ER26-3515-000 · 2026-09-03 · Delaware Division of the Public Advocate, District of Columbia Office of People's Counsel and 4 others
Protest and Comments of Joint Consumer Advocates on the 08/13/2026 filing by PJM Interconnection, L.L.C
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3515-000
PROTEST AND COMMENTS OF JOINT CONSUMER ADVOCATES
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or Commission) Rules of Practice and Procedure,1 the Delaware Division of the Public Advocate, District of Columbia Office of People’s Counsel, Illinois Citizens Utility Board, Office of the Illinois Attorney General, Maryland Office of the People’s Counsel, and New Jersey Division of Rate Counsel (together, Joint Consumer Advocates or JCA)2 submit this protest of and comments on the August 13, 2026, filing by PJM Interconnection, L.L.C. (PJM) proposing to establish an Interim Resource Adequacy Service (IRAS) and a Large Load Registry.3 While JCA appreciate PJM’s efforts in developing and presenting IRAS, and acknowledge that it is a better outcome than potential alternatives, the proposal falls short of the just and reasonable standard.
For the reasons stated below, the Commission should find PJM’s proposal unjust and unreasonable, and direct PJM to file an amended version of IRAS. PJM has consented to the Commission’s modification or severing of this proposal to the extent “consistent with PJM’s overarching objectives in this filing.”4 To the extent this consent is insufficient to
1 18 C.F.R. § 385.211.2 Each of the Joint Consumer Advocates has separately and timely moved for leave to intervene in this proceeding.3 Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability (Aug. 13, 2026), eLibrary No. 20260813-5118 (IRAS Filing).4 IRAS Filing, Transmittal Letter at 9 (IRAS Transmittal Letter).
PDF page 2
- 2 -
implement the changes sought here, the Commission should exercise its Federal Power Act (FPA) section 2065 authority to require that PJM implement the identified modifications. We note that the Commission’s June 2026 Show Cause Order6 found PJM’s Open Access Transmission Tariff (Tariff) “appears to be unjust, unreasonable, or unduly discriminatory or preferential,” in part because of its treatment of large load customers.7 The Commission should reject PJM’s treatment of IRAS as a compensable resource adequacy service, and instead direct PJM to modify the proposal to provide that new large loads that do not self-supply must take non-firm transmission service. The Commission should also direct PJM to revise the proposal and modify the new large load self-supply provisions (Bring Your Own New Capacity (BYONC)) such that only resources that have not previously cleared a prior Base Residual Auction (BRA) are eligible. In addition, the Commission should direct modification of the proposal to require its review and validation of data supplied for the Large Load Registry, and to expand access to the information in the Registry such that the JCA can review the data. Finally, Commission acceptance of the revised IRAS proposal should be coordinated with the disposition—and rejection—of the separate Reliability Backstop Procurement (RBP) proceeding pending in Docket No. ER26-3380.8
5 16 U.S.C. § 824e.
6 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (June 2026 Show Cause Order).7 Id. P 3. 8 PJM, Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from New Load Adjustments, PJM Interconnection, L.L.C., Docket No. ER26-3380 (July 31, 2026), eLibrary No. 20260731-5214 (PJM RBP Filing).
PDF page 3
- 3 -
SUMMARY
The instant proposal and PJM’s separate RBP initiative address the same reliability problem: unprecedented growth in new large loads—chiefly, data centers—that has
outpaced new generation and transmission development and produced consecutive years of capacity shortfalls in PJM’s BRAs.9 RBP seeks to cover the immediate shortfall, though does so by means that are unjust and unreasonable in myriad ways.10 IRAS also seeks to preserve regional reliability in the face of an unprecedented resource adequacy challenge. The mechanism facilitates the interconnection of new large loads but requires (or should require) that they make a choice: either bring new capacity sufficient to meet their needs or (assuming appropriate state action) face curtailment when circumstances necessitate load reductions.
Joint Consumer Advocates recognize and appreciate that PJM’s IRAS proposal
seeks to navigate a difficult course, and we support the general thrust of the proposal. If implemented correctly, the approach could go far toward maintaining reliability without either stopping the interconnection of non-capacity backed new large loads or socializing the reliability consequences of non-capacity backed large-load growth. We submit that neither of those options was likely to gain regulatory traction or, even more importantly, to be consistent with PJM’s obligation to ensure resource adequacy.11 IRAS rightly strikes a
9 IRAS Transmittal Letter at 14, 21.
10 Protest, Motion to Reject, and Alternative Request for the Imposition of Conditions of Joint Consumer Advocates, PJM Interconnection, L.L.C., Docket No. ER26-3380 (Aug. 21, 2026), eLibrary No. 20260821-5183 (JCA RBP Protest).11 Pursuant to Order No. 2000, PJM serves as the North American Electric Reliability Coordinator (NERC) regional security coordinator and is responsible for “directing actions to maintain [system] reliability, including firm load shedding.” Reg’l Transmission Orgs., Order No. 2000, 89 FERC ¶ 61,285, FERC Stats. & Regs. at 31,089 (1999), order on reh’g, Order No. 2000-A, 90 FERC ¶ 61,201 (2000), appeal dismissed for want of standing sub nom., Pub. Util. Dist. No. 1 v. FERC, 272 F.3d 607 (D.C. Cir. 2001). See also PJM Manual 03 § 1.1 (“PJM is the Reliability Coordinator for the PJM [regional transmission operator (RTO)] and is responsible for all regional Reliability coordination as defined in the NERC and Regional Standards
PDF page 4
- 4 -
different course, requiring new large loads either to balance their load additions with supply additions or to accept curtailment risk. But the IRAS proposal that PJM filed departs from what it discussed with stakeholders and falls short of being just and reasonable in important respects. In short, and as reviewed in the first part of this pleading, PJM’s basic concept is largely sound and potentially beneficial. But, as explained in the second part of the pleading, PJM’s proposed implementation is flawed.
The flaws include that PJM’s proposal fails to capture all the new large load that should be a curtailable IRAS resource. PJM exempts new large loads from IRAS to the extent that they bring their own new capacity but fails to ensure that the “new” capacity in fact adds to the system’s existing capacity. As explained below, PJM’s proposal would allow a new large load to decrease its IRAS service (and curtailment risk) by procuring capacity that already has cleared in previous BRAs. This would increase the amount of load on the system without either increasing system supply or making the new load an IRAS resource subject to curtailment. That is an unjust and unreasonable loophole. Second, PJM’s proposal to compensate IRAS resources when they are curtailed has not been shown to be just and reasonable. The compensation proposal departs from the “connect and manage” proposal it promoted during the stakeholder process, under which non-capacity backed new large loads would be required to take non-firm transmission service akin to the approaches adopted and approved in the Southwest Power Pool (SPP) and Electric Reliability Council of Texas (ERCOT).12 “Connect and manage” was
and applicable PJM Operating Manuals.”). “[T]he role of a security coordinator is central to maintaining grid reliability and non-discriminatory access.” Order No. 2000, FERC Stats & Regs. at 31,090 (citation modified) (quoting Midwest Indep. Transmission Sys. Operator, 84 FERC ¶ 61,231 at 62,158, order on reconsideration, 85 FERC ¶ 61,250, order on reh’g, 85 FERC ¶ 61,372 (1998)).
12 PJM, Powering Reliability Through Market Design at 37 (May 6, 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-
PDF page 5
- 5 -
presented as a demand-side solution that would not impose resource adequacy costs on other customers. But in making its filing initiating this proceeding, PJM has presented IRAS as a supply-side measure akin to demand response.13 Thus, PJM proposes that new large loads that are curtailed pursuant to IRAS should be entitled to compensation, but leaves to the states resolution of the question of who ultimately must fund that compensation—which leaves open the possibility that non-large load customers may yet end up paying resource adequacy costs to the new large data center loads that are driving PJM’s reliability concerns.
That is an unnecessary risk. PJM could have avoided it, while enabling new large load growth and preserving reliability, by having new large loads without incremental capacity come on as non-firm customers, without any right to compensation if they are curtailed. Instead, by declaring that new large loads will be taking firm transmission service14 and will be paid for whatever load curtailments are ordered as a form of involuntary demand response,15 PJM needlessly creates a cost that depends on state action to allocate correctly. It is an unnecessary, and unjust and unreasonable, regulatory two-step. Moreover, as designed, the proposal does not incent new large loads to procure new self-supply but instead incents them to engage in a cost-benefit analysis as to whether it is in their economic self-interest to instead continue as a non-capacity backed load subject to
market-design.pdf (comparing PJM proposed connect and manage approach to ERCOT and SPP use of non- firm transmission service to interconnect and serve non-capacity backed new large loads) (White Paper).
13 PJM, CIFP Framework for Service During Periods of Insufficient Resource Adequacy – PJM Proposal at 5 (July 31, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260727-cifp-framework-for-service-during-periods-of-insufficient-resource-adequacy- executive-summary.pdf (discussing IRAS credits). See also IRAS Transmittal Letter at 101-04.14 “Load reduction under Interim Resource Adequacy Service appropriately treats New Large Loads as [network integration transmission service] customers.” IRAS Transmittal Letter at 100.15 Id. at 104-06.
