ER26-3380-000 · 2026-08-21 · PPL Electric Utilities Corporation

Motion to Intervene, Limited Protest, and Request for Clarification of PPL Electric Utilities Corporation

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C
)
)
)
                   Docket No. ER26-3380-000
MOTION TO INTERVENE, LIMITED PROTEST,
AND REQUEST FOR CLARIFICATION OF
PPL ELECTRIC UTILITIES CORPORATION
Pursuant to Rules 211,1 212,2 and 2143 of the Federal Energy Regulatory
Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, PPL Electric Utilities Corporation (“PPL Electric”) respectfully moves to intervene in the above-captioned proceeding, provides the following limited protest (“Limited Protest”), and requests clarification.

PPL Electric greatly appreciates the engagement of the PJM Interconnection, L.L.C. (“PJM”) stakeholder community and the work of the PJM Board and staff in acting to address the capacity deficiencies arising from the 2027/2028 and 2028/2029 Reliability Pricing Model (“RPM”) Auctions, and is generally supportive of the Reliability Backstop Procurement (“RBP”) Filing.4

However, PPL Electric is compelled to submit this Limited Protest with respect to one component of the RBP Filing concerning Transmission Owner exit.5  This component was

1 18 C.F.R. § 385.211(a)(1) (“Any person may file a protest to object to any application, complaint, petition, order to show cause, notice of tariff or rate examination, or tariff or rate filing.”). 2 18 C.F.R. § 385.212(a)(1) (“A motion may be filed: [a]t any time, unless otherwise provided.”). 3 18 C.F.R. § 385.214(a)(3) (“Any person seeking to intervene to become a party, other than the entities specified in paragraphs (a)(1) and (a)(2) of this section, must file a motion to intervene.”).

4 PJM Interconnection, L.L.C., FPA Section 205 Filing of PJM Interconnection, L.L.C, Docket No. ER26-3380 (Jul. 31, 2026) (“RBP Filing”).
5 Tariff, Attachment DD, Section 18.7 (hereafter, the “TO Exit Provisions”).

PDF page 2

2
neither contemplated nor discussed by any stakeholder during the Critical Issue Fast Path (“CIFP”) Process and appears to have been introduced only shortly before the filing was submitted.

Recognizing that individual elements of the proposal may warrant separate treatment, PJM expressly invited the Commission to “modify and/or sever any element of the proposed Tariff and RAA language to the extent necessary.”6  The Commission should do so here and reject the TO Exit Provisions of the RBP Filing, as discussed below in Section II. Additionally, PPL Electric requests clarification on a specific credit collateral contingency, as discussed below in Section III.

I. MOTION TO INTERVENE
PPL Electric respectfully moves to intervene in the above-captioned proceeding.  PPL Electric is a Pennsylvania corporation and a wholly owned subsidiary of PPL Corporation. PPL Electric is an owner of transmission facilities in PJM, distributes electricity to all retail customers within its service territory in central and eastern Pennsylvania, and is a provider of last resort under Pennsylvania’s Electricity Generation Customer Choice and Competition Act, 66 Pa.C.S.A. § 2801, et seq.  PPL Electric is a designated Load Serving Entity in PJM, and a signatory to the PJM Consolidated Transmission Owners Agreement (“CTOA”) and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”).7 On July 31, 2026, PJM initiated the above-captioned Federal Power Act (“FPA”) section 205 proceeding by submitting proposed Tariff and RAA revisions to establish the

6 RBP Filing at 3.
7 The RAA is currently located under PJM’s “Intra-PJM Tariffs” eTariff title, available here: https://etariff.ferc.gov/TariffBrowser.aspx?tid=1731. Terms not otherwise defined herein shall have the same meaning as set forth in the RAA, the Open Access Transmission Tariff (“Tariff”), and the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”).

PDF page 3

3
RBP—a one-time procurement of new capacity to address resource adequacy challenges in the PJM Region stemming from insufficient commitments of capacity in the 2027/2028 and 2028/2029 RPM Auctions.

Given the direct relationship between the RBP Filing and PPL Electric’s roles and responsibilities within the PJM Region, PPL Electric has a direct, substantial, and independent interest in this proceeding, which no other party can adequately represent, and respectfully requests that the Commission grant this motion to intervene and that PPL Electric be afforded all the rights of a party to this proceeding.

