ER26-3650-000 · 2026-09-18 · Iowa Office of Consumer Advocate, Illinois Attorney General's Office and 7 others

Protest of Iowa Office of Consumer Advocate et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

Word notes use stable document IDs, such as [fn:8], which can differ from printed footnote numbers.

Document text

			UNITED STATES OF AMERICA
			BEFORE THE
			FEDERAL ENERGY REGULATORY COMMISSION
			
						)
			Midcontinent Independent System	)		Docket ER26-3650-000
			      Operator, Inc.	)	
						)
				
			JOINT PROTEST OF THE IOWA OFFICE OF THE CONSUMER ADVOCATE, OFFICE OF THE ILLINOIS ATTORNEY GENERAL, Illinois Citizens Utility Board, MICHIGAN ATTORNEY GENERAL, MICHIGAN CITIZENS UTILITY BOARD, MINNESOTA DEPARTMENT OF COMMERCE, mINNESOTA CITIZENS UTILITY BOARD, WISCONSIN CITIZENS UTILITY BOARD, Citizens Action Coalition of Indiana, INC., and Alliance for Affordable Energy
			
					Pursuant to Rule 211 the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure, 18 C.F.R. section 385.211 and the August 31, 2026 Combined Notice of Filings #1, the Iowa Office of Consumer Advocate (“Iowa OCA”), Office of the Illinois Attorney General (“IL OAG”), Illinois Citizens Utility Board (“IL CUB”), Michigan Attorney General, Michigan Citizens Utility Board (“MI CUB”), Minnesota Department of Commerce (“Commerce”), Citizens Utility Board of Minnesota (“MN CUB”), Wisconsin Citizens Utility Board (“WI CUB”), Citizens Action Coalition of Indiana, Inc., and Alliance for Affordable Energy respectfully submit this Protest in the above-captioned proceeding.  
				PROTEST
				
					The Iowa OCA, IL OAG, IL CUB, Michigan Attorney General, MI CUB, Commerce, MN CUB, WI CUB, Citizens Action Coalition of Indiana, Inc., and Alliance for Affordable Energy (“Joint Protestors”) submit this Protest regarding the proposed tariff revisions filed by MISO regarding Interconnection Reliability Requirements for Large Loads with the Commission 


				in the above-captioned action.[fn:1]  
					On August 28, 2026, MISO filed proposed revisions to its Open Access Transmission, Energy, and Operating Reserves Markets Tariff (“Tariff”) to establish certain Interconnection Reliability Requirements for Large Loads.  As noted in its transmittal letter, MISO’s filing purports to respond to several concerns raised by the Commission in its Show Cause Order in Docket No. EL26-70-000.  Specifically, MISO proposes visibility, ramp rate, and disturbance ride-through requirements for Large Loads, as well as grandfathering transition provisions designed to minimize disruption to existing commercial arrangements.  As demonstrated below, MISO’s proposed Tariff grandfathering transition provisions under Section 37A, discussed at pages 13 and 14 of the transmittal letter do not address the cost-shifting concerns expressed by the Commission in the Show Cause Order.  
	In the Show Cause Order, the Commission found MISO’s Tariff “appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for transmission service.”  Show Cause Order at P 66.  In the ruling, the Commission expressed concern about the lack of transparency regarding the assignment of costs, including Network Upgrades, necessary to provide transmission service to Eligible Customers or Large Load Customers on behalf of Large Loads to ensure Eligible Customers bear the risk and are ultimately responsible for costs incurred to provide transmission service, including the cost of Network Upgrades.  Id. at PP 70-77.  
MISO is proposing to fully exempt or “grandfather” any Large Load with a service commencement date on or prior to December 4, 2026, from all requirements of proposed Section 37A.  MISO is also proposing to partially exempt a Large Load or portion of a Large Load, that does not have a Service Commencement Date prior to December 4, 2026, but that meets the MTEP/EPR Condition from the ramp and ride-through requirements set forth in Sections 37A.6 through 37A.7.  The proposal fully or partially exempts approximately 30 gigawatts of existing and in-flight capacity based on an arbitrary date.[fn:2]  The Joint Protestors are concerned the proposed grandfathering terms would exempt a large portion of the new large data center loads in Iowa and potentially other MISO regions from the reliability protections proposed in MISO’s filing.  Additionally, if this exemption is carried forward to the series of future Federal Power Act section 205 filings that MISO intends to make in response to the Show Cause Order, this could deprive electric consumers of the cost shifting and other consumer protections that MISO has been directed to address in the Show Cause Order.  
Large Loads have reliability impacts regardless of operational date.  Under proposed Section 37A, MISO cannot mandate a grandfathered facility install facility-side hardware protections to prevent severe spikes and triggering system protections from cascading through the grid, shifting the burden to the bulk electric system.  Under this proposal, local electric utilities will be forced to remedy the problem by building expensive, large-scale system and network reliability upgrades to cushion the grid against sudden destabilizing effects.  The cost of these system and network reliability upgrades will be passed onto other customers and will not be assigned to the Large Load, the cost-causer.  This will force captive ratepayers to subsidize the integration of Large Loads, violating the core principles of cost causation.  
If the Commission allows MISO to fully or partially exempt or “grandfather” any Large Load from all requirements of the proposed Section 37A, the costs associated with local reliability projects will not be assigned to the Large Load customer, the cost-causer.  Local reliability costs caused or materially accelerated by a Large Load should follow the cost-causer, the Large Load customer.  Broader allocation of costs to other customers should occur only if the other customers receive commensurate benefits.  Moreover, Large Load customers, and not other customers, should bear the risk if the load does not materialize as planned.  MISO’s Show Cause proposals should apply to any incremental large new load, as defined in this filing, that comes online after December 4, 2026.  
WHEREFORE, the Iowa OCA, IL OAG, IL CUB, Michigan Attorney General, MI CUB, Commerce, MN CUB, WI CUB, Citizens Action Coalition of Indiana, Inc., and Alliance for Affordable Energy pray the Commission reject MISO’s proposed Tariff grandfathering transition provisions under Section 37A, to ensure Large Load customers bear the cost and risk of all costs caused by the Large Load customer, and for any additional relief Commission deems appropriate under the circumstances.