PDF page 6
- 6 -
compensation for curtailment. PJM provides no cost analysis to justify its unnecessary treatment of non-capacity backed loads as firm transmission customers eligible (depending upon state action) for compensation from other ratepayers. And PJM’s proposal violates the minimum standards for formula rates because it is not possible to ascertain what customers will be responsible for paying curtailment charges. Fundamentally, non-capacity backed new large loads cannot come on to the system unless they are subject to curtailment and should be treated as such, i.e., non-firm transmission customers.
Importantly, IRAS itself does not guarantee that any required curtailments will necessarily fall on large loads. PJM proposes to issue curtailment directives to Electric Distribution Companies (EDCs) in the amount of their IRAS load but leaves specific load curtailments to the state and/or Retail Electric Regulatory Rate Authority (RERRA).16 And there are questions about the extent to which the data included in the Large Load Registry, which is the data engine for the IRAS mechanism, are being properly vetted, supported, and made available to regulatory authorities, including ratepayer advocates. Finally, IRAS does not purport to address other, significant issues, including the increased transmission or energy costs that result from new large loads, which should also be their cost responsibility.1716 Id. at 83-86. One of the problems posed by IRAS is that PJM is unable to dictate which specific loads will be curtailed in the event they are necessary. Curtailment decisions will be made by the relevant state/RERRA. In other words, IRAS allows new large data centers without BYONC to come onto the grid, but in so doing may subject to curtailment customers who are not responsible for the reliability problem IRAS aims to solve. Id. “[A]n Interim Resource Adequacy Service Action will not be specific as to which New Large Loads would need to be reduced.” Id. at 83 (emphasis in original).17 According to the Independent Market Monitor’s August 19, 2026, Market Monitor Report comparing January to July 2025 to January to July 2026, energy costs within PJM increased by 46%, capacity costs increased by 138%, and transmission costs increased by 6.3%. Monitoring Analytics, Market Monitor Report at 27 (Aug. 19, 2026), www.monitoringanalytics.com/reports/presentations/2026/IMM_MC_Market_Monitor_Report_20260819. pdf?_sp=674592ab-00d2-413a-9d56-caac654c2c84.1788266063005.
PDF page 7
- 7 -
In short, when considered in context and against alternatives, IRAS is a flawed step forward. The Commission can and should take steps to modify the proposal. FERC should exercise its FPA sections 205 and/or 206 authority and find IRAS unjust and unreasonable as a compensatory resource adequacy measure. PJM should instead be directed to resubmit IRAS as requiring non-capacity backed new large loads to take non-firm transmission service. Indeed, PJM’s tariff already contains non-firm transmission services that appear consistent with the proposed curtailment priority to be accorded IRAS.18 Finally, acceptance of an amended IRAS proposal as urged here renders PJM’s proposed RBP duplicative and unnecessary. The Commission should couple acceptance of an amended IRAS proposal with the rejection of the RBP.
PROTEST AND COMMENTS
I. IF PROPERLY IMPLEMENTED, IRAS COULD INSULATE
RATEPAYERS FROM THE CAPACITY COSTS OF SERVING
PROJECTED NEW LARGE LOADS BY REMOVING THOSE
LOADS FROM THE BRA.
The White House’s Ratepayer Protection Pledge states in part that:19
Companies will build, bring, or buy the new generation
resources and electricity needed to satisfy their new energy
demands, paying the full cost of those resources whether by
building, or buying from, new or otherwise additive power
plants. Where possible, these companies will also add more
capacity that serves the broader public by increasing supply.
18 IRAS Filing, Attach. C, Affidavit of Christopher Pilong on Behalf of PJM Interconnection, L.L.C. ¶ 12 & n. 10 (Pilong Aff.).19 Press Release, The White House, Ratepayer Protection Pledge (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. PJM reports that on July 23, 2026, over 282 utilities, cooperatives, data centers, and 23 governors [had] joined the Ratepayer Protection Pledge, including 38 data centers. The signatories included many of the large hyperscaler/data center developers in the generative artificial intelligence (GAI) industry including Amazon, Google, Meta, Microsoft, OpenAI and Oracle. IRAS Transmittal Letter at 4 n.10.
PDF page 8
- 8 -
PJM identifies two aspects of IRAS that it asserts accord with this Pledge. “First, PJM is proposing revisions to the [Reliability Assurance Agreement (RAA)] to clarify a Load Serving Entity’s (“LSE”) obligation to bring new capacity [BYONC] in an amount that equals or exceeds its New Large Loads’ peak load or be subject to load reduction requests during Emergencies prior to Pre-Emergency Load Management Response.”20 Second, “PJM is proposing to exclude from the [Variable Resource Requirement (VRR)] Curve New Large Loads, to the extent they do not have arrangements with sufficient BYONC, beginning with the 2029/2030 Delivery Year.”21
We focus here on the most beneficial ratepayer aspect of IRAS as currently proposed: PJM’s intent to exclude non-capacity backed new large loads from the VRR curve. Beyond the Ratepayer Protection Pledge, PJM’s effort to insulate ratepayers from the capacity costs associated with serving projected new large loads is grounded in the general recognition that data center development and forecasts of data center load are driving increases in PJM capacity costs. The Independent Market Monitor has determined that “[t]he increase in costs to other PJM customers in the 2027/2028 BRA as a result of data center demand was $6,497,653,512. The total increase in costs to other PJM customers as a result of data center load in the last three BRAs was $23,100,955,341.”22 PJM likewise understands what is driving the recent BRA auction shortfalls, observing that it “hosts the largest concentration of data center load in the world.”23 Of the 32 gigawatts (GW) in
20 IRAS Transmittal Letter at 3-4.21 Id. at 23-24. 22 Monitoring Analytics, Analysis of the 2027/2028 RPM Base Residual Auction: Part A at 3 (Jan. 5, 2026), https://www.monitoringanalytics.com/reports/Reports/2026/IMM_Analysis_of_the_20272028_RPM_Base _Residual_Auction_Part_A_20260105.pdf.23 IRAS Transmittal Letter at 13.
PDF page 9
- 9 -
projected load growth between 2024 and 2030 “30 GW . . . is projected to be from data centers.”24 Each megawatt (MW) of new large load that comes into service without accompanying new generation capacity consumes a portion of the resource adequacy margin that would otherwise stand between normal system operations and an emergency. A new large load that adds to peak demand without contributing commensurate new capacity exacerbates PJM’s current and projected capacity shortfall and increases the risk that PJM will be forced to shed load to maintain system reliability.25 As that shortfall increases, the risk of load-shedding increases correspondingly. Left unaddressed, continued large load growth would progressively erode the reliability margin on which existing customers rely.
The stress on PJM’s capacity market is driven by the unique phenomenon of new large data center load—real and projected—that is unlike the diffuse, organic load growth typical of the U.S. electric industry since its inception. The Commission recognizes that large loads are “a separate category of load” and has directed every RTO/Independent System Operator (ISO), including PJM, to define “large load” in their respective tariffs— because, among other considerations, their integration “poses specific challenges to transmission system operation given their size, operational behavior, and unique potential to impact the transmission system.”26
The ability of new large loads to self-supply capacity or default to IRAS is a safeguard to protect ratepayers from excessive capacity costs driven by a small class of customers. The key to this safeguard is the accompanying removal of IRAS load from the
24 Id.25 Id.26 June 2026 Show Cause Order PP 50, 58.
PDF page 10
- 10 -
VRR curve beginning with the 2029/2030 Delivery Year. This mechanism will protect ratepayers from bearing capacity costs that should rightfully be borne by new large loads or otherwise bearing excessive and unnecessary capacity costs associated with phantom load projections. PJM explains the “core logic” of its proposal:27
Large new loads that seek to interconnect to the system
without bringing commensurate new generation capacity
are, in a meaningful sense, free-riding on the reliability
provided by the existing fleet. If the system is short and load
must be shed, there is a defensible argument that these loads
– which imposed incremental demand on a strained system
without yet being able to contribute commensurate supply –
should be curtailed before legacy load that has been served
by and paid into the shared reliability pool.
Interconnecting large load customers that cause the need for network upgrades or system stress are “differently situated” from customers whose presence on the system causes no such burdens. As such, it is fair and permissible to ask a large load customer to bear “the system-reliability burdens that flow from its decision” to operate ahead of the infrastructure needed to support it.28 Existing load has long supported the PJM resource adequacy framework—through reserve-margin planning, capacity-market procurement, and the reliability-coordination function PJM has performed for decades. The present shortfall does not arise from any change in that existing load’s behavior; it arises from rapid incremental demand growth that is materially different in scale and timing from anything the framework has previously accommodated.29 Removing from the BRA the loads that caused the
27 White Paper at 37 (addressing connect and manage predecessor proposal to IRAS).28 Tenaska Clear Creek Wind, LLC v. Sw. Power Pool, Inc., 183 FERC ¶ 61,043, P 24 (2023) (Tenaska). Although Tenaska was decided in the context of an interconnecting generator, the same reasoning applies with respect to new large loads.29 IRAS Transmittal Letter at 21, 99.
PDF page 11
- 11 -
incremental need —rather than including them and spreading the cost consequences among other customers —honors that existing bargain.
