ER26-3380-000 · 2026-09-08 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to certain comments and protests re the PJM Reliability Backstop Procurement…

PDF page 1

1

UNITED STATES OF AMERICA

BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, L.L.C.

)

Docket No. ER26-3380-000

)

MOTION FOR LEAVE TO ANSWER
AND ANSWER OF CONSTELLATION ENERGY GENERATION, LLC
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC”
or the “Commission”) Rules of Practice and Procedure,1 Constellation Energy Generation, LLC (“Constellation”) respectfully moves for leave to answer and answers certain comments and

protests filed in this proceeding (“Answer”). Constellation seeks to provide additional information and context that will assist the Commission in its decision-making process.2

I. BACKGROUND
On July 31, 2026, PJM Interconnection, L.L.C. (“PJM”) submitted revisions to the PJM
Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among
Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).3

1  18 C.F.R. §§ 385.212, 385.213.
2 Although the Commission’s Rules of Practice and Procedure do not generally permit answers to answers unless otherwise ordered by the decisional authority, the Commission has made exceptions where an answer provides useful and relevant information that will assist the Commission in its decision-making process, corrects factual inaccuracies and clarifies the issues, or assures a complete record in the proceeding. See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co., 140 FERC ¶ 61,057, at P 94 (2012) (accepting answers that “provided information that assisted us in our decision-making process”); Entergy Servs., Inc., 126 FERC ¶ 61,227, at P 76, order on clarification & reh’g, 127 FERC ¶ 61,225 (2009); New Power Co. v. PJM Interconnection LLC, 98 FERC ¶ 61,208, at p. 61,756 (2002) (answer accepted to provide new factual and legal material to assist the Commission in decision-making process).
3 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (the “PJM Proposal”).  Capitalized terms used but not otherwise defined herein have the meaning as defined in the Tariff, the RAA, or the PJM Proposal, as applicable.

PDF page 2

2
Numerous parties filed comments and protests addressing the proposal, including Constellation.4 And many of these protests raised similar concerns, underscoring that the RBP as-proposed

includes serious design flaws.
II. ANSWER
A. Request for Additional Clarification on Resources Eligible to Supply
Qualifying RBP Offset UCAP MW
Constellation maintains the arguments and requested relief set forth in its Limited Protest concerning the treatment of RBP Resources in subsequent RPM Auctions.5  The NRG Companies, the Independent Market Monitor for PJM, the New Jersey Board of Public Utilities (“NJBPU”), and the Office of the Ohio Consumers’ Counsel raised similar concerns regarding PJM’s

mandatory price-taker requirement. Constellation will not repeat those arguments here but
underscores the seriousness of this issue for market integrity going forward.6
Constellation also maintains the arguments and requested relief for the limited
modifications to other Tariff provisions described in its Limited Protest, with one additional clarification.  Constellation agrees with the sentiment expressed by other commenters that Section 18.2 of the proposed Tariff, describing resources eligible to supply Qualifying RBP Offset UCAP

4 PJM Interconnection, L.L.C., Limited Protest of Constellation Energy Generation, LLC, Docket No. ER26-3380- 000 (filed Aug. 21, 2026) (“Limited Protest”).
5 See Limited Protest at 10–13.
6 See, e.g., PJM Interconnection, L.L.C., Limited Protest of the NRG Companies, Docket No. ER26-3380-000 at 10– 11 (filed Aug. 21, 2026) (“[T]he proposed requirement that resources with RBP commitments offer as price-takers into RPM Auctions for the associated Delivery Years ‘is antithetical to creating a normal capacity market,’” and “‘send[s] the wrong signals [to] potential investors of PJM generation capacity.’”); PJM Interconnection, L.L.C., Protest of the Independent Market Monitor for PJM, Docket No. ER26-3380-000 at 11 (filed Aug. 21, 2026) (“Pay as bid is inefficient and does not facilitate competition.”); PJM Interconnection, L.L.C., Protest and Request for Rejection of Filing or in the Alternative for Evidentiary Hearings and/or Settlement Proceedings by Office of the Ohio Consumers’ Counsel, Docket No. ER26-3380-000 at 7–8 (filed Aug. 21, 2026) (“OCC Protest”) (explaining that PJM has not supported the RBP’s proposed departure from the single clearing price approach to a pay-as-bid approach, which is “diametrically opposite what it has supported for over 20 years in its RPM auctions”); PJM Interconnection, L.L.C., Comments of the New Jersey Board of Public Utilities, Docket No. ER26-3380-000 at 5 (filed Aug. 21, 2026) (“NJBPU Comments”) (“[t]he Board has concerns that the pay-as-bid market structure, compared to PJM’s uniform clearing price in the capacity market, would create inefficient market outcomes or allow for market manipulation.”)

