesale functions first, downstream state, RERRA, and Electric Distributor processes could operate in a more administrative capacity and would be less likely to shift costs to entities that did not create or fail to mitigate the incremental procurement need.

VIII. Hedgeability, Traceability, and Collateral Risk
47. Proposed Tariff section 18.8 amplifies the same cost-allocation concerns because it imposes collateral obligations on LSEs based on their RBP exposure. Section 18.8 applies its credit provisions to “LSEs allocated costs for RBP UCAP MW procured through the Reliability Backstop Procurement, as determined in accordance with Tariff, Attachment DD, section 18.3,” and makes clear that RBP credit requirements are “separate from and additional to” credit requirements associated with RPM Auctions, bilateral transactions, and other PJM market activity. Collateral requirements are just and reasonable only when the underlying obligation is sufficiently knowable, measurable, and attributable to the responsible party before collateral is required. Here, however, an LSE’s RBO MW and resulting RBP Charges may depend on subsequent Electric Distributor reporting, state or RERRA allocation determinations, PJM’s treatment of offsets and opt-outs, and the potential application of default Daily Unforced Capacity Obligation allocations. Under those circumstances, an LSE may be unable to determine its exposure with sufficient certainty to plan for future payment obligations or collateral requirements.

48. The insufficiency of the proposal stems from the fact that sections 18.1 and 18.2 reduce the procurement target without clearly establishing how offsets and opt-outs affect LSE-specific cost and collateral exposure. For example, if LSE A serves a new large load that contributes to the need for RBP procurement while LSE B develops or contracts for resources that qualify as a Qualifying RBP Offset UCAP MW, the tariff does not clearly provide whether that offset reduces only the zonal procurement target or also reduces LSE B’s own RBO MW, RBP Charges, and collateral obligations. Without that information, an LSE cannot determine its actual exposure, evaluate the value of mitigation options, or effectively hedge the resulting obligation. The issue is therefore not merely whether offsets are

PDF page 64

Adam Bednarczyk Affidavit
13

recognized, but whether the tariff ensures that the benefit of those offsets follows the LSE that supplied them.

49. Collateral secures an obligation, but it does not make that obligation more transparent, traceable, or hedgeable. Section 18.8 reflects, and therefore inherits, the allocation framework established elsewhere in the RBP proposal. Section 18.8(b)(i)(B)(1) would require certain LSEs to post or maintain RBP Collateral equal to “$1.5 million x the allocated RBP Obligation MW.”2 Section 18.8(b)(i)(B)(2) further provides that, where no RBP Obligations are reported for an Electric Distributor zone or area, PJM may require LSEs to post collateral based on their pro rata share of Daily Unforced Capacity Obligation MW.

50. Collateral secures an obligation, but it does not establish whether the underlying obligation satisfies cost-causation principles. If section 18.3 allocates costs through a broad zonal default mechanism, fails to fully account for recognized offsets and opt-outs, or does not credit an LSE’s owned or contracted resources against that LSE’s own RBO MW, section 18.8 requires the LSE to post collateral against those same potentially misallocated obligations.

51. The consequences can be significant. Consider an LSE with 1,000 MW of owned or contracted resources serving 900 MW of existing load plus a 100 MW large load. If that portfolio already covers the full 1,000 MW requirement, the LSE has not created an incremental need for backstop procurement. Yet if PJM allocates RBP costs through a zonal default mechanism rather than recognizing that resource position, the LSE may be required both to pay for capacity it already procured and to post collateral supporting a separate long-term RBP obligation. In that circumstance, the collateral requirement increases the financial consequences of the allocation framework without improving the connection between cost responsibility and the actions that created the procurement need. The LSE may therefore face collateral obligations that it neither reasonably anticipated nor could effectively hedge.

52. The relevant RBP risk extends beyond ordinary counterparty default risk. The RBP is a large, one- time procurement that may commit substantial quantities of capacity based on forecasts of future load growth. Those forecasts will inevitably differ from actual outcomes. Some forecasted loads may be delayed, reduced, relocated, or abandoned, while others may develop differently than anticipated. Large data centers and other large-load customers may be financially strong and unlikely to default on short- term payment obligations, yet still create significant load-realization risk if future business conditions, technology changes, economic developments, or shifts in demand reduce or eliminate the need for the projected load after PJM has already entered into long-term procurement commitments.

2 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.8(b)(i)(B)(1).

PDF page 65

Adam Bednarczyk Affidavit
14

53. That risk is both temporal and concentrated. It does not scale in proportion to ordinary forecasting error because a small number of very large load decisions can create substantial procurement, deliverability, and stranded-cost consequences within particular PJM zones or areas. Those impacts may also shift over time as the location and timing of large-load development evolve.

54. Because RBO MW assignments and corresponding RBP Charges may remain uncertain or change over time, an LSE may have no practical way to determine in advance the direct costs or collateral obligations for which it will ultimately be responsible. That uncertainty can itself increase default risk. An LSE that receives an unexpected RBP obligation or collateral requirement may not be able to satisfy it. If that occurs, the resulting costs may flow through the same residual or default-allocation mechanisms to other LSEs, including entities that neither served the large load nor contributed to the procurement need. In that respect, the uncertainty embedded in the allocation framework risks creating the same type of mutualized exposure that collateral requirements are ordinarily designed to prevent.

55. The relevant question is whether the collateral framework effectively ring-fences the costs and risks associated with large-load-driven procurement to the loads, or the suppliers serving those loads, that create the exposure.

56. Unlike the Coalition proposal, which would have assigned obligations at the time procurement commitments were established through a registry-based framework, PJM’s proposal leaves RBO MW assignments, offsets, opt-outs, and collateral exposure to be determined through subsequent allocation processes. That approach reduces transparency and predictability for affected LSEs. Without a mechanism that links procurement commitments to identifiable obligations from the outset, collateral may secure obligations that market participants cannot readily identify, trace to the underlying reliability need, or effectively hedge.

57. In my opinion, section 18.8 does not fully address the credit-risk concerns created by the broader RBP allocation framework. The provision requires collateral for RBO obligations that may not be known until PJM determines LSE-specific RBO MW, applies Qualifying RBP Offset UCAP MW and opt-out reductions, completes the section 18.3 allocation process, and reports the resulting obligations. This point is particularly important because the tariff appears to use offsets and opt-outs to reduce the aggregate procurement target without clearly stating that those same reductions will apply to the affected LSE’s own cost and collateral obligations.

58. Until those determinations occur, an LSE cannot reliably determine either the amount or the basis of its obligation. Collateral posted under those circumstances secures a contingent and uncertain exposure rather than a clearly defined obligation. As a result, the provision may increase rather than reduce

PDF page 66

Adam Bednarczyk Affidavit
15

uncertainty, may complicate efforts to hedge future obligations, and may ultimately shift risk to other LSEs, including entities that do not serve large loads as PJM defines them.

IX. FRR and RPM Self-Supply Asymmetry
59. The RBP also treats FRR entities and RPM self-supply entities differently in ways that raise comparability concerns. PJM proposes to exclude “Fixed Resource Requirement (‘FRR’) Entities as of the 2028/2029 Delivery Year” from the Reliability Backstop Procurement, including both the Initial and Final RBP Targets, while continuing to hold an Electric Distributor zone or area responsible for RBP UCAP MW if that zone or area later becomes an FRR Service Area. PJM’s proposed RAA revisions further provide that, beginning with the 2028/2029 Delivery Year and thereafter, an FRR Capacity Plan must consist solely of Capacity Performance Resources and Seasonal Capacity Performance Resources, and that an FRR Entity may not use certain existing generation resources or any resource committed through the RBP to satisfy its FRR Capacity Plan.

60. When those provisions are read together with RAA Schedule 8.1, which requires an FRR Capacity Plan to include sufficient capacity to serve all load in the FRR Service Area, including load growth, an important comparability issue emerges. An FRR entity that satisfies its resource adequacy obligation through qualifying owned resources, and at least some categories of existing resources, is effectively insulated from RBP exposure. By contrast, an RPM LSE that has prudently developed, retained, or contracted for sufficient resources to serve all or part of its incremental load does not appear to receive comparable treatment under the RBP cost-allocation framework. If PJM recognizes resource adequacy actions taken under the FRR construct for purposes of avoiding RBP exposure, principles of comparability and cost causation suggest that it should similarly recognize owned resources, bilateral contracts, and comparable resource commitments maintained by RPM LSEs when determining RBO MW, RBP Charges, and collateral obligations. As filed, the proposal appears to exempt FRR entities from the RBP framework while providing no equivalent mechanism to credit RPM LSEs that have undertaken similar resource adequacy actions.

61. I am not suggesting that existing resources should receive RBP compensation. The issue is instead whether existing owned resources, bilateral contracts, and other resource adequacy commitments should be recognized when determining whether an LSE created the residual need for RBP procurement and whether that LSE should bear RBP-related costs and obligations. PJM can reasonably limit RBP payments to new backstop resources while still recognizing existing resources, or comparable contractual arrangements, for purposes of cost allocation, collateral assignment, and reliability-neutrality determinations.

PDF page 67

Adam Bednarczyk Affidavit
16

62. More fundamentally, an LSE’s choice between the RPM construct and the FRR alternative should not determine whether its resource position receives recognition under the RBP. An LSE that elects RPM but secures sufficient resources to support its incremental load stands in a comparable position to an FRR entity that satisfies its obligations through its FRR Capacity Plan. The relevant question is whether the LSE has taken actions that mitigate or eliminate the incremental reliability need, not which resource adequacy construct it uses to satisfy its RAA obligations.

63. PJM’s proposed revisions also appear unclear regarding the extent to which a future FRR entity may rely on existing resources, including bilateral contracts associated with existing resources, to satisfy FRR obligations. To the extent those provisions conflict with other RAA provisions governing FRR resource eligibility, or are interpreted to restrict reliance on existing bilateral arrangements, they could create additional market-design concerns. That issue is particularly important for LSEs whose resource adequacy strategies rely heavily on long-term bilateral contracts.

64. Ultimately, comparable treatment matters because the RBP is intended to address incremental reliability need, not to favor one resource adequacy construct over another. If two LSEs have each secured sufficient resources to support their incremental load and satisfy reliability-neutrality objectives, the fact that one participates through FRR and the other through RPM should not, by itself, determine whether one avoids RBP obligations while the other remains exposed to RBP costs, collateral requirements, and related risks.

X. Application to EKPC
65. I understand that EKPC is not identified in PJM’s allocation table as directly responsible for RBP costs associated with the large-load adjustments underlying the proposed procurement. That fact is important, but it does not eliminate EKPC’s exposure under the filed proposal. EKPC’s concern is not that it will necessarily receive a direct Electric Distributor assignment or a direct allocation under PJM’s default cost allocation methodology. Rather, EKPC’s concern is that the proposal may impose RBP costs and collateral obligations on other LSEs in a manner that is not closely tied to cost causation, thereby increasing the likelihood that those obligations become unmanageable and ultimately result in defaults.

66. That concern is particularly relevant because proposed Tariff section 18.9(a) provides that, if an LSE defaults and fails to pay an RBP Charge, “the defaulted amount will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share of the total RBP Charges for all such Load Serving Entities,”3 subject to any available RBP Collateral posted by the

3 PJM Interconnection, L.L.C., Proposed Open Access Transmission Tariff, Attachment DD § 18.9(a).

PDF page 68

Adam Bednarczyk Affidavit
17

defaulting LSE. As a result, even if EKPC is not expected to receive an initial RBP allocation associated with the identified large-load growth, EKPC may nevertheless face exposure through the proposal’s default-allocation framework if other LSEs assigned RBP obligations are unable to satisfy them.

67. From EKPC’s perspective, the market-design concern therefore arises one step removed from the initial allocation. The risk is not primarily that EKPC will be identified as causing the need for Reliability Backstop Procurement. Rather, the risk is that PJM’s allocation, offset, collateral, and responsibility- tracking mechanisms may fail to align costs and risks with the entities that created the procurement need. If those entities are assigned obligations that are difficult to predict, hedge, finance, or recover, resulting defaults may transfer costs to other market participants, including EKPC, through the residual allocation provisions.

68. This exposure is a market-design concern independent of whether EKPC receives a direct initial assignment. A tariff framework that does not identify responsible LSEs at the outset, track recognized offsets and opt-ins to those LSEs, and maintain default-allocation rules tied as closely as practicable to cost causation can shift the financial consequences of large-load-driven procurement to entities that did not create the underlying need. I do not offer a legal conclusion regarding the ultimate tariff standard. My point is that, as a matter of market design, the filed framework leaves residual cost and collateral risks that are not fully traceable to the entities responsible for the incremental procurement need and, as a result, may ultimately expose other LSEs, including EKPC, to those risks.

XI. Conclusion
69. In my opinion, PJM has identified a serious reliability challenge, but the proposed RBP does not satisfy PJM's Section 205 burden as filed. My concern is not a general disagreement with PJM's policy objectives. Rather, the specific design choices reflected in proposed Tariff sections 18.1, 18.2, 18.3, 18.4, 18.5, and 18.8, together with proposed RAA Articles 7.2B and 7.2C, do not adequately align responsibility for the procurement with responsibility for the resulting costs, credit exposure, and collateral obligations. The proposal may impose long-term costs and collateral requirements on LSEs that did not create the residual procurement need, may fail to recognize or protect LSEs that prudently addressed resource adequacy through self-supply, bilateral contracting, or other mitigation measures, and relies on Electric Distributor, state, and RERRA processes to resolve allocation questions that should be addressed more directly and transparently in the federal tariff.

70. For these reasons, I conclude that the proposal does not adequately align RBP costs, credits, reporting obligations, and collateral requirements with the reliability-neutrality principle that should govern new large-load growth. The proposed tariff does not consistently satisfy the principles of

PDF page 69

Adam Bednarczyk Affidavit
18

transparency, traceability, and cost causation. It does not consistently identify the entities responsible for the incremental reliability need, track the actions taken to mitigate that need, or ensure that resulting costs, credits, collateral obligations, and risks remain aligned with those entities. The proposal also separates procurement from the operational mechanisms that would otherwise encourage reliability- neutral behavior. Unlike the Coalition proposal supported by EKPC, the filing does not establish a unified framework that identifies the responsible load, records mitigating actions, assigns resulting obligations, and links reliability consequences to the failure to bring sufficient resources. As a result, the proposal weakens the connection between the parties that create or mitigate the need for backstop procurement and the parties that ultimately bear the associated costs and risks.

71. This completes my affidavit.

PDF page 70

VERIFICATION OF AFFIDAVIT
Pursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing Affidavit is true and correct.

Executed August 21, 2026.
By: _____________________________
Adam Bednarczyk

PDF page 71

Attachment 2
Affidavit of Carl F. Coscia

PDF page 72

1

AFFIDAVIT OF CARL F. COSCIA, Ph.D.
On behalf of East Kentucky Power Cooperative, Inc.
PJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000
Prepared by Toller Energy  ·  21 August 2026

I.  INTRODUCTION AND QUALIFICATIONS
1. My name is Carl F. Coscia. I am the Principal of Toller Energy, an independent energy consulting firm. My business address is Wynnewood, Pennsylvania 19096. I have been retained by Eversheds Sutherland (US) LLP on behalf of East Kentucky Power Cooperative, Inc. to evaluate the credit and collateral provisions of the Reliability Backstop Procurement proposed by PJM Interconnection, L.L.C.1 The opinions expressed in this affidavit are my own. No part of my compensation is contingent on the outcome of this proceeding.

2. I hold a Ph.D. in Economics from the University of Minnesota, and a B.S. in Economics and a B.A. in Mathematics from the University of Kansas. I have more than twenty-five years of experience in wholesale power and commodity markets, concentrated in credit risk, market design and regulatory proceedings, and have provided testimony, affidavits or economic analysis in more than forty proceedings before the Federal Energy Regulatory Commission, the Commodity Futures Trading Commission, and other regulatory and self-regulatory bodies.

3. From September 2022 to March 2026 I served as Chief Risk Officer of PJM Interconnection, L.L.C., where I led the corporate risk function across the energy, capacity and financial transmission rights markets. The credit provisions of Attachment Q to the Open Access Transmission Tariff fell within my responsibility, as did the Key Risk Metrics reported to the Risk Management Committee and relied on in this affidavit. I led PJM’s work with stakeholders on Peak Market Activity, Know Your Customer, minimum capitalization and RPM credit support, and PJM’s management of the collateral consequences of Winter Storm Elliott and Winter Storm Fern. I administered the credit policy from which the provisions at issue in this proceeding depart.

4. Based on that experience I am familiar with how collateral requirements in the organized markets are derived from measured exposure, administered as that exposure changes, and released as it declines, and with the liquidity consequences of collateral calls for the participants subject to them. Before joining PJM I held senior risk and commercial roles at EnBW AG, Hartree Partners, LP, Constellation Energy and TXU, and earlier served as a Branch Chief in the Office of Enforcement at the Federal Energy Regulatory Commission and at The Brattle Group. At Constellation I was the primary author of the company’s comments in the Commission’s credit reform rulemaking, Order No. 741, which is cited in this affidavit.

5. In preparing this affidavit I have reviewed the July 31, 2026 filing in this docket and the affidavits submitted with it, the provisions of the Open Access Transmission Tariff, the Operating Agreement and the Reliability Assurance Agreement to which those provisions refer, the materials presented to PJM stakeholders during the development of the proposal, PJM’s Key Risk Metrics and Credit Metrics reporting to the Risk Management Committee, PJM’s audited financial statements, the reports of the Independent Market Monitor, and the public financial reports of the entities discussed. Materials on which I rely are cited where used.

1 I have also been retained by Northern Virginia Electric Cooperative (“NOVEC”) in this docket and have submitted a separate affidavit on its behalf addressing the application of the proposed provisions to that cooperative and to the NOVEC zone/area. Section XI of this affidavit uses the NOVEC zone/area as an illustration because it carries the largest single-zone allocation to a cooperative under PJM's own figures.

PDF page 73

2

II.  PURPOSE AND SUMMARY OF OPINIONS
6. I have been asked by counsel to review the credit and collateral provisions of the Reliability Backstop Procurement proposed by PJM Interconnection, L.L.C. on July 31, 2026 in Docket No. ER26-3380-000, and to address five questions: (i) whether the proposed RBP Credit Rate is derived on terms standard to commercial collateral arrangements, which require an identified measure of exposure, a tenor over which that exposure is held, and a liquidation value at which the defaulted position would be replaced; (ii) whether the proposed requirement meets the standard for collateral, namely to protect the non-defaulting party from loss; (iii) whether a Load Serving Entity subject to an RBP Charge can determine, from the filed rate, the amount it will be required to post; (iv) whether the requirement itself creates systemic liquidity risk among the entities obligated to post it; and (v) how a default is socialized under the proposed provisions, and what follows from that allocation. My opinions address proposed Tariff, Attachment DD, sections 18.8 and 18.9, and the provisions on which those sections depend.

