Motion to Intervene and Comments of MISO Transmission Owners in support of the 08/18/2026 filing by Midcontinent Independent System Operator, Inc
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
Midcontinent Independent System
)
Docket No. ER26-3552-000
Operator, Inc.
)
)
MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF
THE MISO TRANSMISSION OWNERS
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 submit this motion to intervene and comments in support of the August 18, 2026 filing by Midcontinent Independent System Operator, Inc. (“MISO”) in which MISO proposes revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff
1 18 C.F.R. §§ 385.212, 385.214.2 For purposes of this filing, the MISO Transmission Owners consist of Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; American Transmission Company LLC; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; Citizens Electric Corporation; City Water, Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland Power Cooperative; Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power & Light Company d/b/a AES Indiana; International Transmission Company d/b/a ITCTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric Transmission Company, LLC; MidAmerican Energy Company; Minnesota Power (and its subsidiary Superior Water, L&P); Missouri River Energy Services; Montana-Dakota Utilities Co.; Northern Indiana Public Service Company LLC; Northern States Power Company, a Minnesota corporation, and Northern States Power Company, a Wisconsin corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric Company; Otter Tail Power Company; Prairie Power, Inc.; Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a CenterPoint Energy Indiana South); Southern Minnesota Municipal Power Agency; Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc.
PDF page 2
2
(“Tariff”) to create a Zero Injection Generator Interconnection Agreement (“ZGIA”), related study process and operational requirements, and market and resource adequacy rules to interconnect resources that intend to serve load, including large and co-located loads, interconnected at the same substation and with the same voltage level as existing or proposed load, i.e., Zero-Injection Generation (“ZG”) Resources.3 As explained in the August 18 Filing and below, MISO’s proposal to create a new framework to accommodate interconnection of ZG Resources will provide the region with another strategic and operational tool to help meet the rapidly growing demand of large and co-located loads by offering a streamlined interconnection pathway to resources that qualify, while also formalizing an already existing practice, addressing aspects of the Commission’s directives from its recent show cause order,4 and yielding independent benefits for the region’s interconnection process. For these reasons, the Commission should accept the August 18 Filing’s proposed Tariff revisions, effective October 18, 2026.
3 Zero Injection Generator Interconnection Agreement of Midcontinent Independent System Operator, Inc., Docket No. ER26-3552-000 (Aug. 18, 2026) (“August 18 Filing”). All capitalized terms in this pleading that are not otherwise defined herein have the same meaning they are given in the current Tariff or the proposed Tariff revisions of the August 18 Filing.4 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).
PDF page 3
3
I. COMMENTS IN SUPPORT
A. ZG Interconnection Service Will Provide the MISO Region With
Another Efficient, Effective, and Tailored Tool to Address the Region’s Large Load Growth
The MISO Transmission Owners support MISO’s proposed ZG Interconnection Service construct as a just and reasonable framework that provides a limited, streamlined interconnection path for a ZG Resource, i.e., a planned generator seeking to connect at the same substation and with the same voltage level as existing or planned load, including large loads and co-located loads.5 The proposed streamlined ZGIA framework, which is specifically designed to complement MISO’s standard Interconnection Queue process, the Definitive Planning Phase (“DPP”),6 establishes a targeted 90-day study process for generation resources seeking a more limited interconnection service than Energy Resource Interconnection Service (i.e., ERIS), which grants “as available” access to the full MISO Transmission System.7 The ZGIA interconnection study process recognizes “the limited distance over which energy would need to be—and is permitted to—flow,” allowing for a more targeted and efficient study process.8 Load customers, including large load customers, also will benefit from ZGIA interconnection studies that recognize on-site generation, potentially reducing network upgrade requirements to interconnect. As MISO
5 See August 18 Filing at 7.6 See id. at 14.7 See id. at 25; id., Tab C (Prepared Direct Testimony of Marc Keyser, Director, Central Region—External Affairs) at 7-8 (“Keyser Test.”).8 August 18 Filing at 25.
