ER26-3650-000 · 2026-09-18 · Iowa Office of Consumer Advocate, Illinois Attorney General's Office and 7 others

Protest of Iowa Office of Consumer Advocate et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

A joint group of state consumer advocates, attorneys general and citizens utility boards protests MISO's grandfathering of large loads under new Section 37A, arguing it leaves about 30 GW outside the rules and shifts costs to captive customers.

Asks FERC to: Reject MISO's Section 37A grandfathering provisions so Large Load customers bear the cost and risk they cause.

Cites the E-8 order's cost-shifting finding at P 66 and warns that MISO's exemption date could carry into the cost-protection filings MISO owes under the E-8 directives.

E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Minimum cost recovery / security (P 119, p. 74)

Key points

  1. The protestors say grandfathering does not address the cost-shifting concern in the E-8 order.
    do not address the cost-shifting concerns expressed by the Commission in the Show Cause Order. Source text
  2. They put the exempted capacity at about 30 GW, tied to an arbitrary date.
    The proposal fully or partially exempts approximately 30 gigawatts of existing and in-flight capacity based on an arbitrary date. Source text
  3. They warn that grandfathered loads cause reliability upgrades whose cost lands on other customers.
    The cost of these system and network reliability upgrades will be passed onto other customers and will not be assigned to the Large Load, the cost-causer. Source text
  4. Local reliability costs should follow the cost-causer, and Large Loads should bear the risk if load does not materialize.
    Local reliability costs caused or materially accelerated by a Large Load should follow the cost-causer, the Large Load customer. Source text
  5. They want MISO's show cause proposals to apply to incremental large load coming online after December 4, 2026.
    MISO’s Show Cause proposals should apply to any incremental large new load, as defined in this filing, that comes online after December 4, 2026. Source text

Read topic-matched comments in ER26-3650

Topics in the text: Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

Palmer Attorney Attorney Iowa Attorney General Iowa Attorney General Office of the Consumer Advocate Office of the Consumer Advocate 1375 East Court Avenue 1375 East Court Avenue Des Moines, IA 50319 Des Moines, IA 50319 Jennifer.Easler@oca.iowa.gov Heather.Palmer@oca.iowa.gov Attorneys for Iowa…
Read this passage Filed comments: Registry access

CERTIFICATE OF SERVICE

printed heading · Topic match: Registry access

Palmer Attorney Office of Consumer Advocate of Iowa 1375 East Court Avenue Des Moines, IA 50319-0063 (515) 725-7217 heather.palmer@oca.iowa.gov
Read this passage Filed comments: Registry access

Footnotes

Word notes · Topic match: Cost allocation

Footnotes [fn:1] In the Show Cause Order discussed below, the Commission expressly “encourage[d] . . . state consumer advocates to submit comments explaining whether this information is sufficient and granular enough or to submit comments explaining precisely which additional information on…
Read this passage Filed comments: Cost allocation