7. My opinions are as follows.
(a)  The requirement is without precedent in PJM. At the Initial RBP Target, the LSE collateral requirement is approximately $10.2 billion. PJM’s monthly Key Risk Metrics reporting shows total collateral held from all Members, against every market it operates, averaging approximately $6.2 billion in 2024 and $7.0 billion in 2025. It rose in 2026 as measured exposure rose, peaking at approximately $13.1 billion in February 2026 and standing at approximately $10.9 billion on July 30, 2026.

(b)  The requirement is not derived on standard commercial terms. Collateral is sized to the cost of replacing defaulted performance, which requires identifying the position to be replaced, the price at which it would be replaced, and the period over which the exposure is held. Section 18.8 identifies none of the three.

(c)  The requirement is a financing calculation rather than a measure of exposure. The RBP settles as a contract for differences, and the gross strike stream is never billed to load. PJM derived the $1.5 million Credit Rate as approximately fifty percent of the gross fifteen-year contractual value of $3.04 million per MW.

(d)  The requirement does not protect the non-defaulting party from loss in the manner PJM’s own credit policy contemplates. Attachment Q, Section I states that PJM must have authority to monitor and manage credit risk on an ongoing basis and to act promptly, in order to protect the PJM Markets and PJM Members from losses. Section 18.8 provides no ongoing measurement and no recalculation as exposure changes.

(e)  The quantity of MW to which the Credit Rate applies cannot be determined from the tariff. Section 18.8(b)(i)(A) keys the requirement to committed MW reduced only for rescissions, notwithstanding that commercial operation dates are permitted through June 1, 2032, while section 18.8(b)(i)(B)(1) scales each LSE’s posting to the Final RBP Target, a quantity that diverges from committed MW if the procurement clears short as PJM states it may.

(f)  The reduction of the requirement over the term is undefined. Attachment Q provides that collateral no longer required “shall be returned at the request of a Participant” within two Business Days, and Attachment Q, Section VI.B.3 sets out a mandatory, participant-initiated schedule reducing RPM auction credit across five stated milestones. Section 18.8(b)(i)(A) provides only that the Credit Rate “may be reduced” by the Office of the Interconnection “to an amount sufficient,” without methodology, schedule or request mechanism.

(g)  The cost of carrying the requirement is material and is not recovered. The requirement imposes a material financing cost on load-serving entities that no provision of the proposed tariff recovers, and that appears in no figure PJM has presented. Its magnitude depends on

PDF page 74

3

the form of collateral elected and on the entity’s own credit terms. At the Initial RBP Target, the annual cost ranges from approximately $102 million at 100 basis points to approximately $307 million at 300 basis points, against approximately $573 million billed to load in the first Delivery Year. Expressed per unit, the cost is approximately $41.10 to $123.29 per MW-day, or approximately seven to twenty-two percent of the $555 maximum willingness to pay.

(h)  The requirement creates systemic liquidity risk among the entities obligated to post it. Approximately $10.2 billion becomes due on a single date, in a form limited to cash or letters of credit. On PJM’s illustrative figures the Electric Distributor zone/area PJM designates NVEC — served by Northern Virginia Electric Cooperative, and referred to in this affidavit as the NOVEC zone — carries an initial allocation of 1,302.6 UCAP MW, corresponding to collateral of approximately $1.95 billion. The requirement falls without regard to the balance sheet of the entity obligated to post it.

(i)  The socialization of a default increases the obligation of the remaining LSEs and reaches members with no allocation. Section 18.9(a) reallocates a defaulted RBP Charge pro rata among the remaining LSEs paying RBP Charges. Under Operating Agreement, section 15.2.2, the residual exposure extends to PJM Members generally.

8. I do not address the reliability need for the procurement, the absence of a locational requirement, the role assigned to Electric Distributors, or the jurisdictional questions raised by that role. My opinions on the sizing of the credit requirement do not depend on the resolution of any of those issues.

9. The principle underlying my opinions is not complex. A security deposit is sized to the damage a tenant might do, not to the rent due over the life of the lease. A landlord who demanded six months’ rent as a deposit on a twelve-month lease would be asked what damage he expected. That is approximately what the Credit Rate demands, measured against the gross value of the RBP commitment on PJM’s own derivation. Measured against the exposure the collateral actually secures, it demands considerably more. The filing does not identify the corresponding measured exposure.

PART ONE — FRAMEWORK
III.  THE ROLE OF COLLATERAL
10. This section establishes the standards that govern collateral and margining in commercial and organized markets. Those standards are not matters of individual judgment. They are set out in published guidance issued by the Committee on Payments and Market Infrastructures of the Bank for International Settlements together with the International Organization of Securities Commissions, adopted by the Financial Stability Board as one of twelve key standards essential to financial stability, and, for the organized wholesale electric markets specifically, in the orders and credit policy of this Commission. PJM’s own Attachment Q is constructed on the same architecture. I set out those standards here so that the proposed RBP credit requirement can be measured against them in the sections that follow.

11. Collateral secures replacement cost, not the contract. It is a risk instrument, not a revenue instrument. The governing international standard defines the exposure being secured as replacement-cost risk — “the risk of loss of unrealised gains on unsettled transactions with a counterparty,” where “the resulting exposure is the cost of replacing the original transaction at current market prices.” CPSS-IOSCO, Principles for Financial Market Infrastructures (April 2012) (“PFMI”) ¶ 2.5.

PDF page 75

4

12. Collateral is accordingly held “to cover current and potential future exposures.” PFMI ¶ 1.13. Principle 4 requires that credit exposures be effectively measured, monitored and managed, and Principle 6 requires that a margin system be “risk-based and regularly reviewed.”

13. Price. Loss is contract price less replacement price. Because replacement price moves with the market, margin levels must be “commensurate with the risks and particular attributes of each product, portfolio, and market” the infrastructure serves. PFMI, Principle 6, Key Consideration 1. Exposure is therefore recalculated rather than fixed.

14. Liquidation. The exposure period runs from default to replacement. PFMI Principle 6, Key Consideration 3 requires initial margin models “sufficient to cover its potential future exposure to participants in the interval between the last margin collection and the close out of positions following a participant default,” using “a conservative estimate of the time horizons for the effective hedging or close out of the particular types of products cleared.” The driver is the close- out horizon, not the remaining term of the contract.

15. Sizing therefore requires answering three questions: what position is being replaced, at what price, and over what period. That is the structure of PFMI Principle 6, and it is the structure of the Commission’s own credit policy, which identifies the function of collateral as preventing the socialization of a default across the membership. Policy Statement on Electric Creditworthiness, 109 FERC ¶ 61,186, P 17 (2004); Credit Reforms in Organized Wholesale Electric Markets, Order No. 741-A, 134 FERC ¶ 61,126, n.3 (2011). I refer to these below as the three elements.

16. Requirements are recalculated as exposure moves and released as it declines. PFMI Principle 6, Key Consideration 4 requires marking positions to market and collecting variation margin “at least daily to limit the build-up of current exposures,” together with the authority and operational capacity to make intraday calls. PFMI Principle 6, Key Consideration 7 requires that the margin system be regularly reviewed and validated.

17. PJM’s own credit policy is constructed on these principles. The general credit requirement is sized to Peak Market Activity, computed from a participant’s own observed billing history; unsecured credit allowances are keyed to creditworthiness and tangible net worth; and requirements are recalculated on an ongoing basis. Attachment Q, Section V.A provides that collateral no longer required “shall be returned at the request of a Participant no later than two Business Days” following PJMSettlement’s determination; that a Participant may substitute one approved form of collateral for another absent a default; and that interest on cash accrues to the benefit of the Participant.

18. Where PJM faces forward price exposure, it measures that exposure directly. The FTR Credit Requirement is calculated on a portfolio basis as initial margin, less Auction Revenue Right Credits, less Mark-to-Auction Value, less realized gains and losses, subject to a floor. Initial margin for FTR Obligations is “determined utilizing a historical simulation value-at-risk methodology that calculates the size and value at risk of the applicable FTR portfolio,” aggregated by straight sum for long-term positions and by a combination of straight sum and weighted root sum of squares for balance-of-period positions. The model “will employ a confidence interval of 99 percent” — the same standard PFMI Principle 6, Key Consideration 3 requires. Historical values are adjusted forward where PJM’s economic planning model indicates that transmission upgrades will reduce congestion, and PJM may recalculate at any time and must do so no less frequently than after each annual FTR auction.

19. For planned resources in the capacity market, PJM sizes the requirement to Net Cost of New Entry for the applicable region or Locational Deliverability Area, subject to a floor, and reduces it as construction risk is retired. Attachment Q, Section VI.B.3 provides that the RPM Auction Credit requirement “shall be reduced” on a stated schedule of five construction milestones, each initiated by written request of the Market Participant and supported by defined evidence.

PDF page 76

5

20. The concern with access is not incidental to the Commission’s regulation of RTOs. It is the reason the Commission required them. In Order No. 2000 the Commission codified the minimum characteristics and functions an entity must satisfy to be an RTO, with the stated goal of promoting “efficiency in wholesale electricity markets” and ensuring “that electricity consumers pay the lowest price possible for reliable service.” Regional Transmission Orgs., Order No. 2000, 89 FERC ¶ 61,285, order on reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000). The rule was directed at removing the remaining impediments to competition in wholesale power markets, and the Commission grounded it in the observation that efficient and competitive markets develop only where participants have confidence that the system is administered fairly. A collateral requirement imposed by an RTO is a condition of access to the market that RTO was formed to operate. It is measured against that purpose.

21. The Commission has also stated the limiting principle on the other side. In establishing credit policy, “the role of an RTO is to balance the competing goals of minimizing risk to non-defaulting market participants while, at the same time, ensuring that the credit or collateral requirements are not so stringent that they unnecessarily inhibit access to the marketplace.” Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at P 19 (2009) (citing Sw. Power Pool, Inc., 114 FERC ¶ 61,222, at P 1 (2006), and Midwest Indep. Transmission Sys. Operator, Inc., 115 FERC ¶ 61,296, at P 16 (2006)).

22. The Commission has applied that standard to reject a proposed RTO credit provision. In the same order it found a revision defining default as occurring upon a missed invoice date, rather than at the end of the cure period, “may be so stringent as to unnecessarily inhibit access to the marketplace,” and rejected it. Id. at P 21. The Commission did so notwithstanding that the provision had emerged from the RTO’s stakeholder process, holding that “the Commission cannot accept any proposal from the stakeholder process that is unduly burdensome or unduly discriminatory.” Id. The Commission credited the concern that a single default could trigger cross- default provisions in customers’ other agreements, and placed on the RTO the burden of showing that such provisions could be avoided. Id. and n.23.

23. The same standard appears in PFMI Principle 18, which requires “objective, risk-based, and publicly disclosed criteria for participation, which permit fair and open access.”

24. A participant must also be able to determine what the requirement will cost it. PFMI Principle 23 requires that an infrastructure “provide sufficient information to enable participants to have an accurate understanding of the risks, fees, and other material costs they incur by participating,” and that “all relevant rules and key procedures should be publicly disclosed.”

25. Commercial practice outside the organized markets follows the same architecture — rating-based unsecured thresholds, variation margin recalculated as exposure moves, negotiable forms of support, and termination payments measured by replacement cost rather than remaining notional.

26. Where a central counterparty intermediates, an uncovered default mutualizes to the membership, and the defaulting participant’s own margin absorbs the loss first. PFMI ¶¶ 1.13, 3.4.24. PJMSettlement occupies that position in the PJM markets, and Attachment Q, Section I states the purpose accordingly: PJM “must have the authority to monitor and manage credit risk on an ongoing basis, and to act promptly to mitigate or reduce any unsecured credit risk, in order to protect the PJM Markets and PJM Members from losses.”

IV.  PARTIES AND EXPOSURES UNDER THE RBP
27. This section identifies who bears what under the RBP. That question is prior to any judgment about whether the credit requirement is correctly sized, because collateral secures a party against a loss, and one cannot evaluate the amount without first knowing whose loss it is and who is protected from it. A commercial arrangement of this kind involves four distinct roles: the party that posts collateral, the party that pays, the party that receives the benefit, and the party that

PDF page 77

6

absorbs a default. In an ordinary bilateral contract these align. Under the proposed provisions they do not. I set out the structure here and address its consequences in the opinions that follow.

A.  Parties with obligations
28. RBP Sellers submit Sell Offers, receive commitments for a fixed fifteen-year term, and post collateral under section 18.8(a) equal to 20% of the offer price times committed UCAP MW times 365 days, for the first three Delivery Years.

29. A seller that fails to achieve commercial operation is subject to RBP shortfall charges under section 18.6(d), assessed daily on the full committed UCAP at a rate of 20% of the commitment price, for up to three years. A resource delayed solely by Network Upgrades is excepted if it demonstrates readiness through test energy and seeks interim deliverability.

30. Under section 18.6(e), if committed MW fail to come online for three Delivery Years the commitment is rescinded for the remainder of the fifteen-year term. The resource is then neither compensated nor subject to further shortfall charges. Seller exposure is therefore bounded at three years of shortfall charges, and the seller’s collateral is sized to that same quantity. That administrative cap on the seller’s assessed liability is distinct from the economic replacement exposure experienced by load when the capacity does not arrive, which I address at paragraphs 90 to 95.

31. Load Serving Entities allocated RBP Charges pay the contract-for-differences settlement for the full fifteen-year term and post collateral under section 18.8(b) at $1.5 million per RBP UCAP MW. Only LSEs in zones with a non-zero Load Adjustment are allocated RBP Charges.

32. PJMSettlement is counterparty to the transactions.
B.  Parties without obligations
33. Electric Distributors determine the allocation of RBP Obligation MW among LSEs within their zone or area. Proposed Reliability Assurance Agreement, section 7.2C. They incur no payment obligation and post no collateral.

C.  The residual tier
34. Under Operating Agreement section 15.2.2, where a Member defaults on its payment obligations the other PJM Members may be required to pay a share of the defaulted amounts. That exposure extends to Members with no Load Adjustment and no RBP Charge allocation.

D.  How a default travels
35. On an LSE default, section 18.9(a) provides that the defaulted RBP Charge “will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share,” and that such amounts “may be offset by the RBP Collateral posted by the defaulting Load Serving Entity.” Reallocation is mandatory; application of the defaulter’s collateral is permissive.

36. On a seller default, section 18.9(b) provides that where an RBP Resource defaults on payment of shortfall charges, “the corresponding credits will not be allocated to the Load Serving Entities that would otherwise receive the RBP shortfall credits.” Load bears the loss directly.

37. The two provisions are asymmetric in effect. A load default is recovered from other load. A seller default leaves load uncompensated, and after rescission under section 18.6(e) load receives nothing for the remaining twelve years of a fifteen-year commitment.

38. Under section 18.6(f), a commitment follows the resource on a change of ownership and continues through the end of the fixed term. The identity and financial condition of the party performing the commitment may therefore change during the term while the commitment itself does not. I address the treatment of seller credit over the term in Section VII.

PDF page 78

7

E.  Which party is harmed by which failure
39. The RBP has three distinct failure modes, and they harm different parties at different times. The first is a failure by a Load Serving Entity to post the required collateral on the stated date, which is a liquidity event occurring forty-five days before the Delivery Year begins. The second is a failure by a Load Serving Entity to pay an RBP Charge, which is a credit event arising during the Delivery Year. The third is non-delivery by an RBP Seller, which is a physical event. The first two are both financial but are not the same: they are triggered by different conditions, arise on different dates, and are secured differently. Collateral secures the second. It does not secure the first, because the first is a failure to provide the collateral itself. Collateral is ordinarily sized to the loss it prevents, so these distinctions are prior to any judgment about the amount of either requirement.

40. A payment failure by an LSE does not affect whether capacity is delivered. The committed resource remains committed and the procurement proceeds. What occurs is a reallocation. Under section 18.9(a) the defaulted RBP Charge is allocated among the remaining Load Serving Entities responsible for paying RBP Charges; because RBP Charges are assessed against every zone/area holding a share of the RBP Target, that population is footprint-wide rather than confined to the zone in which the default occurred. Under Operating Agreement section 15.2.2 any residual reaches the wider membership. The parties harmed are therefore other load. Within a zone/area, the Electric Distributor assigns RBP Obligation MW in the first instance to the Load Serving Entities serving the Large Loads whose forecast growth generated the Load Adjustment; where it does not, section 18.8(b)(i)(B)(2) reaches load on Peak Load Contribution, which is native load. The Large Loads are not themselves parties to the RBP and bear no share of the reallocation under section 18.9(a).

41. Non-delivery by an RBP Seller has the opposite incidence. The capacity for which the procurement was conducted does not arrive, and the reliability the RBP was designed to secure is not obtained. That harm falls on the loads the procurement was designed to serve. PJM has described a framework under which RBP supply matched to specific Large Loads would be credited as a Bring Your Own Capacity showing for Interim Resource Adequacy Service purposes, but the filed provisions establish no mechanism by which an RBP commitment is matched to a particular Large Load or Load Serving Entity, and I express no view on how such a credit would be determined. The harm falls on load generally, both through the resource adequacy shortfall and financially: under section 18.9(b) load does not receive the shortfall credits, and after rescission under section 18.6(e) load receives nothing for the remaining twelve years of a fifteen- year commitment.

42. Neither the tariff nor the filing quantifies the second of those harms. Shortfall charges under section 18.6(d) are assessed for up to three years at a rate fixed by reference to the commitment price; they are not a measure of the cost of replacing the capacity that did not arrive. PJM identified the same gap in its own analysis, stating that a default in year three of a fifteen-year contract leaves twelve years of capital cost uncovered, and that the current tariff does not calculate liquidated damages. I address the consequences of that gap in Sections VII and IX.

F.  Application to EKPC
43. PJM’s illustrative allocation shows EKPC with a Load Adjustment of zero and no allocation of the RBP Target. EKPC would therefore not be allocated RBP Charges on those figures, and would not post RBP Collateral. EKPC nonetheless remains within the residual tier under Operating Agreement section 15.2.2. EKPC is the Load Serving Entity for its member-owner distribution cooperatives, and an obligation allocated to those cooperatives’ load would be borne by EKPC. The quantity that sets each Load Serving Entity’s collateral requirement is submitted by its Electric Distributor. That entity incurs no payment obligation, posts no collateral, and need not itself be a PJM Member. The party that determines the size of the requirement is therefore not the party subject to it, and PJM’s credit provisions reach only the latter.

PDF page 79

8

V.  THE PROPOSED CREDIT CONSTRUCT
44. This section describes the proposed provisions without evaluating them. I quote the operative language, and PJM’s own stated derivation of the figures, because the questions posed to me turn on what the tariff says and on how PJM arrived at the amounts rather than on how they have been characterized.

A.  Seller collateral
45. Section 18.8(a) requires each RBP Resource seeking to submit a Sell Offer to post collateral equal to the sum, over the first three Delivery Years, of 20% of the RBP Sell Offer price times the offered UCAP MW times 365. Collateral is posted at or before bid submission, in cash or letter of credit. It is returned within five business days for offers that do not clear, and for committed resources only after the resource achieves commercial operation and a subsequent one-year look- back.

