ER26-3552-000 · 2026-09-23 · Midcontinent Independent System Operator Inc.
Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the comments and protests in response to the 08/18/2026 proposed…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.,
)
)
)
)
Docket No. ER26-3552-000
MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE
MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC.
The Midcontinent Independent System Operator, Inc. (“MISO”) respectfully submits1 this Motion for Leave to Answer and Answer to the comments and protests filed in response to MISO’s August 18, 2026 filing proposing revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) to establish Zero Generation Interconnection Service (“ZG Interconnection Service” or “ZIGS”), a corresponding Zero Generation Interconnection Agreement (“ZGIA”), and associated study, operational, market, and resource adequacy requirements (“ZGIA Filing”).2
The comments reflect substantial support for the fundamental design of the proposal in MISO’s ZGIA Filing. The Organization of MISO States, Inc. (“OMS”) cautiously supports the ZGIA Filing, but raises certain reliability and resource adequacy concerns of the states.3 The MISO Transmission Owners (“MISO TOs”) support the ZGIA construct as an additional tool to address large-load growth and provide greater consistency and structure for interconnection requests designed to serve specific loads.4 The Solar Energy Industries Association (“SEIA”)
1 See Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 213 (2026).2 MISO Transmittal at 1-2.3 Motion for Acceptance of Late-Filed Comments in Conditional Support of the Organization of MISO States, Inc. (“OMS Comments”) at 1.4 MISO TOs Comments at 3-4, 7-9.
PDF page 2
similarly supports the proposal and explains that its same-substation and load-following requirements minimize Transmission System impacts and protect other interconnection customers from cost shifting.5 Google LLC (“Google”) describes the ZGIA as a “step in the right direction,” while advocating for additional reforms beyond those proposed here.6 Advanced Energy United (“United”) likewise supports the ZGIA subject to certain requested clarifications.7 The remaining concerns do not demonstrate that MISO’s proposal is unjust or
unreasonable. The sole protest in this matter was filed by Community Organizations and Clean Energy Advocates.8 Several comments and protests arise from a misunderstanding of the limited nature of ZGIS or concern broader large-load issues MISO expressly reserved for subsequent proposals. ZGIS does not provide ERIS, NRIS, Transmission Service, or a general right to inject energy onto the Transmission System.9 Instead, ZGIS is a limited form of Interconnection Service that allows an Interconnection Customer to connect its Generating Facility for the limited purpose of delivering energy to designated ZG Associated Load, subject to the configuration, study, and operational requirements established by the Tariff and ZGIA.10
The Commission should therefore accept the ZGIA Filing without delaying its
implementation or requiring MISO to expand this proceeding to resolve distinct large-load, transmission-service, or generator-interconnection issues.11 Accordingly, MISO respectfully
5 SEIA Comments at 3-6.6 Google Comments at 2-5.7 United Comments at 3-12.8 Protest of Community Organizations and Clean Energy Advocates (“Clean Energy”).9 MISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service.10 MISO Transmittal at 12-16; proposed Tariff, Module A, ZG Interconnection Service; proposed Attachment X §§ 3.2.5, 3.10.1.11 MISO Transmittal at 2, 9-11.
PDF page 3
requests the ZGIA Filing be accepted without modification and with an effective date of October 18, 2026, as requested in the ZGIA Filing.
I. MOTION FOR LEAVE TO ANSWER
Under Rule 213(a)(2) of the Commission’s Rules of Practice and Procedure, answers to protests are generally not permitted.12 Nonetheless, the Commission waives this requirement where an otherwise prohibited answer would clarify the issues under consideration, ensure completeness of the record, or assist the Commission in its decision-making.13 MISO respectfully submits that granting it leave to answer the comments and protests in this docket will assist the Commission in its decision-making and facilitate the expeditious resolution of this matter by clarifying the issues under consideration. Accordingly, Rule 213(a)(2) should be waived for good cause shown.
II. ANSWER
A. The ZGIA Is a Just and Reasonable Standalone Interconnection Service That
Need Not Await MISO’s Other Large-Load Reforms.
While United supports acceptance of the ZGIA Tariff revisions, it asks the Commission to delay implementation of ZGIS to permit further coordination with MISO’s forthcoming Load Addition Resource Study (“LARS”) proposal and seeks additional explanation concerning how the two processes will operate together.14 Google, from a different perspective, urges MISO to
12 See 18 C.F.R. § 385.213(a)(2) (2026).13 See, e.g., Southwest Power Pool, Inc., 143 FERC ¶ 61,018, at P 15 (2013) (accepting answer that assisted in the decision-making process); Texas Eastern Transmission, LP, 122 FERC ¶ 61,205, at P 8 (2008) (accepting answer that completed the record); California Independent System Operator Corp., 105 FERC ¶ 61,284, at P 10 (2003) (accepting answer that clarified the issues).14 United Comments at 1, 3-5.
