ER26-3650-000 · 2026-09-18 · Entergy Services, LLC

Limited Protest of Entergy Services, LLC re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

Midcontinent Independent System
)

Docket No.  ER26-3650-000
Operator, Inc.

)

LIMITED PROTEST OF ENTERGY SERVICES, LLC

Pursuant to Rule 211 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.211, Entergy Services, LLC (“Entergy Services”), on behalf of the Entergy Operating Companies (Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, and Entergy Texas, Inc.) (collectively, “Entergy”), files this Limited Protest in response to the August 28, 2026, filing of the Midcontinent Independent System Operator, Inc. (“MISO”).  In that filing, MISO proposes to revise its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) to establish interconnection reliability requirements for Large Loads (the “Filing”).

Entergy supports adoption of requirements meant to ensure that Large Loads are reliably integrated into the bulk electric system.  Indeed, Entergy has made significant and good faith efforts to work with MISO to identify reliability requirements for Large Loads.  Entergy is filing this Limited Protest because, for certain reliability requirements, MISO proposes to include only generalized requirements in the Tariff, while relegating the operative technical requirements and key numeric thresholds to an unfiled Business Practice Manual (“BPM”).  Specifically, for Large Load forecast data requirements, Phasor Measurement Unit (“PMU”) requirements, Large Load ride-through requirements, and Large Load ramp requirements, MISO improperly proposes to include in a BPM the specific requirements that a Transmission Customer serving a Large Load will be required to meet.  Under the Commission’s “rule of reason” test, those requirements must

PDF page 2

2

be included in the Tariff. The Commission thus should condition any acceptance of MISO’s filing on a compliance filing as described in Part II.C below.  The Commission also should defer the effective date of the Tariff provisions in the Filing until the compliance filing is accepted.

I. BACKGROUND
The Filing is one of a series MISO is making in response to the Commission’s June 18, 2026, order instituting a proceeding under Section 206 of the Federal Power Act, directing MISO to show cause why its Tariff should not be found unjust and unreasonable for failing to adequately address the interconnection and reliable operation of Large Loads.1  The Commission granted MISO a 90-day abeyance to develop its response through the stakeholder process.2 In the Filing, MISO proposes to add a new Module B, Section 37A to the Tariff, establishing interconnection reliability requirements for Large Loads.  New definitions are also set forth for “Large Load” (defined as load with demand of 50 MW or more at a single substation) and “Computational Load” (defined as a Large Load of 25 MW or more of information-technology demand, such as data centers).3  At the center of this Limited Protest are MISO’s proposed new categories of interconnection reliability requirements in the proposed new Module.  Those categories include Large Load forecast data requirements, PMU requirements, Large Load ride-through requirements, and Large Load ramp requirements.  While MISO has filed generic Tariff language mandating compliance, key provisions of the forecast data requirements, PMU requirements, ride-through requirements, and ramp requirements are completely absent from the filing and according to MISO, will be contained in BPMs that in

1 Filing Transmittal at 1; see also Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 at P 57 (“Show Cause Order”), errata notice, 196 FERC ¶ 61,123 (2026).
2 Midcontinent Indep. Sys. Operator, Inc., 196 FERC ¶ 61,333 (2026).
3 MISO Filing Tab A, Proposed Tariff Module B, §§ 1.C, 1.L.

PDF page 3

3

many cases have not yet been drafted.  At this time, the Entergy Operating Companies are involved in ongoing negotiations with Large Loads that may not satisfy MISO’s proposed grandfathering criteria at all, or that may only qualify for limited exemptions from certain of the reliability requirements.  Others may be similarly situated because the grandfathering criteria are not structured to fully exempt projects that are recently developed (and not yet in service) or in the late stages of negotiations.  Without defined and clear reliability standards, however, Large Loads and Transmission Customers lack clarity on how to design data center architecture to comply.

II. LIMITED PROTEST
At the outset, Entergy emphasizes that it supports transparent reliability requirements for Large Loads.  Entergy also supports the ongoing efforts of the North American Electric Reliability Corporation (“NERC”) to develop reliability standards for Large Loads under its authority as the nation’s Electric Reliability Organization.  Importantly, NERC’s process will result in standards that will apply uniformly across the country. As the Commission recognized in the Show Cause Order, large customer projects take significant resources to develop.4 Ensuring compliance with reliability requirements is a complex, technical process that may involve significant capital expenditure depending on the data center design. Yet, to date, MISO’s proposed Tariff language lacks essential technical and operational requirements. The undrafted BPMs will contain critical details on the specific requirements and how compliance can be achieved. Without this transparency, Transmission Customers and Large Loads cannot meaningfully understand the obligations the Tariff would impose, nor evaluate their operational or financial impact.

4 E.g., Show Cause Order, 195 FERC ¶ 61,212 at P 9.

PDF page 4

4

A. The Rule of Reason Test

Section 205(c) of the Federal Power Act requires a public utility to file not only its rates, but the practices affecting those rates.5  When determining whether a practice affecting rates must be included in a tariff or may be included in a BPM, the Commission applies a “rule of reason” standard.6  Under that standard, a tariff must include all practices that: (a) “significantly affect rates, terms, and conditions of service,” (b) are “readily susceptible of specification,” and

(c) “are not so generally understood in any contractual arrangement as to render recitation superfluous.”7

On the other hand, “items better classified as implementation details” may be included in a BPM.8  As the Commission has explained, “[i]t is appropriate for Business Practice Manuals to contain implementation details, such as instructions, guidelines, examples and charts, which guide internal operations and inform market participants of how [the RTO] conducts its operations under [its Tariff].”9  The information contained in a BPM “is meant to provide further explanation of the [Transmission Provider’s] practices but not significantly affect any rates,

5 16 U.S.C. § 824d(c).
6 E.g., Southwest Power Pool, Inc., 169 FERC ¶ 61,048 at P 62 (2019) (citing Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 at P 103 (2018)) (“SPP”).
7 Id.
8 Energy Storage Assoc., 162 FERC ¶ 61,296 at P 103; see also SPP, 169 FERC ¶ 61,048 at P 62 (same). 9 California Indep. Sys. Operator Corp., 122 FERC ¶ 61,271 at P 16 (2008) (“CAISO”).

PDF page 5

5

terms, or conditions, consistent with the Commission’s ‘rule of reason.’”10  Thus, information that is supplemental and secondary in nature may be included in a BPM. 11

The rule of reason test “requires a case-by-case analysis, comparing what is in the . . . tariff against what is in the Business Practice Manuals.”12  A cross-reference cannot be used to relegate to a BPM a rule that should be included a tariff.13

B. MISO’s Filing Contravenes the Commission’s Rule of Reason that Requires
the Operative Reliability Requirements to be Stated in the Filed Tariff, Not an Unfiled BPM

At the time of this filing, MISO has only provided draft BPM language for disturbance ride-through and operational forecasting.  However, pending completion of BPMs, MISO has proposed other reliability requirements in other presentations or statements.  As Entergy will explain, comparing MISO’s proposed Tariff language for Large Load forecast data requirements, PMU requirements, Large Load ride-through requirements, and Large Load ramp requirements to MISO’s draft BPM language or other recommendations makes clear that MISO’s filing fails the rule of reason test for those requirements.  MISO improperly proposes to include in a BPM the specific requirements that a Transmission Customer serving a Large Load will be required to meet.

1. Large Load Forecast Data Requirements
Proposed Section 37A.4 of the Tariff establishes the Large Load forecast data requirements. It comprises a total of two sentences.  First, the proposed Tariff language states

10 California Indep. System Operator Corp., 116 FERC ¶ 61,274 at P 1358 (2006), reh’g granted in part, 120 FERC ¶ 61,271 (2007).

11  CAISO, 122 FERC ¶ 61,271 at P 104.
12 California, 116 FERC ¶ 61,274 at P 1370.
13 Midwest Indep. Transmission Sys. Operator, Inc., 136 FERC ¶ 61,038 at P 11 (2011).

