ER26-3380-000 · 2026-08-21 · Solar Energy Industries Association

Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3380-000
COMMENTS OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION
Pursuant to Rule 213 of the Federal Energy Regulatory Commission’s (“Commission”)
Rules of Practice and Procedure,1 the Solar Energy Industries Association (“SEIA”)2 hereby submits these comments in response to PJM Interconnection, L.L.C.’s (“PJM”) filing proposing a Reliability Backstop Procurement (“RBP Proposal”). PJM filed the RBP Proposal pursuant to Section 205 of the Federal Power Act (“FPA”),3 proposing revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a one-time procurement mechanism to address resource adequacy shortfalls in the PJM Region.4 As set forth below, SEIA does not oppose the RBP Proposal and submits these comments to identify targeted areas where the Commission and PJM may wish to consider refinements that could further unlock capacity participation and reduce procurement costs.

1 18 C.F.R. § 385.213 (2026).
2 SEIA is the national trade association of the solar energy industry. As the voice of the industry, SEIA works to support solar as it becomes a mainstream and significant energy source by expanding markets, reducing costs, increasing reliability, removing market barriers, and providing education on the benefits of solar energy. The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar industry, but do not necessarily reflect the views of any particular member with respect to any issue.
3 16 U.S.C. § 824d (2024).
4 Capitalized terms not defined herein have the same meaning as in the PJM Tariff, RAA or the RBP Proposal, as applicable.

PDF page 2

2
I. INTRODUCTION
SEIA does not oppose PJM’s RBP Proposal as a necessary and timely response to the resource adequacy challenges facing the PJM Region. The recent Base Residual Auctions (“BRAs”) for the 2027/2028 and 2028/2029 Delivery Years each cleared 5.6% below the PJM Region Installed Reserve Margin of 20%,5 driven primarily by unprecedented additions of large loads—particularly data centers—that have outpaced supply additions. PJM’s proposal to conduct a one-time backstop procurement to secure approximately 6,831.3 MW of Unforced Capacity (“UCAP”) is a reasonable mechanism to address this shortfall, particularly given the immense pressure from states, governors, and the White House for PJM to act expeditiously.6 Indeed, the RBP Proposal represents a measured approach to address a serious reliability concern. PJM has designed the procurement initiative to balance urgency with market principles— including a pay-as-bid structure,7 a bilateral contracting offset mechanism,8 and a Contract for Difference (“CfD”) settlement approach that mitigates ratepayer costs. While SEIA commends PJM for bringing this proposal forward under extraordinary time constraints, SEIA respectfully offers the following comments to identify areas where the Commission and PJM may wish to consider refinements that could further unlock capacity participation and reduce procurement costs—both in connection with the RBP and, where applicable, in the broader capacity market reforms that PJM and the Commission may undertake in subsequent proceedings. 5 See RBP Proposal at 124 (explaining that the 2027/2028 and 2028/2029 Base Residual Auctions each cleared 5.6% below the PJM Region Installed Reserve Margin of 20%).

6 See Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), available at: https://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ Principles”) (calling for a backstop auction no later than September 2026).
7 See RBP Proposal at 65–67 (proposing a pay-as-bid clearing structure for the RBP).
8 See id. at 35–42 (describing the Qualifying RBP Offset UCAP MW mechanism by which bilateral contracts reduce the procurement target).

PDF page 3

3
II. COMMENTS
A. ELCC Uncertainty and Commercial Operation Date Requirements May
Limit Timely Capacity Participation.
The RBP Proposal requires successful resources to commit to a fixed period of 15 Delivery Years beginning with the 2028/2029 Delivery Year9 and to achieve commercial operation (“COD”) by no later than June 1, 2032. While SEIA does not oppose the 15-year term or the COD requirement, it identifies two concerns with how these parameters interact with existing capacity market rules in ways that may limit participation and increase procurement costs. First, there is a temporal mismatch: the RBP is designed to address a shortfall beginning in the 2028/2029 Delivery Year, yet resources are not required to achieve COD until June 1, 2032. SEIA notes that PJM’s proposed clearing structure10 partially addresses this concern by ranking offers first by the earliest Delivery Year in which capacity would be available and then by least cost—thereby prioritizing resources that can deliver capacity sooner. However, the COD deadline itself warrants further attention, as discussed below.11

Second, the 15-year commitment exposes resources to long-duration ELCC variability that is difficult or impossible for an individual resource to underwrite—a challenge that exists independent of PJM’s clearing structure and that may deter participation from resources that could otherwise contribute to meeting the reliability need.