PDF page 4
expand ZGIS beyond the same-substation configuration to encompass generation serving electrically proximate load.15
Neither request provides a basis to delay implementation of the ZGIA Filing. MISO developed the ZGIA as a standalone proposal addressing the generator-interconnection service and study framework applicable to generation serving ZG Associated Load connected at the same substation and voltage level.16 ZG Associated Load does not have to be a Large Load. LARS, by contrast, is intended to address distinct study issues associated with new generation and large load that are electrically proximate by aligning the Transmission Service and Interconnection Service evaluations in order to provide coordinated study results on an accelerated basis .17 LARS will not grant ZG Interconnection Service and MISO has not proposed that participation in LARS is a prerequisite to ZGIS.18 Neither the ZGIA nor LARS create a new Transmission Service product for serving co-located or electrically proximate load.19
MISO therefore does not need LARS to implement the ZGIA. They are two entirely
different, standalone processes with distinct use cases. The ZGIA establishes a discrete form of Interconnection Service for generation serving load under the specific configuration and
15 Google Comments at 3-4.16 MISO Transmittal at 2, 9-11. 17 September 23, 2026 Large Load Working Group presentation, “Large Load Addition Resource Study (LARS),” and associated draft Tariff Sheets (Item No. 06) available at Large Load Working Group (LLWG) - September 23, 2026.18 MISO Transmittal at 9-10; Id. As currently envisioned and drafted, the generation portion of the LARS study will require Network Resource Interconnection Service and studies appropriate for such service.19 Id. at 10. New Transmission Service products are being discussed with stakeholders for inclusion in a separate 205 filing.
PDF page 5
operational limitations established in the proposed Tariff.20. Accordingly, MISO can implement the ZGIA independently while continuing to develop other complementary large-load reforms.21 MISO’s decision to limit ZGIS to generation and load at the same substation and voltage level likewise is deliberate.22 MISO considered both a narrower same-POI approach and a broader approach encompassing electrically proximate generation and load, but determined that the broader approach would introduce additional reliability and transmission-service questions, including potential retail-wheeling considerations. Rather than delay implementation of ZGIS while23 those broader issues are resolved, MISO proposed a configuration that can be studied and implemented within the limited ZGIS framework.24
The proposal therefore does not foreclose the broader reforms advocated by United or Google. MISO expressly explained that the ZGIA addresses only some of the issues identified in the Commission’s Show Cause Order and that other issues will be addressed through subsequent proposals.25 The Commission should accept the discrete ZGIA Filing before it without awaiting resolution of every related large-load issue.26
B. ZGIS Is a Limited Zero-Injection Service, and the Transient Tolerance
Window Does Not Confer an Injection Right.
20 MISO Transmittal at 11-16; proposed Attachment X §§ 3.2.5, 3.10.1.
21 MISO Transmittal at 2, 9-11.22 MISO Transmittal at 7, 12-13; Keyser at 11-14, 19-20.23 MISO Transmittal at 7; Keyser at 11-14, 19-20.24 MISO Transmittal at 7, 12-15.25 MISO Transmittal at 2, 9-11; Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).26 MISO Transmittal at 2.
PDF page 6
Clean Energy contends that the proposal does not adequately ensure that “zero means zero,” emphasizing the possibility of injections during and outside the Transient Tolerance Window and requesting additional penalties for unauthorized injections.27
That argument conflates the scope of the Interconnection Service MISO proposes to provide with the physical response of a Generating Facility following a transient event. ZGIS provides no general right to inject energy onto the Transmission System and does not convey Transmission Service.28 ZGIS permits the Generating Facility to operate only for the limited purpose of delivering energy to its designated ZG Associated Load.29
The Transient Tolerance Window does not alter those service limitations. The proposed Tariff defines the Transient Tolerance Window as the period following a reduction or loss of ZG Associated Load by the end of which the Generating Facility must reduce its injections to an amount no greater than the Load of the ZG Associated Load.30 The Tariff limits that period to no more than twenty seconds and subjects it to applicable Transmission Owner Local Planning Criteria.31
The Transient Tolerance Window reflects the physical reality that a Generating Facility generally cannot respond instantaneously to a sudden reduction in associated load.32 Even where communications and other equipment link the Generating Facility and ZG Associated Load, the Generating Facility may require a finite period to reduce its production following an abrupt
27 Clean Energy Protest at 3-11.28 MISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service.29 MISO Transmittal at 12; proposed Tariff, Module A, ZG Interconnection Service.30 MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window.31 Id.32 MISO Transmittal at 21, 26; Keyser at 25-26.
PDF page 7
reduction in demand.33 The Transient Tolerance Window allows MISO to account for that transient response in the ZG Impact Assessment while requiring the Generating Facility to reduce its injections within the defined period.34
An inadvertent transient flow therefore does not create an entitlement to inject energy onto the Transmission System.35 Rather, MISO expressly studies injections occurring during the Transient Tolerance Window by modeling the loss of ZG Associated Load and evaluating the resulting stability and steady-state impacts.36 The ZG Impact Assessment must determine that no Network Upgrades beyond those specifically allow for ZGIS are required to maintain reliability under those conditions.37
The proposal also imposes specific operational requirements designed to enforce the ZGIS limitation. A ZG Resource must install communications and monitoring equipment enabling it to monitor demand of the ZG Associated Load.38 It also must install equipment enabling the Generating Facility to reduce its injections to a level that does not exceed demand of the ZG Associated Load within the Transient Tolerance Window.39
The equipment used to satisfy those requirements must be identified in Appendix A of the ZGIA, and MISO verifies through the interconnection process that the ZG Resource can limit
33 MISO Transmittal at 26; Keyser at 25-26.34 MISO Transmittal at 21-22, 26, 28; Keyser at 25-28.35 MISO Transmittal at 16, 21-22, 42-43; proposed Tariff, Module A, ZG Interconnection Service and Transient Tolerance Window; proposed ZGIA Art. 9.7.4.7.36 MISO Transmittal at 15, 28; Keyser at 28.37 MISO Transmittal at 28; proposed Attachment X § 3.2.5.2.38 MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(a).39 MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(b).
