ER26-3380-000 · 2026-08-21 · Sierra Club, Natural Resources Defense Council

Limited Protest of Sierra Club et al. to one aspect of PJM Interconnection, LLC’s proposed Reliability Backstop Procurement

Sierra Club and NRDC file a limited protest in ER26-3380 of PJM's Reliability Backstop Procurement. They back the plan but ask FERC to require backstop supply to sit near large loads or to pay for its own network upgrades.

Asks FERC to: Approve PJM's RBP filing with a modification requiring RBP supply to be located near large loads or to fund 100% of network upgrades, and encourage states to mandate take-or-pay agreements.

Protest in PJM's separate ER26-3380 backstop procurement docket. It borrows the E-7 order's cost recovery agreement concept to argue large loads should bear backstop capacity costs, and it bears on the E-7 adequacy question.

E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)

Key points

  1. The protesters support PJM's one-time procurement sized to the 2028/2029 shortfall with costs allocated to zones and LSEs serving new large loads.
    PJM proposes a one-time procurement of new capacity sized to the 2028/2029 shortfall, with costs that will be allocated to the zones and load-serving entities (“LSEs”) serving the new large loads PDF p. 2
  2. They read four objectives into the RBP: right amount, new capacity, on time, and large loads bear their costs.
    Procure new capacity that is additive to the PJM system, not a mere reshuffling of existing resources; PDF p. 3
  3. PJM's RBP has no location requirement, which the protesters say makes success depend on large, slow and costly network upgrades.
    PJM’s proposal to allow RBP supply to be located anywhere in the footprint will make the RBP’s success reliant on large-scale network upgrades that will likely cause significant delays and incur significant costs. PDF p. 4
  4. The protesters cite PJM's forecast of 30 GW of large load by 2030 and 70 GW by 2038, and auction shortfalls of 6.8 GW and 6.5 GW.
    PJM predicts that 30 GW of large load demand will come online by 2030 and 70 GW of large load demand will come online by 2038. PDF p. 6
  5. The last three base residual auctions cleared at the price cap, up from $28.92/MW-day in 2024/2025.
    The past three BRAs cleared at the price cap, clearing at $325/MW-day in the 2028/2029 BRA, $333.44/MW-day in the 2027/2028 BRA, and $329.17/MW-day in the 2026/2027 BRA. PDF p. 8
  6. The primary fix is a locational requirement; paying 100% of network upgrades is a partial alternative that should be additional.
    the Commission view this modification as additional to a requirement that RBP supply be located near large loads, not as a completely sufficient alternative modification. PDF p. 17
  7. In PJM's Reliability Resource Initiative, 10 of 51 projects withdrew after upgrade costs were assigned, which the protesters offer as a warning.
    10 out of 51 RRI projects withdrew from the interconnection process, with two projects dropping out before being studied, and eight projects dropping at the first decision point in TC2. PDF p. 20
  8. They liken state-mandated take-or-pay contracts between LSEs and large loads to the cost recovery agreement in the June 18 order.
    Take-or-pay contracts with respect to the RBP would work similarly to the cost-recovery agreements outlined in the Commission’s Order and would serve a similar purpose. PDF p. 40
Contents · 23 sections
  1. Introduction p. 1
  2. Background p. 4
  3. I. PJM’s capacity market is facing reliability and affordability concerns as PJM struggles to meet data center load growth. p. 4
  4. A. PJM’s capacity market faces increased reliability risks as data center load grows too quickly for PJM’s supply. p. 5
  5. B. PJM’s capacity market faces high capacity prices, causing increases in ratepayers’ bills. p. 8
  6. II. PJM’s Reliability Backstop Proposal should be accepted with modifications to better achieve the RBP’s objectives. p. 10
  7. Discussion p. 10
  8. I. The Commission Should Only Modify PJM’s RBP Filing to Better Accomplish PJM’s Objectives. p. 10
  9. A. Objective One: Procure the Correct Amount of Capacity p. 12
  10. B. Objective Two: Procure New Capacity p. 13
  11. C. Objective Three: Procure New Capacity on Time p. 14
  12. D. Objective Four: Ensure That the Large Loads That Require New Capacity Bear Its Costs. p. 15
  13. II. The Commission should modify the RBP by requiring RBP supply to be located new large loads in order to minimize delays and the risk of cost-shifting. p. 16
  14. A. PJM’s proposal to exclude a locational requirement for RBP generation bids could lead to reliability risks. p. 19
  15. B. PJM’s proposal will unjustly and unreasonably shift costs to other interconnection customers or ratepayers. p. 26
  16. 1. The RBP will likely shift costs of network upgrades to other interconnection customers and to all PJM load. p. 27
  17. 2. The RBP will likely shift the costs to study RBP resources to other interconnection customers. p. 28
  18. 3. PJM’s proposal will unjustly and unreasonably shift costs to all PJM customers through RTEP. p. 29
  19. 4. The RBP risks cost shifts that are inconsistent with the Ratepayer Protection Pledge and the Commission’s Large Load Orders. p. 30
  20. a. Cost-shifts in the RBP violate the Ratepayer Protection Pledge and the Commission’s June 18th Large Load Orders. p. 30
  21. b. Cost-Shifts in the RBP violate the Commission’s June 18 Large Load Order. p. 33
  22. III. The Commission should encourage PJM states to do their part in allocating costs to data centers. p. 34
  23. Conclusion p. 41