PDF page 6

6

that, “[p]rior to the later of the Service Commencement Date of a Large Load or September 1, 2027, a Transmission Customer taking Transmission Service on behalf of a Large Load must provide day(s) ahead and real-time Load Forecasts for a Large Load directly to the Transmission Provider to support the Reliability Assessment Commitment (RAC) and Security Constrained Economic Dispatch (SCED) processes, along with other reliability studies.”14  Second, the proposed Tariff language provides that the “Load Forecasts shall be updated to reflect the most current information on the expected Demand, in accordance with the Business Practices Manual for Large Load.”15

Lacking from this provision are the basic requirements that establish the core, legally binding terms and conditions for interconnection of large loads.  This section of MISO’s proposed Tariff identifies no forecast horizon, no update cadence, no accuracy standard, and no consequence for inaccurate forecasts.16 MISO states only that a Transmission Customer must submit “day(s) ahead and real-time” forecasts while deferring the substance of every operative detail to the BPM for Large Load.

The non-substantive character of MISO’s proposed Tariff in this regard is immediately apparent when compared to the forecast requirements MISO has proposed in its draft BPM-025- r14 for Operational Forecasting, draft section 9 of BPM-032 for Large Loads, attached hereto as Exhibits A, and B, respectively, and its Large Load Working Group presentation, made public on

14 MISO Filing Tab A, Proposed Tariff Module B, § 37A.4.
15 Id.
16 Id.

PDF page 7

7

August 27, 2026, one day prior to the Filing.17 Each of these documents include specific, operative requirements that a Transmission Customer serving a Large Load must satisfy.  For instance, the draft BPM requirements include two mandatory forecasts, on fixed horizons and cadences with a delineated “Large Load Hourly Forecast” that must be provided on a minimum “168 Hours Out” time horizon and updated at least hourly “by a defined deadline,” and a “Large Load 5-Minute Load Forecast” with a minimum horizon of “6 Hours Out,” which “must be sent and processed in MISO’s system at least 9 minutes prior to the start of” the applicable interval.18 Next, MISO’s draft BPM requires a specifically-defined forecast submission level, “at the CPNode,” with each Large Load “registered to its own dedicated CPNode . . . not [to] be aggregated or netted across CPNodes,” and the submitted forecast “shall reflect the gross load of the facility” without netting co-located or behind-the-meter generation.19 Beyond these clear operative and significantly impactful standards, MISO has proposed, outside of its Filing, defined accuracy metrics and a forecast-accuracy incentive that will in turn be used to allocate associated costs.  As stated in its Large Load Working Group Presentation of August 27, 2026: “Cost-causation allocation can strengthen the incentive for Large Loads to

17 See MISO, Large Load Operational Forecast Requirements (LLWG-2026-4A), Large Load Working Group (Aug. 27, 2026)  available at https://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin g%20Requirements%20(LLWG-2026-4a)%20Presentation777222.pdf (last accessed Sept. 18, 2026, attached hereto at Exh C); draft BPM-025-r14, Operational Forecasting § 3.2 available at https://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin g%20BPM-025-r14%20Draft%20(LLWG-2026-4A)777225.pdf (last accessed Sept. 18, 2026, attached hereto at Exh. A); draft BPM-032, Large Load § 9 available at https://cdn.misoenergy.org/20260827%20LLWG%20Item%2011%20Operational%20Forecastin g%20BPM-032%20LL%20Draft%20(LLWG-2026-4A)777226.pdf (last accessed Sept. 18, 2026, attached hereto at Exh. B).
18 See Operational Forecasting Business Practices Manual BPM-025-r13 at 21.
19 Id.

PDF page 8

8

submit accurate forecasts by assigning forecast-related costs to the errors that create them. The main cost channels are hourly make-whole / commitment impacts, 5-minute balancing and congestion impacts, and real-time energy price impacts.”20

These requirements are not implementation details, set apart as instructions to an underlying substantive Tariff provision, or secondary in nature to the Tariff.  Rather, they are the basic, specific requirements that a Transmission Customer must meet in order to satisfy the Large Load forecast data requirement, and they are key elements in MISO’s proposed reliability program.

A measure to determine the substantive versus secondary impact of MISO’s proposed forecasting requirements is to view them from the lens of potential cost of compliance.  Whether a Transmission Customer must maintain a rolling 168-hour hourly forecast updated hourly and a rolling 6-hour, 5-minute forecast delivered at least 9 minutes ahead of each interval dictates the metering equipment, associated software systems, and personnel staffing a Large Load must procure to meet the requirement(s).  Additionally, because MISO proposes to enforce the forecasting requirements it sets forth through a cost-causation incentive that allocates make- whole, commitment, balancing, congestion, and shortage-pricing charges commensurate with the forecast error (under a formula MISO dictates),21 the forecast requirements directly determine the charges a Transmission Customer serving a Large Load will pay.  In short, MISO proposes to convert forecast errors measured using its own criteria into costs charged to the Transmission Customer through existing MISO settlement mechanisms.

20 MISO (LLWG-2026-4A) at 7 (Aug. 27, 2026).
21 Id. at slides 7-8.

PDF page 9

9

The requirements currently included in the draft BPM and the Large Load Working Group presentation thus affect rates and services significantly. 22  Moreover, as evidenced by the fact that they are included in MISO’s presentation and draft BPM, these numeric requirements are realistically susceptible of specification.  Finally, they are not so generally understood in any contractual arrangement as to render recitation superfluous.  Absent specification, there would be no basis to know what the requirements are.23  Precedent makes clear that these types of numerical requirements must be included in a tariff rather than a BPM.24

2. PMU Requirements
Under proposed section 37A.5 of the Tariff, a Transmission Customer taking service on behalf of a Computational Load will be subject to PMU requirements.  That proposed section provides (a) the date by which phasor measurement recording and communications equipment must be installed by the Transmission Owner, (b) that the Transmission Customer is responsible

22 Midcontinent Indep. Sys. Operator, Inc., 166 FERC ¶ 61,236 at P 71 (2019) (the term “maintenance margin” should be defined in the Tariff because it is the sole factor in determining whether there is an “adequate projected margin” under the proposed Tariff revisions, which in turn determines whether certain Generator Planned Outages qualify for a safe harbor exemption or are otherwise subject to a potential accreditation penalty); CAISO, 122 FERC ¶ 61,271 at P 23 (a formula used to calculate a rate significantly affects rates, terms, and conditions of service and therefore should be included in the tariff) (“CAISO”); Midwest Indep. Transmission Sys. Operator, Inc., 122 FERC ¶ 61,283 at P 342 (a key element in the development of a reliable program must be included in the Tariff), order on reh’g, 125 FERC ¶ 61,061 (2008); see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires be stated in the Tariff).

23 Compare Hecate Energy Greene County LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023) (finding that provisions need not be included in a tariff because they are clearly implied by the tariff's express terms).
24 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (even if a 75 kW cap for the availability of secondary-voltage service is only a “guidepost,” “that kind of numerical threshold is the type of requirement that the ‘rule of reason’ requires be stated in the Tariff”); SPP, 169 FERC ¶ 61,048 at P 62 (a 4-hour continuous run-time requirement must be included in the tariff because it determines whether a resource is eligible to be used to satisfy a resource adequacy requirement).

PDF page 10

10

for the costs of the equipment, (c) where the equipment must be located, and (d) when existing equipment may be used.25  Beyond that, the proposed provision provides that the equipment must be “capable, at a minimum, of gathering phasor measurements as specified in Business Practices Manual for Large Load” and that “phasor measurements must be streamed in the format specified in the Business Practices Manual for Large Load[.]”26

The shortcomings of MISO’s proposal are evident when its proposed Tariff provision is compared to its June 2026 presentation of a draft Technical Compendium entitled “Interconnection Reliability Requirements for Large Load.”27 That presentation includes the following numeric thresholds and “Telemetry and PMU Requirements”:

▪
“Sampling Rate and Data Quality: High‑resolution sampling (e.g., PMU‑level >60 samples per second) is necessary to capture fast voltage, frequency, and real/reactive power changes characteristic of power‑electronic large loads.”28 The shortcomings of the draft Tariff language are further reinforced when the proposed BPM provisions addressing Telemetry and PMU requirements are considered.  These were posted publicly by MISO on September 4, 2026, a week after MISO submitted the Filing.  Draft section 11.5.1 requires as follows: “All PMU data from Computational Loads must be streamed

25 MISO Filing Tab A, Proposed Tariff Module B, § 37A.5. 26 Id.
27 Midcontinent Independent System Operator, Inc., “Interconnection Reliability Requirements for Large Load” Technical Compendium Draft (June 2026), available at https://cdn.misoenergy.org/20260610%20LLWG%20Item%2006%20MISO%20Large%20Load %20Interconnection%20Reliability%20Requirements_Technical%20Compendium%20Draft763 427.pdf. Note that the August 2026 version of MISO’s Technical Compendium removed reference to the 2-4 seconds or faster threshold and MISO may be continuing to receive stakeholder feedback on this and other topics.
28 Id. at 8.