IRAS likewise seeks to address the problem of uncertain large load projections that are currently plaguing the BRA. If the projected large loads materialize, then PJM will have a resource adequacy tool to address them. If they fail to materialize, IRAS is unused but available as necessary. In either circumstance, removing these large load projections from the BRA demand curve insulates ratepayers from bearing the capacity costs that would otherwise be associated with meeting these large load projections (though, as discussed more fully below, unless corrected, ratepayers could be required to bear the cost of any curtailment that does occur).
The problem of speculative large load forecasts is real. For example, the data center at issue in the Commonwealth Edison transmission security agreement cancellation litigation has a “maximum planned load of 1,800 MW.”30 Thus, whether this single data center project goes forward has resource adequacy implications exceeding the capacity of a new nuclear power generating unit.31 PJM concedes that “[u]ncertainty [in current large load projections] rises significantly after 2030” but apparently believes that the large amount of data centers currently under construction will achieve commercial operation.32 Perhaps, though the facts on the ground are evolving. In May, a “JP Morgan analysis found
30 Protest of Powerhouse Hillwood Holding LLC and Request for Confidential Treatment at 6, Commonwealth Edison Co., Docket No. ER26-3257 (Aug 14, 2026), eLibrary No. 20260814-5241.31 Units 3 and 4 of Georgia Power’s Vogtle nuclear plant have a combined rating of 2,234 MWs. Nuclear Plant Vogtle, Georgia Power, https://www.georgiapower.com/about/energy/plants/plant-vogtle.html (last visited Sep. 2, 2026).32 PJM, Shaping a Powerful Change: PJM Five-Year Strategy at 5 (Aug. 2026), https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-powerful-change-pjm- five-year-strategy.pdf (Five Year Strategy).
PDF page 12
- 12 -
that more than 60% of data-center capacity planned for completion in 2027 isn’t yet under construction, and another 7% is delayed.”33 Even more recently, Exelon Corporation announced a 7-GW reduction (to 11 GW) in its “high probability” data center load within PJM following a review that resulted in culling out speculative projects.34 In short, PJM’s associated RBP and connect and manage/IRAS proposals have been developed against a backdrop of ever-diminishing large load forecasts. On April 17 of this year, PJM identified an anticipated RBP procurement target of 14.8 GW.35 In a little over three months, that forecast has fallen by more than half, to 6.8 GW, a rate of decline of 2.3 GW per month.36 Concerns about the financial sustainability of forecasted investment in AI
infrastructure add to the uncertainty. The June 2026 Annual Report of the Bank for International Settlements warns that the Artificial Intelligence (AI) “capex [capital expenditure] boom [could transform] into a protracted investment bust”37 and like prior investment booms could “induc[e] economy-wide recession[].”38
In the near term, the ongoing AI investment boom raises
questions about the sustainability of the current economic
expansion. The five largest hyperscalers are set to spend over
a trillion US dollars on AI-related capital expenditure from
33 Katherine Blunt, America’s Data-Center Build-Out Is Falling Way Behind Schedule, Wall Street Journal (June 3, 2026), https://www.wsj.com/tech/ai/americas-data-center-build-out-is-falling-way-behind- schedule-e408a9a8?mod=hp_lead_pos1.34 Ethan Howland, Exelon ‘High Probability’ Data Center Load Falls 40%, Utility Dive (July 31, 2026) https://www.utilitydive.com/news/exelon-data-center-load-new-jersey-battery-earnings/826686/.35 PJM Staff, Reliability Backstop Procurement Design: Reliability Backstop CIFP at 11 (Apr. 16-17, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260416/20260416-item-05--- pjm-reliability-backstop-procurement-design---pjm-presentation.pdf.36 PJM RBP Filing, Attach. C, Affidavit of Danielle Croop ¶ 4.37 Bank for International Settlements, Annual Economic Report at 22 (June 2026), https://www.bis.org/publ/arpdf/ar2026e.pdf (BIS Report). The Bank for International Settlements is one of the most prestigious financial institutions in the world. Its “mission is to support central banks’ pursuit of monetary and financial stability through international cooperation, and to act as a bank for central banks.” BIS, About the BIS (last visited Sep. 3, 2026), https://www.bis.org/about/index.htm. 38 BIS Report at 22-23. See also id. at Graph 11(b) showing potential trillions of dollars in revenue shortfall needed to support capex and debt service in an AI industry downside scenario.
PDF page 13
- 13 -
2025 through 2026. These commitments are outpacing
earnings and the free cash flow of these firms, leading some to issue debt to raise additional financing . . . . This investment race may be partly driven by the perception that only a small number of players with superior technology will ultimately dominate the market shares. . . . As competitive pressure drives capex higher, the net economic surplus – the total payoff less investment costs – declines for the sector as a whole and could turn negative in adverse scenarios . . . . Disappointment in returns could trigger a sudden pullback in financing and turn the capex boom into a protracted investment bust, with potential knock-on effects on financial conditions.
Some see “a basic math problem” at the heart of the generative AI industry:39 There is a fundamental mismatch between the trillions being invested in the infrastructure to develop AI and the billions people and companies are spending to use AI. Specifically, J.P. Morgan Chase analysts anticipate $5 trillion of spending on AI infrastructure between now and 2030. This year alone, four tech companies—Amazon,
Alphabet, Meta and Microsoft— have plans to invest $670 billion on AI infrastructure. When measured as a percentage of U.S. GDP, this is more than the Apollo space program, the U.S. interstate highway system, railroads, and every other major capital expenditure in U.S. history except the Louisiana Purchase, according to the Wall Street Journal. Yet OpenAI and Anthropic have annualized revenues of about $25 billion and $19 billion, respectively. Unless AI revenues grow by orders of magnitude soon, there’s a Grand Canyon-sized gap that will be hard to cross.
The Commission’s “first and foremost duty” under the FPA is to “protect consumers from unjust and unreasonable rates.”40 Here, that means that FERC must act to protect ratepayers against the risk of “a protracted [AI] investment bust,” including the risk of the
39 Ganesh Sitaraman and Asad Ramzanali, We Must Prepare for an AI Bubble Now, TIME (Mar. 26, 2026); https://time.com/article/2026/03/26/we-must-prepare-for-an-ai-bubble-now/.40 Morgan Stanley Cap. Grp. v. Pub. Util. Dist. No. 1 of Snohomish Cty., 554 U.S. 527, 551 (2008). See also Atl. Ref. Co. v. Pub. Serv. Comm’n of N.Y., 360 U.S. 378, 388 (1959) (The FPA’s sister Act, the Natural Gas Act, was “framed as to afford consumers a complete, permanent and effective bond of protection from excessive rates and charges.”).
PDF page 14
- 14 -
costs of capacity procured but ultimately unneeded to serve failing or abandoned AI data center projects. Removing projected new large loads from the BRA going forward, as PJM proposes, is essential to safeguarding ratepayer interests.
II. IRAS SHOULD HELP EASE THE DEMAND PRESSURES
PLAGUING THE BRA.
In planning and administering the regional transmission system, PJM seeks “to meet the demands for firm transmission service, and to support competition, in the PJM Region.”41 The misalignment of supply and demand driven by projected new large loads is an impediment to competition. In a supply-constrained market, new entry cannot perform its function of disciplining the market power of incumbent resources:42
[C]ontinuing to simply accept the interconnection of large
data center loads that cannot be served reliably because there
is not adequate dispatchable capacity, is not a reasonable
path forward and is not an efficient or competitive market
solution and is not a solution of any kind. That path leads to
continued shortfalls, increased reliability issues, continued
maximum prices, and continued calls to abandon markets.43
The answer is not to throw out the BRA baby with the new large load bathwater. “[C]urrent data center issues [should not be] a pretext for redefining fundamental elements of the PJM market design.”44 PJM’s IRAS proposal offers an (albeit flawed) market-based solution for new large loads that seek to connect to the grid while providing a pathway for
41 PJM Operating Agreement, Sched. 6 § 1.1.42 The forward-looking BRA was the product of a settlement with “design features [intended to] discourage the exercise of market power and market manipulation generally. Specific mitigation rules and increased competition from new entry are the most important design elements in this regard.” PJM Interconnection L.L.C., 117 FERC ¶ 61,331, P 6 (2006), reh’g granted in part, 119 FERC ¶ 61,318, reh’g denied, 121 FERC ¶ 61,173 (2007), pet. for review denied sub nom., Pub. Serv. Elec. & Gas Co. v. FERC, 324 Fed. Appx. 1 (2009).43 Monitoring Analytics, L.L.C., State of the Market Report for PJM Q1 2026 at 4 (May 14, 2026).44 Id.