B.  The cumulative buyer requirement
46. Section 18.8(b)(i)(A) provides that “the cumulative RBP credit requirement for Load Serving Entities for a given Delivery Year shall be equivalent to the product of the RBP Credit Rate multiplied by RBP UCAP MW committed.”

47. The RBP Credit Rate “shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an amount sufficient to cover the total existing RBP Charges obligations.”

48. The quantity to which the rate applies is “the amount of RBP UCAP MW that receives a commitment through the Reliability Backstop Procurement minus each commitment of RBP UCAP MW that is rescinded pursuant to Tariff, Attachment DD, section 18.6(e).” Rescission is the only stated reduction. Commercial operation dates are permitted through June 1, 2032.

C.  The individual LSE posting
49. Section 18.8(b)(i)(B)(1) requires each LSE with an RBP Obligation, “prior to forty-five (45) days before the start of the Delivery Year,” to “post, or maintain an existing, RBP Collateral equal to $1.5 million x the allocated RBP Obligation MW.” The obligation recurs in advance of each Delivery Year of the fifteen-year term.

50. The allocated RBP Obligation MW is the quantity “submitted for the Load Serving Entity by the Electric Distributor and scaled, as necessary, in the event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the zone/area.”

51. Where no RBP Obligations are reported by the Electric Distributor in a zone in which the LSE serves load, section 18.8(b)(i)(B)(2) provides that the LSE “may be required to post” collateral based on “the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.”

52. Under both subsections, PJM “may evaluate such Load Serving Entity for unreasonable credit risk under the Unreasonable Credit Risk provisions of Tariff, Attachment Q, Section II, and require additional RBP Collateral as appropriate.”

D.  Acceptable forms
53. RBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a letter of credit issued for the benefit of PJM or PJMSettlement, in an amount and form determined by and acceptable to PJM or PJMSettlement as credit support.” Surety bonds, which PJM accepts elsewhere subject to per-issuer limits, are not included. No unsecured credit allowance is provided.

PDF page 80

9

E.  PJM’s stated derivation
54. PJM states that it is proposing to address RBP credit “through rules outside of its Credit Risk Management Policy,” and that the LSE requirement is intended to mitigate potential defaults from non-payment of RBP Charges. PJM states that its “current credit tools do not contemplate the long-term nature of RBP and the risk of future non-payment that results.” PJM Interconnection, L.L.C., “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load Adjustments” Docket No. ER26-3380-000 (filed July 31, 2026) (“PJM RBP Filing”), Attachment D, Affidavit of Gwen Kelly, ¶ 19 (“Kelly Aff.”).

55. For sellers, PJM states the requirement formulaically as the sum over the first three Delivery Years of 0.2 × RBP Sell Offer Price × UCAP MW × 365. Kelly illustrates with a 100 MW commitment at $555/MW-day: a shortfall charge of $4,051,500 in each of the 2028/2029, 2029/2030 and 2030/2031 Delivery Years, and a credit requirement of $12,154,500. Kelly Aff. ¶ 18.

56. For load, PJM states that it sought “collateral that provides commensurate protection against non- payment while avoiding full collateralization of the entire 15-year contractual commitment.” Kelly Aff. ¶ 24.

57. PJM derived the $1.5 million figure from the gross contractual value of the commitment. It “estimated the contractual value associated with a 1-MW RBP commitment using conservative assumptions, including a 15-year commitment term application of the RBP price throughout that commitment period,” yielding “approximately $3.04 million, assuming the RBP clearing price at the price cap of $555/MW.” It then “concluded that an initial credit rate of $1.5 million per committed RBP MW would collateralize approximately 50% of the estimated contractual value associated with the commitment.” Kelly Aff. ¶¶ 25–26.

58. PJM separately checked that figure by discounted cash flow. Taking a 1-MW fifteen-year commitment at $555/MW-day, each year’s payment is $202,575, discounted to September 2026 at 9.5%: $172,841 for 2028/2029, $157,850 for 2029/2030, through $48,514 for 2042/2043. “All the NPV added together is $1,481,569.” Kelly Aff. ¶ 27.

59. PJM states that the 9.5% discount rate “is the capacity market Weighted Average Cost of Capital developed by The Brattle Group as part of PJM’s 2025 periodic review of the Cost of New Entry of Capacity Resources into the PJM Region,” and that “Given Brattle’s thorough analysis in arriving at 9.5%, it represents a well-supported discount rate.” Kelly Aff. ¶ 28.

60. PJM illustrates the resulting requirement for a 100 MW allocation as $1,500,000 × 100 MW = $150,000,000. Kelly Aff. ¶ 33.

PART TWO — THE CREDIT REQUIREMENT
VI.  OPINION 1 — The magnitude has no precedent in PJM
61. This opinion addresses magnitude. The Commission’s standard has two sides: an RTO must minimize the risk that a default is socialized among non-defaulting participants, while “ensuring that the credit or collateral requirements are not so stringent that they unnecessarily inhibit access to the marketplace.” Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at P 19 (2009). Magnitude is the measure of the second. In what follows I compare the proposed requirement to the collateral PJM actually holds, to the relationship PJM maintains between collateral and market activity, and to the annual charge the requirement secures. On each comparison the proposed requirement stands apart from anything in PJM’s experience.

PDF page 81

10

62. At the Initial RBP Target of 6,831.3 UCAP MW, the LSE collateral requirement is approximately $10.2 billion. On the illustrative Final RBP Target of 6,075.7 MW it is approximately $9.1 billion. PJM’s own illustration of a 100 MW allocation is $150,000,000. Kelly Aff. ¶ 33.

63. PJM’s monthly Key Risk Metrics reporting shows the total collateral PJM holds from all Members, against every market it operates, at approximately $6.2 billion on average in 2024 and $7.0 billion in 2025. Collateral rose materially in 2026 as measured exposure rose — PJM reports that three of the highest billing weeks in its history occurred that year — reaching approximately $13.1 billion in February 2026, the highest balance PJM has ever held, and standing at approximately $10.9 billion on July 30, 2026.

64. The proposed requirement for a single procurement of 6,831.3 UCAP MW is therefore approximately 78% of the largest collateral balance PJM has ever held, and approximately 96% of the average balance held during 2026 to date. Against the 2024 and 2025 averages it is 165% and 146% respectively.

65. Methodology. The series is constructed from PJM’s monthly Key Risk Metrics reporting to the Risk Management Committee. Figures are stated as approximate and rounded to the nearest $0.1 billion. I present them as approximate deliberately. At this magnitude the precision of any single month is not material to the conclusion, which rests on the ratio between the collateral PJM holds and the market activity that collateral secures. Attachment A.

66. The relationship PJM maintains between collateral and market activity is stable. Measured against settlements processed, collateral ran approximately 12% in 2024 and 9% in 2025. Measured against the Independent Market Monitor’s total cost of wholesale power, it ran approximately 11% in calendar 2025 and 13% over the twelve months ended June 2026. Two differently constructed measures place PJM’s collateral coverage in a band of roughly 9% to 13% of annual market activity. I use that band below.

67. The requirement is secured at a multiple of the value it secures. At the $555 maximum willingness to pay and the Initial RBP Target of 6,831.3 UCAP MW, the maximum gross annual commitment value — before any offset for RPM revenues — is approximately $1.38 billion, against a collateral requirement of approximately $10.2 billion. The collateral is therefore approximately 740% of one year's gross commitment value. That gross figure is not, however, the amount billed to load. As set out in Section VII.B, the RBP settles as a contract for differences, and at the 2028/2029 Base Residual Auction clearing price of $325.00/MW-day the amount billed in the first Delivery Year is approximately $573 million. Measured against that amount, the collateral requirement is approximately 1,790%. The comparison to PJM's existing markets should be made on a consistent basis: the band of roughly 9% to 13% set out above measures collateral against amounts actually settled and billed, and measured the same way the RBP requirement is on the order of 140 to 200 times the collateral intensity PJM applies to the markets it operates today. Measured instead against the gross annual commitment value — a basis more favorable to PJM, because it credits the requirement with securing a stream that is never billed — the multiple is on the order of fifty- five to eighty-five times. I use the latter figure below. The comparison is not one of scale alone. The collateral PJM holds today secures every market it operates and every class of participant in them — energy, capacity, transmission and financial transmission rights, across sellers, buyers and traders alike. The proposed RBP requirement secures one product, owed by one class of participant, posted on one date. A requirement approaching in magnitude the entire collateral balance PJM has ever held across all of its markets, raised from a subset of the participants in one of them, is a different kind of obligation and not merely a larger one.

68. The aggregate requirement resolves into zonal allocations of substantial size. On PJM’s illustrative figures, the initial allocation produces LSE collateral of approximately $2.29 billion for AEPOHIO, $1.95 billion for NVEC, $1.33 billion for COMED, $1.23 billion for PPL and $1.11 billion for DOM. Attachment B sets out the calculation for each Electric Distributor zone and area.

PDF page 82

11

69. The Commission has rejected a proposed RTO credit provision on the ground that it “may be so stringent as to unnecessarily inhibit access to the marketplace.” Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at at P 21 (2009).  The provision rejected there imposed no monetary requirement at all; it changed only the moment at which a payment default was deemed to occur, from the end of the cure period to the invoice due date.

70. The proposed requirement is materially larger than PJM’s historical collateral requirements. It has no precedent in PJM in magnitude, and the filing identifies no organized market in which a comparable requirement has been imposed on load. The aggregate figure also understates the burden on particular entities, because the requirement is allocated by zone and falls without regard to the balance sheet of the LSE obligated to post. I address that below.

VII.  WHETHER THE REQUIREMENT SECURES A MEASURED EXPOSURE
71. This section evaluates whether the proposed collateral secures a measured risk position, and whether the amount is sufficient or deficient under plausible future price outcomes. The standards set out in Section III require that collateral be sized to replacement cost, which is a function of the price at which the position would be replaced and the period over which the exposure is held; that the requirement be recalculated as exposure moves and released as it declines; and that a participant be able to determine what the requirement will cost it. I apply those elements here.

A.  The requirement is absent during the period of greatest uncertainty
72. Commitments bind when results are posted on December 2, 2026. Buyer collateral is not due until forty-five days before the start of the 2028/2029 Delivery Year, approximately April 17, 2028. For roughly seventeen months no LSE collateral secures the obligation. The obligation is not merely fixed during that period; its first year is already measurable. The 2028/2029 Base Residual Auction cleared in July 2026 at $325.00/MW-day, so at the moment the RBP commitment binds the first Delivery Year’s contract-for-differences exposure is known at $230/MW-day, or $83,950 per MW-year. Nor does the position remain single-year for long. The 2029/2030 Base Residual Auction results post on December 22, 2026, twenty days after RBP commitments bind, so within three weeks two Delivery Years are priced; by the April 2028 posting date they will have been known for approximately sixteen months. PJM requires no collateral against a quantified exposure for seventeen months, and the requirement it does impose is fixed without reference to prices that become observable almost immediately.

73. That interval is when the identity of the obligated party is least certain. RBP Obligation MW are reported to PJM by the Electric Distributor. If a large load fails to materialize, or fails to contract with a Load Serving Entity, the load on which the obligation was premised does not appear.

74. The tariff allocates that shortfall in two tiers. Under section 18.8(b)(i)(B)(1), RBP Obligation MW reported by the Electric Distributor are “scaled, as necessary, in the event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the zone/area.” Because the zonal target is fixed, an obligation that is not reported for one LSE is scaled onto the LSEs that are reported — in the first instance, the LSEs serving the other large loads in that zone. Under section 18.8(b)(i)(B)(2), where no RBP Obligations are reported at all, the requirement is determined by “the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area,” which allocates by total capacity obligation and therefore reaches native load.

75. PJM’s proposal does not address this period of risk. The exposure of a large load and its LSE that fail to materialize does not disappear; it is scaled onto the remaining large-load LSEs in the zone, and where none remain, onto native load. Those parties bear both the reassigned collateral requirement and, under section 18.9(a), the reallocated RBP Charges, “based on their pro-rata share of the total RBP Charges for all such Load Serving Entities.”

PDF page 83

12

B.  The requirement is not measured against the contract it secures
76. The RBP settles as a contract for differences. Under section 18.5(g)(ii), an RBP Resource offers into RPM as a price taker, clears, and receives the RPM clearing price. The RBP Charge pays the resource the difference between that RPM clearing price and its RBP commitment price, so that the resource receives its commitment price in total. The amount billed to load is therefore the difference between the RBP price and the RPM clearing price. The gross RBP price is never billed.

77. PJM nonetheless derived the Credit Rate from the gross price. It “estimated the contractual value associated with a 1-MW RBP commitment using conservative assumptions, including a 15-year commitment term application of the RBP price throughout that commitment period,” arriving at approximately $3.04 million, and set the Credit Rate at “approximately 50% of the estimated contractual value.” Kelly Aff. ¶¶ 25–26. Its discounted cash flow check applied the same gross figure — $202,575 per year, discounted at 9.5% to September 2026, summing to $1,481,569. Kelly Aff. ¶ 27.

78. The exposure can be measured directly for the one Delivery Year in which the RPM price is known. The 2028/2029 Base Residual Auction cleared at $325.00/MW-day UCAP. At an RBP price of $555 — the figure PJM itself assumes — the differential is $230/MW-day, or $83,950 per MW-year. Were that price to persist for fifteen years, the total exposure would be $1,259,250 per MW, already below the $1.5 million Credit Rate.

79. The following comparison is deliberately undiscounted: it equates the Credit Rate to the nominal sum of future differentials, without crediting the time value of exposures arising up to fifteen years forward. Future RPM prices are not known, and the filing contains no forecast of them. The standards require that potential future exposure be estimated. PJM has performed such an estimate. As set out in Section XIII, it modeled the procurement as a fixed-for-float swap and estimated potential future exposure at a 95 percent confidence level across the fifteen-year term, obtaining a profile that rises, reaches a maximum, and declines to zero at expiry. That estimate does not appear in the filing, and the Credit Rate does not reflect it. The filing itself neither produces a forward price path nor marks the most recent clearing price forward as an estimate of the remaining term, as PJM does for FTR portfolios under the Mark-to-Auction methodology in Attachment Q.

80. For the $1.5 million Credit Rate to correspond to the actual exposure, RPM would have to clear at approximately $277.89/MW-day or below in each of the fourteen Delivery Years after 2028/2029, given that year’s known clearing price of $325.00. On a flat assumption across all fifteen years, the required price is $281.03. Both are below the price already realized.

81. The filing identifies no basis for expecting prices at that level. Other statements in the filing contemplate continuing capacity shortfalls. PJM states that the 2029/2030 auction may clear short notwithstanding the RBP. It also proposes at section 16.2 to reinstate the existing Tariff provisions establishing a Reliability Backstop Auction — a mechanism distinct from the RBP proposed here

— beginning with the 2032/2033 Delivery Year, so that from that point forward a clearing shortfall against the Reliability Requirement in three consecutive Delivery Years would again initiate a backstop procurement. In the interim PJM proposes to suspend the trigger on the ground that further shortfall reports would be “substantively repetitive.” PJM therefore contemplates that shortfalls could continue, and provides for the existing backstop mechanism to resume once the RBP commitments are in place. The administrative price collar is a feature of the RPM capacity market rather than of the RBP, and it applies through the 2029/2030 Base Residual Auction only. Because the RBP Charge is the difference between the RBP price and the RPM clearing price, the collar constrains that difference while it is in force. For the remaining thirteen Delivery Years of the RBP term the RPM price is uncollared, and the differential is not bounded by it.

PDF page 84

13

82. PJM’s own analysis indicates where uncollared prices would settle. PJM simulated that, absent the price cap, the 2028/2029 auction would have cleared at $554.72/MW-day RTO-wide, and at $776.69 in the ComEd Locational Deliverability Area. PJM Interconnection, L.L.C., 2028/2029 Base Residual Auction Report at 17 (July 14, 2026) (Appendix, BRA Clearing Simulation Without Cap and Floor). The RBP maximum willingness to pay is $555.00.

83. If prices approach that level once the collar lapses, the contract-for-differences exposure approaches zero. At $554.72 the differential is $0.28/MW-day and the fifteen-year exposure is $1,533 per MW, against $1.5 million of posted collateral. On a blended path — the 2028/2029 Delivery Year at its known clearing price of $325.00, the 2029/2030 Delivery Year at the $333.44 collar proxy used elsewhere in this affidavit, and the remaining thirteen at $554.72 — the exposure is approximately $166,000 per MW, and the collateral would exceed it roughly nine times over. Attachment E.

84. Where the RPM price exceeds the RBP commitment price, the contract for differences reverses and the resource owes the difference to load. The collateral then secures no exposure at all.

85. The characterization of the Credit Rate as approximately half of contractual value depends on whether contractual value is stated on a nominal or a present-value basis. PJM derives $1.5 million per MW as approximately fifty percent of a gross fifteen-year contractual value of approximately $3.04 million per MW, that being the nominal sum of fifteen annual payments of $202,575. But PJM also discounts that same stream at its own 9.5% after-tax weighted average cost of capital, obtaining a present value of approximately $1.48 million per MW. The two measures are of course mathematically consistent with one another, being the nominal and present-value expressions of the same stream. The point is which one the Credit Rate is measured against. Against nominal value the Credit Rate is approximately fifty percent, as PJM describes it at Kelly Aff. ¶¶ 24 and

26. Against PJM’s own discounted value of the same stream it is approximately 101 percent — full collateralization of the entire fifteen-year gross obligation.

86. That comparison uses PJM’s own measure of the obligation, the gross contractual value. As set out above, the amount actually billed to load is the contract-for-differences differential rather than the gross stream. Measured against that differential, the requirement is larger still. The Credit Rate therefore represents full collateralization of a stream that is never billed, and a multiple of the exposure that is billed.

C.  The requirement departs from every methodology PJM applies elsewhere
87. The proposed LSE requirement does not use the exposure-measurement and recalculation features described in Section III. It is not sized to a replacement cost, because PJM measures the gross contractual value rather than the contract-for-differences exposure. It applies no close-out period. It is not recalculated as exposure moves, and it is released only at PJM’s discretion. It provides no unsecured credit allowance and accepts only two forms of collateral.

88. It also departs from each methodology PJM applies in its existing markets. For general market activity, PJM sizes the requirement to Peak Market Activity computed from a participant’s own observed billings. For forward price exposure in FTRs, PJM applies a historical simulation value- at-risk model at a 99% confidence interval, adjusted by Mark-to-Auction value and recalculated no less frequently than after each annual auction. For planned generation in RPM, PJM sizes the requirement to Net Cost of New Entry subject to a floor and releases it across five defined construction milestones. The RBP uses none of these. The filing offers no explanation for the departure beyond the observation that its “current credit tools do not contemplate the long-term nature of RBP.” Kelly Aff. ¶ 19.

