ER26-3380-000 · 2026-08-21 · Solar Energy Industries Association

Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal

Text extracted from the eLibrary original (SHA-256 40a7a394cb93a51d…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 2
  2. II. COMMENTS p. 3
  3. A. ELCC Uncertainty and Commercial Operation Date Requirements May p. 3
  4. B. The Compressed Timeline for Bilateral Contracting May Result in Higher p. 6
  5. C. Recommendations for Unlocking Additional Capacity p. 7
  6. III. CONCLUSION p. 12

Read topic-matched comments in ER26-3380

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

PJM filed the RBP Proposal pursuant to Section 205 of the Federal Power Act (“FPA”),3 proposing revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a one-time procurement mechanism to address…
Read this passage Filed comments: Reliability and curtailment

I. INTRODUCTION

printed heading · Topic match: Cost allocation

INTRODUCTION SEIA does not oppose PJM’s RBP Proposal as a necessary and timely response to the resource adequacy challenges facing the PJM Region.
Read this passage Filed comments: Cost allocation

II. COMMENTS

printed heading

II.
Read this passage

A. ELCC Uncertainty and Commercial Operation Date Requirements May

printed heading · Topic match: Cost allocation

The RFI administered by Charles River Associates identified over 100 GW of prospective supply interested in participating;18 ensuring that market rules support—rather than discourage—this participation is essential to achieving the lowest possible procurement costs for ratepayers.
Read this passage Filed comments: Cost allocation

B. The Compressed Timeline for Bilateral Contracting May Result in Higher

printed heading

In theory, this mechanism should exert downward pressure on auction prices by reducing the quantity of capacity that must be procured through the competitive auction process.20 However, SEIA is concerned that the accelerated timeline from PJM Board approval on July 27, 2026, to the anticipated…
Read this passage

C. Recommendations for Unlocking Additional Capacity

printed heading · Topic match: Connecting load and generation

Seasonal markets would enable a broader array of 23 See Proposed Tariff, Attachment DD, section 18.2(c)(i). 24 Proposed Tariff, Attachment DD, section 18.2(c)(i); see also RBP Proposal at 39–40 (explaining that bilateral contracts must have a minimum term of at least five Delivery Years to qualify…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION For the foregoing reasons, SEIA respectfully submits that while the RBP Proposal represents a necessary and timely response to PJM’s resource adequacy challenges, the Commission should consider the refinements identified herein—including accommodations for bilateral contracting…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 21st day of August, 2026. /s/ Steven Shparber Steven Shparber