PDF page 15
- 15 -
the BRA to return to a more competitive balance of supply and demand. As discussed above, a central—and essential—IRAS element is that, beginning with the 2029/2030 Delivery Year, PJM will exclude from the BRA VRR demand curve the megawatts of New Large Loads that have not entered into BYONC arrangements, or do not have Allocated RBP Unforced Capacity (UCAP) MW, over and above the megawatts of New Large Loads that were included in the load forecast for the 2028/2029 Delivery Year.45 The competitive market effect follows directly from these mechanics: by removing uncommitted New Large Load MW from the demand curve, and by incentivizing BYONC arrangements that add real, new, and dispatchable capacity to the system, IRAS addresses directly the demand-side driver of the last two BRA shortfalls rather than only adding supply-side procurement on top of an unconstrained and speculative demand baseline.46 Over time, as uncommitted New Large Load MW is either converted to firm, capacity- backed load through BYONC or excluded from the demand curve altogether, the BRA should be expected to reflect a less distorted balance of supply and demand—reducing the frequency and severity of future shortfalls of the kind that gave rise to both the RBP and IRAS proceedings, and moderating the upward trajectory of capacity prices. The numbers bear this out. PJM projects only 2 gigawatts of non-data center load growth between 2024 and 2030.47 On the supply side, PJM notes that there was “a net increase of 1,294.4 MW Installed Capacity (“ICAP”) of supply between the 2027/2028 and 2028/2029 [BRA].”48 PJM also observes that its Reliability Resource Initiative resulted in
45 IRAS Transmittal Letter at 109.46 Id. at 55-58, 109-18 (Parts II.C.3 and II.F). 47 Id. at 13 (quoting June 2026 Show Cause Order P 8 & n.24). 48 Id.
PDF page 16
- 16 -
the “selecti[on of] 51 projects that can come online quickly and provide more than 9,300 MW of reliable capacity.”49 And PJM states in its RBP filing that “[t]he supply-side response to the [Charles Rivers Associates Request for Information] was also significant, with 397 potential projects by 87 entities and approximately 136 gigawatt in total potential capacity,” interested in entering into bilateral arrangements to serve new large load.50 Indeed, there is evidence that PJM is significantly underestimating the amount of Effective Load Carrying Capability (ELCC) already available to serve current load and new load going forward. As explained by a litigant in the RBP proceeding:51 In December 2025, Energy and Environmental Economics,
Inc. (“E3”) delivered to PJM a report titled PJM ELCC / RRS
Model Evaluation. E3 states that it “was retained by PJM to
independently assess PJM’s Effective Load Carrying
Capability / Reserve Requirement Study [RRS] Model . . .
for alignment with industry best practices in loss-of-load-
probability . . . modeling,” and notes that “[t]he outputs of
the ELCC/RRS model are used directly in PJM’s capacity
market.”
E3 determined that if PJM “[u]se[d] more temporal granularity to model capability and deliverability of unlimited resources,” this would reflect “[a]pproximately ~8 GW of additional unlimited resource capability in the winter months.”52 PJM performed its own sensitivity analysis and53
quantified
the
winter
capability
question
directly.
Comparing summer and winter ICAP for unlimited
49 Id. at 19.50 PJM RBP Filing, Transmittal Letter at 18 (RBP Transmittal Letter). See also Charles River Associates, PJM Reliability Backstop RFI Summary (May 27, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-informational-only---reliability- backstop-rfi-summary---charles-river-associates.pdf.51 Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers ¶ 22, Docket No. ER26-3380 (Aug. 20, 2026), eLibrary No. 20260820-5015.52 Id. ¶ 24.53 Id. ¶ 30.
PDF page 17
- 17 -
resources across nuclear, coal, gas combined cycle, gas
combustion turbine, diesel, steam and other thermal classes,
PJM's table shows 163,149 MW of summer ICAP against
171,710 MW of winter ICAP — a difference of 8,561 MW.
E3’s and PJM’s findings are consistent with (a subset of) the recommendation advanced by some of the JCA (in a separate proceeding) that PJM “use winter ratings for combustion resources,” which the JCA witness estimated would result in some additional 5,439 MWs of available UCAP MWs not reflected in the 2025/2026 BRA.54 PJM’s failure to implement these accreditation changes has not been explained, and its inaction is particularly noteworthy given the need to restore competitive balance in the BRA and accurately reflect the amount of available capacity.
As the foregoing shows, there is good reason to believe that PJM’s proposal to remove new large loads from the VRR curve for the 2029/2030 BRA could begin to restore the competitive balance of supply and demand in the auction and there is every reason to do so.
III. WHILE POTENTIALLY BENEFICIAL, IRAS AS PROPOSED IS
FLAWED.
PJM’s principal means of addressing resource adequacy concerns is the BRA. “The objective of [the BRA is] to procure the least-cost, competitively-priced combination of resources necessary to meet the region’s reliability objectives.”55 In proposing IRAS, PJM seeks to respond to the evident concern that the BRA supply-side mechanism is no longer adequate to ensure resource adequacy given projected new data center load. The problem facing PJM is that new supply is unable to keep pace with these load projections, which
54 Complaint of Joint Consumer Advocates and Request for Fast Track Processing, Attach. A, Declaration of Marc D. Montalvo, ¶¶ 20-21, Docket No. EL25-76 (Apr. 14, 2025), eLibrary No. 20250414-5190.55 N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 101 (3d Cir. 2014) (quoting PJM Interconnection, L.L.C., 137 FERC ¶ 61,145, P 90 (2011) (subsequent history omitted)).
PDF page 18
- 18 -
are driven primarily by (uncertain) forecasts of new data centers. According to PJM affiant Pilong:56
New Large Loads are developing more quickly than
generation and transmission can be built. As a result, this
may impact the ability for PJM to maintain a reliable system
and continue to meet the demand for existing customers and
maintain reserve requirements during times of peak demand
and/or significant generator outages. Therefore, a new
operational tool is needed to ensure the current level of
reliability for our customers is maintained.
The White Paper explains that “[t]oday, due to compounding frictions in siting,
permitting, supply chains and interconnection, it can take two or three times as long to build a gas resource as it does to build a hyperscale data center.”57 Other resources, such as renewables combined with battery storage, may not face the same supply-chain
difficulties as gas combustion turbine generators, but nevertheless face permitting, financing and other project—including regulatory—hurdles.58 “[T]he addition of new supply has not kept pace with rapid large load demand growth, thus giving rise to the significant tightening of the capacity market in recent years and subsequent resource adequacy shortfalls.”59
Given the uncertainties of new generation supply-side capabilities to meet regional resource adequacy needs, PJM here proposes IRAS as a demand response solution, aimed
56 Pilong Aff. ¶ 19.57 White Paper at 18.58 See, e.g., Comments of the Solar Energy Industries Association at 9-12, PJM Interconnection, L.L.C., Docket No. ER26-3380 (Aug. 21, 2026), eLibrary No. 20260821-5105 (identifying barriers to entry resulting from PJM rules governing surplus interconnection service).59 IRAS Transmittal Letter at 13. See also id. at 21 (highlighting “the ‘unprecedented surge in data center load’ at a faster pace than new supply can come online, and the ‘speed of connecting these large loads creates a fundamental misalignment between demand and supply cycles,’ resulting in ‘resource adequacy in the PJM service area [being] under significant stress.’” (quoting PJM, 2027/2028 Base Residual Auction Reserve Target Shortfall Report at 1-4 (Feb. 9, 2026), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm- auction-info/2027-2028/2027-2028-bra-reserve-target-shortfall-report.pdf)).
PDF page 19
- 19 -
at ensuring resource adequacy while requiring the data center loads that are causing the problem either to bring sufficient capacity to address their contribution to the concern or face the possibility of curtailment should a system problem arise. Under the proposal, PJM will calculate the amount of IRAS it needs to procure each year based on BRA shortfalls,60 identify amounts of available IRAS from the Large Load Registry based upon new large loads that have not procured BYONC,61 and when needed direct EDCs with IRAS loads to implement necessary curtailments consistent with state/RERRA regulation.62 IRAS is an interim resource adequacy measure. Under PJM’s proposal, New Large Loads eligible for IRAS procurement will terminate after three consecutive Delivery Years when the BRA clears with sufficient capacity to obviate the need for IRAS. If the BRA thereafter clears short, however, subsequent New Large Loads will become eligible for IRAS.63 As proposed, IRAS is a potentially beneficial—but flawed— means to ensure resource adequacy and manage the reliability problem posed by new large data center loads.64 Rather than treating non-capacity-backed load as involuntary, compensated demand response, IRAS should return to its connect and manage roots and require non- capacity backed new large loads to take non-firm transmission service. Making this change should not require a major sea-change or novel tariff development, as PJM already has a
60 IRAS Filing, Attach. A, Attach. DD-4 §§ IV(b)-(c) (Attach. DD-4).61 Id.62 IRAS Transmittal Letter at 79 (“[I]t is appropriate for PJM to direct Electric Distributors to reduce those New Large Loads that have failed to cover their capacity obligations . . . .”).63 Id. at 77. See also id. at 79, fig. 1; Pilong Aff. ¶¶ 35-47.64 As discussed below, to the extent IRAS is called upon, this will impose unnecessary costs on ratepayers, compared to a requirement that new large loads that do not BYONC will be served by non-firm transmission service akin to PJM’s original connect and manage proposal.