PDF page 8
injections as proposed.40 The required equipment and configuration are then documented in Appendix A and become enforceable terms of the ZGIA.41
The Commission should not require MISO to characterize unauthorized ZGIS injections as unreserved use. The existing unreserved-use provisions address Transmission Service and are not the enforcement mechanism MISO proposes for ZGIS.42 MISO instead proposes to address ZGIS compliance directly through the technical, operational, study, and contractual requirements applicable to the ZG Resource.43 A potential for injection above an established interconnection service limit is hardly unique to the ZGIA. Any Generating Facility, especially one with capacity above its Interconnection Service level, has a similar potential. The Commission explored this issue in Order No. 845 and found that existing GIA mechanisms were sufficient to address unauthorized injections without establishing penalties.44 Should MISO determine in the future that penalties have become necessary or appropriate for enforcing interconnection service limits, MISO expects that it would explore potential penalty frameworks for application generally to all interconnection agreements that have such a potential rather than singling out only some generating facilities or service types for penalties. This docket, however, is not the appropriate vehicle for considering such proposals.
C. MISO Appropriately Establishes Performance-Based System Protection
Requirements Rather Than Mandating a Single Technical Configuration.
40 MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7.41 MISO Transmittal at 43; proposed ZGIA App. A § 2.42 Tariff, Module B at Sections 13.7, 14.5, 27A.1.6 and/ 27A.2.4.43 MISO Transmittal at 21-22, 26-28, 42-43; proposed ZGIA Art. 9.7.4.7.44 Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 FERC ¶ 61,043 (2018), order on reh'g and clarification, Order No. 845-A, 166 FERC ¶ 61,137 (2019), order on reh'g, Order No. 845-B, 168 FERC ¶ 61,092 (2019)at P 416 (“Based on these facts, we decline to generically adopt into the pro forma LGIP any additional financial penalties for exceeding the limitations for interconnection service established in the interconnection agreements”) and P 417 (“Because of these existing provisions, and the fact that no other consequences currently apply in the analogous situations described above, we see no need to devise new penalties at this time.”).
PDF page 9
Clean Energy argues that the Tariff should specify a minimum configuration of System Protection Facilities, require automatic corrective action, and prescribe specific testing and inspection intervals.45
MISO’s proposal instead establishes the required performance and permits the particular equipment and configuration to be tailored to the ZG Resource, ZG Associated Load, Point of Interconnection, and applicable Transmission Owner system.46 The ZG Resource must identify the equipment it proposes to use to satisfy the injection limitations, and MISO must verify that the ZG Resource can limit injections as proposed.47 MISO then documents the required equipment and configuration in Appendix A of the ZGIA, making those requirements enforceable terms of ZGIS.48
This performance-based approach permits the technical solution to reflect the actual configuration rather than assuming that a single prescribed technology is appropriate for every ZG Resource.49 MISO and the applicable Transmission Owner remain involved in evaluating the proposed configuration, and a project cannot proceed under ZGIS if the safeguards are insufficient to satisfy the applicable study and operating requirements.50 By focusing on the required result, this approach avoids limiting Interconnection Customers to certain types of equipment or configurations that may be incomplete or rapidly obsolesce.
45 Clean Energy Protest at 6-11.46 MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7.47 MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7.48 MISO Transmittal at 43; proposed ZGIA App. A § 2.49 MISO Transmittal at 42-43.50 MISO Transmittal at 13, 28, 42-43; proposed Attachment X §§ 3.2.5.2, 3.10.1; proposed ZGIA Art. 9.7.4.7.
PDF page 10
Clean Energy’s testing concern similarly overlooks requirements already contained in MISO’s pro forma ZGIA. Section 6.1 addresses pre-Commercial Operation Date testing and modifications, including testing of control equipment used to limit injections at the Point of Interconnection to the level of Interconnection Service specified in Appendix A and testing necessary to ensure safe and reliable operation of the Interconnection Customer’s Interconnection Facilities.51 Section 6.1 also provides for similar testing after initial operation where appropriate.52 Section 6.2 separately establishes post-Commercial Operation Date testing and modification requirements.53
The absence of a separate ZGIS-specific inspection interval therefore does not mean that the control and protection equipment is exempt from testing.54 The MISO TOs likewise recognize that the ZGIA provides a framework for addressing the control and protection systems necessary to limit injections from generation serving associated load.55
D. The Twenty-Second Maximum Transient Tolerance Window Has a
Reasonable Engineering Basis.
Clean Energy asks MISO to provide additional engineering support for the twenty-second maximum Transient Tolerance Window and argues that the standards governing a shorter window should appear in the Tariff rather than the Business Practices Manual.56
The twenty-second maximum is tied to MISO’s existing planning methodology. MISO’s dynamic simulations analyze transient response over a zero-to-twenty-second study period.57 The
51 Pro Forma ZGIA § 6.1.52 Pro Forma ZGIA § 6.1.53 Pro Forma ZGIA § 6.2.54 Pro Forma ZGIA §§ 6.1-6.2; proposed ZGIA Art. 9.7.4.7.55 MISO TOs Comments at 8-9.56 Clean Energy Protest at 12-14.57 MISO Planning Modeling Manual § 5.4; Keyser at 25-26.
