ER26-3380-000 · 2026-08-21 · PPL Electric Utilities Corporation

Motion to Intervene, Limited Protest, and Request for Clarification of PPL Electric Utilities Corporation

Text extracted from the eLibrary original (SHA-256 0589c1aa3be8a3e6…). Download the original from the official source.

Contents · 8 sections
  1. I. MOTION TO INTERVENE p. 2
  2. II. LIMITED PROTEST p. 3
  3. A. The TO Exit Provisions Concern Transmission Owner Rights and Obligations p. 3
  4. B. The TO Exit Provisions Raise Standards of Conduct Concerns, Allocate p. 7
  5. C. The TO Exit Provisions Address a Contingency That PJM Acknowledges Is p. 9
  6. D. The Vagueness of PJM’s Transmission Owner Exit Provisions Violates FPA p. 10
  7. III. REQUEST FOR CLARIFICATION p. 12
  8. IV. CONCLUSION p. 13

Read topic-matched comments in ER26-3380

Topics in the text: Credit and exit · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Credit and exit

Additionally, PPL Electric requests clarification on a specific credit collateral contingency, as discussed below in Section III.
Read this passage Filed comments: Credit and exit

I. MOTION TO INTERVENE

printed heading · Topic match: Reliability and curtailment

Terms not otherwise defined herein shall have the same meaning as set forth in the RAA, the Open Access Transmission Tariff (“Tariff”), and the Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”). 3 RBP—a one-time procurement of new capacity to address…
Read this passage Filed comments: Reliability and curtailment

II. LIMITED PROTEST

printed heading

LIMITED PROTEST The Commission should reject the TO Exit Provisions for the reasons discussed below in subsections II.A–D.
Read this passage

A. The TO Exit Provisions Concern Transmission Owner Rights and Obligations

printed heading · Topic match: Cost allocation

Revenues collected in such an event shall be credited to Load Serving Entities that are allocated a share of the RBP Charges on a pro rata basis through the remaining term of the RBP commitment. (b) Exiting Transmission Owner with Load Allocated RBP Charges Any Transmission Owner seeking to exit…
Read this passage Filed comments: Cost allocation

B. The TO Exit Provisions Raise Standards of Conduct Concerns, Allocate

printed heading

First, the proposal ignores the functional separation that must exist within a Transmission Owner’s organization.
Read this passage

C. The TO Exit Provisions Address a Contingency That PJM Acknowledges Is

printed heading

Proposed Section 18.7 would unnecessarily constrain the parties involved in that process, including the Commission and state regulatory authorities, by preemptively mandating how the costs and contractual arrangements of generation resources and load within an exiting Transmission Owner’s zone must…
Read this passage

D. The Vagueness of PJM’s Transmission Owner Exit Provisions Violates FPA

printed heading

Every public utility shall file with the Commission and post, in conformity with the requirements of this part, full and complete rate schedules and tariffs and those service agreements not meeting the requirements of § 35.1(g), clearly and specifically setting forth all rates and charges for any…
Read this passage

III. REQUEST FOR CLARIFICATION

printed heading · Topic match: Credit and exit

Regarding the collateral requirements for Load Serving Entities, PJM states that “[b]uyers of RBP UCAP MW, i.e., LSEs that have been allocated cost responsibility for RBP Charges . . . will be required to post RBP Collateral to mitigate the risk of potential defaults from non-payment of RBP…
Read this passage Filed comments: Credit and exit

IV. CONCLUSION

printed heading · Topic match: Cost allocation

CONCLUSION Wherefore, for the foregoing reasons, PPL Electric respectfully requests that the Commission grant PPL Electric’s timely intervention in this proceeding and accept this 28 Id. at 118. 29 Id. 30 Ratepayer Protection Pledge, The White House (Mar. 4, 2026),…
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Washington, DC 20006 Tel: 202-778-9148 stuart.robbins@klgates.com Dated: August 21, 2026