89. PJM’s initial proposal in the stakeholder process would have secured the LSE obligation on a basis comparable to Peak Market Activity, covering approximately three to four weeks of billed obligations. PJM, Reliability Backstop Procurement Design, Reliability Backstop CIFP (June 10–

PDF page 85

14

11, 2026) (“Design Presentation”), at slide 35.2 At the RBP price of $555/MW-day, four weeks of the gross obligation is approximately $15,600 per MW; measured against the contract-for- differences exposure at the 2028/2029 clearing price, it is approximately $6,500 per MW. The filed Credit Rate of $1.5 million is between ninety-six and two hundred thirty-two times those figures. The Joint EDC and Data Center Coalition proposal contemplated that a credit obligation would attach when the LSE subscribed MW into the procurement, although the timing of collection was not specified. No proposal advanced during the stakeholder process, including PJM’s own, established a collateral requirement of the magnitude filed for the interval between commitment and the first Delivery Year.

D.  The seller requirement is deficient by the same standard
90. The seller requirement is derived from an administrative penalty rate — 20% of the offer price, the same rate as the shortfall charge under section 18.6(d) — rather than from the cost to load of replacing capacity that does not arrive. In an ordinary commercial arrangement the non- performing supplier makes the buyer whole for the prudently incurred cost of replacement. Here the replacement cost is the contract-for-differences differential.

91. The analysis that follows adopts PJM’s own assumption that the RBP clears at the price cap of $555/MW-day. Kelly Aff. ¶¶ 18, 25, 27.

92. For the 2028/2029 Delivery Year the differential is known: the Base Residual Auction cleared at $325.00/MW-day, and the exposure is $83,950 per MW. For 2029/2030, whose auction had not been held when this filing was made, I use as a proxy the 2027/2028 Base Residual Auction clearing price of $333.44/MW-day, giving $80,869 per MW. The two-year total is $164,819. PJM has not published the ELCC of the reference resource so the effective cap is not known. I selected the 2027/2028 auction as a proxy on the following grounds. First, the accreditation basis is the closest match available for a CT technology. Second, both Delivery Years are subject to the same price collar. Third, both are expected to clear short of the Reliability Requirement. The proxy is therefore an observed collared outcome under comparable accreditation and comparable supply conditions, rather than a forecast. Lastly, it is conservative in the direction that matters here. The 2029/2030 class rating is below the rating underlying the 2027/2028 auction, and a lower accredited rating corresponds to a higher cap expressed per megawatt of unforced capacity. If the 2029/2030 auction clears above $333.44/MW-day, the differential between the RBP price and the RPM price narrows, the exposure falls, and every ratio in this affidavit that depends on the proxy understates the disproportion I identify. The 2029/2030 Base Residual Auction results post on December 22, 2026, and will replace the proxy with an observed price before any collateral is posted under section 18.8(b).

93. Seller collateral at that price is $121,545 per MW. It covers 73.7% of those first two Delivery Years, and falls $43,274 short before any uncertain year is reached.

94. The first two Delivery Years therefore exhaust the seller collateral and leave a deficit before any uncertain year is reached. For the seller collateral to cover the modeled exposure over the full term, the contract for differences would have to reverse sufficiently during the remaining thirteen Delivery Years to offset approximately $43,274 per MW of that first-two-year exposure. That requires an average RPM clearing price of approximately $564.12/MW-day, or $9.12/MW-day above the RBP price, across the 2030/2031 through 2042/2043 Delivery Years. In that

2 Presentation available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop-procurement-design-presentation.pdf. Additional related materials including PJM’s CFIP Proposal is available here: https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop- procurement-paper.pdf. And PJM’s post-meeting materials are available here: https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04a---pjm-reliability-backstop- proposal---post-meeting-materials.pdf

PDF page 86

15

circumstance the contract for differences reverses and the resource pays load rather than the reverse.

95. The two requirements — the LSE collateral requirement and the seller collateral requirement — rest on opposite assumptions about the same variable. On PJM’s own price assumption, the seller’s collateral is adequate only if RPM clears at or above approximately $532.80/MW-day on average. The LSE’s collateral corresponds to the exposure only if RPM clears at an average of approximately $281.03 or below. The two implied prices differ by $251.77/MW-day. PJM states neither assumption, and no single average RPM price can satisfy both conditions. Attachment E.

E.  Neither requirement is measured against the party that bears it
96. Nothing in section 18.8(a) revalues the seller’s collateral for the credit of the entity performing at the time. The requirement is a formula — the greater of $20 or twenty percent of the bid or clearing price, multiplied by committed UCAP MW, by 365, by three — keyed to the commitment price fixed at selection. It does not vary with the seller’s rating, tangible net worth or any other measure of creditworthiness, and it is not recalculated when the resource changes hands. As set out at paragraph 38, section 18.6(f) provides that a commitment follows the resource on a change of ownership, so an entity acquiring a committed resource in a later Delivery Year posts the amount fixed at selection, whatever its own financial condition. Attachment Q evaluates creditworthiness on an ongoing basis and permits PJM to require additional security as a participant’s condition changes; section 18.8(a) contains no equivalent.

97. The LSE requirement is not measured against the party that bears it either, and it does not account for the collateral that party already provides. An LSE’s existing financial security under Attachment Q is determined by its Peak Market Activity, which is derived from its historical activity across the PJM Markets and therefore already reflects its RPM charges. The RBP Charge is the difference between the RBP price and the RPM clearing price. When RPM clears high, an LSE’s RPM charges rise, its Peak Market Activity rises with them, and the RBP differential falls; when RPM clears low, the reverse occurs. The two exposures move in opposite directions against the same variable.

98. Section 18.8(b) nonetheless requires the RBP posting in addition to, and without reference to, financial security already held under Attachment Q. It does not net the two, does not reduce either when the other rises, and does not extend the unsecured credit allowance that Attachment Q applies to Peak Market Activity. An LSE therefore posts the full Credit Rate against an exposure that declines precisely when the collateral supporting its other PJM obligations increases. Part of the same obligation is in consequence collateralized twice. The RBP Charge is secured in advance by the Credit Rate, and once the Delivery Year begins and RBP Charges are billed, those same charges enter the LSE’s Peak Market Activity through the ordinary operation of Attachment Q and are secured again by the financial security that Peak Market Activity requires. The filing does not address the relationship between the two requirements.

VIII.  THE QUANTITY OF MW TO WHICH THE CREDIT RATE APPLIES IS
INDETERMINATE
99. This section addresses the third question posed to me: whether a Load Serving Entity subject to an RBP Charge can determine, from the filed rate, the amount it will be required to post. The Credit Rate is a price per MW. The amount an LSE must post is therefore the product of that rate and a quantity of MW. Section 18.8 specifies three different quantities and does not state which governs when they diverge.

A.  The three quantities
100.
The first is committed MW. Section 18.8(b)(i)(A) provides that the cumulative requirement “shall be equivalent to the product of the RBP Credit Rate multiplied by RBP UCAP MW committed,”

PDF page 87

16

defined as “the amount of RBP UCAP MW that receives a commitment through the Reliability Backstop Procurement minus each commitment of RBP UCAP MW that is rescinded pursuant to Tariff, Attachment DD, section 18.6(e).”

101.
The second is the Final RBP Target. Section 18.8(b)(i)(B)(1) requires each LSE to post “$1.5 million x the allocated RBP Obligation MW,” where that quantity is “submitted for the Load Serving Entity by the Electric Distributor and scaled, as necessary, in the event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the zone/area.”

102.
The third is the Daily Unforced Capacity Obligation. Section 18.8(b)(i)(B)(2) provides that where no RBP Obligations are reported for a zone, the requirement is based on “the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.” That quantity is a function of the LSE’s peak load contribution and bears no relationship to the RBP commitment.

B.  Committed MW and the Final RBP Target will not be the same
103.
PJM states expressly that the two will diverge, and in both directions. Section 18.5(f) provides that “RBP Resources shall not be partially cleared,” and that “[i]n the event that the Reliability Backstop Procurement cannot meet the Final RBP Target, the Reliability Backstop Procurement shall clear short of the Final RBP Target.” The same section permits PJM to “commit an RBP Sell Offer with an offered quantity that exceeds the remaining Final RBP Target to the extent such solution provides greater economic efficiency.”

104.
PJM explains the reason: “Because the RBP is procuring new capacity and not simply fungible UCAP MW … there exists the possibility that PJM may clear a set of resources with a cumulative RBP UCAP MW total that does not exactly match the Final RBP Target.”

105.
The divergence is material. On the illustrative Final RBP Target of 6,075.7 UCAP MW, the requirement scaled to that target is approximately $9.11 billion. Were the procurement to clear five percent short, the requirement computed on committed MW would be approximately $8.66 billion — a difference of approximately $456 million. Were it to clear five percent over, the difference would be the same amount in the opposite direction. Nothing in section 18.8 states which figure controls.

C.  Committed MW is not in-service MW
106.
The only reduction to committed MW is rescission under section 18.6(e), which requires that MW “fail to come online for three Delivery Years.” Commercial operation dates are permitted as late as June 1, 2032, and RBP Sell Offers may be selected for first Delivery Years through 2032/2033. Demand Resources and Distributed Energy Resources may also participate, with their own in- service dates, so the composition of committed MW varies across the term as well as its quantity. 107.

A resource committed for a first Delivery Year of 2032/2033 is therefore included in committed MW from the 2028/2029 Delivery Year, when it is neither in service nor generating any RBP Charge. A resource that fails to appear in 2028/2029 remains in committed MW until rescission takes effect after the 2030/2031 Delivery Year. In the first Delivery Year of the term, the quantity to which the Credit Rate applies may bear no relationship to the capacity actually delivering or to the charges actually billed.

D.  Consequence
108.
An LSE cannot compute the collateral it would be required to post from the tariff. It does not know whether the governing quantity is committed MW, the zonal Final RBP Target, or its share of the Daily Unforced Capacity Obligation; it does not know the extent to which committed MW will exceed or fall short of the Final Target until procurement results are posted; and it cannot determine from any of the three what capacity will actually be in service in the Delivery Year for

PDF page 88

17

which it is posting. The standards set out in Section III require that a participant be able to have “an accurate understanding of the risks, fees, and other material costs” it incurs. PFMI, Principle

23. IX.  THE REDUCTION OF THE REQUIREMENT OVER THE TERM IS UNDEFINED
109.
This section addresses the release of collateral as exposure declines. The standards set out in Section III call for recalculation as exposure moves and release as it declines. For purposes of this section only, I accept PJM’s own measure of the obligation — the gross fifteen-year contractual value — notwithstanding that, as set out above, the amount actually billed to load is the contract- for-differences differential and not the gross stream. Even on the measure PJM selected, and even accepting that the requirement is intended to decline, the filing does not define how or when that decline occurs.

A.  How PJM releases collateral elsewhere
110.
For collateral generally, release is mandatory and participant-initiated. Attachment Q, Section V provides that Collateral which may no longer be required to be maintained under provisions of the Agreements “shall be returned at the request of a Participant, no later than two (2) Business Days following determination by PJM within a commercially reasonable period of time that such Collateral is not required.” The same section permits a Participant, absent an Event of Default, to substitute one approved form of Collateral for another of equal value.

111.
For planned generation in the capacity market, release follows a stated schedule. Attachment Q, Section VI.B.3 provides that the RPM Auction Credit requirement “shall be reduced periodically, after the Market Participant has provided PJM a written request for each reduction, accompanied by documentation sufficient for PJM to verify attainment of required milestones.” The schedule specifies five milestones and the percentage released at each: fifty percent on the effective date of an executed interconnection service agreement, fifteen percent at financial close, five percent at full notice to proceed and commencement of construction, five percent on delivery of main power generating equipment, and twenty-five percent at commencement of interconnection service. Each milestone other than the first and last requires a sworn certification by an independent engineer. 112.

That provision was made effective on March 10, 2026 in Docket No. ER26-980-000, approximately five months before the filing in this proceeding.

B.  How the RBP releases collateral
113.
Section 18.8(b)(i)(A) provides that the Credit Rate “shall equal $1.5 million, as may be reduced, for reasons including a change in the total committed RBP UCAP MW, when total posted RBP Collateral is greater than the total remaining RBP Charges obligations, over time by the Office of the Interconnection to an amount sufficient to cover the total existing RBP Charges obligations.” 114.

The provision is permissive rather than mandatory; it is exercised by the Office of the Interconnection rather than requested by the participant; and it specifies no methodology, no schedule, no evidentiary standard, and no time by which a reduction must occur once the stated condition is met. Neither “over time” nor “an amount sufficient” is defined. No mechanism exists by which an LSE may request a reduction or contest a determination that none is due. The transmittal supplies none of these. It states that PJM “proposes to reduce this RPM Credit Rate value to correspond with decreasing risk over time,” and quotes its witness for the proposition that the provision permits reductions “when changes in the underlying RBP commitment portfolio demonstrate that previously required collateral exceeds the remaining expected payment exposure.” Transmittal at 117–18; Kelly Aff. ¶ 30. Neither identifies a formula, a schedule, a triggering calculation, or a time by which a reduction must follow the condition being met. 115.

PJM has nonetheless represented that the requirement will decline. Its witness states that the requirement “will start at an amount sufficient to mitigate the long-term risk of the RBP

PDF page 89

18

commitment at the beginning of the commitment term and decrease over time as the term winds down,” and that an LSE’s requirement should “generally only go down over time.” PJM RBP Filing at 111, 120; Kelly Aff. ¶¶ 30–31. The tariff does not require it.

C.  Absent reduction, the requirement exceeds the obligation it secures
116.
At the maximum willingness to pay, the gross obligation is $202,575 per MW-year. The Credit Rate of $1.5 million equals 7.4 years of that obligation. Measured against the gross remaining obligation — again, PJM’s own measure — the posted amount is below the remaining obligation for the first eight Delivery Years and above it thereafter, reaching 106% in the 2036/2037 Delivery Year and 740% in the final year of the term.

117.
That is the most favorable measure available to PJM. Measured against the amount actually billed, the crossover occurs earlier and the terminal ratio is higher. The deficiency identified in this section does not depend on which measure is correct.

118.
The estimation of potential future exposure is the method the standards set out in Section III prescribe for a long-dated obligation of this kind, and it is the method PJM applied to this construct. As set out in Section XIII, PJM modeled the procurement as a fixed-for-float swap and estimated potential future exposure across the fifteen-year term — the same measure it applies to FTR portfolios under Attachment Q, and the measure the standards identify. PJM Interconnection, L.L.C., Credit & Securitization Overview, Reliability Backstop Procurement Workshop, at slide 12 (Mar. 4, 2026) (“March 4 Credit Overview”).3 That estimate begins at zero, rises through the early Delivery Years, reaches a maximum within roughly the first third of the term, and declines to zero at expiry. PJM stated the reason: value uncertainty increases with tenor, while quantity exposure decreases as Delivery Years elapse.

119.
That shape is consistent with what is presently observable. The RBP Charge is a differential between the RBP price and the RPM clearing price, and for the first two Delivery Years that differential is measurable rather than forecast. The 2028/2029 Base Residual Auction cleared at $325.00/MW-day, producing a differential of $230.00/MW-day, or $83,950 per MW-year. The 2029/2030 Delivery Year is subject to the price collar, and at the applicable proxy of $333.44/MW-day the differential is $221.56/MW-day, or $80,869 per MW-year. Exposure in the near term is therefore both small and measurable. It is in the later Delivery Years, for which no price is observable, that the range of outcomes widens, and it is in those same years that the quantity remaining to be settled contracts.

120.
A requirement that does not vary cannot track an exposure that does. The Credit Rate stands at its maximum in the first Delivery Year, when the exposure is approximately $83,950 per MW and is measurable rather than estimated — a ratio of approximately eighteen to one. Across the first two Delivery Years, cumulative exposure is approximately $164,800 per MW against a posting of $1.5 million per MW, a ratio of approximately nine to one. Both of those years will be priced before any collateral is posted: the 2029/2030 Base Residual Auction results post on December 22, 2026, and the requirement takes no account of them. The Credit Rate stands at its maximum again in the final Delivery Year, when a single year of settlement remains. PJM itself applied that methodology to the RBP during the stakeholder process. March 4 Credit Overview at slide 12. It was applied to this construct, it produced an exposure profile that varies across the term and amortizes to zero, and section 18.8(b) does not reflect it. The filing does not address the difference.

3 Presentation available at: https://www.pjm.com/-/media/DotCom/committees- groups/workshops/rbpw/2026/20260304/20260304-item-03---credit-and-securitization-overview---pjm- presentation.pdf

PDF page 90

19

D.  Consequence
121.
An LSE cannot determine its posting for any Delivery Year after the first. PJM adopted a mandatory, participant-initiated, milestone-based release mechanism for sellers in the capacity market five months before this filing, and a mandatory two-business-day return obligation for collateral generally. It proposed neither for load in the RBP. Having selected the gross contractual value as the measure of the obligation, PJM did not then specify the mechanism by which the requirement tracks that value as it declines.

X.  THE COST OF CARRYING THE REQUIREMENT IS MATERIAL AND IS NOT
RECOVERED
122.
This section addresses the cost to a Load Serving Entity of holding the required collateral. That cost is not a charge under the tariff and appears in no figure PJM has presented. It is nonetheless a real cost, it is borne by load, and it is a direct consequence of the amount and form of collateral PJM has proposed.

123.
The analysis in this section rests on an assumption that I state expressly. It assumes that the Load Serving Entity is able to fund the required amount — from balance sheet cash, from committed credit capacity, or by incurring debt — and it measures only the cost of doing so. It does not address whether an entity of a given size can obtain funding of the required magnitude at all, and it does not attempt to quantify the effect on an entity’s credit standing of assuming an obligation of this size. Those questions are distinct from the carrying cost and I address them separately in Section XI, where I examine the financial capacity of one investment-grade Load Serving Entity against the allocation PJM’s illustrative figures would assign to it. The figures in this section are therefore a lower bound: they represent the cost to an entity for which funding is available on the terms assumed.

A.  Only two forms of collateral are permitted
124.
RBP Collateral is defined as “either (1) a cash deposit, including any interest thereon, or (2) a letter of credit issued for the benefit of PJM or PJMSettlement.” Surety bonds are excluded, although PJM accepts them elsewhere subject to per-issuer limits, and section 18.8 provides no unsecured credit allowance. An LSE therefore has two options, and the cost of the requirement is the cost of whichever it elects.

B.  Cash
125.
An LSE posting cash must fund the amount. The cost is its own cost of funds, less whatever return the deposit earns. Attachment Q provides that interest on cash accrues to the benefit of the Participant, without specifying a rate. PJM’s audited financial statements for 2025 indicate a credited return of approximately 3.8%, below the effective federal funds rate for the same period, and interest is credited to a member account periodically rather than continuously. 126.