While PJM captures ELCC decline in its published 10-year forecast, PJM has not published a forecast out to 15 years.12 An individual RBP resource cannot control, predict, or hedge its ELCC

9 See RBP Proposal at 34.
10 See Proposed Tariff, Attachment DD, section 18.5(f)(ii) (providing that RBP Sell Offers shall be selected “in rank order from earliest to latest offered Delivery Year, and then in least-cost order based on the levelized cost ($/MW- day) of UCAP MW over the fixed 15-year term, until the Final RBP Target is satisfied”).
11 See id. at 39.
12 See PJM Interconnection, L.L.C., Preliminary ELCC Class Ratings for Period 2026/2027 Through 2034/2035, available at: https://www.pjm.com/-/media/DotCom/planning/res-adeq/elcc/preliminary-elcc-class-ratings-for- period-2026-2027-through-2034-2035.ashx.

PDF page 4

4
accreditation 10 to 15 years into the future. The result is that rational developers will either embed a disproportionate risk premium in their bids or decline to participate.13 SEIA supports the concept of a fixed-for-floating ELCC mechanism—whereby a resource’s RBP contract volume would be set based on PJM’s published ELCC forecast at the time of commitment, while year-over-year variance between the forecast and actual ELCC flows into RPM settlement, where such variability already manifests annually for all resources. This approach would decouple the developer’s long- term revenue certainty from uncontrollable ELCC fluctuations, yielding lower, more competitive bid prices.14

Turning to the COD requirement, the June 1, 2032 deadline is too late to address the immediate shortfall PJM faces. The 2028/2029 BRA cleared 6,831.3 MW short of the PJM Region Reliability Requirement.15 PJM should not have to wait four years for generation to come online. Solar, energy storage, and demand response resources—which have the shortest construction timelines of any asset class—are the marginal resources of capacity during this period and can deliver timely UCAP. At the same time, because PJM’s transmission expansion planning process addresses deliverability needs reactively—identifying and constructing network upgrades only after capacity has been committed—larger resources that require significant network upgrades to become deliverable may not achieve full deliverability by June 1, 2032. This is particularly true given documented network upgrade construction timelines of three to five years or more in the

13See REV Renewables, LS Power, Middle River Power & Geronimo Power, PJM Reliability Backstop Procurement Design — Executive Summary, at 2 (June 30, 2026), available at: https://www.pjm.com/-/media/DotCom/committees- groups/cifp-rbp/2026/20260630/20260630-item-02k---rev-renewables--ls-power---mrp---geronimo---rbp--- executive-summary.pdf.
14See id. (explaining that an individual RBP resource cannot control, predict, or hedge its ELCC accreditation 10 to
15 years into the future, and that unhedgeable long-duration ELCC uncertainty will command a risk premium above expected loss); see also MN8 Energy, Feedback on Select RBP Design Components, at 3 (June 11, 2026), available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04d---mn8- energy-presentation.pdf (proposing a fixed-for-floating class ELCC mechanism and noting that today’s project financing environment necessitates conservative views on capacity attributes, which is reflected in higher bid prices). 15 See RBP Proposal at 7.

PDF page 5

5
PJM region. PJM itself publicly acknowledged in a January 2026 stakeholder meeting that
significant new capacity additions are unlikely to come online before 2032 due to, among other factors, transmission constraints.16 While the COD requirement cannot account for all real-world issues,17 this limitation should be considered in evaluating the effectiveness of the RBP. SEIA therefore urges PJM to prioritize timely UCAP and to ensure that resources capable of delivering capacity sooner are appropriately valued.