II. LIMITED PROTEST
  The Commission should reject the TO Exit Provisions for the reasons discussed below in subsections II.A–D.

A. The TO Exit Provisions Concern Transmission Owner Rights and Obligations
and Therefore Belong in the CTOA.
The CTOA is the bilateral contract establishing the rights, obligations, and commitments between PJM and the PJM Transmission Owners.  Indeed, the contract explicitly codifies as one of its core purposes “[to] establish certain rights and obligations that will apply to the Parties and PJM.”8  By contrast, Attachment DD to the PJM Tariff is not a bilateral contract establishing the rights, obligations, and commitments between PJM and the PJM Transmission Owners.  It is a Tariff9 of general applicability that contains the rules of PJM’s

8 CTOA, Article 2.
9 18 C.F.R. § 35.2(c)(1) (“The term tariff as used herein shall mean a statement of (1) electric service as defined in paragraph (a) of this section offered on a generally applicable basis, (2) rates and charges for or in connection with that service, and (3) all classifications, practices, rules, or regulations which in any manner affect or relate to the aforementioned service, rates, and charges.”).

PDF page 4

4
capacity market, with its sole, self-identifying purpose as being to “set[] forth the terms and conditions governing the Reliability Pricing Model for the PJM Region.”10

The Commission has been clear that the purpose of a PJM Governing Agreement is an
important consideration in determining where particular provisions belong within the PJM Governing Agreements.  As relevant here, the Commission has consistently found that rules that “predominantly” affect the rights and responsibilities of the RTO and the Transmission Owners are appropriately included in the applicable Transmission Owner agreement (and in the case of PJM specifically, in the CTOA).11  Proposed  Section 18.7 predominately affects the rights and responsibilities of the PJM Transmission Owners and PJM.  Indeed, the

provision imposes new obligations solely on the PJM Transmission Owners while
correspondingly relieving PJM of any responsibilities associated with those commitments. The text of proposed Section 18.7 confirms this conclusion:

18.7 Exiting Transmission Owner RBP Obligations
In
the
event
a
Transmission
Owner
exits
PJM
Interconnection, L.L.C. and the quantity of load with the
Transmission Owner is commensurate with the RBP Resources
that are located in that Transmission Owner’s territory, the
Transmission Owner shall honor the remaining term of the
RBP commitment.
(a) Exiting Transmission Owner with Committed RBP
Resources

10 PJM Tariff, Attachment DD, Section 1.
11 See, e.g., Duquesne Light Co., 189 FERC ¶ 61,181 at P 55 (2024) (“The Commission has previously distinguished provisions that ‘affect only (or predominantly) the rights and responsibilities’ of the RTO and transmission owners, which may appropriately be included in transmission owner agreements, and substantive interconnection and transmission procedures that are more appropriately housed in other governing documents.”); Order on Reh’g, 192 FERC ¶ 61,051 at P 73 (2025) (“Unlike the Overlap Provisions, the provisions that Indicated PJM TOs point to that are already included in the CTOA predominantly affect a PJM TO’s rights and responsibilities rather than substantive transmission planning procedures.”).  See also ISO New England Inc., 106 FERC ¶ 61,280 (2004) (“We find that with the exception of those provisions that affect only (or predominantly) the rights and responsibilities of RTO-NE and the Transmission Owners, i.e., Sections 6 and 7, Schedule 3.09(a) does not belong in the TOA . . .”).

PDF page 5

5
Any Transmission Owner seeking to exit PJM
Interconnection, L.L.C. may, prior to exiting PJM, enter into agreements that maintain appropriate rates, terms, and conditions that preserves the RBP commitments with the owners of RBP Resource(s) that have been committed through the Reliability Backstop Procurement that are located within the physical boundaries of the Transmission Owner’s Zone. PJM and PJM Settlement shall be relieved of any applicable RBP obligations made to RBP Resources that are subject to such agreements. In the event no such agreement is made and such RBP Resource(s) can be pseudo-tied into the PJM Region, the exiting Transmission Owner must, to the extent the Office of the Interconnection elects to retain such RBP Resource throughout the term of its RBP commitment, pay all costs for RBP Resources to pseudo-tie into the PJM Region so that such resource meets the external Capacity Resource eligibility requirements set forth in Tariff, Attachment DD, section 5.5A prior to the Transmission Owner exiting PJM Interconnection, L.L.C. Any Transmission Owner seeking to exit PJM Interconnection, L.L.C. with RBP Resource(s) that (i) are located within the physical boundaries of the Transmission Owner’s Zone and (ii) cannot be pseudo-tied into the PJM Region, and/or which the Office of the Interconnection elects not to retain the RBP Resource as a Capacity Resource throughout the term of its RBP commitment, shall pay costs associated with the remaining term of the RBP Resource, the amount which shall be determined through a filing submitted under the Federal Power Act, prior to exiting PJM Interconnection, L.L.C. Revenues collected in such an event shall be credited to Load Serving Entities that are allocated a share of the RBP Charges on a pro rata basis through the remaining term of the RBP commitment.

