ER26-3515-000 · 2026-08-28 · Organization of PJM States, Inc.

Motion for Extension of Time of the Organization of PJM States, Inc. to submit comments in response to PJM Interconnection, L.L.C.'s 08/13/2026 proposal

The Organization of PJM States moves for an 11-day extension of the comment deadline on PJM's Interim Resource Adequacy Service and Large Load Registry filing. PJM does not oppose the motion.

Asks FERC to: Extend the comment deadline in ER26-3515 from September 3 to September 14, 2026, with action by September 1.

Moves the comment schedule in PJM's separate interim resource adequacy docket ER26-3515, PJM's proposal on how to serve load that outpaces capacity, the subject of the E-7 adequacy report.

E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)

Key points

  1. OPSI asks to move comments from September 3 to September 14, 2026, and PJM does not oppose.
    OPSI requests that the Commission extend the time for comments in this docket from September 3, 2026 to September 14, 2026. PDF p. 1
  2. PJM's August 13 filing proposes a load reduction service for new large loads and a large load registry.
    a new supplemental capacity product through which New Large Loads [(“NLL”)] provide a load reduction service that is a tool available to PJM to manage resource adequacy shortfalls PDF p. 1
  3. PJM's compensation mechanism creates new obligations for Electric Distributors and touches retail ratemaking.
    PJM proposes a compensation mechanism for loads that provide this new service, which creates new obligations for Electric Distributors. PDF p. 2
  4. State regulators need time to assess the interaction of PJM, distributors and retail regulators in implementing the service.
    to allow the retail regulators in the PJM region additional time to consider the complex interaction between the rights and responsibilities of PJM, Electric Distributors, and retail regulators PDF p. 2
Contents · 3 sections
  1. I. BACKGROUND p. 1
  2. II. MOTION FOR EXTENSION OF TIME p. 2
  3. III. CONCLUSION p. 3

Read topic-matched comments in ER26-3515

Topics in the text: Filing procedure · Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Pursuant to Rules 212 and 2008 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”),1 the Organization of PJM States, Inc. (“OPSI”) submits this Motion for an Extension of Time to submit comments in response to PJM’s August 13, 2026, filing…
Read this passage Filed comments: Filing procedure

I. BACKGROUND

PDF bookmark · Topic match: Registry access

ER26-3515-000 (August 13, 2026) (“IRAS Filing”). 3 The OPSI Board of Directors approved this Motion for Extension of Time pursuant to its Bylaws on August 28, 2026. 4 IRAS Filing at 22. of NLL that has not brought its own new capacity in a delivery year, among other things.5 Importantly, PJM…
Read this passage Filed comments: Registry access

II. MOTION FOR EXTENSION OF TIME

PDF bookmark · Topic match: Filing procedure

In order to ensure that the retail electric regulators in the PJM region have the opportunity to provide substantive comments, OPSI respectfully requests a limited extension of time to file comments in this docket.
Read this passage Filed comments: Filing procedure

III. CONCLUSION

PDF bookmark · Topic match: Filing procedure

CONCLUSION Accordingly, OPSI respectfully requests that the Commission grant this Motion for Extension of Time to respond to PJM’s IRAS filing by the close of business on September 14, 2026.
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

Egen_______ Director of Legal and Regulatory Affairs Organization of PJM States, Inc. 700 Barksdale Road, Suite 1 Newark, DE 19711 336-254-4915 ellen@opsi.us Dated at Newark, Delaware this August 28, 2026.