In light of these challenges, SEIA encourages the Commission and PJM to provide greater
capacity certainty to all resources to maximize participation in the RBP. This includes stability in ELCC accreditation values and broader capacity market reforms that would give prospective participants confidence in projecting their obligations and revenues over the commitment period. The RFI administered by Charles River Associates identified over 100 GW of prospective supply interested in participating;18 ensuring that market rules support—rather than discourage—this participation is essential to achieving the lowest possible procurement costs for ratepayers. Accordingly, SEIA recommends that PJM and the Commission address ELCC accreditation

uncertainty and prioritize timely UCAP delivery—both of which would expand the pool of
competitive offers and reduce procurement costs for ratepayers.
16 See Devin Leith-Yessian, Government-Proposed “Backstop” Auction to Test PJM Stakeholder Process, RTO INSIDER (Jan. 26, 2026), available at: https://www.rtoinsider.com/124178-government-proposed-backstop-auction- test-pjm-stakeholder-process/ (“Even with a backstop auction, [David] Mills [PJM board chair and interim CEO] said there are significant barriers to getting new resources built, including transmission upgrades, financing, tariffs, siting, permitting and supply chain constraints. Significant new capacity is unlikely to be available until 2032.”).
17 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,197, at P 43 (2026); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, at P 157 (2025).
18 See RBP Proposal at 68 (noting the RFI administered by Charles River Associates identified over 100 GW of prospective supply interested in participating); see also PJM Reliability Backstop RFI Summary, Charles River Associates, at 5 (May 27, 2026), available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260527/20260527-informational-only---reliability-backstop-rfi-summary---charles-river-associates.pdf (reporting 397 potential supply-side projects by 87 entities, representing approximately 136 GW in total potential capacity).

PDF page 6

6
B. The Compressed Timeline for Bilateral Contracting May Result in Higher
Procurement Costs.
The compressed timeline for the RBP procurement window may limit bilateral contracting opportunities and result in unnecessarily higher auction clearing prices. While SEIA does not oppose the RBP Proposal in principle, it notes that without sufficient time for load-serving entities and prospective suppliers to negotiate bilateral contracts, the Qualifying RBP Offset mechanism may not achieve its intended effect of reducing the procurement target. PJM is targeting commencement of the procurement window on September 30, 2026, with a three-week offer submission window and clearing concluding six weeks thereafter.19

Indeed, the RBP Proposal appropriately incorporates a mechanism by which bilateral contracts and self-supply arrangements for new capacity serving new load reduce the Initial RBP Target through the Qualifying RBP Offset. In theory, this mechanism should exert downward pressure on auction prices by reducing the quantity of capacity that must be procured through the competitive auction process.20 However, SEIA is concerned that the accelerated timeline from PJM Board approval on July 27, 2026, to the anticipated September 30, 2026 procurement commencement may not provide sufficient opportunity for load-serving entities and prospective suppliers to negotiate and execute the bilateral contracts that would qualify as offsets. In turn, if the time available for bilateral contracting proves insufficient, fewer Qualifying RBP Offsets may be available to reduce the Final RBP Target, and the resulting auction may clear a larger volume of capacity at potentially higher prices than would otherwise be necessary. SEIA encourages the Commission and PJM to monitor the effectiveness of the bilateral contracting mechanism and to

19 See id. at 32, 48 (describing the offer submission window of three weeks, with clearing and selection concluding six weeks thereafter).
20 See id.

PDF page 7

7
consider adjustments if the compressed timeline proves insufficient to support meaningful bilateral engagement.

SEIA recognizes that PJM and the Commission are under immense pressure—including from the thirteen PJM-state governors and the National Energy Dominance Council, whose joint statement of principles21 urged expeditious action—for this procurement to proceed on an expedited basis, and that the fundamental timeline is unlikely to change. SEIA is lodging this concern into the record insofar as the current RBP may set precedent for future central procurements.