(b) Exiting Transmission Owner with Load Allocated RBP Charges

Any Transmission Owner seeking to exit PJM
Interconnection, L.L.C. with net load that has been allocated RBP Charges for RBP Resources not located within the physical boundaries of the Transmission Owner’s Zone may, prior to exiting PJM, enter into agreements that maintain appropriate rates, terms and conditions that preserves the RBP commitments with the owners of such RBP Resource(s). PJM and PJM

PDF page 6

6
Settlement shall be relieved of any applicable RBP
obligations made to RBP Resources that are subject to
such agreements. In the event no such agreement is made,
the exiting Transmission Owner must pay all forward
obligations on an accelerated basis, the amount which
shall be determined through a filing submitted under the
Federal Power Act, prior to exiting PJM Interconnection,
L.L.C. Any such revenues collected shall be distributed to
the RBP Resources under the standard daily RBP settlement
schedule to such resources through the remaining term of
the RBP commitment.

Rules regarding the residual commitments and obligations of PJM Transmission Owners after withdrawal are appropriately addressed in the CTOA.  Indeed, the CTOA already contains provisions governing such obligations.  Section 3.4 of the CTOA is titled “Obligations After Withdrawal:”

3.4 Obligations After Withdrawal, Transfer, or Assignment.
Any Party that withdraws from, transfers, or assigns this
Agreement in accordance with Sections 3.2 or 3.3 hereof, shall
remain liable for any and all obligations under this Agreement
that such Party incurred, that were incurred on behalf such
Party, or that arose hereunder prior to the date upon which
such Party’s withdrawal, transfer, or assignment became
effective. Withdrawal from, transfer, or assignment of this
Agreement shall not relieve such Party of any of its
indemnification or liability obligations pursuant to Article 9
hereof for any events occurring prior to the time that its
withdrawal from this Agreement became effective.

As evidenced by Section 3.4, a PJM Transmission Owner’s obligations after withdrawal were specifically contemplated, negotiated, and agreed to by PJM and the PJM Transmission Owners as part of the CTOA.  Moreover, the scope of these agreed-upon obligations consists of “any and all obligations under this Agreement that such Party incurred, that were incurred on behalf [of] such Party, or that arose hereunder prior to the date upon which such Party’s

PDF page 7

7
withdrawal, transfer, or assignment became effective.”12  Rather than addressing Transmission Owner withdrawal obligations through the CTOA, proposed Section 18.7 would create

additional withdrawal-related obligations via the PJM Tariff.  The Commission has repeatedly emphasized the importance of locating provisions within the Governing Agreements that correspond to the rights and obligations at issue, and PJM’s proposal is inconsistent with that approach.13

B. The TO Exit Provisions Raise Standards of Conduct Concerns, Allocate
Responsibility for Capacity Commitments in a Manner That Warrants Further
Scrutiny, and Do Not Account for Differences Among Transmission Owners.
By their terms, the TO Exit Provisions apply to “any Transmission Owner seeking to
exit PJM,” (emphasis added) and, as described above in Section II.A, seek to impose residual commitments on “any” exiting Transmission Owner that are predicated on the continuing obligation of an exiting Transmission Owner to serve load within its service territory.14 There are (at least) two significant flaws with this proposal.  First, the proposal ignores the functional separation that must exist within a Transmission Owner’s organization.  For those Transmission Owners that will also own RBP Resources, it is unclear how compliance with the TO Exit Provisions could be effectuated in the absence of intimate coordination