PDF page 3

3
MW, requires additional clarity and should be adjusted to avoid unintentionally “limiting [the] pool of qualifying resources.”7  Consistent with the request in Constellation’s Limited Protest with respect to resources qualifying as RBP Resources, the Commission should similarly condition acceptance of PJM’s RBP proposal on PJM revising the eligibility criteria for Qualifying RBP Offset UCAP MW.8  In particular, Energy Resources seeking new Capacity Interconnection Rights (CIRs) through an Interconnection Request should be able to satisfy the criteria for resources eligible to supply Qualifying RBP Offset UCAP MW.

B. Credit and Collateral Requirements of Load Serving Entities
The remainder of this Answer addresses the distinct load serving entity (“LSE”) credit and collateral issues raised in the responsive pleadings. Multiple commenters raised substantial concerns regarding PJM’s proposed LSE credit and collateral provisions. EKPC states that the magnitude of the proposed requirement “stands apart from anything in PJM’s experience.”9

NOVEC characterizes the requirement as excessive and onerous.10 The NJBPU cautions that the size of the collateral requirement may challenge LSEs’ ability to obtain the required collateral and

7 PJM Interconnection, L.L.C., Protest of Northern Virginia Electric Cooperative, Inc., Docket No. ER26-3380-000 at 7–8 (filed Aug. 21, 2026) (“NOVEC Protest”); see also See PJM Interconnection, L.L.C., Comments of Equinix Inc. on the PJM Interconnection, LLC Filing Regarding its Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming From Large Loads, Docket No. ER26-3380-000 at 2 (filed Aug. 21, 2026) (“Equinix Comments”).
8 See Limited Protest at 13–14 (requesting modifications to the proposed Tariff to add Energy Resources seeking new CIRs as a category of resource eligible under 18.5(b)(iii)(2) to qualify as an RBP Resource).  Notably, the PJM Proposal explained that “Qualifying RBP Offset UCAP MW has been deliberately designed to be more inclusive than the resources that qualify to sell RBP UCAP MW [i.e., RBP Resources].”  PJM Proposal at 42.  Because PJM has explicitly stated that the criteria for resources qualifying as RBP Resources are more restrictive, while the pool of Qualifying RBP Offset UCAP MW is intended to be more inclusive, it logically follows that the relief requested in Constellation’s Limited Protest extends to the criteria for resources eligible to supply Qualifying RBP Offset UCAP MW.  However, out of an abundance of caution, Constellation requests clarification and any necessary Tariff modifications to confirm that Energy Resources as described herein may also be eligible to supply Qualifying RBP Offset UCAP MW.
9  PJM Interconnection, L.L.C., Protest of East Kentucky Power Cooperative, Inc., Docket No. ER26-3380-000 at 26 (filed Aug. 21, 2026) (“EKPC Protest”) (citing Attachment 2, Affidavit of Carl F. Coscia at ¶ 61 (“Coscia Affidavit”)).
10 NOVEC Protest at 3.