C. Recommendations for Unlocking Additional Capacity
In order to enable PJM to unlock additional capacity and reduce procurement costs, SEIA respectfully offers the following recommendations for the Commission’s and PJM’s consideration: First, PJM should offer a fixed-for-floating ELCC swap option for resources

participating in the RBP and for bilateral arrangements qualifying as RBP Offsets. Year-over- year volatility in ELCC accreditation values creates significant uncertainty for resources contemplating long-term commitments such as those required by the RBP. Stabilizing ELCC values—whether through longer averaging periods22 or other mechanisms—would give prospective participants greater confidence in projecting their capacity revenues over the 15-year commitment period and would thereby encourage broader participation. When a resource can reasonably forecast its accredited capacity value over the commitment term, it can underwrite financing and commit to a 15-year obligation with confidence that its revenues will support the investment. Absent such predictability, resources face the risk that declining ELCC values will

21 See NEDC/PJM Governors’ Principles at 1.
22 Cf. PJM Interconnection, L.L.C., 186 FERC ¶ 61,080 (2024) (accepting PJM’s transition from average to marginal ELCC methodology, reflecting the Commission’s ongoing consideration of ELCC approaches that balance accuracy with predictability).

PDF page 8

8
erode their revenue stream below the level needed to service project debt, deterring participation in the RBP altogether.

Second, the Commission should consider whether the minimum contract length for
bilateral arrangements under the RBP is sufficient to enable meaningful bilateral contracting.23 The minimum five-year contract requirement for bilateral arrangements24 qualifying as RBP Offsets may be insufficient to enable meaningful bilateral contracting. While parties are free to negotiate contracts of any length, the five-year minimum effectively sets a floor that, as a practical matter, is likely to define the standard term for bilateral arrangements under the RBP Proposal. Project economics and financing structures for new capacity resources typically require a commitment term closer to ten years to justify the capital investment and development risk associated with new generation. To the extent the Commission can encourage bilateral contracting by providing clarity that longer-term bilateral arrangements are acceptable and supported under the Qualifying RBP Offset framework, such action would incentivize supply participation in bilateral contracting and thereby reduce reliance on the auction, with attendant downward pressure on clearing prices.

Third, moving beyond the RBP, PJM and the Commission should pursue seasonal
capacity markets.25 A seasonal market construct would better align capacity obligations with the periods in which resources can deliver capacity value, recognizing that different resource types contribute to reliability in different seasons. Seasonal markets would enable a broader array of

23 See Proposed Tariff, Attachment DD, section 18.2(c)(i).
24 Proposed Tariff, Attachment DD, section 18.2(c)(i); see also RBP Proposal at 39–40 (explaining that bilateral contracts must have a minimum term of at least five Delivery Years to qualify as Qualifying RBP Offset UCAP MW).
25 See PJM Interconnection, L.L.C., 186 FERC ¶ 61,080, at P 293 (2024) (encouraging PJM to continue evaluating whether and how a seasonal capacity construct could support reliability and efficiency); see also Transmittal Letter of PJM Interconnection, L.L.C., Docket No. ER24-99-000, at 18 (Oct. 13, 2023) (stating that “PJM and its stakeholders are committed to continuing to assess the design of PJM’s capacity construct, including whether and how a seasonal capacity market could help support reliability and efficiency in the PJM region”).

PDF page 9

9
resources to participate in meeting PJM’s reliability needs, including resources whose contributions are concentrated in particular seasons. Because ELCCs depend heavily on the balance of reliability risk between seasons, seasonal capacity markets should also reduce ELCC volatility, improving the hedging value of resources and making them easier to underwrite.26 This reform would complement the RBP by expanding the pool of resources willing and able to make long-term capacity commitments.