An LSE that posts cash therefore bears the difference between its cost of funds and that credited return. For an investment-grade load-serving entity with a cost of funds in the range of 5% to 6%

— the range addressed at paragraph 130 — the net cost of posting cash is therefore approximately 120 to 220 basis points on the amount posted. A lower-rated entity would bear a higher cost. I do not use the 9.5% after-tax weighted average cost of capital PJM applied in deriving the Credit Rate. As explained at paragraphs 129 through 132, that figure describes the cost of capital for merchant generation investment, not the cost of funds of the load-serving entities required to post the collateral.

C.  Letter of credit
127.
A letter of credit does not require the LSE to fund the amount, but it consumes committed credit capacity and is priced accordingly, as a spread over a reference rate together with a facility fee. The cost is a function of the issuing bank’s pricing and the borrower’s credit, and the filing places

PDF page 91

20

no evidence of either on the record. I therefore state the cost as a range rather than a single figure. At 100 basis points the annual cost is approximately $15,000 per RBP UCAP MW; at 200 basis points, approximately $30,000; and at 300 basis points, approximately $45,000. A letter of credit fee is not the same quantity as a corporate bond yield, and I do not equate them. I use these values as sensitivities rather than as estimates of the price any particular load-serving entity would obtain. 128.

I do not state a single blended cost across the two forms. PJM presently observes a mix of approximately thirty-five percent cash and sixty-five percent letters of credit across its markets, but that mix is observed against a total collateral balance that has never exceeded approximately $13.1 billion across every market and every participant, and against a period in which PJM's own reporting records the extension of unsecured credit alongside it. I do not assume that this historical mix would remain unchanged under a single incremental requirement of approximately $10.2 billion imposed on one class of participants on one date, and I do not rely on it.

D.  The rate PJM selected is not the rate applicable to load
129.
PJM applied a discount rate of 9.5% in deriving the Credit Rate, stating that it “is the capacity market Weighted Average Cost of Capital developed by The Brattle Group [ ] as part of PJM’s 2025 periodic review of the Cost of New Entry of Capacity Resources into the PJM Region.” Kelly Aff. ¶ 28. That figure is an after-tax weighted average cost of capital for merchant generation investment. It describes the cost of capital of the party selling into the procurement, not the party paying for it. The filing offers no rationale for its application to load-serving entities. I express no view on whether 9.5% was an appropriate input to PJM’s own valuation exercise. My point is narrower: that figure is not evidence of the financing cost a Load Serving Entity incurs to post cash or obtain a letter of credit, and the filing offers no other evidence of that cost. 130.

PJM has separately represented that approximately seventy-seven percent of load is served by investment-grade entities. Published market data establish the cost of funds available to corporate borrowers across the rating spectrum, and none of it approaches 9.5% for a population of that description. As of August 12, 2026, the ICE BofA index effective yields were: BBB, the lowest investment-grade tier, 5.58 percent; BB, the highest non-investment-grade tier, 5.98 percent; single-B, 7.25 percent; and CCC and lower, 14.51 percent. PJM’s seventy-seven percent figure is load weighted; the entity-count measure PJM presented separately, addressed at paragraph 138 below, identifies 24 of 105 Load Serving Entities as investment grade. The rating distribution of the remainder is not stated, so I present scenarios rather than a single blended figure. A population that is seventy-seven percent BBB with the remainder at BB implies approximately 5.67 percent; with the remainder at single-B, approximately 5.96 percent; and with the remainder entirely at CCC and lower, approximately 7.63 percent. To reach 9.5 percent, approximately forty-four percent of the population would have to be rated CCC or below if the remainder were BBB, or approximately thirty-one percent if the remainder were single-B. The distribution of those yields is itself instructive: the interval between the lowest investment-grade tier and the highest non- investment-grade tier was forty basis points on that date, and between the highest non-investment- grade tier and single-B, 127 basis points, while the interval between single-B and CCC and lower was 726 basis points. Credit is not priced as a single category above and below the investment- grade boundary, and the rate PJM selected lies materially above the BBB, BB and single-B index yields and below the CCC-and-lower index. Attachment C.

131.
This distinction has a further consequence. A predominantly investment-grade population is one to which Attachment Q’s unsecured credit allowance would ordinarily extend, keyed to creditworthiness and tangible net worth — a mechanism section 18.8 omits entirely.

E.  In aggregate
132.
At the Initial RBP Target, the aggregate annual cost of carrying the requirement ranges from approximately $102 million at 100 basis points to approximately $307 million at 300 basis points. Measured against the approximately $573 million billed to load in the first Delivery Year, that is

PDF page 92

21

between approximately eighteen and fifty-four percent of the amount billed. Each 100 basis points on the $1.5 million Credit Rate is $15,000 per MW-year, or approximately $41.10 per MW-day. On the sensitivities used above the per-unit cost is approximately $41.10 per MW-day at 100 basis points, $61.64 at 150, $82.19 at 200 and $123.29 at 300 — which, measured against the $555 maximum willingness to pay rather than against the amount billed, is between approximately seven and twenty-two percent of that cap, additional to it and recovered nowhere in the proposed tariff. The two ranges differ because the denominators differ: the first states carrying cost as a proportion of what load is billed, the second as a proportion of the ceiling PJM has represented as the limit of what load will pay. The per-MW-day figure does not depend on the size of the procurement: because both the collateral and the MW-days scale with committed UCAP MW, the quantity cancels.

F.  The cost is not recovered and is not disclosed
133.
No provision of the proposed tariff recovers this cost. It does not appear in the maximum willingness to pay, in the RBP Charge, or in any figure PJM has presented to the Commission. A Load Serving Entity must either absorb that cost or recover it through its applicable retail or contractual arrangements, and where an LSE or the large load it serves fails to appear, the requirement is reassigned under section 18.8(b)(i)(B) to the remaining large-load LSEs in the zone and, where none remain, to native load.

134.
As set out above, the Commission established Regional Transmission Organizations to promote efficiency in wholesale electricity markets and to ensure that consumers pay the lowest price possible for reliable service, and has held that credit and collateral requirements must not be “so stringent that they unnecessarily inhibit access to the marketplace.” PJM has presented the $555 maximum willingness to pay as the limit of what load will pay under this procurement. On PJM’s own figures and the forms of collateral its tariff permits, the cost of carrying the required collateral is additional to that limit, and on the sensitivities set out above amounts to approximately $102 million to $307 million each year, or approximately eighteen to fifty-four percent of the amount billed to load in the first Delivery Year. The filing does not identify that cost. The analysis in this affidavit indicates that a requirement sized on standard collateral practice would be substantially smaller for load-serving entities, and larger for RBP Sellers.

XI.  THE REQUIREMENT CREATES SYSTEMIC LIQUIDITY RISK AMONG THE ENTITIES
OBLIGATED TO POST IT
135.
This section addresses whether the requirement can be met — in the forms the tariff permits and on the date it specifies. I approach that question at two levels. The first is aggregate: whether approximately $10.2 billion can be raised at one moment, from one class of participants, in two instruments, drawn from a limited group of issuing institutions. The second is particular: whether the obligation allocated to a given zone is within the financial capacity of the parties serving it. The second question is not incidental to the first. A requirement of this design becomes entity- specific at the point where the required posting approaches or exceeds the obligor’s available liquidity and committed credit capacity, and the tariff performs no test of that at any stage. I use the NOVEC zone as the illustration because PJM’s own allocation and the obligated entity’s own reported financials are both on the public record. The standard is the one set out in Section III: credit requirements must not be so stringent that they unnecessarily inhibit access to the marketplace, and the Commission has identified cascading default as the consequence it guards against.

A.  The requirement falls at one moment, in two instruments
136.
Section 18.8(b)(i)(B)(1) requires each Load Serving Entity with an RBP Obligation to post forty- five days before the start of the Delivery Year. Every obligated LSE across the footprint posts on the same date; nothing in section 18.8 staggers the requirement, phases it, or permits it to be sequenced. RBP Collateral is defined as either a cash deposit or a letter of credit. Surety bonds are

PDF page 93

22

excluded, although PJM accepts them elsewhere and held approximately $606 million of them on July 30, 2026. No unsecured credit allowance is provided and no corporate guaranty is permitted. Approximately $10.2 billion therefore becomes due at a single moment, from a single class of participants, in two instruments.

B.  The obligation is concentrated and is not adjusted for the financial capacity of the obligor 137.

As set out in Attachment B, five zones each carry an obligation exceeding $1 billion — AEPOHIO at approximately $2.29 billion, NVEC at $1.95 billion, COMED at $1.33 billion, PPL at $1.23 billion and DOM at $1.11 billion — together approximately $7.9 billion, or 77 percent of the initial requirement. Each zone’s share is determined by the Electric Distributor’s submission of RBP Obligation MW, scaled as necessary to the fixed zonal target. Nothing in that derivation refers to the financial capacity of the entity required to post, and nothing in section 18.8 tests it at any stage.

138.
PJM has measured the credit quality of the population required to post. In the Credit and Securitization Overview presented on March 4, 2026, PJM identified 105 Load Serving Entities, of which 24 were investment grade and 81 were sub-investment grade. It reported that 46 percent had tangible net worth below $5 million and 30 percent below $1 million, that these figures indicated “limited financial flexibility,” and that investment-grade entities had “provided corporate guarantees.” PJM therefore had a measurement of the financial capacity of the obligated population before the requirement was filed.

139.
For scale, $10.2 billion is equivalent to approximately $97.6 million for each of the 105 Load Serving Entities PJM identified if distributed evenly across that population, in which 48 entities report tangible net worth below $5 million. The actual requirement is not distributed evenly; it is concentrated among the Load Serving Entities that receive RBP obligations. The allocation to the NOVEC zone alone is approximately nineteen percent of the entire initial requirement and approximately twenty times the average share, and it falls on a single distribution cooperative.

C.  The NOVEC zone
140.
The consequence is visible in the largest cooperative-served zone. Northern Virginia Electric Cooperative is the Electric Distributor for that zone/area and the Load Serving Entity for the load within it. Virginia’s retail choice provisions do not reach the customers of a distribution cooperative, so no other Load Serving Entity serves load there. It therefore both makes the RBP Obligation MW assignment under proposed Reliability Assurance Agreement, section 7.2C and bears the resulting RBP Charge and collateral obligation under Tariff, Attachment DD, section 18.8(b).

PDF page 94

23

Table 1. The NOVEC zone obligation against the reported financial position of the cooperative serving it

($ millions except where noted)

Amount
NVEC initial allocation (RBP UCAP MW)
1,302.6
Zonal collateral obligation at $1.5 million per MW
1,954
Total assets, FY2025
1,716
Total liabilities, FY2025
797
Total margins and equities, FY2025
920
Operating revenue, FY2025
1,475
Patronage capital and margins, FY2025
44.7
Obligation as % of total assets
114%
Obligation as % of margins and equities
212%
Obligation as % of annual revenue
132%
Annual cost of the obligation at 100 bps
19.5
Annual cost at 200 bps
39.1
Annual cost at 300 bps
58.6
Sources: Croop Aff. ¶ 46 (initial allocation); Proposed Tariff, Attachment DD, § 18.8(b)(i)(A) (Credit Rate); Northern Virginia Electric Cooperative, Financial and Operating Report Electric Distribution, U.S. Dep’t of Agriculture, Rural Utilities Service, Borrower Designation VA0055, period ended December 2025 (prepared with audited data), Parts A, C, I, O and Q.

141.
The obligation allocated to that single zone is approximately $1.95 billion. The cooperative serving it reports total assets of approximately $1.716 billion and total margins and equities of approximately $919.7 million. The collateral required for the zone exceeds the entire asset base of the entity whose customers give rise to it, and exceeds its equity by a factor of more than two. It exceeds the cooperative’s total long-term debt of approximately $69.2 million by a factor of approximately twenty-eight, and its cash and temporary investments of approximately $243.2 million by a factor of approximately eight. It also exceeds the approximately $34.4 million of cash collateral the cooperative reports as posted to PJM by a factor of approximately fifty-seven. That $34.4 million secures the cooperative’s existing obligations under Attachment Q and continues to be required; the RBP requirement is incremental to it, so total credit support would rise to approximately $1.988 billion.

142.
The cooperative is rated investment grade and stands on its own balance sheet. I do not assume that its present credit standing establishes that approximately $1.95 billion of incremental credit support would be available on the terms that standing reflects, because the terms available to an entity after it assumes an obligation of this size are not necessarily the terms available to it before. Taking the most favorable assumption available — that its credit standing is maintained and that a letter of credit can be obtained at 100 basis points — the annual cost would be approximately $19.5 million. The cooperative reported patronage capital and operating margins of approximately $20.8 million for FY2025, a figure already stated after its existing interest expense of approximately $0.8 million. The carrying cost of the required collateral would therefore have to be absorbed out of that residual margin, and at 100 basis points alone it consumes approximately 94 percent of it. At 150 basis points it would be approximately $29.3 million, or roughly 141 percent of that figure; at 200 basis points, approximately $39.1 million, or roughly 188 percent; and at 300 basis points, approximately $58.6 million, or roughly 281 percent. Each figure is between approximately twenty-five and seventy-five times the cooperative’s entire existing annual interest expense of approximately $0.8 million, and would be incremental to it. Each is an annual cost that could recur while the requirement remains outstanding; section 18.8 provides no mandatory reduction schedule. The significance of that conclusion is not confined to this cooperative. It is

PDF page 95

24

investment grade, and unlike the entities PJM describes as having provided corporate guarantees it is member-owned and stands on its own balance sheet rather than a guarantor’s. If a requirement of this magnitude cannot be borne by an obligor of that credit quality, PJM’s classification of the remaining eighty-one Load Serving Entities as sub-investment grade does not describe a lesser problem.

143.
The customers on whom that cost would ultimately fall cannot select another supplier. Virginia’s large-customer retail choice provision permits individual nonresidential customers whose noncoincident peak demand exceeded five megawatts to purchase electric energy from a licensed competitive supplier, but by its terms it reaches only customers “of a Phase I or Phase II Utility, as those terms are defined in subdivision A 1 of § 56-585.1” — Appalachian Power Company and Virginia Electric and Power Company. Va. Code § 56-577(A)(3). A distribution cooperative is neither. Neither the large loads whose forecast growth produced the NOVEC zone allocation nor the native load that would bear the cost in their absence has any general right to purchase generation from a competitive supplier.

144.
The zone is the illustration and not the limit of the problem. If the largest and most visible allocation in the procurement was not tested against the financial capacity of the entity serving it, the filing identifies no requirement that any allocation be tested at all.

D.  Letter of credit capacity is concentrated
145.
As of July 30, 2026 PJM held approximately $6.87 billion in letters of credit issued by 43 institutions, of which the ten largest accounted for approximately 65 percent of the total and two individually exceeded 10 percent. PJM Interconnection, L.L.C., Credit Risk Metrics, Risk Management Committee, at slide 4 (Aug. 18, 2026).4 Satisfying the RBP requirement predominantly by letter of credit would more than double the letter of credit exposure PJM holds, drawn from substantially the same group of institutions.

146.
PJM monitors and reports monthly on the letters of credit posted by issuing banks. That reporting includes the concentration by volume among the largest issuers. It is provided to keep Members informed of how PJM is managing the credit risk it holds through third parties. PJM has broad discretion to decline a letter of credit from a bank on concentration grounds. The membership prudently supported that discretion in the comprehensive credit policy overhaul PJM filed in 2020, because it allows PJM to manage not only a Member’s direct credit risk but also the manner in which the Member chooses to mitigate the risk it presents to the broader membership. No analysis appears on the record addressing whether the RBP requirement can be satisfied without creating concentration risk among the banks that would issue the letters of credit. PJM measures that concentration every month because it bears directly on the quality of the collateral PJM holds. The filed requirement would roughly double the letter of credit portfolio, drawn from substantially the same institutions, and the filing does not measure it at all.

E.  The failure mode is correlated, and PJM has handled the same structure differently 147.

The exposures created by the requirement are correlated rather than independent. All obligated Load Serving Entities post on the same date, in the same two instruments, drawn from the same limited group of issuing institutions, against an obligation whose quantity a Load Serving Entity has only limited means to affect. The assignment is made by the Electric Distributor under proposed Reliability Assurance Agreement, section 7.2C, and may be reassigned by it; and the procurement target itself may be reduced before the procurement closes on evidence of the kind PJM identified during the stakeholder process. Neither is a means by which a Load Serving Entity holding an assigned obligation can reduce that obligation once the commitment binds, which is the period during which the collateral is required. Under section 18.9(a), a default is reallocated pro

4 Presentation available at: https://www.pjm.com/-/media/DotCom/committees- groups/committees/rmc/2026/20260818/20260818-informational-only---credit-metrics---august-2026.pdf

PDF page 96

25

rata to the remaining LSEs — entities that by construction have just funded or renewed their own postings, from the same sources, on the same date. The reallocation therefore arrives at the point in the annual cycle when the remaining LSEs have committed liquidity or bank capacity to their own annual postings.

148.
PJM has faced a structurally comparable situation. Following Winter Storm Elliott, PJM assessed approximately $1.8 billion in non-performance charges. Most of the affected units had already been liquidated into high real-time energy prices during the event, creating balance sheet and liquidity stress. The non-performance charges, and the collateral required to secure them, therefore fell on participants whose liquidity had already been depleted. The structure is similar to that of the RBP, except that under the RBP it is the demand side that faces the collateral call. See PJM Interconnection, L.L.C., 185 FERC ¶ 61,204 (2023) (order approving offer of settlement resolving fifteen complaints concerning Winter Storm Elliott Non-Performance Charges) (“Elliott Settlement Order”).

149.
PJM did not demand the full amount at a single moment. It sought authority to extend the period for payment of non-performance charges from three months to nine months to reduce the risk of defaults, and the tools available under Attachment Q permitted it to evaluate participants individually and to exercise judgment about timing rather than treating every participant identically on a single date. The charges were ultimately resolved by settlement at approximately $1.2 billion against approximately $1.8 billion assessed. See PJM Interconnection, L.L.C., 183 FERC ¶ 61,001 (2023) (permitting Members to elect an extended nine-month payment term for Non-Performance Charges); PJM Interconnection, L.L.C., 185 FERC ¶ 61,204 (2023) (approving a uniform 31.7 percent reduction in Non-Performance Charges across all market participants) (“Elliott Settlement Order”). Defaults did occur; at least one resource owner sought bankruptcy protection after receiving charges its filings described as a multiple of the affected plants’ annual revenue. What did not occur was a collateral call that itself became a source of stress. 150.

Section 18.8 contains no equivalent. It states a date and an amount. It provides no phase-in, no schedule, no discretion to sequence, and no mechanism through which a Load Serving Entity unable to satisfy the requirement on the stated date may propose an alternative. The consequence of failing to satisfy the requirement on the stated date is the default machinery in the governing documents. I note the absence of sequencing discretion because it describes what the filed provision does, not because supplying that discretion would answer the questions addressed in this affidavit. A schedule for posting an amount that is not measured against the exposure it secures would change when the requirement falls due; it would not change its magnitude, its basis, or the population on which it lands.