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, LLC ) ) ) Docket No.
Read this passage

Introduction

PDF bookmark · Topic match: Cost allocation

For example, PJM is admirably candid about the fact that the capacity shortfalls are “primarily driven by the unprecedented addition of large loads, most notably data centers.”5 PJM also takes seriously and attempts to realize the Ratepayer Protection Pledge, in which the nation’s largest data…
Read this passage Filed comments: Cost allocation

Background

PDF bookmark

Background
Read this passage

I. PJM’s capacity market is facing reliability and affordability concerns as PJM struggles to meet data center load growth.

PDF bookmark · Topic match: Cost allocation

Its market was built for predictable, gradual load growth where new generation resources could be built within the market’s three- 5 year forward timeline.13 However, as load growth, generation retirement, and supply chain development time have all increased in the past few years, PJM has…
Read this passage Filed comments: Cost allocation

A. PJM’s capacity market faces increased reliability risks as data center load grows too quickly for PJM’s supply.

PDF bookmark

While developers can typically build hyperscale data centers within 18 to 17 Id. at 3; Jonathan Koomey et. al, Bipartisan Pol’y Ctr. & Koomey Analytics, Electricity Demand Growth and Data Centers: A Guide for the Perplexed, 10 (Feb. 2025),…
Read this passage

B. PJM’s capacity market faces high capacity prices, causing increases in ratepayers’ bills.

PDF bookmark · Topic match: Cost allocation

PJM’s capacity market faces high capacity prices, causing increases in ratepayers’ bills.
Read this passage Filed comments: Cost allocation

II. PJM’s Reliability Backstop Proposal should be accepted with modifications to better achieve the RBP’s objectives.

PDF bookmark · Topic match: Cost allocation

Specifically, the Commission should accept PJM’s proposal, but only on the conditions that PJM either require RBP supply to be located near to large loads, which will help ensure that new supply can come online timely, and that reliability risks or costs associated with delivering new RBP capacity…
Read this passage Filed comments: Cost allocation

Discussion

PDF bookmark

Discussion
Read this passage

I. The Commission Should Only Modify PJM’s RBP Filing to Better Accomplish PJM’s Objectives.

PDF bookmark · Topic match: Cost allocation

The RBP Filing invokes the Ratepayer Protection Pledge’s commitment that large loads will pay the “full 41 RBP Filing, supra note 2, at 52. 42 Id. at 22 n.69 (quoting PJM Board July 2026 Decisional Letter at 2). 43 Id. at 51. 44 Id. at 42. 45 Id. at 51 (requiring new capacity to be online no later…
Read this passage Filed comments: Cost allocation

A. Objective One: Procure the Correct Amount of Capacity

PDF bookmark

Objective One: Procure the Correct Amount of Capacity The RBP’s quantity of procured megawatts is set by administrative decision, not by market clearing.
Read this passage

B. Objective Two: Procure New Capacity

PDF bookmark · Topic match: Cost allocation

The need for genuinely new supply is recognized by the PJM Board, the Governors’ Principles, and the Ratepayer Protection Pledge.
Read this passage Filed comments: Cost allocation

C. Objective Three: Procure New Capacity on Time

PDF bookmark

This means that PJM is willing to pay a higher price for capacity that arrives sooner.52 Timeliness of projects is also important because PJM proposes to reset the trigger for the Tariff’s pre-existing Reliability Backstop Auction so that no such auction can occur unless BRAs clear short for three…
Read this passage

D. Objective Four: Ensure That the Large Loads That Require New Capacity Bear Its Costs.

PDF bookmark · Topic match: Cost allocation

Because these new costs are so clearly and uniquely caused by the massive expansion of data centers and similar new large loads, cost causation principles require that the RBP allocate costs to those new large loads.
Read this passage Filed comments: Cost allocation

II. The Commission should modify the RBP by requiring RBP supply to be located new large loads in order to minimize delays and the risk of cost-shifting.

