Protest and Comments of Joint Consumer Advocates on the 08/13/2026 filing by PJM Interconnection, L.L.C
Six state consumer advocates (the Joint Consumer Advocates) protest PJM's Interim Resource Adequacy Service and Large Load Registry filing. They support the concept but ask FERC to require non-firm transmission service, tighten bring-your-own-capacity eligibility, and reject the separate backstop procurement.
Asks FERC to: Find IRAS unjust and unreasonable as filed and direct an amended filing with non-firm service for non-capacity-backed loads, new-only self-supply, a validated registry, and rejection of the backstop procurement.
Invokes the June 2026 PJM show cause order and urges FERC to use Section 206 to require non-firm service for non-capacity-backed loads, the type of flexible-load service E-7 directs PJM to address.
E-7 PJM: Service for flexible loads (P 85, p. 56) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- The advocates cite the June 2026 show cause order's finding on PJM's tariff and ask FERC to require non-firm service for new large loads that do not self-supply.
new large loads that do not self-supply must take non-firm transmission service. PDF p. 2
- They want only resources that have not cleared a prior Base Residual Auction to count as new capacity.
only resources that have not previously cleared a prior Base Residual Auction (BRA) are eligible. PDF p. 2
- PJM's design lets a load reduce curtailment risk with capacity that already cleared, adding load without adding supply.
This would increase the amount of load on the system without either increasing system supply or making the new load an IRAS resource subject to curtailment. PDF p. 4
- Compensating curtailed loads leaves states to decide who pays, so other customers may fund payments to data centers.
which leaves open the possibility that non-large load customers may yet end up paying resource adequacy costs to the new large data center loads that are driving PJM’s reliability concerns. PDF p. 5
- The Market Monitor figures show data center demand raised costs to other customers by $23.1 billion over three auctions.
The total increase in costs to other PJM customers as a result of data center load in the last three BRAs was $23,100,955,341. PDF p. 8
- FERC has called large loads a separate category and directed every RTO and ISO to define them.
a separate category of load PDF p. 9
- IRAS could meet the roughly 6.8 GW need the backstop targets, sooner and more durably, making the backstop unnecessary.
IRAS can satisfy the capacity need at which the RBP is aimed sooner, more durably, and, if correctly modified as non-firm transmission service, at less cost. PDF p. 38
Contents · 12 sections
- protest and comments OF JOINT CONSUMER ADVOCATES
- SUMMARY
- PROTEST AND COMMENTS
- I. IF properly implemented, IRAS could Insulate Ratepayers from the Capacity Costs OF Serving Projected New Large Loads by removing those loads from the Bra.
- II. IRAS Should Help ease the Demand Pressures Plaguing the BRA.
- Summary
- III. while potentially beneficial, iras as proposed is flawed.
- IV. The Commission Should Exercise either Its FPA Section 205 or section 206 authority to Direct PJM to make IRAS a Non-Firm Transmission Service.
- V. PJM’S PROPOSAL IS FLAWED BECAUSE IT IMPROPERLY TREATS AS “NEW” CAPACITY THAT previously cleared a base residual auction.
- VI. The commission should condition acceptance upon revisions to the Large Load Registry.
- VII. The Acceptance of IRAS Is Further Reason to Reject RBP.
- CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
protest and comments OF JOINT CONSUMER ADVOCATES
PDF bookmark · Topic match: Registry access
We note that the Commission’s June 2026 Show Cause Order6 found PJM’s Open Access Transmission Tariff (Tariff) “appears to be unjust, unreasonable, or unduly discriminatory or preferential,” in part because of its treatment of large load customers.7 The Commission should reject PJM’s treatment of…Read this passage Filed comments: Registry access
SUMMARY
PDF bookmark · Topic match: Reliability and curtailment
But in making its filing initiating this proceeding, PJM has presented IRAS as a supply-side measure akin to demand response.13 Thus, PJM proposes that new large loads that are curtailed pursuant to IRAS should be entitled to compensation, but leaves to the states resolution of the question of who…Read this passage Filed comments: Reliability and curtailment
PROTEST AND COMMENTS
PDF bookmark
PROTEST AND COMMENTSRead this passage
I. IF properly implemented, IRAS could Insulate Ratepayers from the Capacity Costs OF Serving Projected New Large Loads by removing those loads from the Bra.
PDF bookmark · Topic match: Cost allocation
The Commission’s “first and foremost duty” under the FPA is to “protect consumers from unjust and unreasonable rates.”40 Here, that means that FERC must act to protect ratepayers against the risk of “a protracted [AI] investment bust,” including the risk of the 39 Ganesh Sitaraman and Asad…Read this passage Filed comments: Cost allocation
II. IRAS Should Help ease the Demand Pressures Plaguing the BRA.
PDF bookmark
IRAS SHOULD HELP EASE THE DEMAND PRESSURES PLAGUING THE BRA.Read this passage
Summary
printed heading · Topic match: Cost allocation
Summary (May 27, 2026), https://www.pjm.com/- /media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-informational-only---reliability- backstop-rfi-summary---charles-river-associates.pdf. 51 Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer…Read this passage Filed comments: Cost allocation
III. while potentially beneficial, iras as proposed is flawed.
PDF bookmark · Topic match: Reliability and curtailment
The White Paper explains that “[t]oday, due to compounding frictions in siting, permitting, supply chains and interconnection, it can take two or three times as long to build a gas resource as it does to build a hyperscale data center.”57 Other resources, such as renewables combined with battery…Read this passage Filed comments: Reliability and curtailment
IV. The Commission Should Exercise either Its FPA Section 205 or section 206 authority to Direct PJM to make IRAS a Non-Firm Transmission Service.
PDF bookmark · Topic match: Reliability and curtailment
PJM proposes it as a compensable resource adequacy measure.Read this passage Filed comments: Reliability and curtailment
V. PJM’S PROPOSAL IS FLAWED BECAUSE IT IMPROPERLY TREATS AS “NEW” CAPACITY THAT previously cleared a base residual auction.
PDF bookmark · Topic match: Reliability and curtailment
IRAS is intended to enable PJM to address auction shortfalls and ensure system reliability.97 Because new large loads are driving BRA shortfalls, PJM proposes through IRAS to require these loads either to bring their own new capacity or be subject to curtailment (depending upon state load shed…Read this passage Filed comments: Reliability and curtailment
VI. The commission should condition acceptance upon revisions to the Large Load Registry.
PDF bookmark · Topic match: Registry access
The duty to populate the Registry falls on “[e]ach Party,” which must “submit, or cause to be submitted,” the required information “related to each Large Load served by the Party.”107 Electric Distributors, in turn, are required to provide “any information or data the Electric Distributor believes…Read this passage Filed comments: Registry access
VII. The Acceptance of IRAS Is Further Reason to Reject RBP.
PDF bookmark · Topic match: Reliability and curtailment
There is every reason to believe that IRAS— a resource adequacy measure that will be available to PJM before the availability of any RBP resources—will provide a source of new resource adequacy roughly equivalent to PJM’s final RBP target.Read this passage Filed comments: Reliability and curtailment
CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, the Commission should direct PJM to revise its IRAS proposal consistent with the recommendations herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated on this 3rd day of September, 2026. /s/ Lauren L.Read this passage