PDF page 11

11

to MISO in IEEE/IEC 60255 118-1-2018 format at a sampling rate of 60 samples per second,” and calibration accuracy requirements are further specified in draft section 11.5.2.29 The requirements identified in MISO’s draft June 2026 technical compendium, recently posted BPM, or whatever requirements MISO ultimately proposes to adopt in those regards, are not mere implementation details such as instructions, guidelines, examples and charts; do not serve as guides for internal operations; and are not supplemental or secondary in nature.  They are the basic, specific requirements that a Transmission Customer must meet in order to satisfy the PMU reliability requirement and are key elements in MISO’s proposed reliability program. As the proposed Tariff sets forth, the Transmission Customer will be responsible for the expense of installing the “phasor measurement recording and communications equipment . . . that is capable, at a minimum, of gathering phasor measurements as specified in the Business Practice Manual for Large Load.”30  The requisite PMU sampling rate and streaming format, GPS time synchronization for intermediary phasor data concentrator (“PDC”), and latency from PMU to MISO PDC determines the type of hardware that the Transmission Owner or Transmission Customer must procure and the continuous streaming requirement drives the costs of additional required equipment, including data system architecture and secure communications systems that can handle the volume of data that will be required at a sampling and streaming rate that is double what Entergy currently uses.

29
Draft
Section
11
of
BPM-032
(Large
Loads),
available
at
https://cdn.misoenergy.org/20260909%20LLWG%20Item%2004%20BPM-
032%20Large%20Load%20DRAFT%20-%20Section%2011%20PMU780059.pdf (last accessed September 18, 2026, attached hereto as Exh. E).

30 MISO Filing Tab A, Proposed Tariff Module B, §37A.5.

PDF page 12

12

The requirements currently included in the draft BPM thus affect rates and services significantly.31  Moreover, as evidenced by the fact that they are included in MISO’s presentation and draft BPM, these numeric requirements are realistically susceptible of specification.  Finally, they are not so generally understood in any contractual arrangement as to render recitation superfluous.  Absent specification, there would be no basis to know what the requirements are.32 Precedent makes clear that these types of numerical requirements must be included in a tariff rather than a BPM.33

3. Large Load Ride-Through Requirements
Proposed Section 37A.6 includes Large Load ride-through requirements.  MISO’s
proposed Tariff language states only that a Transmission Customer taking Transmission Service on behalf of a Computational Load must “remain[] connected to the Transmission System and continue operation during voltage and frequency disturbances within the performance criteria established by the Transmission Provider in the Business Practices Manual for Large Load,” and that ride-through requirements “may include evaluation, testing, modeling, monitoring, and other compliance measures established by the Transmission Provider in the Business Practices Manual

31 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, 122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires be stated in the Tariff).
32 Compare Hecate Energy Greene County LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023) (finding that provisions need not be included in a tariff because they are clearly implied by the tariff’s express terms).
33 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (even if a 75 kW cap for the availability of secondary-voltage service is only a “guidepost,” “that kind of numerical threshold is the type of requirement that the ‘rule of reason’ requires be stated in the Tariff”); SPP, 169 FERC ¶ 61,048 at P 62 (a 4-hour continuous run-time requirement must be included in the tariff because it determines whether a resource is eligible to be used to satisfy a resource adequacy requirement).

PDF page 13

13

for Large Load.”34  The proposed Tariff language contains no voltage magnitudes, no frequency band, and no ride-through duration curve.

In comparison, MISO’s draft section 11 of BPM-032 specifies a voltage ride-through envelope, measured as Root Mean Square (“RMS”)Voltage at the Point(s) of Withdrawal, detailing RMS voltage ranges and corresponding minimum ride-through times; and it further requires specific active-power recovery performance as follows: “After voltage recovers above 0.90 p.u., restore at least 90% of pre-disturbance active power within two seconds (default).”35 Draft section 11 also specifies a frequency ride-through envelope, where minimum ride-through times are specified for corresponding system frequency levels (measured in Hz). Again, these requirements or whatever requirements MISO ultimately proposes to adopt in those regards, are not mere implementation details, do not serve as guides for internal operations, and are not supplemental or secondary in nature.  They are the basic, specific requirements that a Transmission Customer must meet in order to satisfy the Large Load ride- through requirement and are key elements in MISO’s proposed reliability program.  For example, whether a data center must ride through a 0.50 p.u. dip for 0.15 seconds versus longer periods, or recover 90% of its load within 2 seconds, dictates the electronic equipment and controls the Computational Load must install to achieve compliance.  The post-disturbance ride- through requirements related to post-disturbance performance and other criteria, if varied by only small measurements of time and permissible volume of load to be drawn from the grid, may

34 MISO Filing Tab A, Proposed Tariff Module B, § 37A.6.
35 MISO Business Practices Manual for Large Loads, Section 11 (BPM-032); See page 61 of 67, (posted August 27, 2026) available at https://cdn.misoenergy.org/20260827%20LLWG%20Item%2010%20BPM- 032%20Large%20Load%20Ride-through%20Draft777237.pdf (last accessed Sept. 18, 2026, attached hereto at Exh. D).

PDF page 14

14

create unachievable technical standards.  And even if they are achievable, small changes in the requirements can result in project-sized changes in costs (e.g., a $100 million project may need to spend another $100 million) to achieve compliance.  These are determinations that could decide project viability.  They thus affect rates and services significantly.36 Moreover, as evidenced by the fact that they are included in draft BPM requirements, these numeric requirements are realistically susceptible of specification.  Finally, they are not so generally understood in any contractual arrangement as to render recitation superfluous.  Absent specification, there would be no basis to know what the requirements are.37  Precedent makes clear that these types of numerical requirements must be included in a tariff rather than a BPM.38

4. Large Load Ramp Requirements
Proposed Section 37A.7 includes ramp requirements for Transmission Customers taking Transmission Service on behalf of Computational Loads.  Proposed Section 37A.7 includes language regarding the measurement of ramp limits, and then provides that “Computational Load shall be subject to up-ramp and down-ramp limits established by the Transmission Provider consistent with the process set forth in the Business Practices Manual for Large Load.”39  That section also provides that “[t]he Computational Load must have an effective up and down ramp rate not exceeding the specified limit outlined in the Business Practices Manual for Large Load unless otherwise directed by the Balancing Authority, Reliability Coordinator, or Transmission

36 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, 122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires be stated in the Tariff).
37 Compare Hecate, 72 F.4th at 1314.
38 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022); SPP, 169 FERC ¶ 61,048 at P 62.
39 MISO Filing Tab A, Proposed Tariff Module B, § 37A.7.

