ER26-3380-000 · 2026-09-02 · Kentucky Attorney General

Motion for Leave to Answer and Answer of the Attorney General of the Commonwealth of Kentucky to the comments and protests of PJM Interconnections, L.L.C.’s…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.

Docket No. ER26-3380-000

MOTION FOR LEAVE TO ANSWER,
AND ANSWER, OF
THE ATTORNEY GENERAL OF THE COMMONWEALTH OF KENTUCKY

Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213 (2025),1 the Attorney General of the Commonwealth of Kentucky (“Kentucky Attorney General” or “Attorney General”)2 hereby moves for leave to answer, and answers, comments on and protests of the July 31, 2026 filing by PJM Interconnection, L.L.C. (“PJM”) in this proceeding.3

I. MOTION FOR LEAVE TO ANSWER
Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure generally prohibits answers to protests and other pleadings unless otherwise ordered by the decisional authority. The Kentucky Attorney General is authorized by statute to represent the interests of ratepayers in the Commonwealth of Kentucky and through this Answer offers its comments on the comments on and protests of the PJM Reliability Backstop Procurement (“RBP”) Filing.4 Good cause justifies the Commission’s granting this motion and accepting this Answer because the Answer provides

1 18 C.F.R. §§ 385.212 and 385.213 (2026).
2 The Kentucky Attorney General submitted a timely, doc-less motion to intervene in this proceeding on August 6, 2026.
3 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026) (“PJM RBP Filing”).
4 KRS 367.150(8).

PDF page 2

2
information that may assist the Commission in its decision-making process and ensures a complete record.5 For these reasons, the Commission should accept this Answer.

II. COMMENTS
On August 21, 2026, East Kentucky Power Cooperative, LLC (“EKPC”) filed a protest in this docket. EKPC’s protest states several important concerns related to the RBP proposed by PJM.6 The Attorney General is equally concerned that steps should be taken to ensure that ratepayers are protected from the potential unjust and unreasonable cost allocation that could occur under the proposal.

Of particular concern is whether Load Serving Entities who have met their obligations are protected from cost allocation in the event of default by the cost causer.  As detailed on pages 11, et seq, of the EKPC protest and in the Testimony of Adam Bednarczyk, the potential appears to exist for inappropriate cost shifting in the instance of default by responsible entities.  This potential is exacerbated by the lack of protection for Reliability Pricing Model entities who have prudently planned to fully serve their load. Under the RBP proposal, it does not appear that PJM appropriately decrements the target, or otherwise provides sufficient offsets, for utilities who have already taken appropriate actions to serve their load.7

In general, the Kentucky Attorney General is concerned with the potential for others to free ride on the prudent resource adequacy decisions made by Load Serving Entities in Kentucky.  By allocating these costs unjustly, Kentucky utilities who have steel in the ground to serve their load

5 See, e.g., Southwest Power Pool, Inc., 190 FERC ¶ 61,018 at P 18 (2025) (accepting answers to protests and answers because they provided information that assisted the Commission in its decision-making process); PJM Interconnection, L.L.C., 189 FERC ¶ 61,110 at P 22 (2024) (accepting answers to protests and answers because they assisted the Commission in its decision-making process); Potomac-Appalachian Transmission Highline, LLC, 140 FERC ¶ 61,229 at P 102 (2012) (accepting answer to an answer because it provided material evidence that corrected the record and informed the Commission’s decision-making process).
6 See Protest of East Kentucky Power, Inc. filed August 21, 2026.
7 Id. at 13-14, 28, et seq.

PDF page 3

3
could effectively be required to fund redundant resources from which they do not earn an additional reliability benefit. These concerns are particularly striking given that these costs could continue to compound over the 15-year term of the agreement, resulting in large potential penalties to utilities who have planned their systems prudently. Thus, great effort should be made to ensure that ratepayers are protected from unjust and unreasonable cost shifting that could occur pursuant to the foreseeable consequences of PJM’s RBP proposal. Importantly, doing otherwise would run afoul of the President’s Ratepayer Protection Pledge, which prohibits such cost shifting.8 FERC simply must not allow the RBP to proceed unless reasonable assurance is provided that Kentucky ratepayers will be held harmless from the costs caused by others, whether those costs are driven by usage or insufficient planning.

RUSSELL COLEMAN
ATTORNEY GENERAL

/s/ J. Michael West
J. MICHAEL WEST
T. TOLAND LACY
ASSISTANT ATTORNEYS GENERAL
1024 CAPITAL CENTER DRIVE SUITE 200
FRANKFORT, KY 40601-8204
PHONE: (502) 696-5433
FAX: (502) 573-1005
Michael.West@ky.gov

Thomas.Lacy@ky.gov

8 Ratepayer Protection Pledge, https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/, March 4, 2026.