F.  Conclusion
151.
In my opinion the filing does not establish that the proposed requirement can be met by the population required to post it. It does not analyze the aggregate letter of credit capacity available to the obligated population, the effect of a simultaneous call on entities that cannot reduce their exposure by managing their positions, or the consequences in any zone where the obligation exceeds the financial capacity of the parties serving it. The NOVEC zone shows that the question is not hypothetical: an obligation of approximately $1.95 billion is allocated to a footprint served by a cooperative reporting approximately $1.716 billion in total assets, whose customers have no general right to select an alternative Load Serving Entity that would bear the cost and collateral exposure in its place.

152.
Where an obligation of that kind cannot be met, the proposed provisions do not extinguish it. Section 18.9(a) reallocates the defaulted charge pro rata to the remaining Load Serving Entities, and Operating Agreement section 15.2.2 extends what remains to Members with no allocation at all. The same features that make the requirement difficult to satisfy — its concentration, its single date, and the absence of any adjustment for the financial capacity of the obligor — also determine where the loss travels when it is not satisfied. That is the subject of the following section.

PDF page 97

26

XII.  THE SOCIALIZATION OF A DEFAULT INCREASES THE OBLIGATION OF THE
REMAINING LSEs AND REACHES MEMBERS WITH NO ALLOCATION
153.
This section addresses where a loss goes. The Commission has identified the prevention of socialization as the function collateral performs: where collateral posted by a defaulting party is insufficient, the remaining exposure and costs are socialized across the membership. The standards set out in Section III order those two things — the defaulting participant’s own margin absorbs the loss first, and mutualization is what remains after it is exhausted. Section 18.9(a) does not expressly establish that sequence. The proposed provisions also contain two distinct reallocation mechanisms, operating on different triggers and different scopes, and the tariff does not distinguish them.

A.  Section 18.9(a) does not expressly require collateral to be applied before reallocation 154.

Section 18.9(a) provides that a defaulted RBP Charge “will be allocated to all remaining Load Serving Entities responsible for paying RBP Charges based on their pro-rata share,” and that such amounts “may be offset by the RBP Collateral posted by the defaulting Load Serving Entity.” Reallocation to non-defaulting parties is stated as mandatory. Application of the defaulting party’s own collateral is stated as permissive.

155.
That differs from the sequence the standards describe and from the sequence PJM applies elsewhere. Under Attachment Q, collateral posted against an obligation is applied to that obligation upon default, and mutualization under Operating Agreement, section 15.2.2 is the residual. Section 18.8 collects $1.5 million per MW from load, and section 18.9(a) does not commit PJM to apply it to the loss against which it was collected.

156.
I do not suggest that PJM would decline to apply the collateral. The point is that the tariff does not require it. The collateral posting is mandatory, while section 18.9(a) states its application to a defaulted RBP Charge in permissive terms. If PJM intends that the collateral be applied first, the filed text does not state it.

B.  Two reallocation mechanisms of different scope
157.
The proposed provisions reallocate an obligation in two circumstances, and the scope differs. Where a large load does not materialize or ceases operation, the obligation is reassigned within the zone. Where an allocated Load Serving Entity fails to pay, section 18.9(a) reallocates the defaulted charge to “all remaining Load Serving Entities responsible for paying RBP Charges,” language that on its face reaches the entire footprint rather than the zone. The tariff does not state that the two operate on different scopes, and nothing in section 18.9 confines the payment-default reallocation to the zone in which the default occurs.

C.  Where the load does not appear, the obligation reaches native load
158.
PJM described the treatment of a load that does not appear during the stakeholder process. In materials presented to the Reliability Backstop Critical Issue Fast Path on June 10–11, 2026, PJM stated that where a load does not materialize or shuts down before the end of the RBP term, the corresponding large load obligation must be reassigned, and identified three options: the Electric Distributor may assign the obligation to another Load Serving Entity; if it does not, and other Load Serving Entities in the zone/area hold assignments, the obligation is allocated pro rata among those remaining entities by zonal share; and if the Electric Distributor makes no assignments in the zone/area, “the costs will be reallocated across all load in the zone on a pro rata basis using the Obligation Peak Load Contribution MW (the same methodology used to allocate RPM costs).” Design Presentation,  at slide 30. PJM stated in the same materials that if states have not established frameworks to allocate costs to new data center loads, “it is unclear to which customers those costs would be assigned,” and that as a backstop PJM will allocate to all load in the zone, “including non-large loads,” using existing Peak Load Contribution assignments. Id. at slide 27. PJM’s stakeholder materials refer to the quantity assigned to a Load Serving Entity as the

PDF page 98

27

Large Load Contribution or “LLC” Obligation MW; the PJM Board’s July 27, 2026 decisional letter refers to the same quantity as the Reliability Backstop Obligation or “RBO,” described there as a new defined term exclusively for the RBP; and the proposed tariff language refers to it as the RBP Obligation MW submitted for a Load Serving Entity by the Electric Distributor. The quantity is the same in each. I use the tariff term.

159.
The filed tariff assigns the allocation function to the Electric Distributor and specifies the outcome where it is not performed. Section 18.8(b)(i)(B)(1) provides that the RBP Obligation MW values uploaded by the Electric Distributor are “scaled, as necessary, in the event that the RBP Obligation MW values uploaded by the Electric Distributor do not sum to the fixed, Final RBP Target MW for the zone/area.” Because the zonal quantity is fixed, an obligation not reported for one Load Serving Entity is not extinguished; it is scaled onto the others. Section 18.8(b)(i)(B)(2) addresses a Load Serving Entity for which the Electric Distributor reports no obligation at all, providing that such an entity “may be required to post” collateral determined by its “pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8” — that is, on Peak Load Contribution. Section 18.3(a) fixes the zonal allocation for the full fifteen-year term. 160.

The structure is a two-step one: the Electric Distributor assigns, and where it does not, the cost falls on all load in the zone/area on Peak Load Contribution. PJM has described the assignment step as similar to the existing Peak Load Contribution and Network Service Peak Load processes, and Electric Distributors perform an analogous function today. The difference lies in what is assigned. Those processes allocate charges that follow measured load: if the load falls, the allocated quantity falls with it. The RBP Obligation MW allocates a fixed quantity for fifteen years, set on a forecast, which does not decline if the forecast load does not appear. The tariff states no standard governing how the Electric Distributor is to make the assignment, and no mechanism by which a Load Serving Entity may determine in advance whether it will hold one. What the tariff does specify is where the quantity comes to rest if the assignment is not made: on all load in the zone/area, including load that is not large load. In the NVEC zone/area the two steps reach the same entity. Northern Virginia Electric Cooperative performs the assignment as Electric Distributor and is the Load Serving Entity on which the cost falls if it does not, and there is no other Load Serving Entity in that zone/area to which the obligation could be assigned. 161.

The quantities that fix each zone’s share were not prepared for this purpose. The Load Adjustments underlying the RBP Target derive from large load additions reported through PJM’s load forecasting process and taken from Table B-9b of the 2026 Load Forecast, as the difference between forecast summer 2028 and summer 2026 peak load. Those submissions were made to inform a planning forecast. They carried no cost consequence for the submitting entity, and were not accompanied by verification procedures directed to their use in allocating a fifteen-year payment and collateral obligation. Section 18.3(a) then fixes the resulting allocation for the full fifteen-year term on that single vintage.

D.  The NOVEC zone
162.
The consequence is measurable, and its distribution across customer classes is not uniform. As set out in the preceding section, the NOVEC zone carries an initial allocation of 1,302.6 UCAP MW and a collateral obligation of approximately $1.95 billion. Northern Virginia Electric Cooperative serves that zone and reports energy sales of approximately 14.649 billion kilowatt-hours for the year ended December 31, 2025, against a coincident peak demand of approximately 2,360 MW — a system load factor of approximately 71 percent. That system figure conceals two classes with materially different characteristics. The cooperative reports that data centers represent more than 65 percent of its energy sales. I use 65 percent in the calculations that follow, which is therefore a lower bound. Data center load typically operates at a load factor of 85 to 95 percent; residential and small commercial load operates at approximately 40 to 55 percent, and load factors for the residential class are observable from default service and basic generation service supply auctions. The conclusion does not depend on the precise figures. What the difference in load factor

PDF page 99

28

establishes is that a charge collected on peak load contribution rather than on energy falls on the two classes in materially different proportion to the energy each consumes, and that the direction of the disparity is against the class that consumes less. Selecting the low end of the data center range and the high end of the residential range understates that disparity, and I do so below. 163.

That difference matters because RBP Charges are allocated on a demand basis rather than an energy basis. Where obligations are not assigned to the Large Loads that produced them, the quantity falls to Peak Load Contribution — the Obligation Peak Load Contribution MW that PJM states is “the same methodology used to allocate RPM costs.” The two classes therefore bear the obligation in proportion to their contribution to peak, not to their consumption of energy. On the load factors stated above, non-data-center load accounts for approximately 35 percent of energy but approximately 45 to 53 percent of peak load contribution.

164.
The effect is to shift the burden toward the lower-load-factor class. At the 2028/2029 Base Residual Auction clearing price of $325.00/MW-day and an RBP price of $555, the contract-for- differences differential is $230/MW-day, or $83,950 per MW-year, and the first-year charge allocated to the zone is approximately $109 million. Allocated on peak load contribution, that charge falls at approximately $11.63 to $13.62 per megawatt-hour on non-data-center load, against approximately $6.45 to $7.53 per megawatt-hour on the data center load whose forecast growth produced the allocation. The uniform energy-basis figure, approximately $8.96 per megawatt- hour, understates the former and overstates the latter. The conclusion does not depend on the particular load factors selected; it holds across the full range set out in Attachment D. 165.

The cost of carrying the collateral is allocated the same way and compounds the same disparity. At 150 basis points — a midpoint of the sensitivity range set out in Section X, stated here for illustration — the annual carrying cost for the zone is approximately $29 million, of which approximately $14 million falls on non-data-center load — approximately $3.38 per megawatt- hour, against approximately $1.88 per megawatt-hour for data centers. Taken together, the charge and the cost of the collateral securing it fall at approximately $16 per megawatt-hour, or 1.6 cents per kilowatt-hour, on native load, against approximately $8.88 per megawatt-hour on data centers. The cooperative reports a monthly average residential cost of $113.74 for 1,000 kilowatt-hours; the incremental burden on that bill is approximately fourteen percent. These figures are borne by the customers of a distribution cooperative reporting total assets of approximately $1.716 billion and patronage capital and margins of approximately $44.7 million, who have no general right to purchase generation from a competitive supplier. I do not suggest that outcome is the expected one. I state it because the tariff makes it available, because it arises under the allocation methodology PJM itself specifies, and because PJM has acknowledged that it does not know to which customers the costs would be assigned. Passing the cost through does not resolve the matter. Whether the cooperative assigns it to the Large Loads it serves or recovers it from native load, the allocation from PJM is unchanged. Those loads did not face a charge of this kind before the RBP was proposed, and a cost of this magnitude may bear on whether a given development proceeds. If it does not proceed, the allocation does not follow it: the RBP Obligation MW for the zone/area is fixed under section 18.3(a) for the full fifteen-year term on the basis of the load forecast used to set it, and it is not revised if the forecast load does not materialize. The cooperative would remain responsible for an allocation calculated on load that did not arrive. The cooperative was in any event already before its state commission on the question of assigning large-load costs: on July 17, 2026 it announced a filing to update the rate classes applicable to large-load customers so that costs attributable to serving those customers are assigned to them rather than shifted to smaller users, with a further step to follow involving updated load forecasts and a power supply solicitation.

E.  The NOVEC zone does not satisfy the conditions for the opt-out
166.
PJM identified this problem during the stakeholder process and included an opt-out addressing that concern. Explaining the opt-out at section 18.1(d), PJM states that cooperatives raised the concern

PDF page 100

29

that an Electric Distributor in a retail choice state, not regulated by the state and not otherwise serving as the LSE for generation to the load, “would be forced to have its customers absorb the costs of an ‘overbuy’ if a particular large load included in the forecast were to fail to materialize,” and that unlike a state-regulated investor-owned utility, cooperatives and municipal utilities “are not governed by a state regulatory authority that would be responsible for addressing the potential reallocation of RBP costs.” PJM describes this as a limited regulatory gap faced by cooperatives and municipal utilities “whose rates are not regulated by the states.”

167.
The opt-out is available only on that condition. The retail rates of Virginia distribution cooperatives are regulated by the Virginia State Corporation Commission. A distribution cooperative is a utility consumer services cooperative under Chapter 9.1 of Title 56 of the Code of Virginia, and its regulated utility services are subject to the jurisdiction of the Commission in the same manner and to the same extent as those provided by other persons under the laws of the Commonwealth. Va. Code §§ 56-231.33, 56-231.34; see also Va. Code § 56-585.3; 20 Va. Admin. Code § 5-200-21 (rules governing streamlined and general rate proceedings for electric cooperatives subject to the Commission’s rate jurisdiction). Each of the cooperative’s filed rate schedules provides that service is available “subject to the Terms and Conditions of the Cooperative filed with the State Corporation Commission of Virginia.” Northern Virginia Electric Cooperative, Schedule HV-2, Large Power Dedicated Facilities Contract Service, Regulated Rates. The cooperative states on the same basis that the Commission “approves rates, fees and all terms and conditions of service of the Cooperative.” The cooperative serving the NOVEC zone is therefore ineligible for the opt-out, notwithstanding that it faces precisely the exposure PJM described: an obligation fixed for fifteen years on a forecast of large load additions, which under section 18.8(b)(i)(B)(2) reaches its native load if that load does not materialize. The zone carrying the second largest allocation in the procurement, and the only zone in which the obligation exceeds the reported assets of the entity serving it, cannot use the remedy PJM built for the problem PJM identified.

F.  The residual reaches Members with no allocation
168.
Operating Agreement, section 15.2.2 provides that where a Member defaults on its payment obligations, the other PJM Members may be required to pay a share of the defaulted amounts. That provision is not limited to Members allocated RBP Charges.

169.
East Kentucky Power Cooperative is in that position. PJM’s illustrative allocation shows EKPC with a Load Adjustment of zero and no allocation of the RBP Target. On those figures EKPC would be allocated no RBP Charges and would post no RBP Collateral. It nonetheless remains a PJM Member and remains within the residual tier. The assessment under section 15.2.2 is made to EKPC as the PJM Member.

170.
A Member in that position receives no capacity from the procurement, pays no RBP Charge, and posts no collateral, yet bears exposure to a default under it. No collateral is posted against that exposure by any party, because the requirement in section 18.8 reaches only Load Serving Entities with an allocated obligation. I do not suggest that a Member in EKPC’s position should be required to post collateral. The observation is that the requirement PJM has designed does not reach the exposure such a Member bears.

G.  The seller side runs the same direction
171.
Section 18.9(b) provides that where an RBP Resource defaults on payment of shortfall charges, “the corresponding credits will not be allocated to the Load Serving Entities that would otherwise receive the RBP shortfall credits.” There is no reallocation among sellers and no provision applying the seller’s collateral to make load whole.

172.
The seller’s assessed liability is limited to the three-year shortfall period, while the economic consequence to load can continue after the commitment is rescinded. Under section 18.6(e), a commitment that fails to come online for three Delivery Years is rescinded for the remainder of

PDF page 101

30

the term; the resource is thereafter neither compensated nor charged, and its collateral is released. Load receives nothing for the remaining twelve years of a fifteen-year commitment. 173.

The two provisions produce the same result from opposite facts. A load default is recovered from other load. A seller default is also borne by load. Under the two default paths identified in the filing, any unrecovered loss ultimately reaches load or the residual PJM membership.

H.  Conclusion
174.
In my opinion the proposed provisions do not prevent the socialization of a default. They establish the paths by which residual losses are reallocated. The collateral posting is mandatory, while section 18.9(a) states its application to a defaulted RBP Charge in permissive terms. Where forecast Large Load does not materialize, the obligation remains within the zone and, under the final allocation step PJM describes, may ultimately be allocated to native load by Peak Load Contribution. An LSE payment default is addressed separately under section 18.9(a), which reallocates the defaulted charge among all remaining Load Serving Entities responsible for paying RBP Charges. Because RBP Charges are assessed against every zone/area holding a share of the RBP Target, that reallocation reaches the footprint and is not confined to the zone in which the default occurs. The remedy PJM designed for the cooperative overbuy problem is conditioned so as to exclude cooperatives whose rates are state-regulated. And the residual extends to Members who take nothing from the procurement and post nothing against it.

XIII.  THE FILED CREDIT CONSTRUCTS WERE NOT EXAMINED IN THEIR FINAL FORM
175.
This section addresses the process by which the credit provisions developed. I raise it because credit and collateral were material design issues throughout the stakeholder process, because materially different approaches were proposed by PJM and other stakeholders, and because the methodologies ultimately filed were not examined in their final form. The Commission has held that credit requirements emerging from an RTO stakeholder process must still be reviewed for whether they are unduly burdensome. Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at PP 20-21 (2009). The relevant question for my analysis is what opportunity existed for stakeholders to examine the magnitude, mechanics and liquidity consequences of the credit requirements ultimately proposed.

A.  PJM proposed using its existing credit framework for LSEs
176.
PJM addressed LSE credit requirements in its stakeholder materials on at least two occasions. In the Design Presentation, PJM stated that upon notification by the Load Serving Entity of known changes to its load, “the credit, and collateral requirements for LSEs are expected to be managed by the current credit processes,” and that those processes “include, but are not limited to, credit evaluation, peak market activity (PMA) recalculation and use of other mitigation tools, such as posting of credit support and/or unreasonable credit risk collateral calls (UCRs).” The same language appears in PJM’s Stage 4 proposal paper of June 30, 2026.

177.
That was a description of PJM’s existing credit framework applied to a new charge. It contained no fixed rate per megawatt, no aggregate requirement, no single posting date, and no stated departure from Peak Market Activity. As discussed above, Peak Market Activity based on historical billing would not by itself have captured the prospective exposure created by a new fifteen-year RBP obligation, and that limitation was raised during the stakeholder process. But the approach PJM described retained the principal elements of its existing credit framework: credit evaluation, recalculation of expected exposure through PMA, and the use of additional mitigation tools where the calculated exposure was not adequately secured. Nothing in the June 10–11 or June 30 materials identified a Credit Rate of $1.5 million per RBP UCAP MW or an aggregate LSE collateral requirement of approximately $10.2 billion.

PDF page 102

31

B.  Other stakeholder proposals addressed buyer credit differently
178.
Credit and collateral were not absent from the stakeholder debate. Other proposals addressed the issue directly and proposed materially different approaches. The Joint EDC and Data Center Coalition proposal, which ultimately received the greatest sector-weighted support, tied procurement to the ability of the subscribing LSE or Large Load to satisfy the applicable credit requirement at the time PJM committed supply resources. An LSE unable to satisfy that requirement could not subscribe MW into the procurement. The Joint Consumer Advocates likewise identified credit and collateral as an issue in the procurement.

