ER26-3650: the filed comments

Positions read for this site

Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.

Data center operators want the binding standard in the tariff

Data Center Coalition · ER26-3650-000 · 2026-11-03

The coalition asked FERC to reject the reliability proposal without prejudice and require substantive standards in the tariff itself. It said future changes should be filed with FERC rather than made outside the tariff.

Municipal utilities seek a clear limit on regulated loads

Midwest Transmission Dependent Utilities · ER26-3650-000 · 2026-10-28

The utilities said MISO’s answer disclaimed applying the rules to distribution-connected loads but the tariff still did not say so unambiguously. They wanted the tariff to explain how a utility could assign a compliance task to the large load.

Mississippi and Arkansas want binding rules filed with FERC

Mississippi and Arkansas Public Service Commissions · ER26-3650-000 · 2026-09-18

The two commissions asked FERC to condition acceptance on putting the specific requirements in the tariff. They said MISO could otherwise change costly requirements through business manuals without comparable review. These are not the same signatories as the LARS comments from Mississippi and Louisiana.

Consumer offices challenge the exemption for earlier projects

Iowa Office of Consumer Advocate, Illinois and Michigan attorneys general, Minnesota Department of Commerce and co-protesters · ER26-3650-000 · 2026-09-18

The coalition challenged MISO’s grandfathering provisions. It said existing loads can also trip or ramp suddenly and that utilities and other customers could inherit the cost of local reliability projects if those loads were exempt.

Other passages, matched by topic

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Connecting load and generation

Data Center Coalition

ER26-3650-000 · 2026-09-18

Additionally, if MISO is going to apply its proposed reliability requirements to co-located load, it should demonstrate that the proposed standards are appropriately tailored to account for the characteristics of these arrangements. PDF p. 18

Cost allocation

Data Center Coalition

ER26-3650-000 · 2026-09-18

- 30 - responsible load growth, support the development of new generation, and enhance grid resilience system-wide without imposing undue costs on existing ratepayers. PDF p. 30

Entergy Services, LLC

ER26-3650-000 · 2026-09-18

Measure forecast error Apply tolerance band Allocate costs using cost causation Tolerance and metrics • What should the tolerance band be: comparable MISO error, Large Load group typical error, a minimum MW floor, or a combination? PDF p. 38

CMTC et al.

ER26-3650-000 · 2026-09-18

Speaker, I rise in support of my bill, the Ratepayer Protection Act. PDF p. 15