ER26-3552-000 · 2026-09-11 · Organization of MISO States, Inc.

Motion for Acceptance of Late-Filed Comments and Comments in Conditional Support of the Organization of MISO States, Inc. re Midcontinent Independent System Operator, Inc.’s proposed tariff revisions

The Organization of MISO States moves for acceptance of late comments and conditionally supports MISO's Zero Injection Generator Interconnection Agreement, asking FERC to require reliability, cost-shifting, resource adequacy and transparency safeguards.

Asks FERC to: Accept the late comments, and approve MISO's ZGIA only if reliability, cost, resource adequacy and transparency protections are clear and enforceable, while treating it as one part of a broader large-load framework.

State regulators comment on MISO's ZGIA filing in ER26-3552, MISO's first response to the E-8 order on co-located load, and ask FERC to weigh it with the rest of the E-8 response.

E-8 MISO: Services for flexible / co-located loads (P 6(d), p. 7) E-8 MISO: 30-day report on serving large loads with adequate generation (p. 7) E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. OMS offers conditional support for the ZGIA and does not oppose it.
    OMS cautiously supports the ZGIA proposal PDF p. 1
  2. OMS treats the ban on injection beyond the substation as a reliability requirement and wants studies before execution.
    That limitation must be treated as a reliability requirement, not merely a contractual condition. PDF p. 4
  3. OMS objects that MISO left the Transient Tolerance Window definition to its Business Practice Manual.
    MISO has deferred establishing an explicit definition of the appropriate Transient Tolerance Window to the development of its Business Practice Manual. PDF p. 5
  4. OMS backs keeping the ZGIA limited to generation and load at one substation and voltage level.
    recommends that the Commission accept the common-substation and voltage-level limitation as the appropriate scope of ZGIA. PDF p. 7
  5. OMS supports the requirement that the generator's full output serve the associated load for at least five years.
    with an expected period of at least five years. PDF p. 7
  6. OMS says upgrades needed if supporting generation fails to materialize should not automatically fall on existing customers.
    the costs of that incremental need should not automatically shift to existing transmission customers. PDF p. 7
  7. OMS asks MISO to explain ZGIA treatment across its resource adequacy models, including LOLE, UCAP, SAC and the Planning Resource Auction.
    OMS requests that MISO explain in a compliance filing, subsequent BPM rules, or a workshop how ZGIA resources and associated loads will be represented in PDF p. 9
  8. OMS wants any later move to injection rights sequenced so it does not bypass the Definitive Planning Process queue.
    must not allow a ZGIA resource to circumvent or obtain an advantage over interconnection customers already participating in the DPP queue. PDF p. 10
  9. OMS asks FERC to judge the ZGIA together with MISO's other large-load reforms on a complete record.
    the Commission should evaluate the ZGIA Filing together with other reforms developed during that process only after a complete record is developed PDF p. 13
Contents · 11 sections
  1. I. MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS p. 1
  2. II. COMMENTS p. 2
  3. A. OMS Supports ZGIA as a Potential Tool to Interconnect Large Loads, Subject to p. 3
  4. B. Reliability Protections Must Be Fundamental to the ZGIA Framework. p. 4
  5. C. The Initial ZGIA Framework Should Be Limited to Generation and Load at the p. 6
  6. D. MISO Must Prevent Cost Shifting When the Associated Generation or Load Does p. 7
  7. E. Resource Adequacy Treatment Must Be Complete, Transparent, and Consistent p. 8
  8. F. ZGIA Should Provide a Clear Transition Path Without Circumventing the DPP. p. 10
  9. G. OMS Supports Transparency and Meaningful State and Stakeholder Oversight. p. 11
  10. H. ZGIA Should Complement, Not Displace, Broader Transmission and Large-Load p. 12
  11. III. CONCLUSION p. 13

Read topic-matched comments in ER26-3552

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

OMS cautiously supports the ZGIA proposal but highlights several critical reliability and resource adequacy concerns for the Commission’s consideration.
Read this passage Filed comments: Reliability and curtailment

I. MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS

printed heading

MOTION FOR ACCEPTANCE OF LATE-FILED COMMENTS Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure, OMS respectfully requests that the Commission accept these late-filed comments.2 On September 8, 1 Midcontinent Indep.
Read this passage

II. COMMENTS

printed heading · Topic match: Reliability and curtailment

Furthermore, nothing in the ZGIA Filing shall supplant state and local rules regarding generation and load application, approval, and interconnection processes.
Read this passage Filed comments: Reliability and curtailment

A. OMS Supports ZGIA as a Potential Tool to Interconnect Large Loads, Subject to

printed heading · Topic match: Connecting load and generation

MISO began developing the ZGIA framework with the recognition that co-located arrangements were necessary to quickly integrate large loads and their associated generation while shielding existing customers from any resulting costs.5 The ZGIA framework is further premised on the understanding that a…
Read this passage Filed comments: Connecting load and generation

B. Reliability Protections Must Be Fundamental to the ZGIA Framework.

printed heading · Topic match: Connecting load and generation

Reliability Protections Must Be Fundamental to the ZGIA Framework.
Read this passage Filed comments: Connecting load and generation

C. The Initial ZGIA Framework Should Be Limited to Generation and Load at the

printed heading · Topic match: Connecting load and generation

MISO’s ZGIA Filing limits ZG Interconnection Service to generation and associated load located at the same substation and voltage level.
Read this passage Filed comments: Connecting load and generation

D. MISO Must Prevent Cost Shifting When the Associated Generation or Load Does

printed heading · Topic match: Cost allocation

MISO Must Prevent Cost Shifting When the Associated Generation or Load Does Not Materialize.
Read this passage Filed comments: Cost allocation

E. Resource Adequacy Treatment Must Be Complete, Transparent, and Consistent

printed heading · Topic match: Reliability and curtailment

Resource Adequacy Treatment Must Be Complete, Transparent, and Consistent with Physical Capability.
Read this passage Filed comments: Reliability and curtailment

F. ZGIA Should Provide a Clear Transition Path Without Circumventing the DPP.

printed heading · Topic match: Connecting load and generation

OMS recognizes that MISO’s proposal expressly permits a ZG Resource to pursue another form of interconnection service separately, including full integration and injection rights through Network Resource Interconnection Service (“NRIS”) through MISO’s Definitive Planning Process (“DPP”), with the…
Read this passage Filed comments: Connecting load and generation

G. OMS Supports Transparency and Meaningful State and Stakeholder Oversight.

printed heading

OMS Supports Transparency and Meaningful State and Stakeholder Oversight.
Read this passage

H. ZGIA Should Complement, Not Displace, Broader Transmission and Large-Load

printed heading · Topic match: Filing procedure

Consistent with OMS’s support for MISO and the MISO Transmission Owners’ abeyance request, the Commission should therefore evaluate ZGIA as one component of a broader, comprehensive framework for large load integration rather than as a standalone solution.12 That framework should address the…
Read this passage Filed comments: Filing procedure

III. CONCLUSION

printed heading · Topic match: Cost allocation

OMS’s support, however, is conditioned on maintaining the fundamental principles of reliability, cost causation, transparency, and equitable treatment of customers and market participants as detailed above.
Read this passage Filed comments: Cost allocation