PDF page 20
- 20 -
Commission-approved menu of non-firm service options and a set of curtailment priorities with respect to co-located loads.65
Similar actions have been taken elsewhere. Texas has successfully used a “connect and manage” non-firm transmission service approach to manage large amounts of new data center load for over a year.66 In a similar vein, the Commission has approved SPP’s implementation of “a new type of non-firm transmission service called Conditional High Impact Large Load Service (CHILLS)” to serve new high impact large loads such as large data centers.67 The Commission found that CHILLS is “narrowly tailored to reflect the interim nature of CHILLS and the unique characteristics of the CHILLs that transmission customers will serve.”68 The Commission has explained that CHILLS allows transmission customers serving new large loads (such as data centers) “to reliably receive transfers of energy [subject to curtailment and interruption] until sufficient designated resources and/or network upgrades are in place to support long-term firm transmission service.”69 Along the same lines, the academic literature likewise supports the conclusion that flexible transmission service is a feasible means of expediting the connection of new large data center load to the grid while protecting ratepayers. In 2025, Norris et al. estimated that
65 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209, P 551 (2026); see also Pilong Aff. ¶ 12.66 An Act Relating to the Planning for, Interconnection and Operation of, and Costs Related to Providing Service for Certain Electrical Loads and to the Generation of Electric Power by a Water Supply or Sewer Service Corporation, S.B. 6, 89th Tex. Leg. (enacted June 20, 2025). Although the Governor of Texas has imposed a moratorium on new large load interconnections and ERCOT is performing a new large load interconnection audit, connect and manage is operative in ERCOT as a resource adequacy measure with respect to the substantial amount of data center load already on the system. Robert Walton, ERCOT aims to complete Texas governor’s data center audit by December, Utility Dive (Aug. 21, 2026), https://www.utilitydive.com/news/ercot-texas-puc-data-center-audit/828472/.67 Sw. Power Pool, Inc., 195 FERC ¶ 61,196, P 1 (2026) (SPP CHILLS Order).68 Id. P 85.69 IRAS Transmittal Letter at 4 (alteration in original) (quoting June 2026 Show Cause Order P 17).
PDF page 21
- 21 -
PJM could serve an additional 18 GW of load using interruptible service at “0.5% annual curtailment” of their maximum uptime without adding new generation.70 Other
commentators have noted the ability of data centers to self-supply or operate with flexible service:71
Large loads can deliver on flexibility commitments by
moderating their energy consumption and by meeting
electricity needs through nearby resources that provide
power without relying on the transmission system. Data
centers—which comprise the largest share of expected
growth in large loads, and which are typically conceived of
as
inflexible
loads—can
modulate
compute-related
consumption by scaling down computing power for tasks
that are less performance-sensitive (including some AI
training tasks), postponing tasks that are less time-sensitive,
or shifting tasks that are less location-sensitive to other sites.
Data centers may also be able to reduce consumption in
certain circumstances by modulating cooling system
consumption.
The trade press is rife with reports that one of the core bottlenecks delaying the construction and commercial operation of new data centers is access to electrical power: “Alphabet, Amazon, Meta, and Microsoft remain on track to deploy more than $650 billion in 2026 on AI infrastructure, with some projects now expected to wait up to five years for utility power interconnection.”72 Although PJM’s focus in proposing IRAS is to ensure
70 Tyler H. Norris et al., Rethinking Load Growth Assessing the Potential for Integration of Large Flexible Loads in US Power Systems at 2, Nicholas Institute for Energy, Environment & Sustainability at Duke University (Feb. 2025), https://nicholasinstitute.duke.edu/publications/rethinking-load-growth.71 Sam Walsh et al., Leveraging Large Load Flexibility to Facilitate Access to Power While Protecting Customers: Considerations for State Regulators at 6, Nicholas Institute for Energy, Environment & Sustainability at Duke University (Mar. 2026) (footnote omitted) (citing Williams et al., Power-Flexible AI Factories: A UK-First Demonstration of Grid-Responsive AI Infrastructure, National Grid (March 2026), https://ngpartners.cdn.prismic.io/ngpartners/aabLtVxvIZEnjRNr_v11_emerald-ai_march2026.pdf), https://nicholasinstitute.duke.edu/publications/leveraging-large-load-flexibility-facilitate-access-power- while-protecting-customers.72 Nadia Dubois, Half of U.S. AI Data Centers Delayed or Canceled: Inside the 7 GW Capacity Crisis Reshaping a $650B Buildout, Tech Insider (Apr. 17, 2026), https://tech-insider.org/us-ai-data-center-delays- cancellations-7gw-capacity-crisis-2026/.
PDF page 22
- 22 -
resource adequacy,73 IRAS could also help to unlock currently untapped electrical service within PJM for new data centers by means of flexible service.
Although PJM has proposed IRAS as a new interim resource adequacy product,74 it is functionally akin to the interim non-firm CHILLS transmission service used to serve large data center load in SPP and the connect and manage non-firm transmission service used for that purpose in ERCOT—albeit with the unjust and unreasonable possibility of ratepayers potentially having to compensate New Large Loads when they are curtailed. The solution to these concerns is for FERC to direct PJM to refile IRAS as non-firm transmission service.
IV. THE COMMISSION SHOULD EXERCISE EITHER ITS FPA
SECTION 205 OR SECTION 206 AUTHORITY TO DIRECT PJM
TO MAKE IRAS A NON-FIRM TRANSMISSION SERVICE.
While IRAS offers the promise of significant customer benefits, it also suffers from a serious flaw. PJM proposes it as a compensable resource adequacy measure. “PJM is proposing a rate for IRAS that is equal to 50% of the Non-Performance Charge Rate.”75 “Electric Distributors bear the responsibility to implement the compensation scheme for New Large Loads that provide the IRAS load reduction service,”76 and PJM envisions a collaborative state/federal arrangement where new large loads receive payment for their
73 See IRAS Transmittal Letter at 90 (“[T]he reforms in this filing address issues that the FPA’s drafters would have certainly considered science fiction—the resource adequacy impacts of New Large Loads, including data centers, driven primarily by exponential technological advancements in artificial intelligence.”).74 “IRAS is a supplemental capacity product through which Eligible New Large Loads may be directed by the Electric Distributor to reduce their load in response to an Interim Resource Adequacy Service Action called by PJM.” Id. at 74.75 IRAS Transmittal Letter at 102. 76 Id. at 101.
PDF page 23
- 23 -
service interruption.77 PJM’s proposal to compensate new large loads for interruptible service is contrary to precedent, a departure from the Ratepayer Protection Pledge, and a potential windfall to new large loads who must take interruptible service to mitigate the reliability risks posed by their connection to the grid that are not met through BYONC. As described above, PJM’s current service offerings include some new forms of non-firm transmission.78 Similarly, the Commission, in the SPP CHILLS Order, approved the applicant’s implementation of “a new type of non-firm transmission service called [CHILLS].”79 This new non-firm service enables transmission customers serving new large loads (such as data centers) “to reliably receive transfers of energy [subject to curtailment and interruption] until sufficient designated resources and/or network upgrades are in place to support long-term firm transmission service.”80 PJM nowhere in its filing addresses why it has proposed IRAS as a compensable resource adequacy measure, as opposed to non- firm transmission service akin to the service arrangement the Commission approved in the SPP CHILLS Order.
At its core, PJM’s compensable IRAS service defeats the goal of the rate design. PJM portrays IRAS as providing new large loads a choice between bringing their own new capacity or taking interruptible IRAS. But unlike the arrangement in the SPP CHILLS Order, which “incentivize[s] transmission customers . . . to obtain the designated resources and/or complete the network upgrades needed to procure long-term firm transmission
77 “The IRAS rate is compensation for a wholesale load reduction service, but the entities to be paid the rate and the loads to be charged to support such compensation must be determined at the state level consistent with the Electric Distributor’s state-approved load reduction plans and other state-approved programs, rates, and rules.” Id. at 104.78 See supra note 69. 79 SPP CHILLS Order P 1.80 IRAS Transmittal Letter at 4 (quoting June 2026 Show Cause Order).
PDF page 24
- 24 -
service,”81 new large loads will receive firm transmission service regardless of whether they bring their own new capacity. “Load reduction under [IRAS] appropriately treats New Large Loads as [network integration transmission service ] customers.”82 What this means is that new large loads are presented with the cost-benefit choice of either providing compensable interim resource adequacy service or offering some other form of qualifying new resource. Unlike the CHILLS service in SPP, by offering the potential of curtailment compensation, IRAS does not necessarily incent new large loads in PJM to obtain new self- supply resources to avoid possible curtailments.
PJM’s claims aside, IRAS is not consistent with the Ratepayer Protection Pledge. As proposed, IRAS will serve to insulate ratepayers from the increased capacity costs associated with: (i) simply connecting more and more new large data center load to the grid faster than resources can be built to serve it; or (ii) including speculative new data center load forecasts in the VRR demand curve. Nevertheless, it is fundamentally contrary to the Ratepayer Protection Pledge for PJM to include the possibility that other customers will be obliged to pay new large loads for taking the interruptible service that is a prerequisite to those loads connecting to the grid without unduly impairing system reliability. PJM seeks to justify IRAS as “similar to the Pre-Emergency Load Response Program.”83 But that comparison rests upon a fact that PJM’s filing fails to clarify. Load participating in the Pre-Emergency Load Response Program has paid and is paying its ratable share of BRA capacity costs and is making the choice of foregoing the benefits of the firm service it paid for by providing demand response in Pre-Emergency Load
81 June 2026 Show Cause Order P 17.
82 IRAS Transmittal Letter at 100.83 Id. at 103.
PDF page 25
- 25 -
Response conditions. Beginning with the proposed implementation of IRAS in the 2027/2028 Delivery Year, PJM intends to treat non-capacity backed new large loads as taking network transmission service. What this should mean is that these new large load customers will pay their ratable share of BRA capacity costs. But PJM’s filing fails to explain whether this is so, leaving the possibility that that service to new large loads is being treated simultaneously as both capacity backed and non-capacity backed. Beginning with the 2029/2030 Delivery Year, new large loads will be excluded from the VRR demand curve.
