ER26-3650-000 · 2026-09-18 · Entergy Services, LLC

Limited Protest of Entergy Services, LLC re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

Text extracted from the eLibrary original (SHA-256 1b2a5044bc1e148d…). Download the original from the official source.

Contents · 6 sections
  1. I. BACKGROUND p. 2
  2. II. LIMITED PROTEST p. 3
  3. A. The Rule of Reason Test p. 4
  4. B. MISO’s Filing Contravenes the Commission’s Rule of Reason that Requires p. 5
  5. C. The Commission Should Accept MISO’s Filing Subject to a Compliance p. 16
  6. CONCLUSION p. 17

Read topic-matched comments in ER26-3650

Topics in the text: Cost allocation · Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 21, 22, 23, 24.

Opening text

opening text

In that filing, MISO proposes to revise its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) to establish interconnection reliability requirements for Large Loads (the “Filing”).
Read this passage

I. BACKGROUND

printed heading · Topic match: Filing procedure

BACKGROUND The Filing is one of a series MISO is making in response to the Commission’s June 18, 2026, order instituting a proceeding under Section 206 of the Federal Power Act, directing MISO to show cause why its Tariff should not be found unjust and unreasonable for failing to adequately address…
Read this passage

II. LIMITED PROTEST

printed heading

LIMITED PROTEST At the outset, Entergy emphasizes that it supports transparent reliability requirements for Large Loads.
Read this passage

A. The Rule of Reason Test

printed heading

The Rule of Reason Test Section 205(c) of the Federal Power Act requires a public utility to file not only its rates, but the practices affecting those rates.5 When determining whether a practice affecting rates must be included in a tariff or may be included in a BPM, the Commission applies a…
Read this passage

B. MISO’s Filing Contravenes the Commission’s Rule of Reason that Requires

printed heading · Topic match: Reliability and curtailment

Cir. 2022) (even if a 75 kW cap for the availability of secondary-voltage service is only a “guidepost,” “that kind of numerical threshold is the type of requirement that the ‘rule of reason’ requires be stated in the Tariff”); SPP, 169 FERC ¶ 61,048 at P 62 (a 4-hour continuous run-time…
Read this passage

C. The Commission Should Accept MISO’s Filing Subject to a Compliance

printed heading

Core, statable, and specific reliability requirements must be included in the filed Tariff.
Read this passage

CONCLUSION

printed heading

CONCLUSION For the foregoing reasons, Entergy respectfully requests that the Commission accept MISO’s filing subject to a compliance filing that requires MISO to include in its Tariff operative interconnection reliability requirements in accordance with the Commission’s rule of reason.
Read this passage

CERTIFICATE OF SERVICE

printed heading · Topic match: Cost allocation

Consistent with Section 37A.6 of the Tariff, Computational Load subject to this Section shall remain connected to the Transmission System and continue operation during voltage and frequency disturbances within the applicable performance criteria specified in this Section. 11.2 General Ride-Through…
Read this passage Filed comments: Cost allocation