PDF page 4
4
states, this framework “enables a pathway for certain large load configurations to achieve speed to reliable power while maintaining system reliability.”9
With its ZGIA proposal, MISO adds another tool to the region’s growing toolbox for addressing the urgent and exponential load growth across the region. Specifically, the ZGIA will complement MISO’s other recent strategic initiatives, including: the Expedited Resource Addition Study, which provides a temporary accelerated interconnection process tailored to generators needed within the region to serve important, near-term new load; MISO’s improved Expedited Project Review (“EPR”) process, part of the MISO Transmission Expansion Plan (“MTEP”), which expeditiously studies network upgrades necessary for new large loads; and the MISO-Southwest Power Pool, Inc. (“SPP”) Joint Targeted Interconnection Queue Study, which provides a pathway to build network upgrades at the MISO-SPP seams.
The crux of the proposed ZGIA framework is the new limited product, ZG Interconnection Service,10 available for a Generating Facility that will only serve ZG Associated Load,11 i.e., a designated load either at the same POI or has a POW12 on the
9 Id. at 10.10 See id., Tab A (Marked Tariff Sheets) at Definitions – Z (“Marked ZGIA Tariff Sheets”) (defining ZG Interconnection Service).11 See id. at Definition – Z (defining ZG Associated Load as “[a] source of electrical load that has a Point of Withdrawal [(“POW”)] that is at the same substation as the Point of Interconnection [(“POI”)] to the Transmission System (i.e., same voltage level at the interconnecting substation) as the Generating Facility with ZG Interconnection Service that will serve it”). 12 POW is a new term proposed to be defined as “the point(s) where a non- transmission facility that is used to withdraw Energy from the Transmission System to serve Load connects to the Transmission System.” Id. at Attachment X. Put another way, POW is the “point that a Load interconnects to the Transmission
PDF page 5
5
same voltage side of the same substation at the same voltage level, as identified in its Interconnection Request.13 The ZG Interconnection study process, i.e., the ZG Impact Assessment, will occur on an accelerated timeline, within ninety Calendar Days, at the end of which MISO will issue a ZGIA to the parties. With an interconnection agreement, the ZGIA Resource can then be modeled as an input to the subsequent MTEP (or MTEP EPR) load study for its ZG Associated Load, potentially reducing the network upgrades needed to integrate the new load.14
MISO proposes requirements for eligibility of ZG Interconnection Service similar to the requirements for standard Interconnection Service through its DPP process, but includes additional requirements to allow MISO to study the generation in connection with the ZG Associated Load and verify the ability of proposed configurations and control equipment to limit injections, as required.15 Specifically, as MISO explains, the criteria for a resource to qualify and proceed through the ZG Interconnection study process deviates from MISO’s usual criteria for interconnection requests in five key ways:16
(1) The Interconnection Customer must demonstrate a documented relationship with the planned or anticipated load to be connected at the same voltage side of the same substation, i.e., ZG Associated Load, and affirm the ZG
System . . . the Load analog to the generation-specific term ‘Point of Interconnection’.” Keyser Test. at 23.
13 August 18 Filing at 12.14 See id. at 8.15 Keyser Test. at 27-28.16 August 18 Filing at 12-13, Keyser Test. at 9-10. In addition to the five listed, the ZGIA Interconnection Request process will use a serial “first-come, first-served” approach and will group ZGIA projects per cycle capping the number of requests per cycle to the first ten requests. Keyser Test. at 24. MISO proposes this deviation from the DPP process to prevent disruptions to the DPP process and ensure MISO maintains appropriate staffing levels. Id.
PDF page 6
6
Associated Load’s intention to take service from the Interconnection Customer’s Generation Facility, i.e., the ZG Resource,17 using a ZGIA;
(2) The Interconnection Customer requesting ZG Interconnection Service is not limited in the quantity of nameplate capacity of generation to be built, but is limited to receive only ZG Interconnection Service at a level that will not exceed peak demand of the ZG Associated Load, ensuring the maximum expected energy generated by the ZG Resource does not exceed maximum demand by the ZG Associated Load;18
(3) When studying the Interconnection Request for ZG Interconnection Service, MISO will model the ZG Associated Load and confirm the proposed equipment sufficiently limits injections, which means MISO will study the load and generation together;19
(4) The ZG Resource must interconnect at the same substation and voltage level as the POWs where the ZG Resource will serve the ZG Associated Load;20 and
(5) Study of the ZG Interconnection Service must find that the ZG Resource does not require Network Upgrades beyond the substation except for system protection facilities at adjacent substations.21
These enhanced requirements ensure that others on the Transmission System are not negatively impacted by a ZG Resource.
