ER26-3380-000 · 2026-09-04 · East Kentucky Power Cooperative, Inc.

Motion for Leave to File Limited Answer, and Limited Answer, of East Kentucky Power Cooperative, Inc. in support of Protest filed by American Electric Power…

Text extracted from the eLibrary original (SHA-256 c41adf4b4b3691a4…). Download the original from the official source.

Contents · 6 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 1
  2. II. LIMITED ANSWER p. 2
  3. A. The TO Exit Provisions Violate the Cost Causation Principle. p. 4
  4. B. The TO Exit Provisions Lack the Required Clarity and Specificity to be p. 5
  5. C. The TO Exit Provisions “Unnecessarily Constrain Future Decision-Making.” p. 7
  6. III. CONCLUSION p. 8

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.
Read this passage

I. MOTION FOR LEAVE TO ANSWER

printed heading

MOTION FOR LEAVE TO ANSWER Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure generally prohibits answers to answers or protests unless otherwise ordered by the decisional authority.
Read this passage

II. LIMITED ANSWER

printed heading · Topic match: Cost allocation

EKPC filed a protest to PJM’s RBP Proposal.7 As explained in the RBP Protests, PJM proposed new rules that “set forth the responsibilities of various parties in the event a Transmission Owner exits from PJM”8 (“TO Exit Provisions”) and that would impose new financial obligations on any TO that…
Read this passage Filed comments: Cost allocation

A. The TO Exit Provisions Violate the Cost Causation Principle.

printed heading · Topic match: Cost allocation

The Commission’s cost causation principle requires that “all approved rates reflect to some degree the costs actually caused by the customer who must pay them,” in order to be found just and reasonable and not unduly discriminatory or preferential under FPA section 205.13 Here, the TO Exit…
Read this passage Filed comments: Cost allocation

B. The TO Exit Provisions Lack the Required Clarity and Specificity to be

printed heading · Topic match: Cost allocation

Moreover, any exit obligation related to the RBP Proposal should be limited to that which is necessary to prevent RBP charges from being shifted to remaining load.24 Should the Commission accept PJM’s RBP Proposal,25 EKPC urges the Commission to be clear that its determination in this proceeding is…
Read this passage Filed comments: Cost allocation

C. The TO Exit Provisions “Unnecessarily Constrain Future Decision-Making.”

printed heading

The TO Exit Provisions “Unnecessarily Constrain Future Decision-Making.” PJM concedes that a TO withdrawing is a “remote” possibility yet proposes rigid obligations that very likely would need to be revisited if a TO sought to withdraw over the 15-year RBP commitment period.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION Wherefore, EKPC respectfully requests that the Commission accept this answer, consider the arguments set forth herein, and take such action as requested herein and in the EKPC Protest.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 4th day of September, 2026. /s/Kelly A.
Read this passage