PDF page 11
twenty-second maximum therefore permits MISO to evaluate the ZG Resource’s response during the same period in which transient stability impacts are analyzed.58 If the study identifies a reliability issue requiring a Network Upgrade that is incompatible with ZGIS, the project cannot proceed through the ZGIA process.59
The proposed Tariff itself establishes the controlling outer limit. The Transient Tolerance Window “shall be no greater than 20 seconds” and is subject to applicable Transmission Owner Local Planning Criteria.60 Thus, the Business Practices Manual cannot expand the permitted period beyond twenty seconds.61 Rather, the BPM will identify the circumstances in which a shorter interval applies.62 This is a reasonable balance between certainty and flexibility because there may be circumstances where shorter Transient Tolerance Window is appropriate for reliability based on situation-specific factors that are likely to be technical in nature. Requiring MISO to specify these rules in in the Business Practices Manual ensures ZG Interconnection Customers are treated consistently.
The ZG Impact Assessment also includes the ZG Associated Load and simulates a scenario in which that load trips offline.63 The resulting analyses evaluate injections occurring during the Transient Tolerance Window and help validate the protection scheme necessary for the particular ZGIA project.6458 MISO Planning Modeling Manual § 5.4; Keyser at 25-26.59 MISO Transmittal at 13, 28; proposed Attachment X §§ 3.2.5.1-.2.60 MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window.61 MISO Transmittal at 21-22; proposed Tariff, Module A, Transient Tolerance Window.62 MISO Transmittal at 21-22 & n.53.63 MISO Transmittal at 15, 28; Keyser at 28.64 MISO Transmittal at 15, 28; Keyser at 28.
PDF page 12
The twenty-second limit therefore is not an authorization for every ZG Resource to inject for twenty seconds.65 It is the maximum response interval within which a project must satisfy the applicable study and operating requirements, subject to a shorter interval where Transmission Owner Local Planning Criteria or the BPM so require.66
E. The ZGIA Provides Appropriate Operational Visibility and Verification.
United requests clarification concerning MISO’s ongoing visibility into coordination between the ZG Resource and ZG Associated Load after execution of the ZGIA and how compliance with the Transient Tolerance Window and associated equipment requirements will be monitored and verified.67
The proposal includes multiple mechanisms that provide operational visibility and facilitate verification. First, each ZG Resource must install communications and monitoring equipment enabling it to monitor demand of the ZG Associated Load.68 The Resource must install equipment enabling it to reduce injections to no greater than the demand of the ZG Associated Load within the Transient Tolerance Window.69
Second, an Interconnection Customer receiving ZGIS must install metering for the Generating Facility that is separate from the metering used for the ZG Associated Load.70 This requirement allows the generation and associated load to be measured separately rather than netted behind a common meter.7165 MISO Transmittal at 21-22, 26-28; proposed Tariff, Module A, Transient Tolerance Window.66 MISO Transmittal at 21-22 & n.53; proposed Tariff, Module A, Transient Tolerance Window.67 United Comments at 11-12.68 MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(a).69 MISO Transmittal at 42; proposed ZGIA Art. 9.7.4.7(b).70 MISO Transmittal at 41; proposed ZGIA Art. 7.1.71 MISO Transmittal at 41; Keyser at 38.
PDF page 13
Third, a ZG Resource greater than 5 MW must register as a Generation Resource, Energy Storage Resource, or Dispatchable Intermittent Resource, as applicable, and maintain the registration required by the Tariff.72 MISO explained that the registration requirement provides visibility of the ZG Resource and allows MISO to account for the gross amount of ZG Associated Load.73
Fourth, the equipment and configuration used to satisfy the injection limitations are memorialized in Appendix A of the ZGIA and therefore remain enforceable requirements after the initial study is complete.74 Changes to the studied configuration that could affect the impacts of ZGIS are subject to MISO’s applicable modification rules.75
Taken together, the communication, monitoring, metering, registration, testing, and contractual requirements provide continuing mechanisms for observing and enforcing the operational limitations applicable to ZGIS.76
F. MISO’s Study and Model-Reconciliation Processes Protect Existing DPP
Customers and Address the Asserted Cost-Shifting Concerns.
Clean Energy and United raise related questions concerning interactions among the ZGIA, DPP, and MTEP study processes. Clean Energy contends that differences in study timing may shift Network Upgrade costs to load and argues that a ZG Resource could use ZGIS as a pathway to later obtain ERIS or NRIS.77 United requests additional clarification concerning base-case reconciliation and cost responsibility for constraints identified through MTEP.7872 MISO Transmittal at 18, 41; proposed Tariff § 38.2.2; proposed ZGIA Art. 7.1.1.73 MISO Transmittal at 18; Keyser at 38.74 MISO Transmittal at 42-43; proposed ZGIA Art. 9.7.4.7; proposed ZGIA App. A § 2.75 MISO Transmittal at 43; proposed ZGIA App. A §§ 1-2.76 MISO Transmittal at 18, 41-43; Pro Forma GIA §§ 6.1-6.2; proposed ZGIA Arts. 7.1, 7.1.1, 9.7.4.7.77 Clean Energy Protest at 18-26.78 United Comments at 7-10.