PDF page 15

15

Operator.”40  MISO states in the Filing that it “is proposing initial up- and down-ramp limits of 30MW/minute,” measured in aggregate across the applicable Points of Withdrawal during stable- state transitions, while allowing eligible generation or other resources to provide “ramp smoothing.”41

As an initial matter, tariff provisions, not statements in a transmittal letter, are binding.42 And, once again, it is the specific ramp limits that a Transmission Customer will need to satisfy. The ramp limits themselves are not mere implementation details, do not serve as guides for internal operations, and are not supplemental or secondary in nature.  Moreover, high-cost solutions may be the only technically feasible options to meet these requirements.  The specific ramp rates thus affect rates and services significantly.43  Moreover, as evidenced by the fact that MISO was able to easily describe the ramp limits in its Filing, these numeric requirements are realistically susceptible of specification.  Finally, they are not so generally understood in any contractual arrangement as to render recitation superfluous.  Absent specification, there would be no basis to know what the requirements are.44  Precedent makes clear that these types of numerical requirements must be included in a tariff rather than a BPM.45

40 Id.
41 Filing Transmittal at 20.
42 E.g., Louisville Gas and Elec. Co., 137 FERC ¶ 61,195 at P 55 (2011) (finding that statement in transmittal letter was not binding and directing applicant to include that statement in its tariff).
43 Midcontinent, 166 FERC ¶ 61,236 at P 71; CAISO, 122 FERC ¶ 61,271 at P 23; Midwest, 122 FERC ¶ 61,283 at P 342; see also City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022) (numerical threshold requirements are the type that the “rule of reason” requires be stated in the Tariff).
44 Compare Hecate, 72 F.4th at 1314.
45 E.g., City & Cnty. of San Francisco v. FERC, 24 F.4th 652, 661 (D.C. Cir. 2022); SPP, 169 FERC ¶ 61,048 at P 62.

PDF page 16

16

C. The Commission Should Accept MISO’s Filing Subject to a Compliance
Filing, With the Effective Date Deferred Until That Filing Is Accepted

Entergy recognizes that MISO and its Transmission Owners are under a Commission directive to address Large Load reliability, and Entergy shares the goal of reliable integration of Large Loads. Entergy’s interest is in a Tariff it can read, comply with, and plan for costs needed to implement it.  Indeed, that is what is required under the rule of reason test.  Core, statable, and specific reliability requirements must be included in the filed Tariff.

Consistent with the rule of reason and precedent,46 the Commission should direct MISO, in a compliance filing, to include in the Tariff specific Large Load forecast data requirements, PMU requirements, Large Load ride-through requirements, and Large Load ramp requirements, consistent with the rule of reason.  Among other things, the Tariff provisions should include specific forecasting parameters (including the applicable time horizons and any requirements to update operational forecast data), ramp-rate limits, disturbance ride-through timing (including applicable voltage or frequency levels and duration criteria), post-fault active power recovery timing requirements, and PMU sampling and streaming rates, data-quality, and retention thresholds.  These requirements will inform Transmission Customers serving Large Loads of the conditions that must be met for interconnection, and invoke precisely the kind of significant, specifiable terms the rule of reason requires in the filed Tariff.  Entergy agrees that genuine implementation details should be included in the BPM; the list above is narrowly tailored to the terms that meet the Commission’s rule of reason criteria.

46 E.g., Midcontinent Indep. Sys. Operator, Inc., 166 FERC ¶ 61,236 at P 71 (2019) (requiring MISO to move a rate-significant definition from a BPM into the Tariff by compliance filing, rather than rejecting the filing).

PDF page 17

17

The Commission also should defer the effective date of the Tariff provisions included with the Filing until the compliance filing is accepted.  The Commission has deferred effective dates pending a curative compliance filing in comparable circumstances.47  Finally, the Commission should require MISO to attach the relevant BPM as part of its compliance filing, for informational purposes.  This is an important step to provide an opportunity for parties to compare language in the BPM and recommend, as appropriate, operative language to be included in the Tariff.48  As noted above, the rule of reason test “requires a case-by-case analysis, comparing what is in the . . . tariff against what is in the Business Practice Manuals.”49 Overall, the Commission must ensure that any adopted reliability requirements are detailed in the Tariff, technically vetted, and supported by a complete record—protecting both system reliability and stakeholder fairness. Absent this, MISO’s filing risks premature approval of undefined reliability standards that could hamper the development of data centers in MISO. CONCLUSION

For the foregoing reasons, Entergy respectfully requests that the Commission accept MISO’s filing subject to a compliance filing that requires MISO to include in its Tariff operative interconnection reliability requirements in accordance with the Commission’s rule of reason. The Commission also should defer the effective date of the Tariff provisions until the compliance filing is accepted.

47 Id.
48 Cf. Midwest, 122 FERC ¶ 61,283 at P 400 (stakeholders need to be able to review BPMs to have a complete understanding of their responsibilities and obligations under the resource adequacy proposal).
49 CAISO, 122 FERC ¶ 61,271 at P 17.

PDF page 18

18

Respectfully Submitted,

/s/ Jeffrey Phillips

Jeffrey Phillips
Senior Counsel
Entergy Services, Inc.
101 Constitution Avenue, NW
Suite 200 East
Washington, DC  20001

(202) 530-7312

Jphil36@entergy.com

Andrea Weinstein
Vice President, Deputy General Counsel
Entergy Services, Inc.
101 Constitution Avenue, NW
Suite 200 East
Washington, DC  20001
(202) 530-7342
aweinst@entergy.com

Karis Parnham
Assistant General Counsel
Entergy Services, Inc.
101 Constitution Avenue, NW
Suite 200 East
Washington, DC  20001

(512) 487-3986

kparnha@entergy.com

Dated: September 18, 2026

PDF page 19

CERTIFICATE OF SERVICE
I certify that I have this day served the foregoing document by email upon each person designated on the official service list compiled by the Secretary in this proceeding.

/s/Jeffrey Phillips
Jeffrey Phillips
Entergy Services, Inc.
101 Constitution Avenue, NW
Suite 200 East
Washington, DC  20001

Dated: September 18, 2026

PDF page 20

20

EXHIBIT A

PDF page 21

[No extractable text on this page.]

PDF page 22

[No extractable text on this page.]

PDF page 23

[No extractable text on this page.]

PDF page 24

[No extractable text on this page.]

PDF page 25

21

EXHIBIT B

PDF page 26

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 51 of 68
OPS-12
Public
9. Large Load Forecast Data Requirements
9.1
Purpose
This section establishes the obligation for Transmission Customers serving Large Loads to provide day‑ahead and real‑time Load Forecasts directly to the Transmission Provider. These forecasts supply critical inputs to the Reliability Assessment Commitment (RAC), Security Constrained Economic Dispatch (SCED), and other reliability studies, enabling reliable operations and efficient market outcomes. To maintain situational awareness and accuracy, forecasts must reflect the most current expected Demand and be updated whenever material changes occur; submission, granularity, and validation expectations are harmonized with MISO’s operational forecasting processes referenced in BPM‑025.

9.2
Requirement Applicability
For each Large Load(s) meeting the requirement applicability in Section 2, the Transmission Customer must provide day(s) ahead and real-time Load Forecasts for Large Load directly to the Transmission Provider in accordance with BPM-025 Operational Forecasting.

9.3
Applicable BPMs and Processes
•
BPM-025 Operational Forecasting

PDF page 27

22

EXHIBIT C

PDF page 28

Large Load Operational Forecast Requirements (LLWG-2026-4A)

Large Load Working Group (LLWG)
August 27, 2026
8/28/2026
Correction to slide 6

PDF page 29

Purpose & Key
Takeaway
Key Takeaways
Purpose
Summarize stakeholder feedback requested at the June 29th  Large Load Working Group meeting, review the BPM-032 and BPM-025 language, discuss the forecast incentive proposal, and introduce the forecasting submission system.

2
• MISO has incorporated stakeholders feedback into the Interconnection Reliability Requirements Tariff and BPM language, and is collaborating closely with stakeholders to refine accuracy, compliance expectations, and implementation details.

• Detailed forecast requirements, submission, validation, and compliance processes are formally defined in BPM-025 (Operational Forecasting) and BPM-032 (Large Load BPM).

• Large Load forecasting requirements integrate directly with MISO’s existing mid-term and short-term forecasting systems, using participant-submitted data to strengthen operational forecasting.