								Respectfully submitted,
				
						/s/ Jennifer Easler			/s/ Heather L. Palmer			
					Jennifer Easler 		Heather L. Palmer
					Attorney		Attorney
					Iowa Attorney General 		Iowa Attorney General
					Office of the Consumer Advocate		Office of the Consumer Advocate
					1375 East Court Avenue		1375 East Court Avenue
					Des Moines, IA  50319		Des Moines, IA  50319
					Jennifer.Easler@oca.iowa.gov		Heather.Palmer@oca.iowa.gov 
					
					Attorneys for Iowa Office of the Consumer Advocate
					
				
					/s/ Susan L. Satter		/s/ Samuel C. Lukens			
					Susan L. Satter		Samuel C. Lukens
					Bureau Chief		Assistant Attorney General
					Public Utilities Bureau		Public Utilities Bureau
					Office of the Illinois Attorney General		Office of the Illinois Attorney General
					115 South LaSalle Street, 25th Floor		115 South LaSalle, 25th Floor
					Chicago, IL  60603		Chicago, IL  60603
					susan.satter@ilag.gov		samuel.lukens@ilag.gov 
				
				Attorneys for the Office of the Illinois Attorney General
					
						/s/ Sarah Moskowitz			/s/ Eric DeBellis				
					Sarah Moskowitz		Eric DeBellis
					Executive Director		General Counsel
					Illinois Citizens Utility Board		Illinois Citizens Utility Board
					309 West Washington Street, Suite 800		309 West Washington Street, Suite 800
					Chicago, IL  60606		Chicago, IL  60606
					smoskowitz@citizensutilityboard.org		edebellis@citizensutilityboard.org
				
				For the Illinois Citizens Utility Board
				
						/s/ Michael E. Moody			/s/ John Liskey				
					Michael E. Moody		John Liskey
					Special Litigation Division Chief		General Counsel
					Assistant Attorney General		Citizens Utility Board of Michigan
					Michigan Department of Attorney General	921 North Washington Avenue
					P.O. Box 30212		Lansing, MI  48906
					Lansing, MI  48909		john.liskey@cubofmichigan.org
					Moodym2@michigan.gov 		
				
					Attorney for the Michigan		Attorney for the Citizens Utility
					    Attorney General		   Board of Michigan
							/s/ Sydnie Lieb				/s/ Brandon Crawford			
					Sydnie Lieb 			Brandon Crawford
					Assistant Commissioner of Regulatory			Regulatory Advocate
					  Affairs, Energy Resources Division 			Citizens Utility Board of Minnesota
					Minnesota Department of Commerce			332 Minnesota Street, Suite W1360
					85 7th Place East, Suite 280			Saint Paul, MN  55101
					Saint Paul, MN  55101  			brandonc@cubminnesota.org
					Sydnie.Lieb@state.mn.us
				
					For the Minnesota Department of 		For the Citizens Utility Board of 
					   Commerce		   Minnesota
					
						/s/ Corey Singletary			/s/ Daniel Narvey				
					Corey Singletary		Daniel Narvey
					Executive Director		General Counsel
					Citizens Utility Board of Wisconsin 		Citizens Utility Board of Wisconsin
					625 North Segoe Road, Suite 101		625 North Segoe Road, Suite 101
					Madison, WI  53705		Madison, WI  53705
					singletary@cubwi.org		narvey@cubwi.org
					
					For the Citizens Utility Board of Wisconsin
				
					Kewin L. Olson		Jennifer A. Washburn
					Executive Director		Regulatory Director
					Citizens Action Coalition of Indiana, Inc.	Citizens Action Coalition of Indiana, Inc.
					1915 West 18th Street, Suite C		1915 West 18th Street, Suite C
					Indianapolis, IN  46202		Indianapolis, IN  46202
					kolson@citact.org		jwashburn@citact.org
					
				For the Citizens Action Coalition of Indiana, Inc.
				
							/s/ Yvonne Cappel-Vickery			
					Yvonne Cappel-Vickery	
					Clean Grid Manager	
					Alliance for Affordable Energy	
					4505 South Claiborne Avenue	
					New Orleans, LA  70125	
					yvonne@all4energy.org	
					
					For the Alliance for Affordable Energy	
					
				
				Dated:		September 18, 2026
				


				CERTIFICATE OF SERVICE
				
				I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
				
					Dated at this 18th day of September, 2026.
				
						Heather L. Palmer		
					Heather L. Palmer
					Attorney
					Office of Consumer Advocate of Iowa
					1375 East Court Avenue
					Des Moines, IA 50319-0063
					(515) 725-7217
					heather.palmer@oca.iowa.gov


Footnotes
[fn:1] In the Show Cause Order discussed below, the Commission expressly “encourage[d] . . . state consumer advocates to submit comments explaining whether this information is sufficient and granular enough or to submit comments explaining precisely which additional information on transmission cost allocation may be needed to inform proper state-jurisdictional cost allocation.”  Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 at P 70 (2026) (“Show Cause Order”).
[fn:2] Midcontinent Indep. Sys. Operator, Large Load Working Group, Large Load Interconnection Reliability Requirements (LLWG) at 8 (Aug. 12, 2026), https://www.misoenergy.org/events/2026/large-load-working-group-llwg---august-12-2026/ (last visited on Sept. 16, 2026).