179.
The Coalition described the objective of its credit methodology in exposure terms. It proposed a requirement intended to ensure that “any emerging buyer default exposure is recognized early, funded continuously, and contained entirely within the LSE buyer” that subscribed to or received the RBP obligation. It also contemplated that the credit requirement would attach when the RBP commitment was made and “adjust[] over time.” That approach therefore contemplated both measurement of emerging exposure and adjustment of the requirement as that exposure changed. 180.

The Joint Consumer Advocates likewise identified demand-side credit and collateral as a necessary element of the RBP design, but proposed a different structure. Their June 30 executive summary stated that demand-side credit and collateral “should be established before procurement,” rather than assigned later. Their final recommendations to the Board again called for PJM to “[e]stablish demand-side credit and collateral prior to procurement.” They recorded PJM staff’s position on that issue as “collateral timing/assignment is later,” and identified as a source of stranded cost risk the absence of any opportunity to require Large Loads to commit to pay their RBP obligations and to post collateral with the Electric Distributor. Joint Consumer Advocates, Stage 4 of PJM CIFP Stakeholder Process Regarding Large Load Additions and Reliability Backstop Procurement and Connect & Manage, Executive Summary to the PJM Board of Managers (June 30, 2026), at 2, 4, 5.

181.
The significance of these proposals for my analysis is not that the Commission should have preferred one stakeholder proposal over another. It is that the stakeholder process had identified buyer credit as a material RBP design issue and produced materially different approaches to addressing it. PJM proposed use of its existing credit framework, including credit evaluation and recalculation of exposure. The Coalition proposed that emerging buyer-default exposure be recognized early, funded continuously and contained within the subscribing buyer, with the requirement adjusting over time. The Joint Consumer Advocates proposed establishing demand- side collateral before procurement. None of those approaches proposed the fixed $1.5 million per MW requirement ultimately filed.

C.  The seller requirement was materially revised in the final stakeholder proposal 182.

Seller credit was also changing late in the process. In the June 10–11 Design Presentation, PJM proposed seller credit equal to Max($20, 0.2 × bid price) × MW UCAP committed × 365 × a year multiplier, defined as the ratio of the net present value of the multi-year penalty cash flow to the nominal value of one year. PJM stated that a fifteen-year tenor at a 9.5% discount rate “equates to ~seven years.” Its worked example applied a multiplier of 7.31, producing approximately $21.4 million for a 100 MW commitment at $400/MW-day, or approximately $214,000 per MW. 183.

PJM materially revised that construct in its final June 30 proposal. The Stage 4 proposal paper states the seller requirement as “Max ($20, 0.2 x bid/clearing price) x MW UCAP committed x 365 x 3 (years),” and explains that PJM was “proposing to require credit support equivalent to three years of the RBP shortfall charges.” Compared on a common basis, at the maximum willingness to pay of $555/MW-day the June 10–11 formulation with its 7.31 multiplier produces approximately $296,166 per MW, while the June 30 formulation produces $121,545 per MW — a reduction of approximately 59 percent. Section 18.8(a) as filed adopts the June 30 formulation without further change.

PDF page 103

32

184.
The timing is relevant. The material revision to seller credit was disclosed in PJM’s final June 30 stakeholder proposal, after which no further stakeholder meetings were held. Stakeholders therefore received the revised seller methodology before the filing, but had no subsequent stakeholder meeting at which to examine it. The RBP proposal was filed on July 31, 2026, thirty- one days after the final stakeholder proposal.

D.  The LSE requirement changed after the final stakeholder proposal
185.
The treatment of LSE credit followed a different sequence. PJM’s final June 30 proposal continued to state that LSE credit and collateral requirements were expected to be managed through existing credit processes, including credit evaluation, Peak Market Activity recalculation and other mitigation tools. The fixed $1.5 million per RBP UCAP MW requirement does not appear in those materials.

186.
The July 31 filing replaced that approach. Section 18.8(b) establishes a fixed Credit Rate of $1.5 million per RBP UCAP MW, which PJM derived from approximately fifty percent of the gross fifteen-year contractual value. At the Initial RBP Target, that produces an aggregate LSE collateral requirement of approximately $10.2 billion. The methodology therefore first appeared after the final stakeholder proposal and in the filing itself.

187.
The change was not an increase in the amount of collateral produced by the methodology presented to stakeholders. The filed construct instead departed from the criteria PJM had identified for determining LSE credit under its existing process. The $1.5 million per MW Credit Rate does not depend on the credit quality of the LSE, a recalculation of Peak Market Activity or expected exposure, or the use of other mitigation tools to address an identified deficiency. It applies the same fixed rate per megawatt before unsecured credit to every LSE subject to section 18.8(b), regardless of those considerations.

188.
Both credit constructs were therefore moving late in the process, as were other elements of the proposal. The Joint Consumer Advocates recorded that PJM staff had revised substantial elements of the Reliability Backstop Procurement and Connect and Manage proposals at least three times in the month preceding June 30, 2026, including on the evening before the original deadline for stakeholders to submit their own Stage 4 proposals. Id. at 2 n.6. The material change to seller credit was disclosed in PJM’s final June 30 proposal, but there was no subsequent stakeholder meeting at which it could be examined. The material change to LSE credit occurred after that final proposal and first appeared in the July 31 filing. At the same time, the stakeholder process had produced other approaches to buyer credit that were substantively different from both PJM’s June 30 approach and the methodology ultimately filed. Neither filed construct therefore received stakeholder examination in its final form, and the specific $1.5 million per MW LSE methodology was not presented for stakeholder examination before the filing.

E.  The filed methodologies departed from the exposure-based criteria considered during the process 189.

The sequence is relevant to the substance of the methodologies ultimately filed. The approaches presented during the stakeholder process differed in important respects, but collectively they reflected several criteria ordinarily associated with managing credit exposure, and PJM’s own analysis presented to the process applied those criteria directly. PJM’s June 30 proposal retained credit evaluation, PMA recalculation and additional mitigation tools. The Coalition proposal expressly called for emerging buyer-default exposure to be recognized early, funded continuously and contained within the responsible buyer, with the requirement adjusting over time. The Joint Consumer Advocates emphasized establishing the credit and collateral requirement before the procurement occurred.

190.
PJM also presented an exposure-based analysis of the construct to the stakeholder process. In the March 4 Credit Overview, PJM stated that the Reliability Back-Stop Auction “introduces 15-year contractual durations, which current PJM credit rules were not designed to mitigate,” and that Attachment Q “is primarily built for short-term settlement cycle and one-year capacity

PDF page 104

33

obligations.” It identified the resulting vulnerability as a “liquidity squeeze,” comprising a “sizable collateral requirement,” constraints on liquidity, and “cost of capital.” It also stated that “[c]urrent tariff does not calculate liquidated damages.”

191.
That presentation modeled the procurement as a fixed-for-float swap and estimated potential future exposure across the fifteen-year term. PJM defined potential future exposure as the maximum exposure of economic value to a counterparty at a future point in time, at a stated confidence level such as 95 percent. PJM did not present a flat profile. The estimate begins at zero, rises through the early Delivery Years, reaches a maximum within roughly the first third of the term, and declines to zero at expiry. PJM stated the reason: “The value uncertainty goes higher deeper into the future, while quantity exposure decreases as time goes by. This makes PFE peaks at 1/3 of life.” PJM’s estimate is denominated in millions of dollars per MW, and at no point across the fifteen-year term does the exposure PJM depicted reach $1.2 million per MW. By contrast, section 18.8 establishes a fixed $1.5 million per MW Credit Rate rather than a requirement that follows that modeled exposure profile. The filed requirement therefore exceeds the maximum exposure PJM itself modeled at every point in the term, and exceeds it by a wide margin in the opening and closing years, when PJM’s own estimate approaches zero. PJM had before the stakeholder process an estimate of buyer-side exposure that varies across the term and amortizes to zero.

192.
The same presentation set out the credit profile of the population that would be required to post. As described at ¶ 138 above, PJM identified 105 Load Serving Entities, of which 24 were investment grade and 81 sub-investment grade, with 46 percent below $5 million in tangible net worth and 30 percent below $1 million, and noted that investment-grade LSEs had “provided corporate guarantees.” PJM therefore also had before the process a measurement of the credit quality of the entities on which the requirement would fall, and of the mitigation already in place. 193.

Section 18.8(b) as filed adopts none of those criteria for determining the initial LSE requirement. It does not measure the LSE’s expected RBP settlement exposure; it does not establish the initial requirement through Peak Market Activity or another exposure calculation; it does not vary the Credit Rate according to participant credit quality; and it does not establish a methodology for determining when additional or alternative mitigation is required. Instead, the initial requirement is determined by multiplying a fixed $1.5 million Credit Rate by the applicable quantity of RBP UCAP MW. Nor does the filed construct reflect the exposure profile PJM itself modeled, or the credit quality PJM itself measured. Potential future exposure as PJM estimated it rises and then declines to zero across the term; the Credit Rate is a single figure that does not decline at all. And the same $1.5 million per MW Credit Rate applies to each Load Serving Entity that receives an RBP obligation, without regard to the credit classification PJM assigned to that entity.

F.  PJM considered adjustment mechanisms for sellers that were not included for load 194.

The June Design Presentation also demonstrates that PJM considered mechanisms for adjusting seller collateral over the term. It presented a year-by-year seller credit requirement schedule, including a column labeled “RBP Credit Req. Desired (NPV),” defined as “collateral required if the NPV is recalculated through out the contract term,” declining from approximately $21.4 million to $819,568 for the 100 MW commitment used in the example — approximately $214,000 to $8,196 per MW. PJM stated that the step down in collateral would be “contingent on credit valuation per Att. Q,” and that the credit requirement “may be reduced to reflect the remaining years while taking into account the credit quality of the Market Participant.” 195.

PJM therefore considered for sellers both periodic recalculation of the remaining obligation and adjustment for participant credit quality. Neither mechanism appears in the filed LSE construct. Section 18.8(b) provides no schedule for recalculation, no defined reduction methodology, and no unsecured credit allowance keyed to creditworthiness. As discussed in Section IX, it provides only that the Credit Rate “may be reduced” by the Office of the Interconnection over time.

PDF page 105

34

G.  PJM states that the filed proposal was not stakeholder-endorsed
196.
PJM describes the status of the proposal expressly. Distinguishing NRG Power Marketing, LLC v. FERC in its transmittal, PJM states that “the proposal submitted in this filing was authorized by the PJM Board and was not the result of a stakeholder-endorsed proposal.”

197.
The absence of stakeholder endorsement does not itself determine whether a credit requirement is reasonable. The Commission has rejected a credit provision that had been developed through an RTO stakeholder process and approved by its Board, holding that it “cannot accept any proposal from the stakeholder process that is unduly burdensome or unduly discriminatory.” Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at PP 20-21 (2009) (quoting Sw. Power Pool, Inc., 114 FERC ¶ 61,222, at P 19 (2006)). The Commission rejected the provision as “not consistent with or superior to the pro forma OATT” and as potentially “so stringent as to unnecessarily inhibit access to the marketplace,” notwithstanding that the revisions were the product of the SPP stakeholder process and had been approved by the SPP Board of Directors. Id. The relevance of the process here is narrower. Stakeholder review provides an opportunity for the entities subject to a credit requirement to identify its operational, financing and liquidity consequences and to test the methodology used to measure the exposure before it is implemented.

H.  Conclusion
198.
In my opinion, neither of the credit constructs ultimately filed received stakeholder examination in its final form. Seller credit was materially revised in PJM’s final June 30 proposal, after which no further stakeholder meetings were held. The fixed $1.5 million per MW LSE requirement was not included in that final proposal and first appeared in the July 31 filing.

199.
This is significant because the stakeholder process had not ignored credit risk. PJM and other stakeholders had proposed different means of addressing it. Those approaches included credit evaluation, recalculation or continuing measurement of exposure, adjustment of the requirement over time, additional mitigation when needed, and establishment of buyer credit before procurement. The filed LSE methodology did not select among those approaches. It instead established a fixed Credit Rate derived from the gross contractual value and omitted the exposure- based criteria that had been identified during the stakeholder process.

200.
For a credit construct of this magnitude, those differences are material. The stakeholder process provided no opportunity to examine the $1.5 million per MW methodology against the matters addressed in this affidavit: its relationship to measured exposure; the quantity to which the Credit Rate applies; the availability and cost of permitted collateral; the mechanism by which collateral is reduced as exposure declines; the financial capacity of the entities required to post it; the consequences of a simultaneous collateral call; and the allocation of loss following default. The filed $1.5 million per MW methodology therefore was not subjected to stakeholder examination against those considerations before the filing.

XIV.  CONCLUSION
201.
I believe the matters set out above point to a straightforward characterization of what section 18.8 does. PJM took the gross contractual value of a fifteen-year commitment, halved it, and called the result collateral. Nearly every difficulty addressed in this affidavit follows from that single step. 202.

Collateral, as PJM administers it everywhere else in its markets, requires three things: an identified position that would have to be replaced on default, a price at which it would be replaced, and a period over which the exposure is held before replacement is complete. Attachment Q is built on those elements. RPM auction credit, FTR credit and Peak Market Activity are each measured against them, recalculated as conditions change, and released as the exposure declines. Section 18.8 identifies none of the three. It states a rate and a date.

PDF page 106

35

203.
The seller requirement confirms the diagnosis rather than qualifying it. Both sides of the RBP face the same quantity and the same two prices. The obligation is denominated in the same RBP UCAP MW, and the amount that moves between them in any Delivery Year is the difference between the RBP price and the RPM clearing price for that year. The economic consequence being analyzed on each side therefore depends on the same two prices and the same committed quantity. Symmetry in the exposure does not produce symmetry in the collateral. Section 18.8(a) requires a seller to post approximately $121,545 per MW, while section 18.8(b) requires load to post $1.5 million per MW against the same quantity and the same prices — roughly twelve times as much. Measured against the two Delivery Years whose differential is known within twenty days of commitment, the seller posts less than the exposure and load posts about nine times it. As set out in Section VII, the two requirements also imply contradictory RPM price paths: the seller figure is adequate only if RPM clears at or above approximately $532.80/MW-day on average, and above approximately $564.12 across the thirteen years that remain unpriced, while the load figure corresponds to the exposure only if RPM clears at or below approximately $281.03. No single price path satisfies both. Two requirements derived from one measured exposure would not diverge in this way. These did not begin from one.

204.
The timing of the load requirement is the clearest demonstration that it is not calibrated to exposure. Commitments bind when results post on December 2, 2026. The 2028/2029 Base Residual Auction has already cleared at $325.00/MW-day, so the first Delivery Year's exposure is known at the moment the commitment binds. The 2029/2030 results post on December 22, 2026, twenty days later. Within three weeks of commitment, therefore, two Delivery Years are priced, and on the adjusted target of approximately 6,000 MW the exposure they represent is approximately $1.0 billion, taking the 2029/2030 year at the $333.44 proxy discussed above. Against that quantified exposure PJM requires no collateral at all for approximately seventeen months, until roughly April 17, 2028. It instead requires approximately $9.1 billion on the same target against an exposure it has never quantified, beginning at the point when a substantial part of the position has become knowable and is no longer in doubt. A requirement that is absent where the exposure is measurable and largest where it is unmeasured is not a risk instrument. 205.

The remaining difficulties are consequences rather than independent defects. Because the requirement is not tied to a measured exposure, there is no quantity against which to apply it, and the tariff supplies three that do not agree. Because the filed methodology does not measure the exposure, it provides no exposure-based basis for reducing the requirement as that exposure declines, and section 18.8(b)(i)(A) provides only that the Credit Rate “may be reduced.” Because the amount is not sized to a risk, the cost of carrying it — approximately $102 million to $307 million a year against approximately $573 million billed to load in the first Delivery Year — appears in no figure PJM has presented and is recovered by no provision of the tariff. And because it falls on a single date, in two instruments, drawn from the same limited group of issuing institutions, without regard to the balance sheet of the entity obligated to post, it creates the correlated exposure that a credit policy exists to prevent.

206.
The point I made at the outset holds at the end of it. A security deposit is sized to the damage a tenant might do, not to the rent due over the life of the lease. A landlord who demanded six months’ rent on a twelve-month lease would be asked what damage he expected, and would be expected to answer. PJM has not identified the damage.

207.
None of this suggests that the RBP requires no credit support. It plainly does. Section 18.9(a) socializes a defaulted RBP Charge pro rata across the remaining Load Serving Entities, and under Operating Agreement, section 15.2.2 the residual reaches Members holding no allocation at all. A requirement set too low leaves native load bearing the cost of another party’s default. That is the harm collateral exists to prevent, and it is the harm the Commission identified in the Policy Statement on Electric Creditworthiness as the function of collateral to avoid.

PDF page 107

36

208.
But the error runs in both directions, and that is what makes the matter difficult rather than simple. A requirement set too high inhibits access to the market the RTO was formed to operate, and where it is large enough relative to the balance sheets on which it falls, it creates the systemic exposure it was meant to prevent. The Commission has held that “the role of an RTO is to balance the competing goals of minimizing risk to non-defaulting market participants while, at the same time, ensuring that the credit or collateral requirements are not so stringent that they unnecessarily inhibit access to the marketplace,” and has rejected a credit provision on that ground notwithstanding that it emerged from an RTO stakeholder process and was approved by that RTO’s board. Sw. Power Pool, Inc., 126 FERC ¶ 61,153, at PP 19, 21 (2009). The NOVEC zone illustrates that the second error is not hypothetical here: an allocation of approximately $1.95 billion falls on a distribution cooperative reporting total assets of approximately $1.716 billion and cash and temporary investments of approximately $243.2 million.

209.
That two-sided character bears directly on what can be done with the filing. The appropriate requirement cannot be determined from the filed formula alone. It requires the exposure to be measured — the position, the replacement price, the close-out horizon — and it requires the resulting number to be tested against the financial capacity of the entities that would post it. That second step cannot be performed on this record. The balance sheets of the obligated Load Serving Entities are not before the Commission. Neither is the letter of credit capacity available to them, the cost at which they could raise cash, or the effect of a simultaneous call on their existing facilities. Those are the facts on which any sound construct depends, and they reside with the parties rather than with PJM or the Commission.

210.
The stakeholder process ordinarily provides an opportunity for that examination. As set out in Section XIII, credit and collateral were considered during that process, but the specific $1.5 million per MW methodology first appeared in the July 31 filing and therefore was not subjected to stakeholder examination before filing. It was not tested there against the elements set out in Section III, against the quantity to which it applies, against the cost of the permitted forms of collateral, or against the capacity of the entities on which it falls. In my opinion the deficiency in the filed construct is not a matter of calibration that could be corrected by adjusting the rate. It is that the analysis on which any rate would rest was not performed, and the present record does not contain the participant-specific financial and liquidity information needed to perform it.