• MISO proposes improved incentives, including make-whole payments for hourly forecasts and 5-minute settlements for short-interval forecasts. Transmission Customers remain responsible for providing complete and accurate information to ensure compliance. BPM: Business Practice Manual

PDF page 30

The forecast requirement progressed from Tariff obligation to detailed
requirements, and currently focuses on BPM writing process and
incentives design
Discussed Forecast
Requirements
• Proposed what Transmission
Customers submit: CP node level,
Hourly (168-hour horizon) and 5-
minute (6-hour horizon)
• Introduced the error measurement
basis (absolute error vs. actual) and
submission monitoring
Review SH feedback,
BPM redlines, and
incentives proposal
• Review stakeholder feedback from
the 6/29th LLWG meeting
• Introduce BPM-032 (Large Load) and
BPM-025 (Forecast) redlines
• Define forecast error measurement
and initial considerations for accuracy
incentives proposal
• Illustrate forecasting submission
system
Illustrate Forecast
Systems & Processes to
Incorporate Large Loads
• Further details on forecast accuracy
incentive proposal based on
stakeholder feedback
• Software build and implementation
for forecasting submission system
• Software build and implementation
for DART system integration
CPNode: Commercial Pricing Node | LLWG: Large Load Working Group | BPM: Business Practice Manual | DART: Day-ahead and Real-time Last LLWG

Today
Next Steps
3

PDF page 31

4
Stakeholders feedback reflect general support of the forecast requirements and seek clarification on design and implementation details Detailed Stakeholder feedback and MISO responses are available in LLWG Large Load Operational Forecast Requirements Response (LLWG-2026-4A)774944.pdf

Stakeholder Feedback Theme
MISO Response
Forecast Design & Integration: Stakeholders
question the need for 5-minute forecasts and its
overlap with existing hourly/telemetry.
5-minute forecast submissions provide forward-looking operational data to manage intra-hour variability for Unit Dispatch System (UDS) and Look-Ahead Commitment (LAC).

Accuracy, Applicability & Accountability:
Stakeholders seek clarity on accuracy metrics, and
responsibility for submissions.
Accuracy and incentives will be defined in collaboration with stakeholders in the upcoming LLWG meetings.

Transmission Customers are accountable for meeting the forecasting requirements, as specified in MISO’s Interconnection Reliability Requirements Tariff.

Implementation, Transition & Regulatory Basis:
Stakeholders request clearer transition rules,
implementation details, and justification for
requirements.
Forecast requirements stem from FERC’s Show Cause Order and follow MISO’s Interconnection Reliability Requirements. Large Loads already in service are exempt unless changes occur, as described in MISO’s Interconnection Reliability Requirement Tariff. Submission mechanics and timelines will be detailed in BPM/LLWG discussions.

PDF page 32

MISO’s forecast requirements are kept unchanged and stakeholders
feedback on design and implementation details are incorporated into BPM
language
• Forecasts are submitted at the Commercial Pricing (CP) node level, consistent with the Large Load participation model; MISO maps submissions into the network model for congestion and contingency analysis Responsibility: Transmission Customers are accountable for meeting the forecasting requirements Transition: Prior to the later of the Service Commencement Date of a Large Load or September 1, 2027. BPM: Business Practice Manual | LAC: Look-ahead Commitment | RAC: Reliability Assessment Commitment | UDS: Unit Dispatch System Requirements in BPM (unchanged)

Requirements in Tariff (updated)
Forecast
Window and update cadence
MISO process supported
Status
Hourly
Next hour through +168 hours; updated
hourly
Multi-Day, Next-Day and Intraday RACs
(reliability commitment)
New
5-minute
Next 6 hours (72 intervals); updated
every 5 minutes
LAC (look-ahead commitment) and UDS
(real-time dispatch)
New
5

PDF page 33

6
Changes in BPM-025 and new contents in BPM-032 incorporate detailed
Large Load forecasting requirements
• BPM-025-r14 (2026) (Operational Forecasting) establishes the baseline for operational forecasting
• BPM-032 (Large Load) introduces updates focused on Large Load Interconnection Reliability Requirements. CP: Commercial Pricing | LBA: Local Balancing Authority | BPM: Business Practice Manual | DART: Day-ahead and Real-time Proposed changes to BPM-025 (Operational Forecast)

•
Large Load hourly forecasts for the next 168 hours.
•
Large Load 5-minute forecasts for the next 72 intervals.
•
Forecasts at CPNode level as gross load, not netted. Telemetry-based actuals for performance review.

•
MISO validates & integrates submitted forecasts into existing DART processes.
•
Large Load forecast submissions are treated as confidential information and are not posted publicly. Submitted forecast data is reflected only within the aggregate LBA and MISO market footprint forecast information that MISO posts.

PDF page 34

Forecast incentives
7
Measure
forecast error
Apply
tolerance band
Allocate costs
using cost causation

PDF page 35

Forecast errors matter because they can affect commitment efficiency,
balancing reliability outcomes, and real-time energy prices
• Cost-causation allocation can strengthen the incentive for Large Loads to submit accurate forecasts by assigning forecast-related costs to the errors that create them.

• The main cost channels are hourly make-whole / commitment impacts, 5-minute balancing and congestion impacts, and real-time energy price impacts.

Hourly forecast and commitment
efficiency
Make-whole and commitment
cost allocation*, including:
•
Day-ahead Deviation and
Headroom Charge (DDC)
•
Constraint Management
Charge (CMC)
• Large Load forecast errors can
distort RAC and real-time
scheduling: over-forecast can lead
to unnecessary commitment;
under-forecast can require late
commitment with fewer available
resource options
5-minute forecast and real-time
balancing/congestion
RT balancing actions and congestion
impacts
• 5-minute forecast misses can
increase balancing needs and change
how reserves are carried and
deployed
• Congestion impacts may justify a
targeted mechanism; Uninstructed
Deviation Enhancement (UDE)
construct provides a precedent for
linking harmful deviations to
congestion impacts
Settlement intervals and
shortage pricing
Real-time energy prices during tight
intervals
• Forecast errors can contribute to
conditions that produce large five-
minute energy-price movements and
shortage pricing.
• Aligning settlement intervals
allows prices to more closely reflect
real-time system conditions and
supports efficient market outcomes.
*MISO BPM-005 Market Settlements, Market Settlements 5-Minute Calculation Guide, D.14.2 (Constraint Management Charge) and D.14.6 (Day-ahead Deviation and Headroom Charge) 8

PDF page 36

Large Load forecasts are submitted and measured at each individual Large Load CP node

Where forecasts are submitted and measured
• Large Load forecasts are submitted at the applicable CP node
• Forecast accuracy is measured against metered load at that same CP node

• Hourly forecast values use integrated load; 5-minute values use RT interval meter data

Performance metrics at individual CP nodes
• Mean Absolute Error (MAE) at each CP node measures the average magnitude of forecast error in the applicable load units

• Mean Absolute Percentage Error (MAPE) at each CP node
measures forecast error relative to actual load, expressed as a percentage

Hourly MTLF measurement at the CP node*
DA
NDRAC
14:30
Notification
Deadline (NTD) 4-
HA
RT actual
| DA − NDRAC |
| NDRAC − NTD|
| NTD − RT actual |
| NDRAC (14:30) − RT actual |
5-minute STLF at the CP node
9 Min
Ahead
RT
meter
| 9 Min Ahead − RT interval meter |
• Measured at the same CP node using
RT interval meter data
| NTD 4HA − RT actual |
*Note: MISO DDC/CMC already measure deviations across DA to NTD and NTD to RT as part of RT RSG First Pass allocation (MISO BPM-005, Market Settlements 5-Minute Calculation Guide, D.14.2 and D.14.6.) 9

PDF page 37

MISO evaluates forecast accuracy similarly using MAE, MAPE, and unbiasedness

MAE
• Measures the average magnitude of
forecast error in load units
• Captures error volume directly
MAPE
• Measures forecast error relative to
actual load in percentage terms
• Normalizes forecast error for
differences in load size
Unbiasedness
• Measures whether forecast errors are
centered around zero over time
• Identifies persistent over- or under-
forecasting
Examples of MISO forecast-performance reporting
Historical MAE distributions by forecast horizon
Current-period operational MAE reporting by horizon and region
• Operational reporting tracks forecast error at specific horizons and by geography.

• Historical reporting provides an empirical benchmark for current performance.