But even if PJM proposes to allocate BRA capacity costs to new large loads, they are only being allowed to come on to the system by means of taking interruptible service, because PJM has determined that for them to do otherwise jeopardizes system reliability. As far as we can tell, PJM is both declaring that non-capacity backed new large loads are taking firm network transmission service but also involuntarily providing a type of compensable demand response. The Commission analyzes compliance with the cost causation principle “by comparing the costs assessed against a party to the burdens imposed or benefits drawn by that party.”84 Here, it is the new large loads that are the causal basis for IRAS. And as regards the benefits of IRAS, “FERC is not authorized to approve a pricing scheme that requires a group of [customers] to pay for [services] from which its members derive no benefits, or benefits that are trivial in relation to the costs sought to be shifted to its members.”85 Other customers are not benefiting from new large loads taking
84 Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004).85 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009).
PDF page 26
- 26 -
interruptible service because that is the minimum safeguard necessary for these new large loads to interconnect with the PJM grid.
Although PJM has made no effort to calculate the potential adverse cost impact if IRAS compensation obligations are visited on other customers, there is reason to believe that the cost of that obligation could be substantial. FERC approved a 50% reduction on the Non-Performance Charge Rate for purposes of the Pre-Emergency Load Response Program penalty rate “‘to appropriately reflect that such events may be twice as common’ as [Performance Assessment Interval (PAI)] events.”86 The Commission, market
participants, and stakeholders recognize that PAI Non-Performance Charge penalties can be substantial. Due to generator non-performance during Winter Storm Elliot, PJM initially assessed $1.8 billion in PAI penalties, an amount reduced in settlement to $1.25 billion.87 While currently unknown, PJM’s projections indicate that it is possible that the amount of new large load eligible for IRAS could be substantial, and as much as several thousand megawatts.88 Other customers should not bear any costs—let alone millions of dollars—as an accommodation to new large loads. The just and reasonable approach is to require new large loads that do not bring their own new capacity to take non-firm transmission service, consistent with service offerings within PJM and the Commission’s decision in the SPP CHILLS Order.
86 PJM Interconnection, L.L.C., 195 FERC ¶ 61,253 P 14 (2026).87 PJM, Winter Storm Elliott Performance Assessment Interval Settlement Agreement Frequently Asked Questions For Public Use at 3 (Dec. 20, 2023), https://www.pjm.com/-/media/DotCom/markets-ops/winter- storm-elliott/ferc-settlement-faq.pdf. “About 45,950 MW, or 23.2% of PJM’s generating fleet, was unexpectedly offline on Dec. 24, mainly because of plant equipment that didn’t operate and fuel supply problems . . . .” Ethan Howland, PJM generators face up to $2B in penalties for failing to run during December’s Winter Storm Elliott, Utility Dive (Jan. 12, 2023) https://www.utilitydive.com/news/pjm- generators-penalties-power-winter-storm-elliott/640242/.88 From 2024 to 2030, PJM projects 30 GW of additional data center load. IRAS Transmittal Letter at 13.
PDF page 27
- 27 -
The alternative is to prohibit new large loads from coming on to the system altogether unless they BYONC or the BRA secures sufficient resources to serve them. There is no principle of utility law that requires service to customers that jeopardizes utility operations, let alone system reliability. PJM is no stranger to service moratoriums and sought and obtained approval of a multi-year suspension of its interconnection process.89 Although uncommon, moratoriums denying the provision of service to new customers to preserve system reliability are a feature of the utility landscape. For example, in 1971, local regulators authorized Washington Gas to suspend the provision of service to new customers due to the unavailability of natural gas, a service restriction that lasted almost six years.90 Of particular relevance here, Texas, which has adopted a connect and manage non-firm transmission approach to accommodate new large loads, has suspended data center interconnection requests in response to the Governor of Texas’s request for a moratorium due to the threat posed to ERCOT reliability. The Governor’s letter explains:91 The Electric Reliability Council of Texas (ERCOT) is
currently considering approximately 474 gigawatts of
requests to connect to the Texas grid. That is more than five
times Texas’ record peak electricity demand for ERCOT.
Approximately 90 percent of the new power requests are
data centers. That unprecedented load growth could
endanger the reliability and stability of the Texas electric
grid.
89 PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 (2022).90 Washington Gas, Growing With Washington, Part III at 44 (2012), https://cdn.prod.website- files.com/68c82ad46f5fe4c05f17bdf0/68f264a6a9f3949565d0c8d1_growing_with_washington_part- 2_ch_3.pdf.91 Letter from Governor Greg Abbott to Mr. Thomas Gleeson, Chairman, Public Utilities Commission of Texas at 1 (Aug. 3, 2026).
PDF page 28
- 28 -
PJM also seeks to defend its “IRAS framework [as] strik[ing] a straightforward bargain.”92 PJM makes clear that part of this so-called bargain is that “[t]hese Eligible New Large Load customers will be compensated under the IRAS framework to the extent that they reduce load pursuant to IRAS and do not waive compensation.”93 But a bargain implies that there are parties on both sides of a dispute agreeing to a package of gives-and-takes. There is no such bargain here. IRAS is not the product of a settlement. It did not receive stakeholder approval. Indeed, PJM first proposed compensation for IRAS after the June 30, 2026, conclusion of the stakeholder process. The “bargain” was first announced as part of the Board’s July 27, 2026 decision, and explained in a July 31, 2026 presentation.94
In addition, PJM seeks to defend its compensation proposal because it “provides Electrical Distributors and states flexibility in the applicable IRAS rate for its territory, and affords the New Large Load the ability to waive compensation.”95 That is not an adequate safeguard for PJM ratepayers. While new large loads could waive compensation, it is not in their economic interests to do so. This means that cost responsibility for PJM’s IRAS proposal is neither fixed nor predictable. The inability of PJM ratepayers to know whether they will be subject to IRAS compensation charges falls well short of the “irreducible minimum of detail needed for a valid formula rate.”9692 IRAS Transmittal Letter at 94.93 Id.94 See supra note 8.95 IRAS Transmittal Letter at 102.96 Pub. Utils. Of Cal. v. FERC, 254 F.2d 250, 255 (D.C. Cir. 2001).
PDF page 29
- 29 -
The Commission should adhere to the approach adopted in the SPP CHILLS Order and act in a manner consistent with the Ratepayer Protection Pledge. Specifically, FERC should find IRAS to be unjust and unreasonable, and, as explained at the outset, direct PJM—whether pursuant to sections 205 or 206—to refile its IRAS proposal not as a compensable resource adequacy service but instead as a requirement that new large loads that do not self-supply must take non-firm transmission service.
V. PJM’S PROPOSAL IS FLAWED BECAUSE IT IMPROPERLY
TREATS AS “NEW” CAPACITY THAT PREVIOUSLY CLEARED
A BASE RESIDUAL AUCTION.
IRAS is intended to enable PJM to address auction shortfalls and ensure system reliability.97 Because new large loads are driving BRA shortfalls, PJM proposes through IRAS to require these loads either to bring their own new capacity or be subject to curtailment (depending upon state load shed protocols). But PJM’s eligibility criteria defeat that objective by allowing new large loads to satisfy their BYONC and avoid curtailment with capacity that has already cleared in the BRA.98 Such capacity should not be considered the additional or “new” capacity PJM needs to redress the recent series of auction shortfalls. PJM knows this. PJM’s treatment of capacity that has previously cleared an auction as “new” for IRAS purposes cannot be reconciled with its treatment of “new” capacity for the proposed RBP. Both initiatives are intended to redress the recent series of BRA shortfalls. PJM explains in its RBP filing that “[t]he RBP is focused on procuring new capacity. Thus, to be eligible to be offered into the RBP, a resource must: (1) never have
97 IRAS Transmittal Letter at 6.98 Attach. DD-4 § VI(a)(i) (“Capacity Resources that cleared an RPM Auction for the first time in the Base Residual Auction for the 2027/2028, 2028/2029, and 2029/2030 Delivery Years may qualify as BYONC to the extent the underlying resource meets the criteria in subsection (b) below.”).