PDF page 14
MISO’s filing already explains how the ZGIA and DPP models interact. ZGIA studies do not include Interconnection Requests remaining in the generator interconnection queue that do not yet have a GIA.79 Before each ZGIA cycle, Interconnection Requests with GIAs approved since creation of the prior base case are added to the ZGIA base case.80 Those projects are not, however, inserted into an ongoing DPP study.81
Once a DPP cycle begins, its base case generally is not updated to add subsequently approved ZGIA projects, except for ordinary changes resulting from withdrawals or generator retirements.82 MISO designed that sequencing to ensure that transmission capacity available to DPP projects is not taken away by ZGIA projects approved outside the DPP cycle.83 ZGIA projects likewise do not use available transmission capacity reflected in the DPP and ERAS studies.84 After the DPP cycle concludes, completed DPP, ZGIA, and EPR projects are incorporated into a new MTEP base case.85 Any resulting reconciliation issues are addressed through MTEP, and the next DPP cycle uses the reconciled MTEP base case.86 As MISO explained, this process “insulates existing DPP projects from negative impacts or cost shifts due to the existence of the ZGIA process.”87
The limited nature of ZGIS provides an additional safeguard against the cost-shifting concerns raised by Clean Energy. The amount of Interconnection Service awarded to a ZG
79 MISO Transmittal at 15.80 MISO Transmittal at 15.81 MISO Transmittal at 15.82 MISO Transmittal at 15.83 MISO Transmittal at 15.84 MISO Transmittal at 15.85 MISO Transmittal at 15.86 MISO Transmittal at 15.87 MISO Transmittal at 15.
PDF page 15
Resource cannot exceed the peak demand of the ZG Associated Load.88 The ZG Resource must connect at the same substation and voltage level as a Point of Withdrawal for the ZG Associated Load, and the ZG Interconnection Study must determine that the project will not require Network Upgrades beyond that substation except for System Protection Facilities at adjacent substations.89 The costs of equipment necessary to limit injections consistent with ZGIS are borne by the ZG Interconnection Customer.90
SEIA similarly explains that the same-substation and load-following requirements minimize Transmission System impacts and allow ZGIA projects to proceed without consuming transmission capacity required by DPP projects or increasing costs for projects already in the queue.91
Clean Energy’s separate contention that the ZGIA creates a fast-track pathway to ERIS or NRIS likewise misunderstands the service being offered.92 A project receiving ZGIS receives only the limited Interconnection Service defined by the Tariff; it does not receive ERIS or NRIS.93 If a ZG Resource later seeks ERIS or NRIS, it must submit an Interconnection Request and proceed through the DPP or applicable generator-interconnection process on the same footing and on the same study timeline as Interconnection Requests that do not already have ZG Interconnection Service.94 The ZGIA does not provide a mechanism for a ZG Resource to enter an active DPP
88 MISO Transmittal at 13; Keyser at 10-11; proposed Attachment X § 3.10.1.89 MISO Transmittal at 13; proposed Attachment X §§ 3.2.5.1-.2, 3.10.1.90 MISO Transmittal at 26-27.91 SEIA Comments at 3-6.92 Clean Energy Protest at 20-24.93 MISO Transmittal at 12-16; proposed Tariff, Module A, ZG Interconnection Service.94 Keyser at 14-17.
PDF page 16
cycle, retain a prior DPP queue position, or otherwise convert ZGIS into ERIS or NRIS without completing the applicable interconnection process.95
Similarly, if a project already participating in the DPP elects instead to pursue ZGIS, it relinquishes the broader ERIS or NRIS service that could be obtained through its DPP request and receives the more limited ZGIS.96 A later request for ERIS or NRIS would proceed through the applicable queue process rather than retaining priority based on the ZGIA.
The same service limitation addresses Clean Energy’s concern regarding the commitment of the ZG Associated Load. ZGIS is restricted to serving the ZG Associated Load identified in the Interconnection Request and memorialized in the ZGIA.97 MISO requires documentation of the relationship between the ZG Resource and ZG Associated Load specifically because the ZG Resource may serve only that designated load and to prevent speculative Interconnection Requests.98
If the ZG Associated Load does not materialize or ceases to exist, the ZG Resource does not thereby acquire ERIS, NRIS, or a general right to inject onto the Transmission System.99 To obtain broader Interconnection Service, the Generating Facility must proceed through the applicable generator-interconnection process.100 It may not inject onto the Transmission System until granted a right to do so by such process.
G. The ZGIA Provides Appropriate Transparency.
95 Id.96 Id. At 2997 MISO Transmittal at 12; proposed Tariff, Module A, ZG Interconnection Service; proposed Attachment X § 3.2.5.1.98 MISO Transmittal at 12 & n.41; Keyser at 9; proposed Attachment X § 3.10.1.99 MISO Transmittal at 12, 16; proposed Tariff, Module A, ZG Interconnection Service.100 Keyser at 29.