Fourth, PJM and the Commission should address the commercial barriers that prevent surplus interconnection service from delivering additional accredited capacity to the system. PJM’s surplus interconnection service allows new resources to use interconnection rights at existing points of interconnection, providing a pathway for developers to add capacity to existing renewable sites with minimal network upgrades and through an expedited interconnection process.27 The Commission recently accepted PJM’s proposed tariff revisions in Docket No. ER25-778-000 to remove engineering barriers that previously blocked surplus interconnection requests—including the elimination of the “materiality” review that effectively denied most surplus requests before any study could be performed.28 However, significant commercial barriers remain that prevent surplus interconnection from delivering its full potential. Under the current framework, surplus resources face a potentially unworkable choice. Because PJM’s Tariff only grants capacity interconnection rights (“CIRs”) and ELCC

26 See Comments of MN8 Energy, PJM CIFP – Large Load Additions Stakeholder Process, at 22 (Nov. 19, 2025), available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20251119/20251119- stakeholder-written-comments.pdf (discussing capacity market reforms needed for a developer to enter into medium- to long-term contracts).
27 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service).
28 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083, at PP 30, 33 (2025) (accepting PJM’s proposed tariff revisions to remove eligibility restrictions on surplus interconnection service and facilitate the rapid expansion of generating facilities on PJM’s system); see also Comments of the Clean Energy Associations, Docket No. ER25-778- 000, at 1–3 (Jan. 13, 2025) (“Clean Energy Associations Surplus Comments”) (urging Commission acceptance of PJM’s surplus interconnection reforms as a pathway to unlock GWs of storage capacity).

PDF page 10

10
accreditation to surplus resources that merge with the existing facility as a single hybrid resource,29 a developer seeking capacity value through surplus interconnection must elect hybrid treatment— which potentially requires unwinding existing power purchase agreements, tax equity structures, and lender arrangements. The alternative—interconnecting independently as a co-located

resource—preserves independent financing but limits the surplus resource to energy-only market participation, forfeiting capacity value entirely. Because hybrid treatment requires combined market participation as a single resource,30 it does not allow for component-level settlement, and capacity performance penalty risk cannot be isolated from the host resource. Lenders to the existing facility will rarely consent to the addition of a surplus resource under these conditions, because it exposes the existing project to performance liability arising from a resource it does not own or control. This effectively renders the surplus interconnection pathway commercially unavailable for many projects, regardless of whether the interconnection path is clear.

To address these barriers and unlock the significant capacity potential of surplus
interconnection, SEIA recommends three reforms. First, PJM should enable surplus resources to obtain independently recognized and bankable capacity positions—distinct from the host

resource—without requiring the wholesale restructuring of existing commercial arrangements. This could be achieved through several mechanisms, including: (i) split UCAP settlement between component accounts; or (ii) CIR transfer mechanisms between co-located resources.31 Whichever

29 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service); see also Hybrid Resources Market Model Selection—Problem Statement, PJM Interconnection, L.L.C. (Aug. 2026) (“Hybrid PS/IC”), available at: https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-1--- hybrid-resources-market-model-selection---problem-statement.pdf (recognizing that under current rules, the only pathway for surplus resources to obtain capacity value is to become a hybrid resource with the existing project).
30 See Hybrid PS/IC (discussing issues relating to hybrid resource combined market participation as a single market unit in PJM’s energy, capacity, and ancillary services markets).
31 Under PJM’s current framework, a surplus interconnection arrangement results in a revised or amended Generation Interconnection Agreement for the existing facility, rather than a separate, standalone GIA for the surplus resource. See PJM Tariff, Part VIII, Subpart E, § 414(B)(2) (providing that a “revised Interconnection Service Agreement or Generation Interconnection Agreement will be prepared and issued to the owner of the existing or planned Generating

PDF page 11

11
mechanism is adopted, the objective should be to provide each component of a surplus arrangement with independent settlement, revenue allocation, and penalty isolation necessary to support separate financing.

Second, whether adopted in connection with the foregoing reforms or as a standalone measure, PJM should establish clear protections ensuring that a default or performance issue arising from the surplus resource cannot create cross-default risk or otherwise interfere with the existing resource’s GIA or operations. This protection is essential to obtaining lender consent: absent an explicit structural separation of liability, lenders to the existing facility will not approve the addition of a surplus resource that could jeopardize the project’s existing financing and operational arrangements.

