ER26-3650-000 · 2026-09-18 · Data Center Coalition

Motion to Intervene and Comments of the Data Center Coalition re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

The Data Center Coalition accepts that large loads need distinct reliability rules but asks FERC to decline MISO's tariff revisions as filed, citing requirements left to a Business Practices Manual and a grandfathering test tied to transmission milestones.

Asks FERC to: Decline to accept MISO's proposed tariff revisions as filed, without prejudice to a later filing that is objective, transparent and consistent with the Show Cause Order.

Comments on MISO's first filing after the E-8 order. DCC cites the order's calls for clear and consistent rules and for minimizing disruption to existing commercial arrangements.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. DCC says the E-8 order settled that large loads can face distinct operational rules; the open question is whether MISO's framework is just and reasonable.
    Instead, the issue is whether the framework that MISO has proposed in this proceeding represents a just and reasonable means of mitigating these reliability risks. PDF p. 2
  2. DCC says the proposal leaves the covered customers and obligations unclear and moves the substance to a future BPM.
    the proposed tariff revisions do not clearly define the customers that will be subject to those requirements and the obligations that will apply. PDF p. 3
  3. DCC says grandfathering turns on MTEP or EPR project milestones, not on binding agreements or investments by the customer.
    MISO ties grandfathered treatment primarily to whether an associated transmission project has reached specified milestones in the MISO Transmission Expansion Plan (“MTEP”) or Expedited Project Review (“EPR”) PDF p. 4
  4. DCC objects to MISO's unbounded discretion to subject otherwise exempt customers to the standards.
    MISO has proposed to grant itself broad discretion to subject customers that otherwise qualify for an exemption to its reliability standards without including any objective standards or procedures in the tariff PDF p. 4
  5. DCC argues that leaving requirements to BPMs conflicts with FPA section 205 and the filed rate doctrine.
    Section 205 of the FPA requires public utilities to file the rates, terms, and conditions of FERC-jurisdictional service with the Commission. PDF p. 6
  6. DCC asks FERC to decline the filing as submitted.
    DCC respectfully requests that the Commission decline to accept MISO’s proposed tariff revisions as filed, without prejudice to a future filing PDF p. 5
Contents · 9 sections
  1. I. OVERVIEW OF THE DATA CENTER COALITION p. 1
  2. II. INTRODUCTION p. 2
  3. III. COMMENTS p. 6
  4. A. MISO’s Filing Is Inconsistent With The Show Cause Order, The FPA, And p. 6
  5. B. MISO Has Not Demonstrated That Its Proposed Definition Of Large Load Is p. 17
  6. C. MISO Has Not Demonstrated That Its Grandfathering Proposal Will p. 25
  7. IV. MOTION TO INTERVENE p. 29
  8. V. CORRESPONDENCE AND COMMUNICATIONS p. 30
  9. VI. CONCLUSION p. 31

Read topic-matched comments in ER26-3650

Topics in the text: Cost allocation · Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Midcontinent Independent System Operator, Inc. ) Docket No.
Read this passage

I. OVERVIEW OF THE DATA CENTER COALITION

printed heading

OVERVIEW OF THE DATA CENTER COALITION DCC is the membership organization for the U.S. data center industry, representing leading data center owners and operators that develop, operate, and maintain data center infrastructure and teams across the country.4 DCC members operate data centers that…
Read this passage

II. INTRODUCTION

printed heading

MISO proposes to revise its tariff to provide itself with new authority to impose new visibility and reliability requirements on Large Loads and Computational Loads.
Read this passage

III. COMMENTS

printed heading

III.
Read this passage

A. MISO’s Filing Is Inconsistent With The Show Cause Order, The FPA, And

printed heading · Topic match: Reliability and curtailment

While DCC recognizes that not every ministerial implementation detail must be included in the tariff, MISO’s tariff revisions do not include the substantive standards that MISO proposes to apply, leave key aspects of MISO’s proposed framework unaddressed, and grant MISO broad discretion to apply…
Read this passage

B. MISO Has Not Demonstrated That Its Proposed Definition Of Large Load Is

printed heading · Topic match: Connecting load and generation

Additionally, if MISO is going to apply its proposed reliability requirements to co-located load, it should demonstrate that the proposed standards are appropriately tailored to account for the characteristics of these arrangements. 48 Show Cause Order at P 58. - 19 - facility that is used to…
Read this passage Filed comments: Connecting load and generation

C. MISO Has Not Demonstrated That Its Grandfathering Proposal Will

printed heading

MISO Has Not Demonstrated That Its Grandfathering Proposal Will Minimize Disruption To Existing Commercial Arrangements In the Show Cause Order, the Commission recognized that while changes to the MISO tariff are warranted, large loads already are working with transmission owners and other entities…
Read this passage

IV. MOTION TO INTERVENE

printed heading · Topic match: Cost allocation

DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate - 30 - responsible load growth, support the development of new generation, and enhance grid resilience system-wide without imposing undue costs on existing ratepayers.
Read this passage Filed comments: Cost allocation

V. CORRESPONDENCE AND COMMUNICATIONS

printed heading

CORRESPONDENCE AND COMMUNICATIONS DCC requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following:61 Morgan A.
Read this passage

VI. CONCLUSION

PDF bookmark

CONCLUSION For the reasons set out above, DCC respectfully requests that the Commission issue an order consistent with these comments.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 18th day of September 2026. /s/ Stephen J.