PDF page 17
Clean Energy contends that MISO’s proposal does not adequately address transparency because the Tariff does not expressly require publication of ZGIA study reports, affected-system results, required or deferred Network Upgrades, or associated Network Upgrade costs.101 This objection is unfounded. These requirements are not currently imposed on Interconnection Requests seeking Interconnection Service through other processes, such as the DPP and it is not necessary to add such new requirements for ZGIAs independently from any large load transparency reforms. MISO does not propose to reduce any generally applicable transparency requirements currently established in the GIP for Interconnection Requests seeking ZGIS.
ZGIA Interconnection Requests remain subject to MISO’s existing affected-system coordination procedures and screening criteria, subject to the specific timing modifications applicable to ZGIA requests.102 MISO must provide the information necessary for an Affected System to study a ZG Interconnection Request prior to the applicable ZG Impact Assessment and provide any affected-system analysis received to the ZG Interconnection Customer.103 More fundamentally, Clean Energy’s concern regarding undisclosed or “deferred” Network Upgrades does not account for a central eligibility limitation of ZGIS. The ZG Resource must interconnect at the same substation and voltage level as a Point of Withdrawal for its ZG Associated Load, and the ZG Interconnection Study must determine that the ZG Resource will not require Network Upgrades beyond the substation except for System Protection Facilities at
101 Clean Energy Protest at 14-16.102 Proposed Attachment X.103 Id. MISO notes that ZG Interconnection Service is not restricted to Generating Facilities serving large loads. limited to Large Loads.
PDF page 18
adjacent substations.104 The ZG Impact Assessment likewise must determine that no Network Upgrades beyond those specifically allowed for ZGIS are necessary to maintain reliability.105 Thus, the ZGIA process does not permit MISO simply to defer broader Network Upgrades and their associated costs.106 If the study determines that a project requires Network Upgrades inconsistent with the eligibility criteria for ZGIS, the project cannot proceed under the ZGIA process.107
Broader transparency requirements associated with large-load interconnection are distinct from the ZGIA Filing before the Commission here. MISO expressly stated that the ZGIA Filing addresses only certain issues raised in the Show Cause Order and that MISO intends to address additional large-load issues through subsequent section 205 filings.108 ZGIS is not restricted to Generating Facilities serving Large loads. The Commission therefore need not require MISO to resolve those broader transparency issues as a condition of accepting ZGIS.109
H. Additional Aggregate or Temporal Limits Are Unnecessary Given the Limited Nature of ZGIS.
Clean Energy argues that MISO should establish a pilot program, aggregate MW cap, limited application period, or defined term for individual ZGIAs.110
The proposal already contains significant limitations on the availability and operation of ZGIS. ZGIS is available only where the Generating Facility and ZG Associated Load satisfy the
104 MISO Transmittal at 13; proposed Attachment X §§ 3.2.5.1-.2, 3.10.1.105 MISO Transmittal at 28; proposed Attachment X § 3.2.5.2.106 MISO Transmittal at 28; proposed Attachment X § 3.2.5.2.107 MISO Transmittal at 28; proposed Attachment X § 3.2.5.2.108 MISO Transmittal at 2, 10-11.109 MISO Transmittal at 2, 10-11. To the extent that a ZGIA involves a Large Load, nothing in the ZGIA Filing purports to exempt a Large Load from any generally applicable transparency requirements that MISO may propose in a subsequent filing. 110 Clean Energy Protest at 16-18.
PDF page 19
same-substation and same-voltage requirements established by the Tariff.111 The amount of ZGIS awarded cannot exceed the peak demand of the ZG Associated Load.112 The ZG Interconnection Study also must determine that the project will not require Network Upgrades beyond the interconnecting substation except for System Protection Facilities at adjacent substations.113 MISO also limits the number of requests that may be processed during each quarterly ZGIA study cycle.114 MISO adopted that limitation to avoid disruption to the DPP and ensure that sufficient resources are available to process ZGIA requests.115
An additional aggregate MW cap is unnecessary because the amount of ZGIS available to each project already is tied directly to the peak demand of its ZG Associated Load.116 Moreover, ZGIS does not provide general injection rights and cannot require the broader Network Upgrades associated with ordinary ERIS or NRIS requests.117 A predetermined expiration date for each ZGIA similarly is unnecessary because the service remains subject to those limitations throughout the life of the agreement.118 If the studied equipment or configuration changes in a manner that could affect the Transmission System impacts of ZGIS, those changes are subject to MISO’s applicable modification rules.119 MISO specifically incorporated the studied configuration into Appendix A
111 MISO Transmittal at 12-13; proposed Attachment X § 3.10.1.112 MISO Transmittal at 13; Keyser at 10-11; proposed Attachment X § 3.10.1.113 MISO Transmittal at 13, 28; proposed Attachment X §§ 3.2.5.1-.2.114 Keyser at 24.115 Keyser at 24.116 MISO Transmittal at 13; Keyser at 10-11.117 MISO Transmittal at 12-13, 16, 26-28; proposed Tariff, Module A, ZG Interconnection Service; proposed Attachment X §§ 3.2.5.1-.2.118 MISO Transmittal at 12-16; proposed ZGIA.119 MISO Transmittal at 43; proposed ZGIA App. A §§ 1-2.