Third, SEIA encourages PJM to evaluate whether additional resources or process
modifications can be devoted to surplus interconnection studies to reduce the time from application to completion, particularly for projects that could deliver capacity within the RBP’s timeframe. The Commission’s acceptance of PJM’s Docket No. ER25-778-000 reforms removed the prior automatic disqualifications that blocked surplus requests, but developers now need timely study completion to bring resources online within the timeframes contemplated by the RBP.32 Together, these reforms—addressing commercial structure, lender protections, and study timelines for surplus interconnection—would enable surplus interconnection to serve as a meaningful near-term pathway for delivering additional accredited capacity to the PJM system, potentially unlocking Facility”). This structure means the surplus resource’s market participation, obligations, and potential liabilities are housed within the existing project’s agreement, creating the cross-default risk discussed above.

32 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 at PP 30, 33–34 (accepting revisions that expand availability of surplus interconnection service and noting that PJM’s proposal “should expand the use of surplus interconnection service and allow additional capacity resources to connect to the PJM system”); see also Clean Energy Associations Surplus Comments at 3 & n.10.

PDF page 12

12
gigawatts of storage and other resources that are positioned to connect quickly at existing points of interconnection.33

These reforms are not prerequisites for Commission acceptance of the RBP Proposal, but rather constructive improvements that would enhance the effectiveness of the procurement and address resource adequacy challenges on a forward-going basis. Moreover, while SEIA raises these concerns in the context of the RBP, the principles underlying these recommendations— including the need for predictable capacity accreditation, sufficient time for bilateral contracting, and workable commercial frameworks for surplus interconnection—are not limited to this proceeding and warrant the Commission’s attention as it considers broader capacity market reforms. Indeed, the NEDC and PJM Governors’ Principles—which, as the RBP Proposal acknowledges, inform the design and objectives of the RBP—contemplate a subsequent “return to market fundamentals” and continued refinement of PJM’s capacity market framework,34 and these recommendations are consistent with that ongoing effort.

III. CONCLUSION
For the foregoing reasons, SEIA respectfully submits that while the RBP Proposal represents a necessary and timely response to PJM’s resource adequacy challenges, the Commission should consider the refinements identified herein—including accommodations for bilateral contracting timelines, measures to provide capacity certainty over the commitment term, removal of commercial barriers to surplus interconnection, and reforms to unlock additional participation—as it evaluates the RBP Proposal as a means of securing the timely addition of new capacity. To the extent the Commission identifies opportunities to incorporate such improvements,

33 See Clean Energy Associations Surplus Comments at 3.
34 See NEDC/PJM Governors’ Principles at 1 (urging PJM to “embark on a stakeholder process to reform the capacity market to ensure long-term viability and prevent consumers from bearing excessive ongoing costs”); see also RBP Proposal at 6–8 (citing and implementing the NEDC/PJM Governors’ Principles).

PDF page 13

13
whether in its order on the RBP Proposal or in subsequent proceedings, doing so would further the shared objective of procuring sufficient capacity at the lowest reasonable cost. SEIA supports PJM’s effort to address the resource adequacy shortfall on an expedited basis and appreciates the opportunity to provide these comments.

Respectfully submitted,
Melissa Alfano
Senior Director of Energy Markets and
Counsel
Solar Energy Industries Association
1425 K St NW Ste. 1000
Washington, DC 20005
(202) 566-2873
malfano@seia.org
/s/ Steven Shparber
Steven Shparber
Omar Bustami
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo, P.C.
555 12th Street NW, Suite 1100
Washington, D.C. 20004
(202) 434-7417
SShparber@mintz.com
OBustami@mintz.com
Counsel to the Solar Energy Industries
Association
Dated: August 21, 2026

PDF page 14

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, DC, this 21st day of August, 2026.

/s/ Steven Shparber
Steven Shparber