10

PDF page 38

Open design questions remain for the Large Load forecast accuracy
incentives
MISO will work with stakeholders to further develop these design elements.
Measure
forecast error
Apply
tolerance band
Allocate costs
using cost causation
Tolerance and metrics
• What should the tolerance band be: comparable MISO error, Large Load group typical error, a minimum MW floor, or a combination?
• Should the same tolerance band apply to all Large Loads, or should computational Large Loads have a different tolerance? Monitoring and rollout

• Is a monitoring period needed before implementation, and if so for how long?
Incentive Framework
11

PDF page 39

Large Load forecast submission
12

PDF page 40

Establishes externally-facing Application
Programming Interface (API) to accept
the Large Load forecast (5-minute short-
term load forecast (STLF) and 60-minute
mid-term load forecast (MTLF)*
13
Accepting Large Load forecasts will focus on submission and integration with existing systems

*7-days out. | **Similar to how Local Balancing Authorities (LBAs) submit data today. Verifies that the

submitted forecast
meets requirements
(format, tables, time,
values, etc…)
MP/TC

PDF page 41

Next Steps
14
• Develop additional forecast incentive framework details
• Expand forecast submission systems and DART integration
• Present the updates at upcoming LLWG meetings

PDF page 42

Stakeholder Feedback Request
15
• MISO requests feedback on the Large Load Large Load Operational Forecast BPM language and Incentives Proposal by Monday, September 10th, 2026

• Feedback requests and responses are managed through the Feedback Tool on the MISO website at: https://www.misoenergy.org/engage/stakeholder-feedback/

PDF page 43

Send questions or comments to:
LargeLoadProgram@misoenergy.org
16

PDF page 44

23

EXHIBIT D

PDF page 45

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 59 of 67
OPS-12
Public
11. Large Load Ride-Through Requirements
11.1 Purpose
The purpose of the ride-through requirements is to reduce the risk of unnecessary disconnection or rapid changes in Demand associated with Computational Load during voltage and frequency disturbances and to support predictable disturbance performance during credible Transmission System events.

As Computational Loads increasingly incorporate power-electronic interfaces, fast controls, and dynamic operating behavior, their response to Transmission System disturbances may materially affect system performance, operational reliability, and post-contingency recovery. Ride-through requirements establish minimum performance expectations for maintaining connection and stable operation during voltage and frequency disturbances and for recovering active power following disturbance clearance.

Consistent with Section 37A.6 of the Tariff, Computational Load subject to this Section shall remain connected to the Transmission System and continue operation during voltage and frequency disturbances within the applicable performance criteria specified in this Section. 11.2 General Ride-Through Requirements

Ride-through requirements shall apply at the applicable Point(s) of Withdrawal (“PoW(s)”) of a Large Load and shall be evaluated based on voltage and frequency conditions measured at the PoW(s).

When system conditions remain within the applicable ride-through performance limits specified in Sections 11.3 and 11.4, the Computational Load shall remain connected to the Transmission System and maintain stable operation.

Protection systems, converter protections, transfer schemes, facility controls, and other Large Load Equipment shall be coordinated to avoid unnecessary tripping, interruption of service, or unstable operation during disturbances within the applicable ride-through limits. Following disturbance clearance, the Computational Load shall recover toward its pre- disturbance operating condition in accordance with the applicable performance requirements of this Section.

11.3  Voltage Ride-Through Requirements
Computational Load shall remain connected to the Transmission System and maintain stable operation during voltage disturbances when voltage measured at the applicable PoW(s) remains within the voltage ride-through requirements specified in this Section. Protection systems and facility controls shall be coordinated to avoid unnecessary disconnection and to support stable operation during and following voltage disturbances. 11.3.1 Voltage Ride-Through Envelope

Voltage ride-through performance shall be determined based on the root-mean-square voltage magnitude measured at the applicable PoW(s) and the duration of the voltage excursion. Table 11-1. Voltage Ride-Through Requirements at PoW

PDF page 46

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 60 of 67
OPS-12
Public
Root Mean Square Voltage
(p.u. of nominal)
Minimum ride-through time (s)
V > 1.20
May ride-through or trip
1.10 < V ≤ 1.20
0.50
0.90 ≤ V ≤ 1.10
Continuous
0.80 ≤ V < 0.90
2.00
0.50 ≤ V < 0.80
0.50
V < 0.50
0.15

Within the voltage-duration limits defined by the ride-through envelope, the Computational Loads shall remain connected to the Transmission System and maintain stable operation consistent with established performance expectations. Disconnection shall not occur unless voltage conditions exceed the ride-through envelope or otherwise permitted under applicable ride-through provisions.

The ride-through envelope establishes the expected no-trip region for Computational Loads and is intended to support predictable disturbance performance during credible voltage events and reliable operation of the Transmission System.

Computational Loads shall be capable of remaining connected during at least six voltage disturbance events occurring within any 90-second period, including disturbances associated with automatic reclosing, provided the voltage magnitude and duration of each individual disturbance remain within the applicable ride-through envelope specified in Table 11-1. 11.3.2 Performance During Voltage Disturbances

While operating within the voltage ride-through envelope, the Computational Load shall satisfy the following active power performance requirements:

•
Voltage between 0.90 pu and 1.20 pu:
o The Computational Loads shall remain connected to the Transmission System and maintain pre-disturbance active power consumption.

o Temporary reduction of active power shall not occur.
o Protection systems, converter protections, and control logic shall not initiate unnecessary tripping, interruption of service, or curtailment.

•
Voltage between 0.50 pu and 0.90 pu:
o The Computational Loads shall remain connected to the Transmission System within the ride-through envelope.

o Temporary reduction of active power may occur in proportion to the voltage reduction to support continued operation during the disturbance.

•
Voltage below 0.50 pu:

PDF page 47

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 61 of 67
OPS-12
Public
o The Computational Loads shall remain connected to the Transmission System within the ride-through envelope.

o Temporary reduction of active power may occur as necessary to maintain
connection and support ride-through performance during the disturbance.
Protection systems, converter protections, and control logic shall be coordinated to avoid unnecessary disconnection during voltage disturbances occurring within the ride-through envelope. Control systems shall maintain stable operation during and following disturbances and shall avoid oscillatory or unstable behavior that could adversely affect reliable operation of the Transmission System.

11.3.3 Active Power Recovery
Following recovery of system voltage above 0.90 pu, Computational Load shall restore at least 90% of its pre-disturbance active power within two seconds. This shall be the default active power recovery requirement.

MISO may establish an alternative active power recovery time or recovery trajectory where applicable planning studies demonstrate that a slower or otherwise modified recovery is necessary to maintain Transmission System reliability. Such an alternative may be established, for example, in electrically weak systems or where planning assessments identify potential adverse impacts associated with active power recovery, including oscillatory behavior or voltage instability.

11.3.4  Transient Overvoltage Ride-Through
Computational Load shall remain connected to the Transmission System and avoid unnecessary disconnection during short-duration transient overvoltage conditions associated with credible Transmission System events, including faults, transmission energization, switching operations, or other credible system disturbances.

Protection systems, converter protections, and facility controls shall be coordinated to avoid unnecessary interruption of service resulting from instantaneous or short-duration transient voltage excursions that do not represent sustained abnormal system conditions. These requirements are intended to support predictable disturbance performance and reduce the risk of unnecessary changes in large load demand during credible transmission events. 11.3.5 Phase Jump Ride-Through

Computational Load shall remain connected to the Transmission System and maintain stable operation during instantaneous positive-sequence voltage phase angle changes of up to 25 electrical degrees resulting from non-fault switching events on the Transmission System, provided system voltage remains within the voltage ride-through limits specified in Table 11-1. Protection systems, converter protections, and facility controls shall be coordinated to avoid unnecessary disconnection or unstable operation resulting from allowable phase angle changes during credible transmission system events.

11.3.6 Volts per Hz (V/Hz) Ride-Through
Computational Load shall remain connected to the Transmission System and maintain stable operation during abnormal voltage-frequency conditions, provided the Volts per Hertz (V/Hz)

PDF page 48

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 62 of 67
OPS-12
Public
measured at the Point(s) of Withdrawal (PoW(s)) does not exceed 1.10 per unit for more than 45 seconds or exceed 1.18 per unit for more than 2 seconds.

Protection systems, converter protections, and facility controls shall be coordinated to avoid unnecessary disconnection during V/Hz excursions within these limits and support stable operation during and following transmission disturbances.

