ER26-3552-000 · 2026-09-23 · Midcontinent Independent System Operator Inc.

Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the comments and protests in response to the 08/18/2026 proposed…

Text extracted from the eLibrary original (SHA-256 9bb7937a229f214d…). Download the original from the official source.

Contents · 15 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 3
  2. II. ANSWER p. 3
  3. A. The ZGIA Is a Just and Reasonable Standalone Interconnection Service That p. 3
  4. B. ZGIS Is a Limited Zero-Injection Service, and the Transient Tolerance p. 5
  5. C. MISO Appropriately Establishes Performance-Based System Protection p. 8
  6. D. The Twenty-Second Maximum Transient Tolerance Window Has a p. 10
  7. E. The ZGIA Provides Appropriate Operational Visibility and Verification. p. 12
  8. F. MISO’s Study and Model-Reconciliation Processes Protect Existing DPP p. 13
  9. G. The ZGIA Provides Appropriate Transparency. p. 16
  10. H. Additional Aggregate or Temporal Limits Are Unnecessary Given the Limited p. 18
  11. I. MISO’s Treatment of Hybrid Resources Is Consistent with the Limited Nature p. 20
  12. III. CONCLUSION p. 25
  13. IV. COMMUNICATIONS p. 25
  14. V. NOTICE AND SERVICE p. 26
  15. VI. CONCLUSION p. 26

Read topic-matched comments in ER26-3552

Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ZGIS does not provide ERIS, NRIS, Transmission Service, or a general right to inject energy onto the Transmission System.9 Instead, ZGIS is a limited form of Interconnection Service that allows an Interconnection Customer to connect its Generating Facility for the limited purpose of delivering…
Read this passage Filed comments: Connecting load and generation

I. MOTION FOR LEAVE TO ANSWER

printed heading

MOTION FOR LEAVE TO ANSWER Under Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure, answers to protests are generally not permitted.12 Nonetheless, the Commission waives this requirement where an otherwise prohibited answer would clarify the issues under consideration, ensure…
Read this passage

II. ANSWER

printed heading

II.
Read this passage

A. The ZGIA Is a Just and Reasonable Standalone Interconnection Service That

printed heading · Topic match: Connecting load and generation

LARS, by contrast, is intended to address distinct study issues associated with new generation and large load that are electrically proximate by aligning the Transmission Service and Interconnection Service evaluations in order to provide coordinated study results on an accelerated basis .17 LARS…
Read this passage Filed comments: Connecting load and generation

B. ZGIS Is a Limited Zero-Injection Service, and the Transient Tolerance

printed heading · Topic match: Connecting load and generation

Clean Energy contends that the proposal does not adequately ensure that “zero means zero,” emphasizing the possibility of injections during and outside the Transient Tolerance Window and requesting additional penalties for unauthorized injections.27 That argument conflates the scope of the…
Read this passage Filed comments: Connecting load and generation

C. MISO Appropriately Establishes Performance-Based System Protection

printed heading · Topic match: Connecting load and generation

Clean Energy argues that the Tariff should specify a minimum configuration of System Protection Facilities, require automatic corrective action, and prescribe specific testing and inspection intervals.45 MISO’s proposal instead establishes the required performance and permits the particular…
Read this passage Filed comments: Connecting load and generation

D. The Twenty-Second Maximum Transient Tolerance Window Has a

printed heading

Clean Energy asks MISO to provide additional engineering support for the twenty-second maximum Transient Tolerance Window and argues that the standards governing a shorter window should appear in the Tariff rather than the Business Practices Manual.56 The twenty-second maximum is tied to MISO’s…
Read this passage

E. The ZGIA Provides Appropriate Operational Visibility and Verification.

printed heading

United requests clarification concerning MISO’s ongoing visibility into coordination between the ZG Resource and ZG Associated Load after execution of the ZGIA and how compliance with the Transient Tolerance Window and associated equipment requirements will be monitored and verified.67 The proposal…
Read this passage

F. MISO’s Study and Model-Reconciliation Processes Protect Existing DPP

printed heading · Topic match: Connecting load and generation

Resource cannot exceed the peak demand of the ZG Associated Load.88 The ZG Resource must connect at the same substation and voltage level as a Point of Withdrawal for the ZG Associated Load, and the ZG Interconnection Study must determine that the project will not require Network Upgrades beyond…
Read this passage Filed comments: Connecting load and generation

G. The ZGIA Provides Appropriate Transparency.

printed heading · Topic match: Connecting load and generation

These requirements are not currently imposed on Interconnection Requests seeking Interconnection Service through other processes, such as the DPP and it is not necessary to add such new requirements for ZGIAs independently from any large load transparency reforms.
Read this passage Filed comments: Connecting load and generation

H. Additional Aggregate or Temporal Limits Are Unnecessary Given the Limited

printed heading · Topic match: Connecting load and generation

To the extent that a ZGIA involves a Large Load, nothing in the ZGIA Filing purports to exempt a Large Load from any generally applicable transparency requirements that MISO may propose in a subsequent filing. 110 Clean Energy Protest at 16-18. same-substation and same-voltage requirements…
Read this passage Filed comments: Connecting load and generation

I. MISO’s Treatment of Hybrid Resources Is Consistent with the Limited Nature

printed heading · Topic match: Connecting load and generation

Consumers asks the Commission to preserve state authority over retail loads and retail cost recovery, prevent MISO’s regional processes from becoming prerequisites to state authorization of retail service except as necessary to provide jurisdictional transmission service, and preserve sufficient…
Read this passage Filed comments: Connecting load and generation

III. CONCLUSION

printed heading · Topic match: Connecting load and generation

CONCLUSION For the foregoing reasons, MISO respectfully requests that the Commission accept the proposed Tariff revisions establishing ZG Interconnection Service and the ZGIA, effective October 18, 2026, as requested, subject to the limited clarifications identified herein, and reject requests to…
Read this passage Filed comments: Connecting load and generation

IV. COMMUNICATIONS

printed heading

COMMUNICATIONS MISO requests waiver of Rule 203(b)(3)127 of the Commission’s Rules of Practice and Procedure to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all communications related to this filing be directed…
Read this passage

V. NOTICE AND SERVICE

printed heading

NOTICE AND SERVICE MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission…
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION WHEREFORE, MISO respectfully requests that the Commission dismiss the complaint in its entirety.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 23rd day of September 2026, in Carmel, Indiana. /s/ Dawn Kaminski Dawn Kaminski Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, IN 46032 317-249-5400