PDF page 20
so that changes affecting the basis on which ZGIS was granted are subject to those modification requirements.120
Accordingly, the absence of an arbitrary aggregate or temporal cap does not render ZGIS unlimited. Its scope is limited by the electrical configuration, associated-load relationship, service amount, Network Upgrade restrictions, study requirements, and continuing operating obligations established by the Tariff and ZGIA.121
I. MISO’s Treatment of Hybrid Resources Is Consistent with the Limited Nature of ZGIS.
Clean Energy seeks clarification concerning Hybrid Resources, including storage charging, tripping, metering, injections, and capacity accreditation.122
The presence of an Energy Storage Resource does not alter the fundamental nature of the service. Charging behavior that affects the studied configuration will be evaluated as part of the ZG Impact Assessment, consistent with MISO’s treatment of charging in the DPP study process. The Hybrid Resource remains subject to the same fundamental requirement that its operation comply with the ZGIS limitation and the equipment and configuration studied by MISO. Hybrid Resources also are subject to the ZGIA’s separate-metering requirements. MISO therefore will be able to distinguish the generation and load components and verify compliance with the applicable Interconnection Service limitation.123
Finally, MISO does not interpret the phrase “firm interconnection service” in Tariff Section 69.A.4 as excluding ZG Interconnection Service any more than it would exclude ER
120 MISO Transmittal at 43.121 MISO Transmittal at 12-16, 21-22, 26-28, 41-43; proposed Attachment X §§ 3.2.5, 3.10.1; proposed ZGIA Arts. 7.1, 7.1.1, 9.7.4.7.122 Clean Energy Protest at 26-29.123 MISO Transmittal at 41; Keyser at 38.
PDF page 21
Interconnection Service. MISO notes that “firm interconnection service” is not a defined term in Module E-1. Any ambiguity that may exist in how Section 69.A.4 applies to specific types of Interconnection Service under Attachment X was not created by the ZGIA Filing and should not impede Commission acceptance of this filing. MISO also notes that the quoted language in Section 69.A.4 applies only for the limited period of time before operating data becomes available. This said, MISO understands Clean Energy’s concerns and would not object to a compliance directive requiring MISO to clarify that the term “firm interconnection service” is intended to refer to deliverability. MISO has already included revisions to the Tariff sheets included in the ZGIA Filing to provide that Resources with ZG Interconnection Service are considered deliverable to the ZG Associated Load.124 This is consistent with the intent of MISO’s proposal and reflects how MISO would have interpreted the requirements of Section 69.A.4 even without further revisions.
J.
MISO Agrees with Certain Suggested Drafting Corrections. These Limited
Correction Do Not Undermine the Proposal.
MISO appreciates commenters identifying potential drafting errors or language inconsistencies. After carefully reviewing the comments and protest submitted in this docket, MISO agrees that the following limited language corrections are consistent with MISO’s proposal and improve the clarity of the Tariff language. Accordingly, MISO would welcome compliance directive to make these changes:
1. MISO agrees with Clean Energy that the references GIP Section 3.2.3.2 in proposed Attachment X Section 3.2.5.1 and Attachment X, Appendix 19 Section
4.1.4.1 was intended to refer to GIP Section 3.2. be revised to refer to proposed section 3.2.5.2 and should be revised accordingly.
124 See proposed revisions to Section 69.A.3.1.g Part A and Part B.
PDF page 22
2. MISO agrees that the intent of Section 9.7.4.7 of the ZGIA is intended to limit the output of the Generating Facility with ZG Interconnection Service to the current need of the ZG Associated Load, rather than to the ZG Associated Load’s peak demand over some prior period when ZG Associated Load is drawing power below that peak level. MISO therefore agrees that the use of the word Demand, as defined in Module A, may be confusing. MISO believes that any confusion on this point can be clarified by revising Section 9.7.4.7 of the ZGIA to refer to the “amount of Energy currently being withdrawn by the ZG Associated Load”. Consistent with this revision, MISO would also welcome a compliance directive to revise the definition of Transient Tolerance Window as follows:
Transient Tolerance Window: shall mean the period of time after a reduction or loss of load by the ZG Associated Load by the end of which window the Generating Facility with ZG Interconnection Service must have reduced its injections output to an amount not greater than the Load amount of Energy current being withdrawn by the ZG Associated Load. The Transient Tolerance Window shall be no greater than 20 seconds, and is further described by the Business Practices Manual for Large Load. The Transient Tolerance Window will be subject to Transmission Owner local planning criteria.
These revisions are clarifying in nature and will not change how MISO intends to implement ZG Interconnection Service and are consistent with MISO’s original proposal.
4. MISO does not object to changing references to “injections” to instead refer to “output” in GIP Section 1, Attachment X—Appendix 19 Section 1, and Attachment A—Appendix 19 Section 9.7.4.7 as suggested by Clean Energy. MISO does not believe that that the current use of the word “injections” is problematic because the proposed ZGIA Tariff language, supporting testimony, and transmittal letter are
PDF page 23
very clear that non-injection refers to injection past the substation to which the Generating Facility and ZG Associated Load are connected. “Injection” therefore refers to the Generating Facility sending power through the Point of Interconnection to the Point of Withdrawal, which may involve power flowing over a transmission element at that substations for a short distance. This said, the term “output” accomplishes the same purpose as “injection” in the cited areas and therefore would not substantively change MISO’s proposal. Accordingly, MISO would not object to a directive requiring this revision on compliance.
