Comments of Old Dominion Electric Cooperative re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement filing
Text extracted from the eLibrary original (SHA-256 490090c36f58dd0a…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Credit and exit · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
I. INTRODUCTION
printed heading · Topic match: Cost allocation
The proposed RBP would procure capacity needed to meet the reliability requirement shortfall for the 2028/2029 Delivery Year, to the extent new loads coming online in the 2027/2028 or 2028/2029 Delivery Years do not voluntarily procure sufficient new capacity to address the shortfall or otherwise…Read this passage Filed comments: Cost allocation
II. COMMENTS
printed heading
II.Read this passage
A. The subscription model better aligns procurement obligations with cost-causation
printed heading · Topic match: Credit and exit
LSEs will bear the cost of RBP Collateral – which must be in the form of cash or a letter of credit deemed acceptable to PJM or PJMSettlement – that is in addition to and separate from collateral they already must post for the RPM auctions and bilateral transactions.Read this passage Filed comments: Credit and exit
B. The Commission should direct PJM to revise its Opt-Out or at the very least
printed heading · Topic match: Cost allocation
Such request by the Electric Distributor shall specify the associated MW quantity of load in the zone/area that will be opted-out of the Initial RBP Target and be accompanied by supporting documentation demonstrating an inability to address cost allocation associated with capacity procured in the…Read this passage Filed comments: Cost allocation
C. PJM should resolve an inconsistency in its filing.
printed heading · Topic match: Cost allocation
PJM states in its transmittal letter that if an LSE defaults and fails to pay an RBP Charge, “PJM will allocate the defaulted amount to all remaining LSEs that have been assigned responsibility for RBP Charges in the Electric Distributor zone/area based on each LSE’s pro-rata share of the total RBP…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading · Topic match: Credit and exit
CONCLUSION WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider these comments in its determination of the PJM RBP proposal and if the Commission accepts the filing, require PJM to submit a compliance filing to (1) adopt the “subscription model” proposed by Joint EDCs…Read this passage Filed comments: Credit and exit
CERTIFICATE OF SERVICE
printed heading
Clair 1 Joint EDCs & Data Center Coalition (“Coalition”) Reliability Backstop Procurement PackageRead this passage
Executive Summary
printed heading · Topic match: Credit and exit
LL LSE Registry To establish the procurement target, the Coalition proposes the creation of a Large Load Registry, maintained by PJM, through which either the Large Load or its designated LSE would report: • The MW quantity of Large Load assigned to a specific LSE (or assigned directly to the Large…Read this passage Filed comments: Credit and exit