PDF page 4

4
observes that additional time would have permitted development of a more thoughtful collateral framework.11

Constellation joins the chorus of voices raising concerns about the proposed LSE credit requirements.  The magnitude of the proposed collateral obligation for LSEs is enormous—it would rival the PJM credit holdings for all its markets combined.12 PJM proposes an initial RBP Credit Rate of $1.5 million for each MW of allocated RBP Obligation. Applied to the 6,831.3 MW Initial RBP Target, that rate could require LSEs collectively to post approximately $10.2 billion in collateral. In his Affidavit to the EKPC Protest, Mr. Carl Coscia puts this figure in context, noting that “PJM’s monthly Key Risk Metrics reporting shows the total collateral PJM holds from all Members, against every market it operates, at approximately $6.2 billion on average in 2025 and $7.0 billion in 2025,” and approximately $10.9 billion as of July 30, 2026.13 Importantly, the approximately $10.2 billion collateral estimate captures only collateral posted by LSEs to PJM. It does not capture the additional credit support that LSEs are almost certain to require from the large-load customers whose obligations they serve. In other words, if an LSE is required to post significant collateral to PJM as a result of its large load retail customer, the LSE is likely to then require its large load retail customer to provide the same or similar collateral to the LSE, more or less doubling the total collateral required for an RBP customer. Given the magnitude of the collateral PJM proposes to require LSEs to post, this “double collateral” problem will strain liquidity and add significantly to already-significant financing and transaction costs.

11 NJBPU Comments at 5-6.
12 Coscia Aff. ¶ 63. 13 Id. (emphasis added).

PDF page 5

5
As discussed below, Constellation (1) has significant concerns about the fixed $1.5 million/MW RBP Credit Rate and believes it is excessive; (2) suggests, to address the “double collateral issue,” that the applicable large-load customer should be permitted to post qualifying collateral directly for the account of the responsible LSE; and (3) given these concerns and similar concerns raised by other parties, requests that the Commission sever and/or defer proposed Tariff section 18.8(b) for resolution on an expedited paper hearing with a short timeline (about 125 days) for resolution without delaying the RBP solicitation or the seller-side credit requirements.

1. PJM’s Fixed $1.5 Million/MW Rate Is Based on Contract Notional,
Not Measured Credit Exposure
PJM has a legitimate interest in protecting the RBP against reasonably foreseeable nonpayment. But the amount of collateral imposed on LSEs must bear a reasoned relationship to the exposure being secured. PJM has not made that showing for its fixed $1.5 million/MW rate, and it is not “reasonably tailored to the actual credit risk presented”14 nor “derived from measured exposure.”15

PJM derives the proposed rate from approximately one-half of the gross notional value of a hypothetical fifteen-year RBP commitment priced at $555/MW-day. PJM also performs a discounted-cash-flow calculation using the capacity-market weighted average cost of capital. Those calculations explain how PJM arrived at the $1.5 million figure. They do not demonstrate

14 PJM Interconnection, L.L.C., Protest of FirstEnergy Service Company, Docket No. ER26-3380-000 at 8 (filed Aug. 21, 2026).
15 EKPC Protest at 23.

PDF page 6

6
that the figure measures reasonably foreseeable credit exposure. And discounting a gross payment stream does not convert it into a credit-exposure analysis.

The methodology has five material gaps. First, it assumes that every committed RBP megawatt is priced at the $555/MW-day maximum willingness to pay, although accepted RBP prices may be lower and may vary by resource and Delivery Year. Second, it uses fifteen years of gross contract value rather than the net RBP Charges that LSEs actually will be billed, should RBP Resources not be segregated from the market. Third, it does not identify the period of unpaid charges to be secured, the time needed to draw collateral and reallocate any residual default, or the stress assumptions used to estimate net exposure. Fourth, it applies the same $1.5 million/MW base rate without explaining why credit quality may increase—but never reduce—the base requirement. Finally, although PJM may reduce the rate over time, the proposed Tariff establishes no mandatory recalculation schedule, prescribed inputs, or objective collateral-release standard. PJM’s proposed default rule further demonstrates the disconnect. Proposed Tariff section 18.9(a) provides that an unpaid RBP Charge will be reallocated to the remaining LSEs responsible for RBP Charges and that the defaulting LSE’s RBP Collateral may be applied as an offset. PJM does not explain why the exposure arising before collateral can be drawn and any residual default reallocated should be measured by one-half of a fifteen-year gross payment stream. Assuming for the sake of argument that it is accepted, the PJM-proposed contract-for- differences settlement further illustrates the mismatch. If the Commission rejects Constellation’s proposal to segregate RBP Resources and associated load from RPM and accepts PJM’s proposal, the payment due to RBP Resources in any Delivery Year will only equal the amount that the RBP Resources do not recover from RPM, which already has its own credit and collateral obligations. EKPC calculates that, at the $555/MW-day maximum willingness to pay and the Initial RBP