5. MISO has also heard from stakeholder since filing the ZGIA that an misalignment exists between some working in Section 3.11.3 and Sections 3.11.4 of Attachment X. On the third and fourth line of proposed Section 3.11.4, the language reads “Transmission Provider will complete the ZG Facilities Study and then tender a draft ZG Interconnection Agreement.” Section 3.11.4 Section states: Transmission Provider shall tender a draft pro forma ZGIA or ZGIA… within five (5) Business Days after the Interconnection Customer
communicates its election to proceed with ZG Interconnection Service, and complete any unfinished portion of the Facilities Study and tender the results to Interconnection Customer within the timeframe specified in Section 3.11.2 of these GIP.
The proposed language in Section 3.11.4 properly states MISO’S proposed process and matches the description included in the Transmittal letter. However, the inclusion of the word “then” in Section 3.11.3 can be read to suggest that MISO will complete the unfinished portion of the Facilities Study prior to tendering the GIA rather than tendering the draft GIA and then tendering the results of any unfinished portion of the Facilities Study within the timeframe specified in Section
PDF page 24
3.11.2. To avoid confusion and align with the proposal as described in Section 3.11.2. and 3.11.4, MISO requests a limited compliance directive to revise the first sentence of Section 3.11.3 to state “Transmission Provider will complete the ZG Facilities Study within the timeframe specified by Section 3.11.2 of this GIP and then tender a draft ZG Interconnection Agreement within the timeframe specified by Section 3.11.4 of this GIP”. Such a directive would not change the process from that explained in the ZGIA Filing and in surrounding Tariff Sections but will be useful to avoid timing confusion by Interconnection Customers.
MISO submits that these corrections do alter the fundamental design or operation of ZGIS and a largely ministerial clarifications. Such limited drafting corrections provide no basis to reject or delay an otherwise just and reasonable proposal.
K.
Consumers’ Jurisdictional Concerns Do Not Require Modification of the
ZGIA.
Consumers asks the Commission to preserve state authority over retail loads and retail cost recovery, prevent MISO’s regional processes from becoming prerequisites to state authorization of retail service except as necessary to provide jurisdictional transmission service, and preserve sufficient information for state regulators to perform their statutory responsibilities.125 The proposal already respects that jurisdictional divide. The proposed definition of ZG Interconnection Service expressly states that ZGIS does not provide a right to serve, or a right to Transmission Service to serve, ZG Associated Load or a retail customer except as permitted by applicable state law.126125 Consumers Comments at 2-3.126 MISO Transmittal at 16.
PDF page 25
The ZGIA addresses the generator-interconnection component of the arrangement. It does not establish retail rates, authorize retail service, determine retail cost recovery, or otherwise displace applicable state authority. MISO takes no position on whether the Commission should address Consumers’ requested assurances other than to note that because these matters are outside of the scope of MISO’s proposal, to the extent that the Commission determines to include such assurances in its order, this should not such discussion should not impact Commission acceptance of MISO’s proposal.
III. CONCLUSION
For the foregoing reasons, MISO respectfully requests that the Commission accept the proposed Tariff revisions establishing ZG Interconnection Service and the ZGIA, effective October 18, 2026, as requested, subject to the limited clarifications identified herein, and reject requests to delay implementation, impose additional program limitations, or condition acceptance upon resolution of distinct large-load, transmission-service, or generator-interconnection reforms outside the scope of this proceeding
IV. COMMUNICATIONS
MISO requests waiver of Rule 203(b)(3)127 of the Commission’s Rules of Practice and Procedure to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all communications related to this filing be directed to:
Christopher D. Supino
Managing Senior Corporate Counsel
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
James C. Holsclaw
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-7970
127 18 C.F.R. § 385.203(b)(3) (2026).
PDF page 26
Telephone: (317) 249-5400
csupino@misoenergy.org
mkessler@misoenergy.org
jholsclaw@calfee.com
V. NOTICE AND SERVICE
MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission owners, as well as all state commissions within the MISO Region and the Organization of MISO States. The filing has been posted electronically on MISO’s website at https://www.misoenergy.org/legal/ferc-filings/ for other interested parties in this matter.
VI. CONCLUSION
WHEREFORE, MISO respectfully requests that the Commission dismiss the complaint in its entirety.
Respectfully submitted,
/s/ Christoper D. Supino
Christopher D. Supino
Managing Senior Corporate Counsel
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, Indiana 46032
Telephone: (317) 249-5400
csupino@misoenergy.org
James C. Holsclaw
Calfee, Halter & Griswold LLP
3900 Salesforce Tower
111 Monument Circle
Indianapolis, Indiana 46204
Telephone: (317) 308-7970
jholsclaw@calfee.com
Attorneys for the Midcontinent Independent
System Operator, Inc.
DATED: September 23, 2026
PDF page 27
CERTIFICATE OF SERVICE
I hereby certify that I have this day e-served a copy of this document upon all parties listed on the official service list compiled by the Secretary in the above-captioned proceeding, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure (18 C.F.R. § 385.2010).
Dated this 23rd day of September 2026, in Carmel, Indiana.
/s/ Dawn Kaminski
Dawn Kaminski
Midcontinent Independent
System Operator, Inc.
720 City Center Drive
Carmel, IN 46032
317-249-5400