11.3.7 Exception Process
To be developed.

11.4 Frequency Ride-Through Requirements
Computational Load shall remain connected to the Transmission System and maintain stable operation during frequency disturbances when system frequency measured at the applicable PoW(s) remains within the frequency ride-through requirements specified in this Section. Protection systems and facility controls shall be coordinated to avoid unnecessary disconnection during frequency disturbances within the specified limits. 11.4.1 Frequency Ride-Through Envelope

Computational Loads shall remain connected to the Transmission System and maintain stable operation when system frequency remains within the continuous operating range of 58.8–61.2 Hz. For frequency deviations outside this range, Computational Loads shall remain connected for the minimum durations specified in Table 11-2. Disconnection may occur when frequency excursions exceed the applicable limits of the ride-through envelope.

System frequency shall be measured at the applicable PoW(s) over a period of time, typically three to six cycles. The specified durations of the no-trip regions in Table 11-2 shall be cumulative over one or more disturbance events occurring within any 10-minute period.

Table 11-2. Frequency Ride-Through Requirements at PoW
System Frequency (Hz)
Minimum Ride Through Time (Seconds)
f > 61.8
May Trip
61.2 < f ≤ 61.8
299
58.8 ≤ f ≤ 61.2
Continuous
57.0 ≤ f< 58.8
299
f< 57.0
May trip

11.4.2 Performance During Frequency Excursions
During frequency deviations within the ride-through envelope, Computational Loads shall:

PDF page 49

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 63 of 67
OPS-12
Public
•
Remain connected to the Transmission System; and
•
Maintain stable operation consistent with established performance expectations. Computational Loads shall maintain pre-disturbance active power consumption while system frequency remains within the continuous operating range of 58.8 Hz to 61.2 Hz. For frequency excursions outside the continuous operating range but within 57.0 Hz to 58.8 Hz or 61.2 Hz to 61.8 Hz, Computational Loads shall remain connected and maintain active power consumption within ±10% of pre-disturbance levels while maintaining stable operation. 11.4.3  Rate-of-Change-of-Frequency Ride-Through

Computational Loads shall remain connected to the Transmission System and maintain stable operation during frequency excursions within the ride-through limits specified in Table 11-2, provided the absolute Rate of Change of Frequency (RoCoF) measured at the Point(s) of Withdrawal (PoW(s)) does not exceed 5.0 Hz/s.

For purposes of evaluating ride-through performance, RoCoF shall be calculated as the average rate of change of multiple calculated system frequency measurements over a time interval greater than or equal to 0.1 second. Consistent with North American Electric Reliability Corporation (NERC) PRC-029 guidance, RoCoF shall not be calculated during fault occurrence or fault clearance.

Any RoCoF protection installed shall be coordinated with applicable Transmission System reliability requirements and configured to avoid unnecessary disconnection during credible frequency disturbances. Protection settings and control behavior shall support ride-through performance during transient system conditions while avoiding inappropriate operation resulting from temporary fault-induced frequency measurement behavior.

11.5  Demonstration and Verification Requirements
The Transmission Customer shall demonstrate that each Computational Load subject to the ride-through requirements of this Section is capable of satisfying the applicable requirements in Section 11.

Demonstration and verification may include applicable planning studies, verified electrical models, equipment and control documentation, protection settings, commissioning or equipment test information, PMU and disturbance monitoring data, operational event records, or other information reasonably required by MISO to evaluate ride-through capability and performance. The Transmission Customer shall provide, upon request, information necessary to evaluate the behavior of equipment or controls that may affect ride-through performance, including power- electronic equipment, uninterruptible power supply systems, protection systems, transfer schemes, backup generation, energy storage, facility controls, and active power recovery characteristics.

The models and supporting information used to demonstrate compliance shall reflect the configuration and operating characteristics expected to exist as of the Service Commencement Date and shall be updated consistent with the modeling requirements of this BPM. 11.5.1 Planning Demonstration

Prior to the Service Commencement Date, the Transmission Customer shall demonstrate that the Computational Load is capable of meeting the applicable ride-through requirements

PDF page 50

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 64 of 67
OPS-12
Public
specified in this Section. The demonstration shall be based on applicable planning studies, model quality and performance testing, protection and control coordination, equipment documentation, or other technical information, as appropriate for the applicable requirement. The planning demonstration shall address, as applicable to the facility design, equipment, protection systems, controls, and models:

•
Voltage ride-through performance and active power response during voltage disturbances;

•
Active power recovery following voltage recovery;
•
Frequency ride-through performance and active power response during frequency excursions;

•
Consecutive disturbance ride-through capability;
•
Transient overvoltage and phase-jump ride-through capability;
•
RoCoF ride-through capability; and
•
V/Hz ride-through capability.
Not all ride-through requirements require a separate simulation test. MISO may determine the appropriate method of demonstration based on the nature of the requirement and the capability of the applicable models. Demonstration may include simulation results, protection-setting review and coordination, equipment or manufacturer documentation, control-setting verification, or other supporting technical information acceptable to MISO.

The applicable dynamic models shall represent protection, control, disconnection, active power reduction, and active power recovery behavior to the extent necessary to evaluate the applicable ride-through performance requirements.

Where MISO determines that positive-sequence dynamic simulation is insufficient to evaluate applicable ride-through behavior, MISO may require EMT analysis using the applicable EMT models submitted pursuant to the modeling requirements of this BPM.

11.5.2 Operational Performance Verification
MISO may verify actual ride-through performance using available operational and disturbance data, including PMU data, SCADA data, disturbance monitoring records, event records, or other relevant measurements associated with the applicable PoW(s).

Operational performance may be compared with the applicable ride-through requirements and submitted models to support post-event analysis and model validation.

Detailed operational performance verification procedures will be established through a future revision of this BPM.

11.6 Corrective Actions
See Corrective Actions in Section 13.4.

PDF page 51

24

EXHIBIT E

PDF page 52

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 55 of 83
OPS-12
Public

11. Large Load Phasor Measurement Unit (PMU) Requirements

IRR for Large Loads, dated August 28, 2026 (for reference)

PDF page 53

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 56 of 83
OPS-12
Public
11.1 Purpose
The purpose of this section is to establish the technical, operational, installation, communication, and naming requirements for phasor measurement units (PMUs) or equivalent synchronized measurement devices required for Computational Loads. These requirements ensure that high‑resolution, time‑synchronized phasor data is available to support real‑time situational awareness, oscillation detection, performance monitoring, including ride‑through requirement validation, after‑the‑fact event analysis, and dynamic model validation across the MISO footprint.

This section defines the minimum functional capabilities, data quality criteria, measurement types, and streaming expectations necessary for PMUs installed at Points of Withdrawal, and outlines roles and responsibilities for ensuring compliance with Tariff §37A Interconnection Reliability Requirements. Together, these requirements provide a consistent, reliable standard for PMU observability of Computational Loads and ensure alignment with applicable IEEE/IEC synchrophasor measurement and communication standards.

11.2 PMU Definition
A phasor measurement unit (PMU) is a device which measures the electrical voltage and current waveforms on a power grid that are synchronized to a common time source. Time synchronization allows monitoring of synchronized real-time measurements of multiple remote measurement points on the grid. A PMU can be a dedicated device, or the PMU function can be incorporated into a protective relay, digital fault recorder (DFR), dynamic disturbance recorder (DDR), or other devices that can meet the below requirements and additional requirements specified in the later sections of this document.

•
Measurements need to be synchronized with a high accuracy satellite clock (e.g. GPS/IRIG-B)

•
Data needs to be recorded at least at 60 samples per second and support continuous streaming of data to MISO.

•
The device must be capable of sampling and/or calculating all signals specified in 11.10 meeting minimum accuracy limits defined in the standard IEC/IEEE 60255-118-1:2018 for the P-Class PMU.

11.3  Applicability and Scope
PMU requirements defined in this section apply to all Computational Loads as defined under the MISO Tariff Interconnection Reliability Requirements. PMU-capable equipment must be installed prior to the later of the Service Commencement Date of the Computational Load, or September 1, 2027.

Computational Loads are required to have PMU’s to support oscillation detection, wide area monitoring, performance monitoring including ride through requirement validation, after-the- fact event analysis and dynamic model validation.