PDF page 7

7
Target, one year of gross RBP payments would be approximately $1.38 billion. Using the $325/MW-day clearing price from the 2028/2029 BRA, EKPC calculates a first-year net payment of approximately $573 million. The proposed $10.2 billion collateral requirement would equal approximately 740% of one year’s gross commitment value, and approximately 1,790% of the amount actually billed to load ($573 million).16

Those comparisons are illustrative. Neither a one-year exposure horizon nor the $325/MW- day clearing price necessarily supplies the appropriate collateral standard for future Delivery Years. But the comparisons demonstrate why a fixed percentage of the maximum fifteen-year gross notional value is not a reasoned measure of payment exposure.17

The Commission should not replace PJM’s unsupported methodology with another mechanical shortcut.  In particular, if RBP Resources become price-takers in RPM, the replacement RBP Credit Rate should not simply equal $555/MW-day less a single assumed future RPM price. A revised methodology should account for the actual accepted RBP prices and quantities; the net settlement structure, if accepted by the Commission; a defined default- management and reallocation horizon; reasoned stress assumptions for future net RBP Charges; applicable LSE or guarantor credit quality; qualifying collateral or guarantees already held by

16 EKPC Protest at 25 (emphasis added).
17 See Coscia Aff. ¶ 187 (“The $1.5 million per MW Credit Rate does not depend on the credit quality of the LSE, a recalculation of Peak Market Activity or expected exposure, or the use of other mitigation tools to address an identified deficiency. It applies the same fixed rate per megawatt before unsecured credit to every LSE subject to section 18.8(b), regardless of those considerations.”).

PDF page 8

8
PJM; and mandatory periodic recalculation and release standards. Any change the Commission accepts to the RBP settlement structure should be reflected in the collateral methodology.

2. Large Load Customers Should Be Permitted to Post Collateral for the
Account of the Responsible LSE
An excessive collateral requirement can create the very liquidity risk it is intended to mitigate. Under the filed design, an LSE must furnish RBP Collateral to PJM or PJMSettlement and may then prudently obtain corresponding support from the large-load customer associated with the obligation. That structure can encumber two balance sheets and impose two layers of financing and transaction costs for the same payment obligation.

The Tariff therefore should permit the applicable large load customer, or an affiliate acting on its behalf, to post RBP Collateral directly with PJM or PJMSettlement for the account of the responsible LSE. The LSE should remain fully responsible for payment of RBP Charges; PJM or PJMSettlement should have direct and unconditional draw rights; and the customer-posted amount should satisfy the LSE’s collateral requirement dollar-for-dollar. The same collateral should not be credited against more than one obligation, and disputes between the customer and the LSE should not impair PJM’s draw rights.

This option would not reduce PJM’s credit protection or change the entity responsible for paying RBP Charges. It would add the option for another entity18 to furnish the collateral and thereby avoid unnecessary intermediation through the LSE and duplicative credit postings. In addition to the advantages described above, allowing the large load to post collateral will facilitate a seamless transition if the customer changes its LSE, the applicable RBP Obligation changes, or

18 Importantly, the proposed modification to the Tariff would permit a large load customer to post RBP Collateral directly with PJM or PJMSettlement, but would not require such an arrangement.

PDF page 9

9
the posting arrangement otherwise terminates.19
3. The Commission Can Preserve the RBP Procurement Schedule While
Resolving the LSE Collateral Provisions in an Expedited Paper
Hearing
The procurement is urgent; the future LSE collateral methodology is not. RBP Sellers must satisfy the seller-side credit requirements in connection with their RBP Sell Offers. By contrast, the first LSE collateral requirement will not arise, as currently proposed, until forty-five days before the 2028/2029 Delivery Year. The Commission therefore can accept the RBP solicitation, selection process, commitments, and seller-side credit provisions while severing or deferring its decision on only proposed Tariff section 18.8(b). That disposition would not displace

Constellation’s separate request in its Limited Protest that the initial RBP Obligation allocations be determined 365 days before the 2028/2029 Delivery Year.20

The present record is sufficient to conclude that PJM has not supported the fixed $1.5
million/MW rate. The record is not sufficiently developed, however, to prescribe a durable replacement methodology.21  The replacement must be conformed to the RBP settlement structure accepted by the Commission and supported by evidence addressing the relevant exposure horizon, stress assumptions, credit-quality treatment, customer-posted collateral, collateral already held by PJM, switching and transfer mechanics, and mandatory recalculation and release standards.