12 CTOA, Section 3.4.
13 See supra note 11.
14 RBP Filing at 91-92 (“If a Transmission Owner leaves PJM and the load taken with the Transmission Owner is commensurate with the RBP Resources that are located in that Transmission Owner’s territory, the Transmission Owner is expected to honor the remaining term of the RBP commitment since it would need such resources to serve the loads in its service territory. However, in the event a Transmission Owner exits PJM and committed RBP Resources are physically in such Transmission Owner’s service territory, it would be unreasonable for PJM’s Members to continue paying for such excess RBP Resources if they no longer can provide capacity to PJM (e.g., if the resource cannot be pseudo-tied into PJM as further explained below). Similarly, in the event a Transmission Owner exits PJM with the net load that is removed with the Transmission Owner’s departure, it would be unreasonable for PJM’s remaining load to pay for the excess committed RBP Resources that remain in the PJM Region. To address these potential scenarios, proposed Tariff, Attachment DD, sections 18.7(a) and 18.7(b) put committed RBP Resources back in the same position they would have been in had the associated Transmission Owner not exited PJM.”).

PDF page 8

8
between the organization’s transmission business and generation/marketing business. Specifically, the TO Exit Provisions require that the Transmission Owner enter into agreements “that maintain appropriate rates, terms, and conditions that preserve[] the RBP commitments with the owners of the RBP Resources,” or else pay “all costs for RBP Resources to pseudo- tie,” and “pay costs associated with the remaining term of the RBP Resource.”  Yet such contemplated coordination ignores the functional separation that Transmission Owners are required to adhere to under the Commission’s Standards of Conduct,15 whereby the transmission function employees of a transmission-owning public utility must operate independently of the marketing function employees.

Second, not all Transmission Owners under the CTOA are Load Serving Entities that have executed the RAA.  These terms are separate and distinct, with unique rights and obligations arising from their respective Governing Agreements.  The reason why PJM in the RBP Filing submitted extensive revisions to the RAA in order to effectuate the Reliability Backstop Procurement is because the RAA is the contract through which each signatory explicitly stipulates that it “is a Load Serving Entity within the PJM Region,” and is “committing to share its Capacity Resources with the other Parties to reduce the overall reserve requirements for the Parties while maintaining reliable service.”16  It makes sense then that among PJM’s Governing Agreements, the RAA would be a reasonable place to impose obligations on Load Serving Entities and allocate costs.  Yet not all PJM Transmission Owners are signatories to the RAA, nor are all PJM Transmission Owners Load Serving Entities.17  It

15 18 C.F.R. Part 358.
16 RAA at Recitals.
17 CTOA signatories that are not Load Serving Entities include Essential Power Rock Springs, LLC, Neptune Regional Transmission System, LLC, Linden VFT, LLC, Hudson Transmission Partners, LLC, NextEra Energy Transmission MidAtlantic Indiana, Inc., and Silver Run Electric, LLC.

PDF page 9

9
is thus unclear how the TO Exit Provisions would apply to every Transmission Owner seeking to exit PJM, because the proposal does not account for the distinction between Transmission Owners that are RAA signatories and those that are not.

C. The TO Exit Provisions Address a Contingency That PJM Acknowledges Is
Remote and Would Unnecessarily Constrain Future Decision-Making.
PJM acknowledges that “no Transmission Owner has formally sought to exit PJM at
this time.”18  PJM nevertheless argues that “however remote the possibility of a Transmission Owner exiting PJM during or prior to the 2042/2043 Delivery Year, it is imperative that rules are in place to ensure that, even in the event of a Transmission Owner exit, committed RBP Resources will be made whole for the entire term of the commitment.”19  Yet this argument overlooks the fact that CTOA, Section 3.2 already requires several steps, including

Commission authorization, that must be taken to effectuate a Transmission Owner’s
withdrawal from PJM,20 and as a practical matter, any such withdrawal would, by necessity, involve significant negotiations that account for the unique facts and circumstances present at that time.  Just as a Transmission Owner’s integration into PJM necessitates careful