PDF page 30
- 30 -
been committed to provide capacity; [and] (2) not have been the subject of a notice of intent to participate in an RPM Auction prior to and including the 2028/2029 Delivery Year, but if so, must have offered and not cleared any RPM Auction.”99
But the outcome under IRAS is different. As explained in the filing’s Transmittal Letter, “[g]iven that PJM is currently short of capacity and looking to reestablish a healthy capacity reserve margin, . . . any capacity added to the system starting with the 2027/2028 BRA will qualify as new—subject to the gating criteria.”100 This explanation makes no sense: the shortfall in the 2027/2028 BRA is one of the reasons PJM is proposing IRAS.101 PJM suggests that its proposal accommodates purported reliance interests. “Given that New Large Loads are included in the RPM Auctions through the 2028/2029 Delivery Year and eligible BYONC that previously cleared an RPM Auction through the 2028/2029 Delivery Year was not on notice of this limitation, any eligible BYONC that is offered in RPM Auctions through the 2028/2029 Delivery Year can be procured by New Large Loads to avoid IRAS.”102 The seller’s purported reliance interest is irrelevant: the seller’s bid has been selected and the seller has a must offer obligation going forward. But the benefit of this arrangement goes to new large loads—on whose part PJM posits no reliance. Most importantly, PJM nowhere addresses the reliability consequences of this loophole, which include the procurement of a smaller amount of IRAS against an unreduced shortfall. A simple example should flesh out the problems in treating capacity that has cleared an auction as “new” capacity. Assume that prior to the start of the 2028/2029 Delivery
99 RBP Transmittal Letter at 51 (original emphasis) (footnote omitted).100 IRAS Filing Transmittal Letter at 52.101 Id. at 6.102 Id. at 115 n.302.
PDF page 31
- 31 -
Year, new large loads had acquired 6.8 gigawatts of otherwise BYONC-eligible capacity that had cleared in the 2027/2028 BRA. The 2028/2029 BRA auction fell short of PJM’s reliability requirement by 6.8 gigawatts.103 Pursuant to PJM’s IRAS protocol, PJM would look to the Large Load Registry to identify 6.8 GWs of new large load eligible for IRAS in the 2028/2029 Delivery Year. But PJM would not find any. The new large loads who purchased the 6.8 GWs of previously cleared capacity would not be listed in the Registry as eligible for IRAS because they had brought their own “new” capacity.104 The auction shortfall would still exist, but PJM would not have an amount of curtailable IRAS to address its reliability needs in the 2028/2029 Delivery Year. This result holds true for any amount of capacity that new large loads procure that had cleared the 2027/2028 BRA. For IRAS to meet its intended purpose, the BYONC eligibility criteria must be revised and limited to capacity that, as with the RBP, has not cleared a prior BRA auction.
VI. THE COMMISSION SHOULD CONDITION ACCEPTANCE
UPON REVISIONS TO THE LARGE LOAD REGISTRY.
As stated in proposed Attachment DD-4 to the Tariff, PJM shall maintain a Large Load Registry, which “shall inform which New Large Loads are eligible to be called on to provide Interim Resource Adequacy Service.”105 PJM acknowledges that the successful implementation of IRAS is premised upon the inclusion of accurate data in the proposed Registry, explaining:106
The information provided in the Large Load Registry will
form the foundation for an accurate, complete, and reliable
103 RBP Transmittal Letter at 7.104 In a Delivery Year where IRAS applies, the MW subject to IRAS that PJM will allocate to an Electric Distributor zone/area will be limited to the MW quantity of New Large Loads in that zone/area without arrangements for BYONC or RBP UCAP MW allocated to them.” IRAS Transmittal Letter at 40.105 Attach. DD-4 § I(c).106 IRAS Transmittal Letter at 43-44 (footnote omitted).
PDF page 32
- 32 -
database that will inform, inter alia, decisions about the MW
quantity of New Large Loads that is available to provide
IRAS in a Delivery Year.
PJM is aware that false or misleading statements about, for
example, Peak Load Contributions could give rise to
inaccurate baselines on which PJM would rely in the course
of determining Eligible New Large Load Amounts, i.e., the
MW value of load that an Eligible New Large Load in a
given zone/area may be required to be made available for
IRAS.
The proposed Tariff language creating the Registry includes details on the various types of information to be provided to PJM. But the obligation to submit the information falls on the EDCs rather than the large loads themselves. The duty to populate the Registry falls on “[e]ach Party,” which must “submit, or cause to be submitted,” the required information “related to each Large Load served by the Party.”107 Electric Distributors, in turn, are required to provide “any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry.”108 The new large load itself— the entity that presumably possesses firsthand knowledge of its peak, ramp, in-service timing,
backup
generation,
and
coverage—apparently
bears
no
affirmative,
tariff-expressed obligation either to submit data or to substantiate them. Given the importance of the information provided for inclusion in the registry, PJM states in its Transmittal Letter that it “will review the information provided and coordinate with the applicable Transmission Owner and Electric Distributor to check the validity of the information provided, request additional information if needed, and consult with the
107 IRAS Filing, Attach. A, Sched. 11 § B.1(a) (“Each Party shall submit, or cause to be submitted, to the Office of the Interconnection the following information . . . related to each Large Load served by the Party”). The obligation thus runs to the Party serving the load (the LSE), not to the Large Load; no provision of the proposed Tariff imposes a submission or substantiation duty on the New Large Load itself. 108Attach. DD-4 § III(b) (Electric Distributor to provide “any information or data the Electric Distributor believes appropriate to facilitate an accurate Large Load Registry”).
PDF page 33
- 33 -
Large Load.”109 Unfortunately, this level of commitment is not matched by the proposed Tariff language. The proposed revisions to Tariff Schedule 11 phrase PJM’s obligation to assess the validity of the data received to create the Registry in permissive terms, stating that PJM, “may review information and coordinate with the applicable Transmission Owner and Electric Distributor as needed, regarding the validity of the information provided, including through requesting additional information as the Office of the Interconnection deems necessary,” and “also may consult with the Large Load.”110 Given that the Registry is essential to the success of IRAS, PJM should be required to review and validate the information provided to populate it. The Commission should condition any approval on PJM modifying the Tariff language to make mandatory PJM’s obligation to vet and verify data provided in connection with the establishment of the Registry.
Separate from the vetting issues, PJM’s Registry proposal includes two
unreasonable restrictions on access to Registry data: (1) State Consumer Advocates111 are missing from the list of entities that can access the Registry; and (2) even those entities that can do so are subject to onerous and perhaps insurmountable confidentiality restrictions. These limitations are unreasonable, particularly given the important role that states are anticipated to play in IRAS implementation.
PJM’s proposal specifies the entities that “may” access the Large Load Registry and the conditions under which they may do so.112 Access to the Registry is confined to
109 IRAS Transmittal Letter at 43 (emphasis added).110 IRAS Filing, Attach. A, Sched. 11 § B.1(c) (emphasis added).111 See id. § B.1(d).112 IRAS Transmittal Letter at 28.
PDF page 34
- 34 -
“Authorized Commissions, Transmission Owners, Electric Distributors, Load Serving Entities, the Market Monitoring Unit, and FERC.”113 “Authorized Commission” is defined in the PJM Operating Agreement:114
“Authorized Commission” shall mean (i) a State public
utility commission that regulates the distribution or supply
of electricity to retail customers and is legally charged with
monitoring the operation of wholesale or retail markets
serving retail suppliers or customers within its State or (ii)
an association or organization comprised exclusively of
State public utility commissions described in the
immediately preceding clause (i) [presumably, the
Organization of PJM States, Inc. (OPSI)].
PJM’s RAA includes a separate Tariff definition for “State Consumer Advocate,” defined as “a legislatively created office from any State, all or any part of the territory of which is within the PJM Region, and the District of Columbia established, inter alia, for the purpose of representing the interests of energy consumers before the utility regulatory commissions of such states and the District of Columbia and the FERC.”115 State Consumer Advocates are PJM voting members. The JCA are all State Consumer Advocates, required by state statute to represent the interest of retail customers. PJM should be directed to modify the definitions such that State Consumer Advocates have access to the Registry. The information available in the Registry will play a central role in their advocacy efforts. The offices need these data to seek and support IRAS curtailment protocols that ensure that new large loads are curtailed before other retail load. Similarly, these advocates will need access to this data to challenge any proposal that
113 IRAS Filing, Attach. A., Sched. 11 § B.1(d).114 PJM Operating Agreement, Definitions A-B.115 PJM Reliability Assurance Agreement, art. 1, Definitions. This definition of State Consumer Advocate tracks the definition of State Consumer Advocate in the Operating Agreement. See PJM Operating Agreement, Definitions S-T.
PDF page 35
- 35 -
other retail customers fund demand response payments to the new large loads that must take curtailable service in order to come on the system.
The Registry’s proposed confidentiality provisions pose another unreasonable obstacle—both to State Consumer Advocates seeking to carry out their regulatory missions, and to state commissions seeking to exercise their oversight function. All entities must comply with “appropriate data protection safeguards required by Operating Agreement, section 18.17.”116 Specifically, to “the extent such documents, data, or other information provided to” PJM “has been designated as confidential by a Party, Electric Distributor, or other entity supplying the information,” then PJM “shall maintain the confidentiality of the information provided under this RAA, Schedule 11, section B consistent with its obligations under Operating Agreement, section 18.17.”117 Put another way, if a Party118 to the RAA, Electric Distributor, or any un-identified “entity” (such as a new large load) that is “supplying information” to PJM, decides that any such information headed for the Large Load Registry is confidential, then that entity may request that their information be included in the Registry, and it will thereafter be subject to the “appropriate” data protection safeguards set forth in Section 18.17.
