ER26-3552-000 · 2026-09-08 · MISO Transmission Owners

Motion to Intervene and Comments of MISO Transmission Owners in support of the 08/18/2026 filing by Midcontinent Independent System Operator, Inc

Text extracted from the eLibrary original (SHA-256 00cb74bd35b72245…). Download the original from the official source.

Contents · 5 sections
  1. I. COMMENTS IN SUPPORT p. 3
  2. A. ZG Interconnection Service Will Provide the MISO Region With p. 3
  3. B. ZG Interconnection Service Will Address the Show Cause Order’s p. 7
  4. II. MOTION TO INTERVENE p. 10
  5. III. CONCLUSION p. 12

Read topic-matched comments in ER26-3552

Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

ER26-3552-000 Operator, Inc. ) ) MOTION TO INTERVENE AND COMMENTS IN SUPPORT OF THE MISO TRANSMISSION OWNERS Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure,1 the MISO Transmission Owners2 submit this motion to intervene and…
Read this passage Filed comments: Reliability and curtailment

I. COMMENTS IN SUPPORT

printed heading

I.
Read this passage

A. ZG Interconnection Service Will Provide the MISO Region With

printed heading · Topic match: Connecting load and generation

Id. 6 Associated Load’s intention to take service from the Interconnection Customer’s Generation Facility, i.e., the ZG Resource,17 using a ZGIA; (2) The Interconnection Customer requesting ZG Interconnection Service is not limited in the quantity of nameplate capacity of generation to be built,…
Read this passage Filed comments: Connecting load and generation

B. ZG Interconnection Service Will Address the Show Cause Order’s

printed heading · Topic match: Connecting load and generation

ZG Interconnection Service Will Address the Show Cause Order’s Concern With Co-Located Load When discussing MISO’s lack of Tariff provisions regarding interconnection service for generation serving co-located load, the Commission’s Show Cause Order highlighted MISO’s development of a zero-injection…
Read this passage Filed comments: Connecting load and generation

II. MOTION TO INTERVENE

printed heading · Topic match: Reliability and curtailment

Johns III Wright & Talisman, P.C. 1200 G Street, NW, Suite 600 Washington, DC 20005-3898 (202) 393-1200 reed@wrightlaw.com fernandez@wrightlaw.com johns@wrightlaw.com 41 18 C.F.R. § 385.214(b)(2)(ii) (stating that a motion to intervene must demonstrate that “[t]he movant has . . . an interest which…
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION For these reasons, the MISO Transmission Owners request that the Commission grant this motion to intervene and accept the August 18 Filing as just and reasonable, effective October 18, 2026.