Motion to Intervene and Comments of Central Municipal Power Agency/Services et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing
Four Midwest municipal and cooperative power agencies intervene and comment on MISO's large-load reliability requirements, seeking two clarifications: the rules apply only to transmission-connected loads, and they do not unduly burden Transmission Customers.
Asks FERC to: Have MISO clarify scope and customer burden, or direct it by deficiency letter and Tariff revisions to do so.
Comments on MISO's first filing after the E-8 order. They invoke the order's suggested large-load definition, which refers to interconnection at the transmission system, to argue the scope should be stated explicitly.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The Midwest TDUs support swift MISO action and ask for two clarifications.
Midwest TDUs therefore seek clarification on two issues PDF p. 2
- First, the requirements should reach only loads on the MISO Transmission System, not distribution-connected loads.
apply to those Large Loads interconnected to the MISO Transmission System (and not to loads interconnected at to the distribution system). PDF p. 2
- Second, Transmission Customers should be able to rely on agreements with Large Loads to show compliance without undue burden.
But additional clarity is needed to ensure that Transmission Customers can rely on these agreements to avoid undue burdens. PDF p. 2
- They ask FERC to order revisions through a deficiency letter if MISO does not clarify on its own.
To the extent that MISO does not clarify these issues on its own, the Commission should direct it to do so in a deficiency letter. PDF p. 2
- They say the word "behind" in MISO's Large Load definition could be read to reach loads behind a distribution transformer.
the term “behind” could potentially be read broadly to encompass anything behind such Point(s) of Withdrawal PDF p. 7
Contents · 9 sections
- I. Motion to Intervene
- II. Comments
- A. Midwest TDUs seek confirmation that the proposed requirements apply only to those Large Loads directly connected to the MISO Transmission System.
- B. MISO’s new requirements must be implemented in a way that does not unduly burden Transmission Customers and advances their reliability purpose.
- CONCLUSION
- ATTACHMENT A
- ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS
- Attachment A
- Attachment A
Read topic-matched comments in ER26-3650
Topics in the text: Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
At the same time, addressing these complex challenges must be done in a way consistent with the Show Cause Order the Commission issued to MISO5 and that avoids unintended adverse consequences.Read this passage
I. Motion to Intervene
PDF bookmark
MOTION TO INTERVENE Each Midwest TDU (described in Attachment A hereto) moves to intervene with full rights as parties to this proceeding.Read this passage
II. Comments
PDF bookmark
II.Read this passage
A. Midwest TDUs seek confirmation that the proposed requirements apply only to those Large Loads directly connected to the MISO Transmission System.
PDF bookmark · Topic match: Registry access
Specifically, we find that it is within the Commission’s exclusive authority to ensure that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting…Read this passage Filed comments: Registry access
B. MISO’s new requirements must be implemented in a way that does not unduly burden Transmission Customers and advances their reliability purpose.
PDF bookmark · Topic match: Registry access
MISO’s new requirements must be implemented in a way that does not unduly burden Transmission Customers and advances their reliability purpose.Read this passage Filed comments: Registry access
CONCLUSION
printed heading
CONCLUSION For the reasons discussed above, the Commission should (1) grant CMPAS, IMPA, MJMEUC, and WPPI intervention in this proceeding; and (2) ensure that the issues above are adequately clarified by MISO and order further Tariff revisions to the extent that MISO’s proposed language is not…Read this passage
ATTACHMENT A
printed heading
ATTACHMENT A A-1Read this passage
ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS
printed heading
ATTACHMENT A: DESCRIPTION OF MIDWEST TDUS Central Minnesota Municipal Power Agency d/b/a Central Municipal Power Agency/Services (“CMPAS”) is a public power joint action agency organized under Minnesota law.Read this passage
Attachment A
printed heading
Access to the JTS transmission facilities is administered by MISO pursuant to its tariff.Read this passage
Attachment A
printed heading
Attachment A A-3 with a 2024 summer peak load of 58 MW, titled the Southwest Missouri Public Energy Pool (“SWMPEP”).Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated on this 18th day of September, 2026. /s/ Jeffrey M.Read this passage