Most significant to the Large Load Registry, Section 18.17.4 governs the disclosure of confidential information to Authorized Commissions (i.e., the PJM state commissions and OPSI). Under Section 18.17, an Authorized Commission may only request access to confidential information after successfully completing a certification process with FERC
116 IRAS Filing, Attach. A, Sched. 11 § B.1(d).
117 Id.
118 “Party” is defined as “an entity bound by the terms of the Operating Agreement.” See PJM Reliability Assurance Agreement, art. 1, Definitions.
PDF page 36
- 36 -
that will, at a minimum, take over three months to complete, if successful at all.119 As reported by PJM on its website, only six of the 14 state commissions in the PJM footprint have completed the FERC certification process and have the opportunity to post their list of “authorized persons” who may receive confidential information successfully requested by the Authorized Commission.120 It does not appear that OPSI has completed the required FERC certification, though it is included in the definition of Authorized Commission. For the remaining eight state Authorized Commissions (and OPSI),121 there is no guarantee of obtaining FERC certification. Timing considerations alone counsel that most Authorized Commissions will not obtain certification before the IRAS proposed effective date. And even if an Authorized Commission has been FERC-certified, it must still engage in a PJM process to request confidential information. The Authorized Commission must specify the confidential information it is requesting and provide “a general description of the purpose” of the Authorized Commission in making the request.122 Both PJM and an “affected” PJM Member may object to the release of the confidential information.123 Such objections are to be resolved first with a conference, but absent resolution may lead to the
119 PJM Operating Agreement § 18.17.4(a)(i). Section 18.17.4(a)(i) specifies that “[e]ach party shall bear its own costs in connection with such a FERC protest proceeding.” It is unclear what other party would pay the costs of a party’s protest.120 PJM, State Commissions, Authorized Persons Schedule, https://www.pjm.com/committees-and- groups/state-commissions (last visited Sep. 3, 2026). According to the posting of authorized person lists, it appears that the six state commissions that have obtained FERC certification are Indiana, Maryland, New Jersey, Ohio, Pennsylvania, and Virginia. Illinois, Delaware, Michigan, Tennessee, Kentucky, North Carolina, West Virginia, and the District of Columbia are not on the list.121 While it appears that OPSI has not attempted the certification process at FERC, OPSI may take on an enhanced role in governance at PJM. See, e.g., Post-Technical Conference Joint Comments of the Organization of PJM States, Inc. and PJM Governors’ Collaborative, PJM Governance & Stakeholder Reforms, Docket No. AD26-7 (Aug. 21, 2026), eLibrary No. 20260821-5102.122 PJM Operating Agreement § 18.17.4(c)(i).123 Id. § 18.17.4(c)(iii).
PDF page 37
- 37 -
filing of a FERC complaint.124 While how and when such complaints would be resolved is unclear, what is clear is that absent resolution, state commissions may never see the information, let alone have access in a timely manner.
We recognize that changes to the Tariff process for handling confidential information is beyond the scope of this proceeding. But the inability of consumer representatives to review Registry data that is the lynchpin of the IRAS proposal renders the proposal unjust and unreasonable. State Consumer Advocates should have express authorization to access the Large Load Registry because doing so will provide the strongest likelihood that retail ratepayers will be protected from the imposition of costs and curtailment impacts wrought by the presence of new large loads. And both they and their respective state commissions should have access to any information designated confidential by means of adequate protective orders or other forms of certification. At its core, the successful implementation of IRAS depends upon successfully engaging federal and state actors—which can happen only where the necessary transparency protections are in place.
VII. THE ACCEPTANCE OF IRAS IS FURTHER REASON TO
REJECT RBP.
Pursuant to its RBP proposal, pending before the Commission in Docket No. ER26-3380-000, PJM seeks to procure an initial target of 6.8 gigawatts of new capacity for 15-year terms (or less) beginning with the 2028/2029 Delivery Year until the 2042/2043 Delivery Year at an average price of $555/MW-day.125 The RBP is proposed as a “one-
124 Id. The grounds for filing such a complaint are set forth in Section 18.17, and they are expansive, including the existence of “exceptional circumstances . . . such that complying with the Information Request would result in harm to the complainant.” Id.125 See JCA RBP Protest at 5-7, 13-14 (describing PJM RBP Filing).
PDF page 38
- 38 -
time, supplementary mechanism” and an “interim step” to address a “near-term” shortfall,126 and identifies its object as a discrete, near-term reliability gap rather than a durable long-term deficiency. The Initial RBP Target is the 6,831.3 MW UCAP shortfall observed in the July 2026 BRA for the 2028/2029 Delivery Year.127
Provided that the Commission fixes the BYONC eligibility requirements to exclude resources that have cleared in a BRA auction, FERC’s acceptance of IRAS—either in its current form or as correctly modified as non-firm transmission service—obviates the need for the RBP. IRAS, like the RBP, is a resource adequacy measure intended to address a large load-induced capacity shortfall. The difference between the two proposals is that IRAS can satisfy the capacity need at which the RBP is aimed sooner, more durably, and, if correctly modified as non-firm transmission service, at less cost. “IRAS ‘is a load reduction service, effective starting with the 2027/2028 Delivery Year . . . for the purpose of supporting the integration of New Large Loads to the PJM Region that are not in arrangements with new capacity additions to the PJM Region.’”128
PJM intends to require an amount of IRAS equivalent to the auction shortfall, which for the 2027/2028 Delivery Year was roughly 6.8 GW;129 roughly the same amount as PJM’s initial RBP procurement target.130 PJM’s RBP procurement target will be reduced by self-supply in the same way that the amount of new large load eligible for IRAS
126 RBP Transmittal Letter at 6-7, 21-22.127 Id. at 31; PJM RBP Filing, Attach. A, Attach. DD § 18.1(a). 128 IRAS Transmittal Letter at 74-75 (quoting Attach. DD-4 § I(a)). JCA in their RBP Protest mistakenly asked the Commission to accelerate the implementation date of IRAS. Upon further review of PJM’s IRAS Filing, it is clear that there is no need to do so.129 RBP Transmittal Letter at 8.130 Id. at 31 (initial RBP target of 6.8 GW based upon shortfall in 2028/2029 BRA).
PDF page 39
- 39 -
procurement will be reduced by self-supply. There is every reason to believe that IRAS— a resource adequacy measure that will be available to PJM before the availability of any RBP resources—will provide a source of new resource adequacy roughly equivalent to PJM’s final RBP target.
And unlike the RBP, IRAS is a resource adequacy measure of indefinite duration.131 PJM is not proposing an end date to the IRAS program.
Regardless of whether the PJM Region has maintained
capacity sufficient to meet the PJM Region Reliability
Requirement for three or more years, PJM will continue to
maintain the Large Load Registry. However, if the region re-
enters capacity shortfall conditions, then the need for New
Large Loads to provide IRAS will re-emerge. The definition
of New Large Load allows for this and explicitly provides
that New Large Loads will then be defined as entering
service “after June 1 of the first Delivery Year” the PJM
Region is short of capacity.
By comparison, RBP is a one-time procurement of new resources for terms of up to 15 years, notwithstanding that PJM has admitted that far shorter and less costly five- year procurements will satisfy regional reliability needs.132 And although PJM has provided no estimate of the costs associated with IRAS, our protest in Docket No. ER26- 3380-000 demonstrates that the costs associated with PJM’s RBP proposal are excessive and unjustified, and will likely reflect the exercise of seller-side market power as opposed to competition based upon the sellers’ production costs.133 Moreover, should the Commission exercise its FPA section 206 authority (perhaps incident to the June 2026 Show Cause Order) and direct PJM to refile IRAS as a non-firm transmission service,
131 IRAS Transmittal Letter at 72.132 JCA RBP Protest at 6. See also RBP Transmittal Letter at 39.133 JCA RBP Protest at 17-25.
PDF page 40
- 40 -
ratepayers will not be subject to any IRAS procurement costs, consistent with both the Ratepayer Protection Pledge and the FPA’s consumer protection objectives. The Commission’s acceptance of IRAS (with proper BYONC eligibility
requirements) renders the RBP duplicative and unnecessary and the Commission should reject it.
CONCLUSION
WHEREFORE, for the foregoing reasons, the Commission should direct PJM to revise its IRAS proposal consistent with the recommendations herein. Respectfully Submitted,
/s/ Susan L. Satter
/s/ Scott H. Strauss
Susan L. Satter
Chief, Public Utilities Bureau
Scott Metzger
Public Utilities Policy Counsel
Kimberly B. Janas
Counsel to the Attorney General
ILLINOIS ATTORNEY GENERAL’S OFFICE
115 South LaSalle Street, 25th Floor
Chicago, IL 60603
susan.satter@ilag.gov
Counsel for the Office of the Illinois
Attorney General
Scott H. Strauss
Peter J. Hopkins
Jeffrey A. Schwarz
Lauren L. Springett
SPIEGEL & MCDIARMID LLP
1818 N Street, NW, 8th Floor
Washington, DC 20036
scott.strauss@spiegelmcd.com
Counsel for Delaware Division of the
Public Advocate, District of Columbia
Office of People’s Counsel, Illinois Citizens
Utility Board, Maryland Office of People’s
Counsel and New Jersey Division of Rate
Counsel
September 3, 2026
PDF page 41
CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated on this 3rd day of September, 2026.
/s/ Lauren L. Springett