PDF page 108

ATTACHMENTS TO THE AFFIDAVIT OF CARL F. COSCIA, Ph.D. PJM Interconnection, L.L.C., FERC Docket No. ER26-3380-000

PDF page 109

Attachment A — PJM Collateral Held and Collateral Intensity
Referenced at ¶ 65.
Source and method. PJM reports credit and collateral metrics to the Risk Management Committee. Materials are public at pjm.com/committees-and- groups/committees/rmc, filterable by year.

The document title changed during the period covered. Through 2024 and 2025 the deck was posted as "Informational Only — Key Risk Metrics," with the file named for the meeting date. Beginning in 2026 it is posted as "Informational Only — Credit Metrics — [Month] [Year]," named for the month of data rather than the meeting. The deck's own title slide reads "Credit Risk Metrics" throughout.

The series is monthly, but the RMC does not meet every month, and PJM posts any intervening months at the next meeting. At the August 18, 2026 meeting PJM posted four decks at once, covering May, June, July and August 2026. The table below is therefore indexed to the month of the data, with the meeting at which each deck was posted recorded separately.

Total collateral held, and its division among cash, letters of credit and surety bonds, appears on slide 4 ("Collateral Summary (Total PJM)"). Total Unsecured Credit Allowance appears on slide 2 ("Full Portfolio Metrics"). Letter of credit issuer concentration appears on slides 4 and 5. Each deck reports as of a date shortly before the meeting or, from 2026, as of the month named in the title.

RMC meeting dates in the period: 2024 — Jan 23, Feb 29, Mar 19, Apr 24, May 21, Jun 26, Jul 23, Aug 20, Sep 24, Oct 29, Nov 25, Dec 17. 2025 — Feb 19, Mar 18, Apr 22, May 20, Jun 17, Aug 19, Sep 26, Oct 22, Dec 2. 2026 — Feb 18, Mar 24, Apr 21, Aug 18.

Where a month's total is stated on the slide, the stated figure is used; where it is not, the value is read from the chart on the same slide and calibrated against the published figures appearing on it. Figures read from the chart rather than stated are marked with an asterisk. Figures are approximate and rounded to the nearest $0.1 billion.

Observations relied on. The affidavit relies on the observations below rather than on the full monthly record. Annual figures are averages of the month-end balances reported in the series; month-end figures are as printed on slide 4 of the deck for that month.

Observation
As of
Source deck
Total ($B)
Cash ($B)
LC ($B)
Surety ($B)
Illustrative mid-series
observation
Jun 27, 2024
RMC Jul 23, 2024
5.97
2.23
3.47
0.271
CY2024 average
monthly, 2024
series
6.2

CY2025 average
monthly, 2025
series
7.0

Month-end
Jan 29, 2026
RMC Feb 18, 2026
10.24
3.23
6.60
0.407
Maximum recorded — Winter
Storm Fern
Feb 26, 2026
RMC Mar 24, 2026
13.12
3.82
8.76
0.531
Month-end
Mar 26, 2026
RMC Apr 21, 2026
9.51
2.67
6.30
0.538
Most recent before filing
Jul 30, 2026
Credit Metrics — Aug 2026, RMC Aug 18,
2026
10.9
3.4
6.87
0.606

PDF page 110

Components reconcile to the printed totals in every month for which they are reported.
The balance is volatile and event-driven. Across three consecutive month-ends the total moved from $10.24 billion to $13.12 billion and back to $9.51 billion, a range of approximately 38 percent. PJM attributes the increase to a single weather event, stating on the February slide that "[h]igher credit requirements related to Winter Storm Fern led to a substantial increase in collateral." The chart on that slide shows the balance rising from approximately $6.8 billion in September 2025. PJM's collateral requirement across its markets therefore responds to measured changes in exposure and falls when the exposure recedes. The proposed RBP Credit Rate is fixed at $1.5 million per RBP UCAP MW and does not vary with any measured exposure at any point in the fifteen-year term.

Consistency with the audited statements. PJM's audited financial statements disclose credit deposits of $2.4 billion and letters of credit of approximately $4.5 billion at December 31, 2025, totalling approximately $6.9 billion excluding surety bonds. The average of the month-end balances reported to the Risk Management Committee for 2025 is approximately $7.0 billion. The two are consistent, and the reported series is bracketed at the year end by an audited disclosure. The maximum is a stress observation. The maximum balance PJM has recorded across all of its markets and all classes of participant, $13.12 billion, was reached under storm conditions and had receded to $9.51 billion within a month. The proposed RBP requirement of approximately $10.2 billion at the Initial RBP Target, or approximately $9.1 billion at the illustrative Final RBP Target, is of the same order as the entire collateral balance PJM held from all of its approximately 1,116 members across every market it operates, and would be a standing requirement rather than a response to an event.

Collateral intensity
Numerator throughout: the average of the month-end total collateral balances reported to the Risk Management Committee over the period. Using an average rather than a point-in-time balance places the numerator and the denominator on the same basis, the denominator being a full-year flow. Denominators as noted per row. The collateral figures and the resulting intensities are approximations. The numerator for the twelve months ended June 2026 is the average of the month-end balances reported for 2026 to date rather than for the full twelve-month window, the month-end balances for the second half of 2025 not being separately stated in the decks obtained.

Measure
Period
Denominator
Denominator source
Collateral ($B)
Intensity
Settlements processed
CY 2024
$51,713M
PJM 2025 Financial Report,
Billings for Services
6.2
12.0%
Settlements processed
CY 2025
$80,479M
PJM 2025 Financial Report,
Billings for Services
7.0
8.7%
Total cost of wholesale
power
CY 2025
$66.78B
Independent Market
Monitor, Market Monitor
Report, PJM Members
Committee (July 27, 2026),
at 11 (derived)
7.0
10.5%

PDF page 111

Measure
Period
Denominator
Denominator source
Collateral ($B)
Intensity
Total cost of wholesale
power
12 mo. ended Jun 2026
$83.05B
Independent Market
Monitor, Market Monitor
Report, PJM Members
Committee (July 27, 2026),
at 11 and 15 (derived)
10.7
12.9%

PJM identifies settlements processed under the Tariff, Operating Agreement and Reliability Assurance Agreement as a non-GAAP measure. The 2026 period is not covered by an annual report and the denominator for that row is therefore taken from the Independent Market Monitor's report. Band applied in the affidavit: approximately 9% to 13% of annual market activity.

Independent Market Monitor figures. The Market Monitor does not publish a calendar-year or trailing-twelve-month total; both figures above are derived from the reported year-to-date and monthly series. Monitoring Analytics, LLC, Market Monitor Report, presented to the PJM Members Committee Information Webinar (July 27, 2026), at 11 (“Total Cost of Wholesale Power – YTD 2025/2026,” category table: January–June 2025 total cost $30,071M against 394,842 GWh of real-time load; January–June 2026 total cost $46,340M against 404,710 GWh) and at 15 (“Total Cost of Wholesale Power – July 2025 through June 2026 Monthly,” Total Cost and Total Real Time Load rows), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260727-web/item-02---marketing-monitoring- report---presentation.pdf. Calendar 2025 is the January–June 2025 column at 11 plus the July through December 2025 monthly columns at 15 ($36.71 billion against 416,051 GWh), giving $66.78 billion against 810,893 GWh, or $82.35 per MWh. The twelve months ended June 2026 is the July through December 2025 monthly columns at 15 plus the January–June 2026 column at 11, giving $83.05 billion against 820,761 GWh, or $101.19 per MWh. The monthly columns reconcile exactly to the reported year-to-date figures. Real-time load is the denominator the Market Monitor itself applies: $46,340 million divided by 404,710 GWh is $114.50 per MWh, the total reported at 11.

Collateral did not scale with the market. Settlements processed rose 55.6 percent between 2024 and 2025, from $51.713 billion to $80.479 billion. Collateral intensity over the same period fell from approximately 12.0 percent to approximately 8.7 percent.

A comparator from the audited statements. At December 31, 2025 the estimated fair value of the FTR portfolio under PJM's mark-to-auction model was $2.4 billion, against which PJM held $2.9 billion of collateral — approximately 121 percent of the marked value of the position secured. The proposed RBP requirement of approximately $10.2 billion stands against approximately $573 million billed to load in the first Delivery Year, or approximately 1,790 percent. Peak balance. The maximum total collateral balance recorded across the series is approximately $13.1 billion, held against every PJM market and every class of participant. The proposed RBP requirement of approximately $10.2 billion would be owed by one class of participant, in respect of one product, on one date.

PDF page 112

Attachment B — LSE Collateral Requirement by Electric Distributor Zone/Area
Referenced at ¶¶ 68 and 137.
Initial RBP Target of 6,831.3 UCAP MW allocated on the pro-rata shares derived from the difference between Total Adjustments to Summer Peak Load for summer 2028 and summer 2026 (2026 Load Forecast, Table B-9b), at the proposed Credit Rate of $1.5 million per RBP UCAP MW.

Zone
Zone/Area
2026 (MW)
2028 (MW)
Difference
(MW)
Share
Allocated
MW
Collateral
($B)
BGE
BGE
18.0
43.0
25.0
0.28%
18.9
0.028
PECO
PECO
17.0
281.0
264.0
2.92%
199.6
0.299
PL
PPL
189.0
1,274.0
1,085.0
12.01%
820.5
1.231
PS
PSEG
308.0
628.0
320.0
3.54%
242.0
0.363
AEP
AEPOHIO
1,743.8
3,763.0
2,019.2
22.35%
1,527.0
2.291
APS
PE
165.0
319.0
154.0
1.70%
116.5
0.175
ATSI
PP
0.0
17.8
17.8
0.20%
13.5
0.020
ATSI
OHIO
132.0
281.2
149.2
1.65%
112.8
0.169
COMED
COMED
885.0
2,058.0
1,173.0
12.99%
887.1
1.331
DAYTON
DAY
0.0
277.0
277.0
3.07%
209.5
0.314
DOM
DOM
4,386.2
5,368.8
982.6
10.88%
743.1
1.115
DOM
NVEC
1,995.4
3,717.8
1,722.4
19.07%
1,302.6
1.954
DOM
ODEC
384.9
555.1
170.2
1.88%
128.7
0.193
DOM
REC
299.5
973.3
673.8
7.46%
509.6
0.764
Total
RTO
10,523.8
19,557.0
9,033.2
100.00%
6,831.3
10.247

Five zone/areas each carry an obligation exceeding $1 billion — AEPOHIO, NVEC, COMED, PPL and DOM — together approximately $7.9 billion, or 77.4 percent of the initial requirement.

Note. PJM's Reliability Backstop Procurement Design presentation of June 10–11, 2026, at slide 11, states the REC difference as 167.8 MW. The difference between the values in the adjoining columns is 673.8 MW, and PJM's stated share for REC of 7.5 percent is consistent with 673.8 MW rather than with 167.8 MW. The figure above uses 673.8 MW.

PDF page 113

Attachment C — Cost of Funds Across the Rating Distribution Referenced at ¶ 130.

ICE BofA index effective yields as of August 12, 2026. Rating tier

Effective yield
BBB (lowest investment grade)
5.58%
BB (highest non-investment grade)
5.98%
Single-B
7.25%
CCC and lower
14.51%

Blended cost, 77 percent investment grade
Scenario
IG portion
Remainder
Implied blended rate
1
77% at BBB
23% at BB
5.67%
2
77% at BBB
23% at single-B
5.96%
3
77% at BBB
23% at CCC and lower
7.63%

Distribution required to reach the 9.5% discount rate PJM applied Assumption for the remainder

Share required at CCC and lower
Remainder at BBB
43.9%
Remainder at single-B
31.0%

PDF page 114

Attachment D — Load Factor Sensitivity, NVEC Zone/Area
Referenced at ¶¶ 162 and 164.
Energy sales of approximately 12.2 billion kWh for the year ended December 31, 2024; data centers taken at 65 percent of energy sales; first-Delivery-Year RBP Charge allocated to the zone of approximately $109 million at the 2028/2029 clearing price of $325.00/MW-day against an RBP price of $555.00/MW-day. Class peaks are computed as class energy divided by the product of 8,760 hours and the stated load factor. Uniform energy-basis charge: $8.93 per MWh. Non-DC load factor

DC load factor
Non-DC class peak (MW)
DC class peak
(MW)
Non-DC share of
summed class
peaks
Non-DC $/MWh
DC $/MWh
40%
85%
1,219
1,065
53.4%
13.62
6.41
40%
90%
1,219
1,006
54.8%
13.98
6.22
40%
95%
1,219
953
56.1%
14.33
6.03
45%
85%
1,083
1,065
50.4%
12.87
6.81
45%
90%
1,083
1,006
51.9%
13.24
6.62
45%
95%
1,083
953
53.2%
13.58
6.43
50%
85%
975
1,065
47.8%
12.20
7.18
50%
90%
975
1,006
49.2%
12.56
6.98
50%
95%
975
953
50.6%
12.91
6.79
55%
85%
886
1,065
45.4%
11.59
7.50
55%
90%
886
1,006
46.8%
11.96
7.31
55%
95%
886
953
48.2%
12.30
7.12

Across every cell, the non-data-center class bears a higher charge per megawatt-hour than the data center class, and a higher charge than the uniform energy-basis figure. The disparity is narrowest at the combination least favorable to the conclusion — non-DC at 55 percent and DC at 85 percent — and is approximately 1.55 to 1 even there.

PDF page 115

Attachment E — Derivation of the Implied Average RPM Prices
Referenced at ¶¶ 82, 83, 94 and 95.
RBP price of $555.00/MW-day. Annual differential per MW equals (555 − P) × 365, where P is the RPM clearing price in $/MW-day. Undiscounted, consistent with ¶ 79. LSE side. The $1.5 million Credit Rate corresponds to the cumulative fifteen-year contract-for-differences exposure only if: (555 − P) × 365 × 15 = $1,500,000 → 555 − P = $273.97 → P = $281.03/MW-day

Seller side, full term. Seller collateral of $121,545 per MW equals 0.2 × $555 × 365 × 3. It covers the cumulative fifteen-year exposure only if: (555 − P) × 365 × 15 = $121,545 → 555 − P = $22.20 → P = $532.80/MW-day

Seller side, remaining thirteen years. The first two Delivery Years are priced or proxied: 2028/2029 at $325.00 (differential $230.00/MW-day, $83,950 per MW) and 2029/2030 proxied at $333.44 (differential $221.56/MW-day, $80,869 per MW), a two-year total of $164,819 against $121,545 posted, a deficit of $43,274. Recovering that deficit requires the contract for differences to reverse across the remaining thirteen Delivery Years:

(P − 555) × 365 × 13 = $43,274 → P − 555 = $9.12 → P = $564.12/MW-day
The two requirements are consistent only if the average RPM clearing price is simultaneously at or below $281.03 and at or above $564.12. The difference between the implied prices is $283.09/MW-day, or $251.77 measured against the full-term seller figure of $532.80.

Exposure at the uncapped price PJM simulated. PJM has estimated that, absent the price collar, the 2028/2029 Base Residual Auction would have cleared at $554.72/MW-day RTO-wide. Against the RBP price of $555.00, the annual differential at that clearing price is $0.28/MW-day: (555 − 554.72) × 365 × 15 = $1,533 per MW, against $1,500,000 of collateral.

Blended path. Taking the two Delivery Years that are priced or proxied at their stated values and the remaining thirteen at the uncapped simulation: DY 2028/2029 at $325.00: $83,950 per MW

DY 2029/2030 at $333.44: $80,869 per MW
DY 2030/2031 through 2042/2043 at $554.72: $0.28 × 365 × 13 = $1,329 per MW
Fifteen-year total: $166,148 per MW. Collateral of $1,500,000 per MW is approximately 9.0 times that amount.

PDF page 116

Locational note. PJM’s simulation places the uncapped ComEd Locational Deliverability Area price at $776.69/MW-day, which exceeds the RBP price by $221.69. At any clearing price above $555.00 the contract for differences reverses and the payment runs from the resource to load, so no exposure arises for load in that Delivery Year.

PDF page 117

Table 1 — NVEC Zone/Area Obligation Against Reported Financial Position Referenced at ¶¶ 140 to 142.

The dollar amounts, ratios and multiples in the tables below are approximations. Item

Amount
NVEC initial allocation
1,302.6 UCAP MW
Share of Initial RBP Target
19.07%
Collateral at $1.5 million per MW
$1.954 billion
Total assets (FY2025)
$1.716 billion
Total equities and margins (FY2025)
$919.7 million
Total long-term debt (FY2025)
$69.2 million
Cash collateral posted to PJM (FY2025)
$34.4 million
Patronage capital and margins (FY2025)
$44.7 million
Annual interest expense (FY2025)
$0.8 million
Peak demand, coincident (FY2025)
2,360 MW
Energy sales (FY2025)
14.649 billion kWh
Cash and temporary investments (FY2025)
$243.2 million
Total current and accrued assets (FY2025)
$575.4 million
Patronage capital on the books (FY2025)
$824.0 million
Capital credits retired (FY2025)
$17.9 million
Cost of purchased power (FY2025)
$1,310.1 million
Consumers served (FY2025)
184,104

Ratio
Multiple
Collateral to total assets
1.14×
Collateral to equities and margins
2.12×
Collateral to total long-term debt
28×
Collateral to cash collateral posted to PJM
57×
Allocated MW to system peak demand
55%
Collateral to cash and temporary investments
8.0×
Collateral to total current and accrued assets
3.4×
Collateral to patronage capital on the books
2.4×
Collateral to FY2025 operating revenue
132%
Collateral per consumer served
$10,614

Annual carrying cost of the required collateral
Costs and multiples are approximations.

PDF page 118

Rate
Annual cost
As a multiple of FY2025 patronage capital
and operating margins
As a multiple of FY2025 interest expense
100 bp
$19.5 million
0.94×
25×
150 bp
$29.3 million
1.41×
37×
200 bp
$39.1 million
1.88×
50×
300 bp
$58.6 million
2.81×
75×
Source for the cooperative’s financial and operating figures: Northern Virginia Electric Cooperative, Financial and Operating Report Electric Distribution, U.S. Department of Agriculture, Rural Utilities Service, Borrower Designation VA0055, period ended December 2025 (prepared with audited data). Total assets, Part C line 29; total margins and equities, Part C line 36; patronage capital, Part C line 31; total long-term debt, Part C line 43; cash and temporary investments, Part C lines 15 and 18; total current and accrued assets, Part C line 26; interest expense, Part A lines 16 and 18; patronage capital and margins, Part A line 29; cost of purchased power, Part A line 3; cash collateral posted to PJM, Part Q Section I item 4; capital credits retired, Part I; consumers served, Part O line 10; energy sales, Part O line 11; coincident peak, Part O line 20. The report is prepared on the unconsolidated regulatory basis of the Rural Utilities Service and is not consolidated with the cooperative’s subsidiaries.

PDF page 119

VERIFICATION OF AFFIDAVIT
Pursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing Affidavit is true and correct.

Executed August 21, 2026.
By: _____________________________
       Carl F. Coscia

PDF page 120

Certificate of Service

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC this 21st day of August, 2026.

/s/ Kelly A. Cuthbertson

Kelly A. Cuthbertson