Moreover, a ZG Resource with an executed ZGIA will be subject to MISO’s regional planning process and the specific local planning criteria of its appropriate Transmission Owner.22 It also may participate in the replacement process for like resources (i.e., replacing another Generating Facility that has ZG Interconnection Service in the same
17 See August 18 Filing at 12; Keyser Test. at 9; see also Marked ZGIA Tariff Sheets at Definitions – Z (defining ZG Resource).18 See August 18 Filing at 13; Keyser Test. at 9-10.19 See August 18 Filing at 13; Keyser Test. at 1020 See August 18 Filing at 13; Keyser Test. at 1021 See August 18 Filing at 13; Keyser Test. at 10.22 See August 18 Filing at 13; Keyser Test. at 35.
PDF page 7
7
location), MISO’s resource adequacy construct, and the energy and operating reserve markets.23
By proposing a new ZG Interconnection Service process that echoes MISO’s standard interconnection process with slight variations, the ZG Interconnection Service process adds consistency, transparency, and structure around these distinctive interconnection requests to meet specific load needs. Through its proposed ZGIA framework, MISO will have a uniform process to account for actual impacts of these resources with limited injections; ensure these Interconnection Customers pay for only the necessary upgrades of their limited impacts; confirm the Interconnection Customer’s proposed means for limiting injections; and memorialize and enforce the Interconnection Customer’s commitments, including the control equipment and operational limitations, via a binding ZGIA.24
B. ZG Interconnection Service Will Address the Show Cause Order’s
Concern With Co-Located Load
When discussing MISO’s lack of Tariff provisions regarding interconnection service for generation serving co-located load, the Commission’s Show Cause Order highlighted MISO’s development of a zero-injection generator interconnection process and articulated a concern that such a process and its studies were not part of the Tariff.25 MISO’s proposal here, the culmination of that stakeholder-driven development, addresses that concern. The proposed ZGIA framework is an adaptation of standard interconnection service that aligns with directives of the Show Cause Order. Specifically, MISO’s proposal
23 See August 18 Filing at 13; Keyser Test. at 36-39.24 See Keyser Test. at 8-9.25 Show Cause Order at P 97.
PDF page 8
8
provides a solution to an aspect of the Commission’s concern about the lack of clarity and consistency as to the rates, terms, and conditions of service that apply to interconnection customers serving load that is geographically and electrically close, including co-located load.26
While MISO’s proposal slightly expands the definition of “co-location” envisioned by the Show Cause Order,27 MISO reasonably determined, after extensive stakeholder feedback,28 including from developers (such as developers of established or planned large loads in the region),29 Transmission Owners, and other interested parties in the region, that this broader scope, encompassing arrangements of load and generation not just at the same POI, but generally located at the same substation with the same voltage level, better met the region’s needs30 and struck an appropriate balance, offering a limited product with limited impact on other projects and an accelerated study process.31 In addition to aligning with stakeholder feedback, MISO found that defining a ZG Resource as serving load at the same substation with the same voltage level would be “electrically indistinguishable”3226 Id. at PP 94-98.27 Id. at P 91.28 See Keyser Test. at 39-42 (describing the stakeholder process culminating in the August 18 Filing).29 See id. at 12.30 August 18 Filing at 6 n.30.31 Id. at 12.32 Keyser Test. at 12.