PDF page 54

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 57 of 83
OPS-12
Public
11.4 Installation Requirements
For a Computational Load, the Transmission Owner (TO) is required to install PMU (as defined in Section 11.2) at each Point of Withdrawal (POW) on the Transmission Owner’s side of the POW. The PMU shall provide real-time data output to MISO and adhere to the standards listed below.

•
IEEE/IEC 60255-118-1-2018 – Measurement requirements for synchrophasors, frequency and rate of change of frequency

•
IEEE C37.118.2-2024 – Communication requirements for real-time communication between PMU’s, PDC and other applications

•
Existing PMU’s shall comply to the earlier revisions of these standards including IEEE C37.118.1-2011 for measurement and IEEE C37.118.2-2011 for communication Use of a phasor data concentrator (PDC) on the TO side is preferred to consolidate multiple PMU streams into a single stream. This simplifies integration with MISO’s system and reduces connection complexity, eases data quality management.

11.4.1 Hardware Requirements
•
PMU shall be set to have an output reporting rate of at least 60 samples per second
•
PMU shall have timing accuracy of 3µs
•
All data recorded will be in Coordinated Universal Time (UTC)
•
PMU shall have GPS (UTC) synchronization function either through an internal or external GPS receiver

•
The PMU data stream shall indicate whether it is using GPS clock or local clock
•
GPS clock shall report time and time quality compatible to IEEE/IEC 60255-118-1-2018
•
Any intermediary PDC shall have GPS (UTC) synchronization function either through an internal or external GPS receiver

11.4.2 Communication Requirements
•
Interface to PDC through private IP networks
•
Receive and send real-time data through TCP/UDP ports, user configurable (each port individually configurable).

•
Network communication between PMU and PDC is defined by Member
•
Latency from PMU to MISO PDC shall be no more than 0.50 seconds.

11.5 Operational Requirements
11.5.1 Streaming requirements
All PMU data from Computational Loads must be streamed to MISO in IEEE/IEC 60255- 118-1-2018 format at a sampling rate of 60 samples per second.

11.5.2 Calibration Requirements
•
IEEE/IEC 60255-118-1-2018 Accuracy:
o Total Vector Error (TVE): ≤ 1%
o Frequency Error (FE): ≤ 0.005 Hz

PDF page 55

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 58 of 83
OPS-12
Public
o ROCOF Error (RFE): ≤ 0.4 Hz/s
•
Laboratory Accuracy:
o 0.5% Measurement Accuracy
▪
Calibration signals/measurement devices retain 0.05% to 0.1% Accuracy
•
Field Testing Accuracy:
o GPS Receiver Response
▪
Compatibility with IRIG-B Time Standard
▪
Responds correctly to loss of GPS signal within 1 minute
•
Indicated by status code
▪
Monitor GPS signal loss over a 24-hour period to ensure solid connectivity to Satellites

o Phasor Magnitudes
▪
Voltage
•
Ensure voltage readings are within range of PT accuracy
•
Confirm readings from testing tools are within 0.5 % of PMU reading values

▪
Current
•
Ensure current readings are within range of CT accuracy o If Current magnitude is low (Under 20% of rated current), then allow for extra amps of acceptable error (up to 50 A) in magnitude test

•
Confirm readings from testing tools are within 0.5 % of PMU reading values

o Phasor Angles
▪
Voltage
•
Confirm readings from testing tools are within 1 degree of corresponding signal angle differences

▪
Current
•
Confirm readings from testing tools are within 1 degree of corresponding signal angle differences

o Low current magnitudes will cause extra error here o Analog Readings

▪
Ensure PMU readings agree to other measuring devices in the substation within 5%

o Digital Readings
▪
Confirm digital readings report correct Boolean state
•
Control Center Accuracy:
o Time Stamp and Server Accuracy
▪
Confirm time stamp of received data matches local time to within 500 milli seconds

o Communication Errors and Data Loss
▪
Confirm undesirable data loss is kept below 0.1% over a 24 hour period

o SCADA Comparisons
▪
Voltage
•
Within 1% magnitude of comparable locations
▪
Current

PDF page 56

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 59 of 83
OPS-12
Public
•
Within 3% magnitude of comparable locations
▪
Frequency
•
Within 0.003 Hz over a 5-minute rolling window

11.6 Support/Manageability Requirements
Transmission Customer agrees to comply with any and all NERC Standards applicable to the PMU/PDC data stream in the event NERC or the MISO determines any of the NERC Standards apply to the PMU/PDC data stream and/or any associated hardware.

11.7 Data Retention
Current MISO data retention for synchrophasor data is as below:
•
Full resolution for A, B and C phase data is retained for 6 months; and all other data is retained for 1 year.

•
Down sampled data to one sample per second is retained for 2 years.
•
MISO PMU data retention does not replace any local storage requirements including obligations that come from existing and future NERC standards.

11.8  Required PMU Measurements
PMU’s at the Computational Loads must be able to sample and/or calculate the following signals:

11.8.1  Substation Measurements
•
Frequency - calculated from positive sequence voltage angle
•
Rate of Change of Frequency (ROCOF)
•
Quality
11.8.2  Point of Withdrawal (POW) Measurements
•
Phase A: voltage magnitude and angle
•
Phase B: voltage magnitude and angle
•
Phase C: voltage magnitude and angle
•
Phase A: current magnitude and angle
•
Phase B: current magnitude and angle
•
Phase C: current magnitude and angle
•
Positive sequence for voltage magnitude and angle
•
Positive sequence for current magnitude and angle
•
Quality
11.9  PMU Signal Naming Requirements
•
The fields streamed from the PMU should conform to the naming standards set forth below to provide a standard set of information about the measurement within the measurement name. Each field allows space for 16 characters (bytes).

•
Station Name – Name given to each phasor measurement unit:
o 4 bytes: Company Identifier

PDF page 57

Business Practices Manual for Large Loads
BPM-032
Effective Date: Dec-04-2026

Page 60 of 83
OPS-12
Public
▪
Use MISO EMS Model Control Area Name
o 10 bytes: Station name
▪
Use MISO EMS Model Station Name
o 2 bytes: Device ID Within Station
▪
Allows for uniqueness when there is more than 1 PMU at a station
▪
Align the Device ID to measured equipment identifier where possible. Ex: if there are PMU’s at 2 large loads (L1,L2) in the substation, use 01 for L1 and 02 for L2.

▪
Ex. MISOPMU  01
o Unused bytes should be left as blank spaces.
•
Channel Name – Name given to each individual Phasor measurement signal: o 1 byte: Measurement Identifier

▪
B = Phasor on Bus Side including loads
▪
L = Phasor on Line Side
▪
T = Phasor on Transformer
▪
G = Phasor on Generator
▪
R = Phasor on Reactor
▪
C = Phasor on Capacitor
▪
S = Phasor on Static Var Compensator
▪
D = Digital
▪
A = Non-phasor Analog (Including Frequency, ROCOF)
o 3 bytes: Nominal Voltage
▪
Fill from right (‘069’, ‘345’,’161’, etc.)
▪
For voltages with decimals such as 13.8, round to a whole number. o 9 bytes:

▪
MISO EMS Model Device name for measurement location
▪
Use Spaces after name to fill to 9 characters
•
Ex: L345QWERTY 1V1
▪
For all frequency and ROCOF measurements, use “FREQ”. o 1 byte:

▪
1= First Device, 2= Second Device, 3= Third Device, etc. o 2 bytes: Measurement Identifier

▪
Vx = Voltage Phasor (x = 1, 0, A, B, C, N)
▪
Ix = Current Phasor (x = 1, 0, A, B, C, N)
▪
Px = Real Power (x = 1, 0, A, B, C, N)
▪
Qx = Reactive Power (x = 1, 0, A, B, C, N)
▪
DC = Digital channel
▪
AC = Analog channel
▪
FR = Frequency
▪
DF = ROCOF
o Unused bytes should be left as blank spaces.
11.10 Corrective Actions
See Corrective Actions in Section 14.4.

PDF page 58

Business Practices Manual for Large Loads BPM-032

Effective Date: Dec-04-2026

Page 61 of 83
OPS-12
Public
11.11 Applicable BPMs and Processes
•
BPM-010 Network and Commercial Model
•
BPM-031 ICCP Data Requirements