19 See, e.g., NOVEC Protest at 24 (“The Commission should require PJM to allow other methods to demonstrate creditworthiness besides posting the full collateral or a letter of credit.”); Equinix Comments at 2 (RBP collateral provisions should be revised to “calibrate[] to reasonably foresee forward exposure” and revise “the forms of credit support” required).
20 See Limited Protest at 16–17.
21 See, e.g., OCC Protest (requesting evidentiary hearings and/or settlement proceedings to adequately consider the RBP); NOVEC Protest at 4–9; NJBPU Comments at 5–6 (“[T]he Board is concerned that the size of the collateral requirements may make it difficult for LSEs to secure the required collateral . . . . While the Board does not provide a solution at this time, the Board and stakeholders could have used additional time to build a more thoughtful collateral system.”).

PDF page 10

10
Given that required credit support will not be posted until sometime in April 2028, there is time to consider a “more thoughtful collateral system.”22 The Commission, therefore, should establish an expedited paper hearing limited to proposed Tariff section 18.8(b). Within thirty days after the later of the Commission’s order or PJM’s publication of the final RBP commitments, PJM should file a proposed revised LSE collateral methodology and supporting analysis. Initial briefs should be due twenty days thereafter, and reply briefs fifteen days after the initial briefs. Constellation requests that the Commission issue an order within sixty days after the close of briefing.

This schedule would produce a complete record approximately 125 days after the relevant RBP commitments and well before any LSE collateral must be posted. It also would leave the RBP procurement and seller-side credit protections undisturbed.

Setting the credit requirement and mechanism issues in a separate expedited track to evaluate and form consensus for the collateralization requirements will help ensure the cost allocation methodology keeps the RBP costs with large loads and not residential customers, properly sizes collateral requirements commensurate with exposure and credit risk, and considers alternative solutions to credit support that will help alleviate the incredible burden faced by LSEs, particularly smaller entities. The current record and procedural schedule is not adequate to address the necessary details of the credit and collateral requirements.

22 NJBPU Comments at 6.

PDF page 11

11
III. CONCLUSION
In accordance with PJM’s willingness to accept changes under NRG Power Marketing,23 the Commission should (i) accept the RBP subject to the modifications Constellation discussed in its Limited Protest in this proceeding, with the additional clarification discussed above permitting Energy Resources seeking new capacity rights to satisfy the criteria for resources eligible to supply Qualifying RBP Offset UCAP MW, and (ii) sever the LSE credit issue discussed herein for further proceedings and refer that issue to an expedited paper hearing.

Respectfully submitted,
Dated: September 8, 2026

23 See PJM Proposal at 3 (“PJM provides notice that it consents to the Commission’s exercise of authority to modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary and permitted under section 205 of the FPA and NRG Power Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching objectives in this filing”).

/s/
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
John M. White
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
john.white@constellation.com

Christopher A. Wilson
Vice President, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Kenneth W. Irvin
Alexandra K. Calabro
Sidley Austin LLP
1501 K Street, N.W.
Washington, DC 20005
Phone: (202) 736-8256
kirvin@sidley.com
alexandra.calabro@sidley.com

Terence T. Healey
Sidley Austin LLP
60 State Street, 37th Floor
Boston, MA 02109
Phone: (617) 223-0306
thealey@sidley.com

Counsel for Constellation Energy Generation,
LLC

PDF page 12

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C. this 8th day of September 2026.

/s/
Alexandra K. Calabro
Sidley Austin LLP
1501 K Street, N.W.
Washington, DC 20005