18 RBP Filing at 90.
19 Id. at 91.
20 CTOA, Section 3.2 (“Any Party may withdraw from this Agreement upon ninety (90) days advance written notice to PJM and the other Parties; provided that such withdrawal shall not be effective until the withdrawing Party has: (i) if its Transmission Facilities do not comprise an entire Control Area, satisfied all applicable standards of NERC and the Applicable Regional Reliability Council for operating a Control Area or being included within an existing Control Area; (ii) put in place alternative arrangements for satisfaction of the FERC’s requirements with respect to comparable transmission services; and (iii) made a filing with the FERC under Section 205 of the Federal Power Act to withdraw from this Agreement, and such filing has been approved, accepted without suspension, or if suspended, the suspension period has expired before the FERC has issued an order on the merits of the filing. Notwithstanding the forgoing, a Zero Revenue Requirement Party may withdraw from this Agreement in the particular circumstance of permanent removal of its owned Transmission Facilities from service, provided that such Party has: (a) provided written notice to PJM and the parties to the Operating Agreement at least twelve months in advance of the intended date of retirement of its owned Transmission Facilities, and (b) complied with all reasonable requirements of PJM for restoration, to the maximum extent reasonably attainable, of the PJM Transmission System to the same configuration and operational capability that existed prior to such Party's installation of its owned Transmission Facilities.”).

PDF page 10

10
deliberation, communication with and approval by state regulatory authorities, bilateral negotiations, an “integration agreement,” and Commission approval,21 a Transmission Owner’s exit would correspondingly necessitate a similar process.  Proposed Section 18.7 would unnecessarily constrain the parties involved in that process, including the Commission and state regulatory authorities, by preemptively mandating how the costs and contractual arrangements of generation resources and load within an exiting Transmission Owner’s zone must be treated.  To the extent that future facts and circumstances would lead the Commission or applicable state regulatory authorities to favor a different set of obligations and requirements on generation resources and load within an exiting Transmission Owner’s zone, an FPA section 206 action would be required to modify the rules codified in the PJM Tariff.  The Commission and state regulatory authorities need not address this issue preemptively, particularly given the absence of any pending withdrawal requests and PJM’s own acknowledgement that the possibility of this contingency is “remote.”22

D. The Vagueness of PJM’s Transmission Owner Exit Provisions Violates FPA
Section 205(c) and the Commission’s Implementing Regulations.
The Commission’s regulations implementing FPA section 205(c) are unambiguous— clarity and specificity are required when rates and charges are filed with the Commission. Every public utility shall file with the Commission and post, in

conformity with the requirements of this part, full and complete
rate schedules and tariffs and those service agreements not
meeting the requirements of § 35.1(g), clearly and specifically
setting forth all rates and charges for any transmission or sale
of electric energy subject to the jurisdiction of this
Commission, the classifications, practices, rules and regulations

21 A recent illustration of this process is available in Docket No. ER18-459, which involves the integration of Ohio Valley Electric Corporation (“OVEC”).
22 RBP Filing at 91 (“Therefore, however remote the possibility of a Transmission Owner exiting PJM during or prior to the 2042/2043 Delivery Year, it is imperative that rules are in place to ensure that, even in the event of a Transmission Owner exit, committed RBP Resources will be made whole for the entire term of the commitment.”).

PDF page 11

11
affecting such rates, charges, classifications, services, rules,
regulations or practices, as required by section 205(c) of the
Federal Power Act (49 Stat. 851; 16 U.S.C. 824d(c)).23
The Commission has explained that an RTO has “[an] obligation to set forth its Commission- jurisdictional rates clearly and specifically in its tariff.”24  The need to set forth rates and charges “clearly and specifically” is essential for the Commission’s own FPA section 205(c) analysis, as “[a] minimum level of specificity within the tariff is necessary for the Commission to determine whether the charges that result are just and reasonable.”25  It is also important in fulfilling the fundamental purpose of FPA section 205(c) to provide notice to customers, as the requirement “allows [] customers the opportunity to assess for themselves whether they were properly charged.”26

The TO Exit Provisions in proposed Section 18.17 fall short of this statutory requirement and the Commission’s implementing regulations in 18 C.F.R. 35.1(a).  For example, under the proposed language, a PJM Transmission Owner is required to pay “all costs for RBP Resources to pseudo-tie into the PJM Region.”  The proposal does not define what constitutes “all costs” or identify a limiting principle for determining when those costs have been paid, creating uncertainty regarding a Transmission Owner’s obligations under the provision.

