ER26-3552: the filed comments
Positions read for this site
Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.
Organization of MISO States · ER26-3552-000 · 2026-09-11
OMS conditionally supported the zero-injection agreement. It wanted enforceable limits on a generator exporting power and asked MISO to explain how paired loads and generators would count in capacity and reliability calculations during outages.
Other passages, matched by topic
These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.
Connecting load and generation
ER26-3552-000 · 2026-09-11
MISO should clearly specify how such transitions will be sequenced, how queue position and study impacts will be determined, and how transmission capability reserved or relied upon under ZGIA will be treated when the resource seeks broader injection rights. PDF p. 10
ER26-3552-000 · 2026-09-08
The ZGIA Proposal limits Zero Injection Generation Interconnection Service (ZG Interconnection Service) to co-located configurations in which ZG Resources and the Zero Injection Generation Associated Load (ZG Associated Load) would be located at the same substation and voltage level, with no injection beyond the interconnecting substation. PDF p. 3
ER26-3552-000 · 2026-09-08
”4 Specifically, the ZGIA would create a “study process tailored to the operational characteristics of generation serving co-located load, including a study process that 3 Id. PDF p. 2
ER26-3552-000 · 2026-09-08
23 By proposing a new ZG Interconnection Service process that echoes MISO’s standard interconnection process with slight variations, the ZG Interconnection Service process adds consistency, transparency, and structure around these distinctive interconnection requests to meet specific load needs. PDF p. 7
ER26-3552-000 · 2026-09-08
[fn:3] United supports acceptance of the tariff revisions subject to a deferred implementation date coordinated with MISO’s forthcoming Large Load Addition Resource Study ("LARS") and large-load compliance filings. Source text
ER26-3552-000 · 2026-09-23
44 Should MISO determine in the future that penalties have become necessary or appropriate for enforcing interconnection service limits, MISO expects that it would explore potential penalty frameworks for application generally to all interconnection agreements that have such a potential rather than singling out only some generating facilities or service types for penalties. PDF p. 8
Cost allocation
ER26-3552-000 · 2026-09-11
OMS’s support, however, is conditioned on maintaining the fundamental principles of reliability, cost causation, transparency, and equitable treatment of customers and market participants as detailed above. PDF p. 13
Filing procedure
ER26-3552-000 · 2026-09-11
12 Answer in Support of the Motion to Hold Proceeding in Abeyance of MISO and the MISO Transmission Owners of OMS, Docket No. PDF p. 12
ER26-3552-000 · 2026-08-28
CONCLUSION For the reasons given above, Public Interest Organizations request the Commission issue an order no later than September 4, 2026, granting the requested extension of time, until September 15, 2026, to comment on MISO’s ZGIA filing. PDF p. 4
ER26-3552-000 · 2026-09-08
38 However, as described by MISO and highlighted in the request for abeyance of the Show Cause Order’s deadlines by MISO and the MISO Transmission Owners,39 the 33 Show Cause Order at PP 113, 116. PDF p. 9
Reliability and curtailment
ER26-3552-000 · 2026-09-11
OMS cautiously supports the ZGIA proposal but highlights several critical reliability and resource adequacy concerns for the Commission’s consideration. PDF p. 1
ER26-3552-000 · 2026-09-08
3 In addition to establishing the ZGIA, MISO’s ZGIA Proposal would establish a study process and operational requirements, and market and resource adequacy rules to accommodate Zero-Injection Generation Resources (ZG Resources) that intend to serve load interconnecting at the same substation as the Generating Facility. PDF p. 1
Retail and wholesale authority
ER26-3552-000 · 2026-09-08
Consumers Energy requests, however, that the Commission ensure that any order accepting the MISO Filing expressly preserves state authority over retail loads and does not permit Commission-jurisdictional processes to supersede, preempt, or otherwise displace state regulation of retail electric service. PDF p. 1