PDF page 9
9
from requiring interconnection for a resource only serving load that is “electrically proximate,” or “co-located” behind the same POI, as described by the Show Cause Order.33 Additionally, the Commission in the Show Cause Order highlighted the absence of Tariff provisions that address the potential need for control equipment and protection systems to ensure that an interconnection customer’s commitment to limit its generating facility’s output to match the forecast of an electrically proximate large load or large co- located load.34 MISO’s proposal includes strict limits on injections to the Transmission System, which will limit the potential impacts to the Transmission System and need for Network Upgrades,35 as well as requirements for control equipment and protection systems as part of the proposed ZGIA.36
MISO’s filing does not establish new rules regarding transmission service. As such the ZG Associated Load must obtain transmission service to be served using the Transmission System, which, for load served by a Load Serving Entity in MISO, is usually Network Integration Transmission Service.37 Relatedly, MISO’s ZGIA filing does not allow netting of load and generation for transmission service or market settlement purposes.38 However, as described by MISO and highlighted in the request for abeyance of the Show Cause Order’s deadlines by MISO and the MISO Transmission Owners,39 the
33 Show Cause Order at PP 113, 116.34 Id. at P 113.35 See August 18 Filing at 7.36 See Keyser Test. at 8, 26.37 August 18 Filing at 8 n.32.38 Id. at 8.39 Motion of the Midcontinent Independent System Operator, Inc. and the MISO Transmission Owners to Hold Proceeding in Abeyance and Request for Shortened
PDF page 10
10
proposed ZGIA framework is only one piece of MISO’s work plan for addressing all aspects of the Show Cause Order and resolving the issues posed by the dramatic large load growth in the region.40
MISO’s proposed ZGIA framework would establish a uniform and tailored interconnection service that will provide regional benefits to generation and load with safeguards to avoid disruptions to the Transmission System and MISO’s current interconnection process. It also addresses the Show Cause Order’s concerns regarding generator interconnection service and the study of generation serving co-located load. Accordingly, the Commission should accept MISO’s proposed ZGIA framework as just and reasonable.
II. MOTION TO INTERVENE
This proceeding involves revisions to MISO’s Tariff to establish an entirely new interconnection agreement, the ZGIA, the related processes and requirements for ZG Resources, and provisions to integrate such resources as part of MISO’s market and resource adequacy. As Transmission Owners within MISO that are subject to the Tariff, each of the MISO Transmission Owners will be affected by whatever action the Commission takes in this proceeding because the Tariff and its interconnection procedures impact the MISO Transmission Owners’ transmission facilities. Additionally, the MISO Transmission Owners have a vested interest in the MISO region’s ability to meet the need for speed to power while maintaining resource adequacy and reliability as well as
Comment Period and Expedited Treatment, Docket No. EL26-70-000 (Aug. 3, 2026).
40 August 18 Filing at 6, 10 (“The ZGIA framework represents an initial step in a broader set of solutions to address the concerns expressed in the Show Cause Order and to meet the evolving needs of the MISO region.”).
PDF page 11
11
addressing aspects of the Show Cause Order’s directives, all of which the August 18 Filing’s proposals do. Consequently, each of the MISO Transmission Owners has a direct, unique, and substantial interest in this case that is not and cannot be adequately represented by any other party.41 Therefore, the Commission should allow the intervention of each MISO Transmission Owner listed supra in note 2.
The MISO Transmission Owners also request that the Commission place the following individuals on the official service list42 for this proceeding: Wendy N. Reed
Anna Fernandez
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
johns@wrightlaw.com
41 18 C.F.R. § 385.214(b)(2)(ii) (stating that a motion to intervene must demonstrate that “[t]he movant has . . . an interest which may be directly affected by the outcome of the proceeding”).42 To the extent necessary, the MISO Transmission Owners request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official service list for this proceeding.
PDF page 12
12
III. CONCLUSION
For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the August 18 Filing as just and reasonable, effective October 18, 2026.
Respectfully submitted,
/s/ Abraham F. Johns III
Wendy N. Reed
Anna Fernandez
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
reed@wrightlaw.com
fernandez@wrightlaw.com
johns@wrightlaw.com
Attorneys for the
MISO Transmission Owners
September 8, 2026
PDF page 13
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, DC, this 8th day of September 2026.
/s/ Abraham F. Johns III
Abraham F. Johns III
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC 20005-3898
(202) 393-1200
johns@wrightlaw.com
Attorney for the
MISO Transmission Owners