Similar questions arise with respect to the requirements that a Transmission Owner “pay costs associated with the remaining term of the RBP Resource” and “pay all forward obligations on an accelerated basis.”  While PJM’s proposed language for these requirements

23 18 C.F.R. § 35.1(a) (emphasis added).
24 Cal. Indep. Sys. Operator Corp., 112 FERC ¶ 61,009 at P 114 (2005).
25 Id.
26 Id.

PDF page 12

12
stipulates that the exact amount of these payments “shall be determined through a filing submitted under the Federal Power Act,” it is entirely unclear who (PJM, the RBP Resource, or the PJM Transmission Owner) would submit this filing, or what value the filing entity, whoever it is, would actually request the Commission’s approval for.

Accordingly, PJM’s proposed Section 18.7 does not “clearly and specifically” set forth the rates and charges that are to be imposed on an exiting Transmission Owner, and fails to satisfy the requirements of FPA section 205(c) and the Commission’s implementing regulations.  At a minimum, the Commission cannot determine whether these charges are just and reasonable where the proposal fails to identify the scope of the obligations being imposed or the methodology by which they would be calculated.

III. REQUEST FOR CLARIFICATION
PPL Electric requests that PJM provide additional clarity in its responsive pleading regarding its approach to a specific credit collateral contingency.  In the event that PJM does not provide the requested clarity, PPL Electric respectfully requests that the Commission articulate its expectations regarding this contingency, and provide any additional guidance it deems appropriate.

Regarding the collateral requirements for Load Serving Entities, PJM states that “[b]uyers of RBP UCAP MW, i.e., LSEs that have been allocated cost responsibility for RBP Charges . . . will be required to post RBP Collateral to mitigate the risk of potential defaults from non-payment of RBP Charges, while those LSEs not allocated cost responsibility generally will not have any credit requirement.”27   To this end, PJM explains that “the RPM

27 RBP Filing at 111.

PDF page 13

13
credit requirement will be based on the level of RBP UCAP MW for which an LSE is allocated cost responsibility.”28

However, PJM then explains that “for LSEs serving load in an Electric Distributor zone/area in which no RBOs have been reported, an LSE’s ‘allocated RBP UCAP MW shall equal the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for the zone/area as determined in RAA, Schedule 8.’”29  PPL Electric understands that if there are no RBOs reported to PJM for a zone with RBP UCAP MW assigned, or if there are “stranded” RBOs (because of how state or local regulatory authorities determine they should be assigned) then the credit requirements will move to all Load Serving Entities in a zone based on Peak Load Contributions reported to PJM.  Presumably, once credit requirements are assigned based on Peak Load Contributions, RBP charges will also flow to those Load Serving Entities for that Delivery Year, and possibly beyond.

PPL Electric is concerned that this scenario could result in LSEs that do not serve large loads receiving these obligations, thereby having nowhere to assign them except to other (non- large load) customers.  This seems inconsistent with the Ratepayer Protection Pledge.30    PPL Electric requests that PJM provide guidance on what would happen if the additional Load Serving Entities in the zone are unable to post collateral and default under this contingency.

IV. CONCLUSION
Wherefore, for the foregoing reasons, PPL Electric respectfully requests that the Commission grant PPL Electric’s timely intervention in this proceeding and accept this

28 Id. at 118. 29 Id.
30 Ratepayer Protection Pledge, The White House (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ (“Ratepayer Protection Pledge”).

PDF page 14

14
Limited Protest into the record.  PPL Electric also requests that PJM provide additional clarity in its responsive pleading regarding its approach to the specific credit collateral contingency outlined above, and if PJM does not, that the Commission articulate its expectations regarding this contingency, and provide any additional guidance it deems appropriate.

Respectfully submitted,

Steven Nadel
Senior Counsel
PPL Services Corporation
645 Hamilton Street, Suite 601
Allentown, PA 18101
Tel: (610) 774-4102
SMNadel@pplweb.com
/s/ Thomas DeVita
Thomas S. DeVita
Kimberly B. Frank
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202.778.9064
kimberly.frank@klgates.com
thomas.devita@klgates.com

Counsel for PPL Electric
Dated: August 21, 2026

PDF page 15

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Respectfully submitted,
/s/ Stuart Robbins
K&L Gates LLP
1601 K Street, N.W.
Washington, DC 20006
Tel: 202-778-9148
stuart.robbins@klgates.com

Dated: August 21, 2026