PDF bookmark · Topic match: Cost allocation

To ensure that PJM accomplishes its objectives to procure the (1) correct amount of (2) new capacity (3) on time to meet the 2028/2029 shortfall and (4) allocate the costs of that capacity to new data center load, PJM must include a locational deliverability requirement for RBP Sell Offers.
Read this passage Filed comments: Cost allocation

A. PJM’s proposal to exclude a locational requirement for RBP generation bids could lead to reliability risks.

PDF bookmark · Topic match: Cost allocation

RBP Filing, supra note 2, at 38–40. 62 Yamit Lavi et. al, Unlocking the Grid, NRDC (Apr. 7, 2026), https://www.nrdc.org/resources/unlocking-grid. 63 Devin Leith-Yessian, PJM Receives 811 Interconnection Requests in Queue Cycle 1, RTO Insider (Apr. 29, 2026),…
Read this passage Filed comments: Cost allocation

B. PJM’s proposal will unjustly and unreasonably shift costs to other interconnection customers or ratepayers.

PDF bookmark · Topic match: Cost allocation

PJM’s proposal will unjustly and unreasonably shift costs to other interconnection customers or ratepayers.
Read this passage Filed comments: Cost allocation

1. The RBP will likely shift costs of network upgrades to other interconnection customers and to all PJM load.

PDF bookmark · Topic match: Cost allocation

In this scenario, higher network upgrade costs from a network upgrade that ensures load deliverability from an RBP resource to a zone with an RBP allocation means higher shared costs for every resource in that cluster. 81 See White House Ratepayer Protection Pledge; see also Order Instituting…
Read this passage Filed comments: Cost allocation

2. The RBP will likely shift the costs to study RBP resources to other interconnection customers.

PDF bookmark

Under Order No. 2023, costs of cluster studies are shared between interconnection customers on a per capita and pro rata MW basis.85 Order No. 2023’s study cost allocation requirements acknowledge that cluster study costs are affected by the number of interconnection requests and the size of the…
Read this passage

3. PJM’s proposal will unjustly and unreasonably shift costs to all PJM customers through RTEP.

PDF bookmark · Topic match: Cost allocation

As a result, the costs of any reliability-driven upgrades that are caused by any transmission constraints associated with RBP resources and identified through RTEP will be unjustly and unreasonably socialized to all load in PJM, which fails to achieve PJM’s objective to allocate RBP costs to LSEs…
Read this passage Filed comments: Cost allocation

4. The RBP risks cost shifts that are inconsistent with the Ratepayer Protection Pledge and the Commission’s Large Load Orders.

PDF bookmark · Topic match: Cost allocation

The RBP risks cost shifts that are inconsistent with the Ratepayer Protection Pledge and the Commission’s Large Load Orders.
Read this passage Filed comments: Cost allocation

a. Cost-shifts in the RBP violate the Ratepayer Protection Pledge and the Commission’s June 18th Large Load Orders.

PDF bookmark · Topic match: Cost allocation

To allow data centers to carry out this promise, PJM’s RBP must include a locational element to mitigate the study costs assigned to other generators, or PJM must assign the increased study costs caused by RBP resources to those resources. 98 PJM, Joint EDCs and Data Center Coalition Reliability…
Read this passage Filed comments: Cost allocation

b. Cost-Shifts in the RBP violate the Commission’s June 18 Large Load Order.

PDF bookmark · Topic match: Cost allocation

As described in the Commission’s June 18 Large Load Order, the Commission has a duty to address the risk of cost shifting among transmission customers that may result in unjust and unreasonable rates.99 PJM’s current RBP proposal will likely result in unjust and unreasonable rates by shifting RBP…
Read this passage Filed comments: Cost allocation

III. The Commission should encourage PJM states to do their part in allocating costs to data centers.

PDF bookmark · Topic match: Cost allocation

The Commission has acknowledged states’ role in cost allocation as well, stating in its June 18 Large Load Order that “states determine how Commission-approved rates are collected among the relevant retail consumers along with the rates for state-jurisdictional matters.”103 The PJM Governors…
Read this passage Filed comments: Cost allocation

Conclusion

printed heading · Topic match: Retail and wholesale authority

Conclusion PJM’s RBP filing generally presents a just and reasonable mechanism to procure capacity for large loads that are currently causing a shortfall in PJM’s capacity market and to facilitate the allocation of costs to large loads while respecting state jurisdiction over retail rates.
Read this passage Filed comments: Retail and wholesale authority